Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
Main PSB Construction SiteConstruction Fencing & Early Package Activities Start: July 2015Sitework and Bulk Excavation Activities Start: January 2016Concrete Foundation Activities Start: ~March 2016Structural Steel Erection Activities Start: ~June 2016Structural Steel Substantially Complete: ~September 2016PSB Exterior Envelope Substantially Complete: ~December 2016WES Exterior Envelope Substantially Complete: ~February 2017Site Improvements & Landscape Activities Start: ~February 2017Construction Activities Substantially Complete: ~January 2018Final Completion & Occupancy: ~April 2018
New Steam Manhole Construction AreaConstruction Activities Start: November 2015Construction Activities Finish: ~March 2016
North Pleasant Street Work AreasLimited Duration WorkSummer 2016 and Summer 2017
North Pleasant Street Work AreasLimited Duration WorkSummer 2016 and Summer 2017
New Storm Drain Manhole Construction AreaLimited Duration WorkConstruction Activities Start: ~February 2016Construction Activities Finish: ~July 2016
Goessmann - Ellis Way Work AreaLimited Duration WorkSummer 2017
Marcus, Cleanroom Renovations SiteConstruction Activities Start: December 2015Construction Activities Finish: ~August 2016
PSB Loading Dock & Tunnel Site AreaConstruction Activities Start: February 2016Construction Activities Finish: ~October 2017
Polymer Chiller Plant Upgrades - Piping Distribution Site AreaConstruction Activities Start: ~July 2016Construction Activities Finish: ~June 2017
New Storm Drain Manhole Construction AreaLimited Duration WorkConstruction Activities: 02/26/16 - 03/04/16