March 21, 2018 ALCA Meeting
March 21, 2018
Agenda 1. Process and Timeline
2. Original Submission
3. Revised Submission
4. Next Steps
The City of Calgary
Role:
• The City is responsible for capturing and using public feedback, along with a comprehensive
technical review, to assess the application and make a recommendation to Calgary Planning
Commission (CPC) and City Council.
Process:
• Aug. 2017: Open house and online engagement.
• Sept. 2017: City provides technical review comments to applicant.
• Jan. 2018: Applicant submits amended application. Revised application shared with the public.
• Feb. 2018: City provides additional technical comments on revised application.
• (Current) Mar. 2018: Applicant working on final application.
• Spring 2018: Tentative date for final land use application submission.
• Summer 2018: Tentative date for presentation to CPC.
• Summer 2018: Tentative date for City Council Public Hearing.
March 21, 2018 ALCA Town Hall Meeting 3
ORIGINAL
SUBMISSION
MAY 2018
Plan Considerations
• Generally slopes from the north and
east to the south and west
• Predominantly undeveloped – except
for one existing homestead
• Existing views from the existing
community to the north and east
• High pressure gas line (to be
converted to a low pressure gas line in
2020) along the northern boundary
• Crowfoot LRT located approximately
600 metre from southern boundary
• Regional pathway on east boundary
• Close proximity to the Crowfoot
Commercial Centre
• Existing loam pile requiring removal
March 21, 2018 ALCA Town Hall Meeting 5
Environmental Studies
• Preliminary Biophysical Impact
Assessment (BIA) conducted by
Stantec Consulting
• Field assessments completed in the
Spring and Summer of 2015 & 2017
• Stantec Determined:
• Six wetland areas ranging in class
• Most of the habitat provide limited
wildlife potential
• Treed areas may provide some
opportunities for songbirds, raptors
and bats
• Wetlands provide low to moderate
habitats for wildlife
• Disconnected and fragmented habitat
• Overall, due to existing level of
disturbance and previous impacts to
vegetation, leading to a low quality
wildlife habitat, the development is
considered to have an “overall low
environmental consequence.”
March 21, 2018 ALCA Town Hall Meeting 6
Wetlands
• Still under consideration is the
retention of Wetland 4
• City policy interpretation is the driving
force behind keeping Wetland 4
• Due to elevation of wetland, building
heights would be higher and park
space would likely not be as central
and large
• Impact to the plan is still under review,
to be considered by the City, Hopewell
and affected stakeholders.
March 21, 2018 ALCA Town Hall Meeting 7
Staged Master Drainage Plan
Conclusions:
• The stormwater management facility
proposed in this report will control the
discharge from the proposed
development, at the discharge rate
stipulated by the City of Calgary, Water
Resources.
• The Best Management Practices
suggested in this report will reduce the
runoff volume discharge to the Bow
River to an average annual of 50
mm/year.
• Water quality enhancement will be
achieved by the proposed oil/grit
separator.
• This stormwater will be cleaner than
the stormwater coming from the
existing community
March 21, 2018 ALCA Town Hall Meeting 8
Developing the Block Pattern
• Access, combined with grading
constraints, determined the block
layout and access points.
• Access points are relatively fixed
based on:
1. the existing access point to
Watergrove Mobile Home park
2. City requirements of a 150 m technical
offset from the northern plan boundary
3. City requiring minimum intersection
distances of 60 metres.
• The project team proposed the
northern access slightly south of the
fixed point to provide additional
distance from Arbour Meadows Close
NW, while allowing a 90 degree
connection to Arbour Lake Road, and
to allow space to work with challenging
grades to the north.
March 21, 2018 ALCA Town Hall Meeting 9
Concept Plan
Original Submission
• A variety of housing options including
single-detached and multi-residential
• Townhomes: 2-3 storeys
• Apartments: 4-6 storeys
• Higher densities located along Arbour
Lake Road and in close proximity to
similar uses to the north and
southeast; and in closer proximity to
the LRT
• Large central open space
• Maintain connections to the existing
community
• Approximately 890 units
• No commercial uses
March 21, 2018 ALCA Town Hall Meeting 10
Transportation
• Transportation Impact Assessment
(TIA) conducted by Bunt and
Associates
• Weekday peak hour intersection
capacity analysis was completed at
four (4) study area intersections for the
Existing and Opening Day Post
Development horizons.
• The Existing analysis indicates that all
study area intersections are currently
operating within acceptable capacity
parameters therefore no intersection
improvements are required to
accommodate the existing traffic.
March 21, 2018 11
Transportation
The Post Development intersection
capacity analysis indicated:
• All study area intersections will
continue operating within acceptable
capacity parameters therefore no
intersection improvements are
required to accommodate the
proposed development.
• A sensitivity analysis was completed to
determine the effect of a higher
percentage of vehicles utilizing the
main site access, specifically 70% to
the main access and 30% to the
secondary access. The intersection
of the Main Site Access/Arbour Lake
Road NW will continue operating
within acceptable capacity
parameters as a stop controlled
intersection
• Signalization is not required at the site
access intersections with Arbour Lake
Road NW.
March 21, 2018 12
Sanitary Servicing
• Sanitary Servicing Study completed by
Pasquini and Associates
• Sanitary sewer pipe capacity is
reviewed under existing and post
development scenarios.
• Any infrastructure replacements will be
addressed in due course as required
by the City of Calgary
• Therefore, service won’t be
interrupted.
March 21, 2018 ALCA Town Hall Meeting 13
Fulfillment of Municipal Development Plan Goals
(including the Developed Areas Guidebook)
1. The plan proposes to sensitively intensify the existing community of Arbour Lake in order to
leverage the City’s existing capital investments and location of major employment centres.
2. Shaping a more compact urban form is an overarching city-wide strategic goal of the City.
3. Aligns with the MDP’s intent to integrate land use planning and transit investments by providing
residential densities in areas served by existing transit service.
4. The plan proposes a diverse housing mix and varying built forms. This aligns with the MDP’s intent
to encourage a broad range of housing options through intensification and redevelopment of the
Developed Area.
5. The plan will maintain existing connections to the community of Arbour Lake by providing direct
road and pathway connections to existing amenities, exceeding the connectivity expectations
outlined in the MDP.
March 21, 2018 ALCA Town Hall Meeting 14
REVISED
SUBMISSION
DECEMBER 2018
Community Engagement
What we heard?
• Citizens expressed concern about the
proposed locations of apartment
buildings and the potential for them to
block existing views from their homes.
• Citizens mentioned that they would like
to see additional access points
throughout the area, to improve
walkability.
• Concerns relating to the density of the
Plan Area
March 21, 2018 ALCA Town Hall Meeting 16
Major Changes – Location/Configuration of Apartment Buildings
March 21, 2018 ALCA Town Hall Meeting 17
Major Changes – New Pedestrian Connections
March 21, 2018 ALCA Town Hall Meeting 18
Concept Plan
Revised Submission
• Similar to the original submission in
terms of uses and units
• Density is appropriate given close
proximity to Crowfoot LRT station and
Crowfoot Commercial Centre
• Southeast multi-residential now
provides an opportunity for commercial
uses (i.e. a small day care facility or a
coffee shop near the park)
• Improved connections through the
multi-residential sites to Arbour Lake
Road NW
• Relocated apartment buildings to
maintain existing views from nearby
residents
March 21, 2018 ALCA Town Hall Meeting 19
NEXT
STEPS
Spring/Summer 2018