42

March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being
Page 2: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

March 9, 2016

ADDENDUM NO. 2

Solicitation HH-89

Design/Build for Rehabilitation of Skewbacks, Viaduct Piers and Lower Level North Abutment at the Henry Hudson Bridge

To all Prospective Proposers:

The due date to submit Expressions of Interest remains unchanged: March 29, 2016

Attached is the following additional or clarified information for the Project:

1. The presentation from the March 4, 2016 Pre-EOI Informational Meeting is attached. This presentation is being shared for general information and reference only.

2. A copy of the March 4, 2016 Pre-EOI Informational Meeting sign-in sheet is attached.

3. Closing date for Questions is revised to 3/11/16. Please submit your questions in writing to the Point of Contact by 3/11/16 so there is ample time for a complete response.

Below are questions received and the Authority responses:

Q 5 Can the designated Construction Inspection Firm also provide the services of the Material Testing Firm provided that it has the required credentials?

A 5 Yes

Q 6 Will there be an Alternative Technical Concept (ATC) process in the RFP stage?

A 6 Will be answered in a future addendum.

Q 7 Is it acceptable for a contractor to self-perform the geo technical construction provided that it can demonstrate the requisite experience and resources to perform the work?

A 7 Yes.

Q 8 Does the Geotechnical Subcontractor as identified in the EOI have to be exclusive to a particular team?

A 8 No.

Page 3: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Solicitation HH-89 Addendum #2 March 9, 2016

Form CU-078 Page 2 (Rev. 1/4/99)

Q 9 The scope of work for the Geotechnical Subcontractor is undefined at this point

in the process. Can the Contractor name alternate Geotechnical Subcontractors in order to retain a competitive field of bidders?

A 9 Yes.

Q 10 Would the TBTA consider removing the naming of the Geotechnical Subcontractor until the RFP process when the scope of work is more clearly defined?

A 10 No.

Q 11 Please confirm if subcontractors, sub designers or sub consultants of the Design Professional and the Construction Inspection Professional Engineering Firm are required to submit Standard Forms RFQ-4 (rev 8.22.12) and SF-330.

A 11 Confirmed except as noted below in A16

Q 12 Is there a limit to the number of Design-Build firms that will be shortlisted from the evaluation of these Expressions Of Interest? If so, how many?

A 12 No.

Q 13 May the documents that do not count towards the 60 page total, the RFQ-4 Form and Financial Statements, be submitted on a disk only or shall they be printed out as well?

A 13 All submittals must be made as hard copies as well as in electronic format.

Q 14 Can the firm performing the Construction Inspection /QC services also provide the Structural Health Monitoring System?

A 14 No.

Q 15 Can the letter from surety not be included in the page count as they can be multiple pages and vary in page length due to the surety attachments?

A 15 The only exclusions from the 60-page limitation are the RFQ-4 forms and financial statements.

Q 16 It was stated at the 3/4 pre-EOI meeting that any sub consultants to the Design Professional or Construction Inspection Professional Engineering Firm that are included in the EOI would need to submit the appropriate forms as well (RFQ-4 and SF330). Would the SF330 be an individual SF330 for each subconsultant(s) or would a combined SF330 for the Professional firm and its sub(s) be acceptable?

A 16 A combined SF-330 is acceptable as long as the company affiliations are clearly noted.

Page 4: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Solicitation HH-89 Addendum #2 March 9, 2016

Form CU-078 Page 3 (Rev. 1/4/99)

Q 17 The last paragraph on REOI page 2 of 5 states that no more than five (5) past

project descriptions should be provided for the Designer. Is this limitation for the customized SOQ (Item 3.b.ii)? Is the Designer also able to cite the 10 project examples as per the requirements of the SF330 Part I Section F?

A 17 Please refer to the instruction under Part I Section F which states: “Present as many projects as requested by the agency, or 10 projects, if not specified…”.

