Main PSB Construction Site Construction Fencing & Early Package Activities Start: July 2015 Sitework and Bulk Excavation Activities Start: January 2016 Concrete Foundation Activities Start: ~March 2016 Structural Steel Erection Activities Start: ~June 2016 Structural Steel Substantially Complete: ~September 2016 PSB Exterior Envelope Substantially Complete: ~December 2016 WES Exterior Envelope Substantially Complete: ~February 2017 Site Improvements & Landscape Activities Start: ~February 2017 Construction Activities Substantially Complete: ~January 2018 Final Completion & Occupancy: ~April 2018 New Steam Manhole Construction Area Construction Activities Start: November 2015 Construction Activities Finish: ~March 2016 North Pleasant Street Work Areas Limited Duration Work Summer 2016 and Summer 2017 North Pleasant Street Work Areas Limited Duration Work Summer 2016 and Summer 2017 New Storm Drain Manhole Construction Area Limited Duration Work Construction Activities Start: ~February 2016 Construction Activities Finish: ~July 2016 Goessmann - Ellis Way Work Area Limited Duration Work Summer 2017 Marcus, Cleanroom Renovations Site Construction Activities Start: December 2015 Construction Activities Finish: ~August 2016 PSB Loading Dock & Tunnel Site Area Construction Activities Start: February 2016 Construction Activities Finish: ~October 2017 Polymer Chiller Plant Upgrades - Piping Distribution Site Area Construction Activities Start: ~July 2016 Construction Activities Finish: ~June 2017 New Storm Drain Manhole Construction Area Limited Duration Work Construction Activities: 02/26/16 - 03/04/16

Marcus, Cleanroom Renovations Site Construction Activities ... Plan...Construction Activities Start: ~February 2016 Construction Activities Finish: ~July 2016 Goessmann - Ellis Way

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Marcus, Cleanroom Renovations Site Construction Activities ... Plan...Construction Activities Start: ~February 2016 Construction Activities Finish: ~July 2016 Goessmann - Ellis Way

Main PSB Construction SiteConstruction Fencing & Early Package Activities Start: July 2015Sitework and Bulk Excavation Activities Start: January 2016Concrete Foundation Activities Start: ~March 2016Structural Steel Erection Activities Start: ~June 2016Structural Steel Substantially Complete: ~September 2016PSB Exterior Envelope Substantially Complete: ~December 2016WES Exterior Envelope Substantially Complete: ~February 2017Site Improvements & Landscape Activities Start: ~February 2017Construction Activities Substantially Complete: ~January 2018Final Completion & Occupancy: ~April 2018

New Steam Manhole Construction AreaConstruction Activities Start: November 2015Construction Activities Finish: ~March 2016

North Pleasant Street Work AreasLimited Duration WorkSummer 2016 and Summer 2017

North Pleasant Street Work AreasLimited Duration WorkSummer 2016 and Summer 2017

New Storm Drain Manhole Construction AreaLimited Duration WorkConstruction Activities Start: ~February 2016Construction Activities Finish: ~July 2016

Goessmann - Ellis Way Work AreaLimited Duration WorkSummer 2017

Marcus, Cleanroom Renovations SiteConstruction Activities Start: December 2015Construction Activities Finish: ~August 2016

PSB Loading Dock & Tunnel Site AreaConstruction Activities Start: February 2016Construction Activities Finish: ~October 2017

Polymer Chiller Plant Upgrades - Piping Distribution Site AreaConstruction Activities Start: ~July 2016Construction Activities Finish: ~June 2017

New Storm Drain Manhole Construction AreaLimited Duration WorkConstruction Activities: 02/26/16 - 03/04/16