Q 18 If subconsultant(s) are being included, are their project examples part of the Professional firm’s limitations or can they submit five (5) as well.

A 18 Additional sub firms may list their own most relevant project examples. Please remain within the stated page limitations.

Please be governed accordingly in submitting your Expressions of Interest for this solicitation. Additionally, please acknowledge receipt of this Addendum 2 in your Expression of Interest cover letter.

Sincerely, Susan Higgins Director, Procurement

Page 5: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

DESIGN-BUILD

CONTRACT

HH-89 / DB

REHABILITATION OF SKEWBACKS, APPROACH

CONCRETE PIERS, AND LOWER LEVEL NORTH

ABUTMENT AT THE HENRY HUDSON BRIDGE

TRIBOROUGH BRIDGE AND TUNNEL AUTHORITY

REQUEST FOR EXPRESSIONS OF INTEREST (EOI)

INFORMATIONAL SUMMARY

MARCH 2016

Page 6: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

SUSAN HIGGINS, Director

Triborough Bridge & Tunnel Authority

Law & Procurement Department

Two Broadway, 24 th Floor

New York, NY 10004

[email protected]

Alternate Point of Contact is John Weldon – email: [email protected]

Designated Point of Contact for al l questions and comments during the procurement phase of the

project as stated in the Request for Expressions of Interest and in accordance with the New York

State Finance Law §§139-j and 139-k.

DESIGNATED POINT OF CONTACT

2

Page 7: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Project Overview

General Location

Project Schedule

Goals

General Scope of Work

Utilities

HH-89 DESIGN-BUILD PROJECT

3

Page 8: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

HENRY HUDSON BRIDGE - GENERAL LOCATION

BRONXMANHATTAN

PROJECT HH-89

- Rehabilitation of Skewbacks (4)

- Replacement of Bent Pedestals Piers (16)

- Replacement of LL North Abutment Pilasters (2)

4

Page 9: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Notice of Award is anticipated for

December 2016

Contract Duration

Not to exceed 33 Months

Coordination with other projects

HH-13A / HH-88B – Reconstruction of Toll Plazas and Southbound Approach, and

Replacement of Facility Lighting System

Construction 11/2016 thru 5/2020

HH-07A / HH-30 – Miscellaneous Structural Rehabilitation and Overcoat Painting

at Henry Hudson Bridge

Construction 6/2019 thru 12/2021

PROJECT SCHEDULE

5

Page 10: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Meet project requirements:

Safety

Quality

Schedule

Budget

Provide Alternate Load Path system for arch and tower column loads

Replace concrete bent pedestals and Lower Level North Abutment

Mitigate concrete expansion and cracking due to Alkali -Silica

Reaction (ASR)

Reduce moisture and water infiltration into concrete substructures

PROJECT GOALS

6

Page 11: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

HH-89 - Rehabilitation of Skewbacks, Approach Concrete Piers and

North Abutment

Rehabilitation of (4) concrete skewbacks

Replacement of (16) bent pedestal piers

Replacement of (2) concrete abutment pilasters.

GENERAL SCOPE OF WORK

7

Page 12: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Alternate Load Path system

Design, fabricate, and install structural

system to allow transfer of superstructure

loads directly to bedrock

Reinforced concrete encasement

Demolition of 7” of concrete from all

vertical faces and 1’ of top slab excluding

tower column footings

Drill and grout dowels into existing

concrete

Install new 1’-2’ thick concrete encasement

Apply waterproofing/sealant on all surfaces

SKEWBACK REHABILITATION

8

Page 13: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

SKEWBACK REHABILITATION

One concept for Alternate Load Path System The Authority is open to and encourages other methods

9

Page 14: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Full replacement of all bent pedestals down to

bedrock

Replacement of pin bearings at Bent 9 and 10 to

fixed connections.

Perform temporary support

BENT PEDESTAL REPLACEMENT

10

Page 15: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Full replacement of Lower Level North Abutment pilasters

Replacement of seismic isolation bearings

Perform temporary support

NORTH ABUTMENT PILASTER REPLACEMENT

11

Page 16: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

STRUCTURAL HEALTH MONITORING SYSTEM

Design, install, and operate a structural health monitoring (SHM)

system including sensors for: Strain measurement

Displacement measurement

Vibration measurement

Load cell measurement

Tilt monitoring

Weather Station

System shall monitor the performance of the new construction and

existing bridge elements.

System shall be web-based and modular to allow for future

expansion.

Design-Build Team will be required to maintain and operate a SHM

System for up to 2 years following substantial completion of

Construction.

Monitoring reports shall be provided

12

Page 17: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

ADDITIONAL ITEMS

Environmental Permitting

Construction Access

Noise Monitoring and Mitigation

MPT for Local Roads

Allowable Work Days and Hours: Bronx Weekdays Only: 8:00 AM to 4:00 PM

No Nights or Weekends

Manhattan All Days: 7:00 AM to 4:00 PM

13

Page 18: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

POTENTIAL INTERFERENCE

NORTH VIADUCT

SOUTH VIADUCT

PIER 18W

(LOOKING WEST)

ADJACENT TO EDSALL AVE

PIER 9W

(LOOKING SOUTH)

ADJACENT TO PARK PATH

PIER 20E

(LOOKING WEST)

ADJACENT TO OVERHEAD

POWER LINES

PIER 11W

(LOOKING NORTHWEST)

ADJACENT TO PARK PATH

14

Page 19: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

PROJECT WORK AREAS (NORTH – BRONX)

15

Page 20: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

PROJECT WORK AREAS (SOUTH – MANHATTAN)

16

Page 21: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

SITE ACCESS

MANHATTAN – INWOOD HILL PATH ACCESS

17

Page 22: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

SITE ACCESS

BRONX – SPUYTEN DUYVIL PARK PATH ACCESS

18

Page 23: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Relocate existing utilities that are interfering with

work

Ensure coordination with utility owner:

Consolidated Edison

Known existing utilities will be reflected in the RFP

Documents

UTILITIES COORDINATION

19

Page 24: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Design-Build Team shall identify the following:

Construction Contractor

Geotechnical Subcontractor

Design Professional

Construction Inspection Professional Engineering Firm

Design-Build Team shall be fully experienced in all project aspects

including:

Fixed steel bridge analysis

Rehabilitation and replacement of concrete foundations

High capacity deep foundation design and construction

Agency coordination and permitting

EXPRESSIONS OF INTEREST (EOI)

20

Page 25: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

QC/QA is Design-Build Team’s Responsibility

Design-Build Team shall appoint a QC/QA Manager responsible for

Project QC/QA

Construction Inspection shall be by an Independent Engineering Firm

(Retained by the Design-Build Team)

Materials Testing shall be by an Independent Testing Firm or

Laboratory (Retained by the Design-Build Team)

The Authority will perform audit and review QA on Design-Build

Team’s Design and Construction Activities. Additionally, the Authority

will perform in-depth QA inspections of any possible environmental

work.

QUALITY CONTROL / QUALITY ASSURANCE

(QC/QA)

21

Page 26: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Activity Due Date

Request for EOIs Released 02/01/2016

Final Date for receipt of Proposer’s questions 03/11/2016

EOI Due Date 03/29/2016

Shortlisted DB Teams Announced April, 2016

RFP Issued May, 2016

Proposals Due August, 2016

Contract Award December, 2016

ANTICIPATED PROCUREMENT SCHEDULE

22

Page 27: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Design-Build Contract amount shall include all construction

and engineering services as required by the RFP

RFP will include a Price Schedule

Two-Step Design-Build Procurement Process

Project Schedule Total Duration Not to Exceed 33 Months

Milestones, potential incentives, and liquidated damage assessments will be

detailed in the RFP

Stipend Amount and Agreement will be provided in the RFP

M/WBE Goals have been set at 15% / 15% respectively

CONTRACT INFORMATION

23

Page 28: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Evaluation Factors

Organization and Key Personnel

Past Performance of the proposed Team/Firms

Record of performing together as a Team and on Design-Build Projects

EOI EVALUATION AND SELECTION

24

Page 29: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Solicitation No: HH-89

Attn: Victoria Warren, Manager, Procurement Administration

Triborough Bridge and Tunnel Authority

2 Broadway – Mail Center

Procurement Department

New York, NY 10004

For additional information and required forms,

Visit: http://web.mta.info/bandt/procure/conrfp.html

SUBMIT EXPRESSION OF INTEREST TO:

25

Page 30: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Submittal requirements – page limits Cover letter

Statement of Qualifications

HH-89 Form A

RFQ-4, SF-330

Financial statements

Letter from Surety

Any additional project information will be posted to the Authority website where you obtained this REOI http://web.mta.info/bandt/procure/conrfp.html

Final date for receipt of questions pertaining to this EOI is March 11, 2016 – Email questions to Designated Point of Contact [email protected]

ADDITIONAL INFORMATION

26

Page 31: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

SUSAN HIGGINS, Director

Triborough Bridge & Tunnel Authority

Law & Procurement Department

Two Broadway, 24 th Floor

New York, NY 10004

[email protected]

Alternate Point of Contact is John Weldon – email: [email protected]

Designated Point of Contact for al l questions and comments during the procurement phase of the

project as stated in the Request for Expressions of Interest and in accordance with the New York

State Finance Law §§139-j and 139-k.

DESIGNATED POINT OF CONTACT

27

Page 32: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being
Page 33: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being
Page 34: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being
Page 35: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being
Page 36: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being
Page 37: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being
Page 38: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being
Page 39: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being
Page 40: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being
Page 41: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

February 18, 2016

ADDENDUM NO. 1

Solicitation HH-89

Design/Build for Rehabilitation of Skewbacks, Viaduct Piers and Lower Level North Abutment at the Henry Hudson Bridge

To all Prospective Proposers:

The due date to submit Expressions of Interest remains unchanged: March 29, 2016

You are hereby notified of the following change to the above referenced solicitation:

1. The date for the Pre-EOI Informational Meeting is changed to March 4, 2016 (meet at 10:00AM, at the Robert Moses Building on Randall’s Island, NY)

Below are questions received and the Authority responses:

Q1 Reference Solicitation Section 3, Par. b – Please confirm the statement “60 pages of text both sides” is equivalent to 60 sheets of paper with double sided text.

A1 Confirmed

Q2 Reference Solicitation Section 3, Par. b – Please confirm that only the RFQ-4 form and the Financial statements are excluded from the page count and the SF-330 forms are included,

A2 Confirmed

Q3 Reference Solicitation Section 2, Par. e – Please confirm that the proposed Independent Construction Inspection Professional Engineering Firm and Materials Testing Firm or Laboratory is not required to be exclusive to any one Design-Build proposer.

A3 Confirmed

Q4 What is the definition of the Geotechnical Subcontractor a. Is it the firm which designs / engineers the foundation? b. Is it the firm which performs the actual foundation / anchor work?

A4 “Geotechnical Subcontractor” is referring to the firm performing the actual foundation / anchor work.

Page 42: March 9, 2016 - MTAweb.mta.info/bandt/procure/HH-89 Addendum 2.pdf1. The presentation from the March 4, 2016 Pre- EOI Informational Meeting is attached. This presentation is being

Solicitation HH-89 Addendum #1

February 18, 2016

Form CU-078 Page 2 (Rev. 1/4/99)

Please be governed accordingly in submitting your Expressions of Interest for this solicitation and be sure to register to attend the Informational Meeting as instructed in the solicitation letter.

Additionally, please acknowledge receipt of this Addendum 1 in your Expression of Interest cover letter.

Sincerely, Susan Higgins Director, Procurement