54
March 13, 2012 Scott Hill Development Ltd. c/o Mr. Doug Chysik Chysik Project Management Ltd. 15095 Royal Avenue White Rock, BC V4B 1M1 Dear Mr. Chysik: Re: Report of Findings – Phase 2 Environmental Site Assessment 7000 and 6976 Scott Road, Surrey, BC Project No: 11272 This letter report presents the findings of a KEYSTONE ENVIRONMENTAL TM Phase 2 Environmental Site Assessment (ESA) prepared at the request of Scott Hill Development for the properties located at 7000 and 6976 Scott Road, in the City of Surrey, BC (the Site). The Site location is shown on Figure 1. It is understood that this Phase 2 ESA will be used for financing purposes. 1. BACKGROUND Keystone Environmental conducted Phase I Environmental Site Assessment (ESA), at the request of Scott Hill Development. Summary of the areas of potential environmental concern (APECs) identified in the Phase 1 ESA are as follows. APEC 1 – Potential Heating Oil Tank located at 7000 Scott Road A single-family residence was located on the northwest corner of the Site from the early 1950s or earlier to the late 1980s. It is unknown how the former Site building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site and was stored in an underground storage tank (UST). APEC 2 – Service Station located at 11996 70 th Avenue Various service stations have been located at 11996 70 th Avenue, approximately 30 m to the west of the Site, since the early 1970s. This property is listed in the MOE Site Registry as 11996 70 th Avenue (Site ID: 369). The property was registered in February 1998 and was last updated in September 2006. The Record Status is listed as “Active – Under Assessment.” A notation indicates that a notification about likely or actual substance migration to neighbouring site was initiated in July 2006. During the Site reconnaissance, five monitoring wells were observed on this property and four monitoring wells were observed along 120 th Street, approximately 25 m to the west of the Site.

March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

March 13, 2012 Scott Hill Development Ltd. c/o Mr. Doug Chysik Chysik Project Management Ltd. 15095 Royal Avenue White Rock, BC V4B 1M1 Dear Mr. Chysik: Re: Report of Findings – Phase 2 Environmental Site Assessment

7000 and 6976 Scott Road, Surrey, BC Project No: 11272 This letter report presents the findings of a KEYSTONE ENVIRONMENTALTM Phase 2 Environmental Site Assessment (ESA) prepared at the request of Scott Hill Development for the properties located at 7000 and 6976 Scott Road, in the City of Surrey, BC (the Site). The Site location is shown on Figure 1. It is understood that this Phase 2 ESA will be used for financing purposes.

1. BACKGROUND

Keystone Environmental conducted Phase I Environmental Site Assessment (ESA), at the request of Scott Hill Development. Summary of the areas of potential environmental concern (APECs) identified in the Phase 1 ESA are as follows.

APEC 1 – Potential Heating Oil Tank located at 7000 Scott Road

A single-family residence was located on the northwest corner of the Site from the early 1950s or earlier to the late 1980s. It is unknown how the former Site building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site and was stored in an underground storage tank (UST).

APEC 2 – Service Station located at 11996 70th Avenue

Various service stations have been located at 11996 70th Avenue, approximately 30 m to the west of the Site, since the early 1970s. This property is listed in the MOE Site Registry as 11996 70th Avenue (Site ID: 369). The property was registered in February 1998 and was last updated in September 2006. The Record Status is listed as “Active – Under Assessment.” A notation indicates that a notification about likely or actual substance migration to neighbouring site was initiated in July 2006. During the Site reconnaissance, five monitoring wells were observed on this property and four monitoring wells were observed along 120th Street, approximately 25 m to the west of the Site.

Page 2: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Report of Findings – Phase 2 Environmental Site Assessment

7000 and 6976 Scott Road, Surrey, BC

2 Project 11272 / March 2012

The Keystone Environmental Stage 1 PSI report concluded that further investigation of the APECs was warranted.

The objective of the Keystone Environmental Ltd. (Keystone Environmental) Phase 2 ESA was to investigate groundwater and soil vapour quality in the vicinity of the off-Site service station and perform a field level survey to determine the likelihood of potential on-Site USTs in the vicinity of the former on-Site residence to provide due diligence information. No on-site APECs were identified other than the potential heating oil tank.

2. STUDY LIMITATIONS

Findings presented in this report are based upon the results of this Keystone Environmental Phase 2 ESA that includes field investigations conducted in March 2012 including groundwater and soil vapour sample analyses. Geologic observations and analytical results reflect conditions encountered at a specific test location. Site conditions (geologic, hydrogeologic, and chemical characterization) may vary from that extrapolated from the data collected during this investigation. Consequently, while findings and conclusions documented in this report have been prepared in a manner consistent with that level of care and skill normally exercised by other members of the environmental science and engineering profession practising under similar circumstances in the area at the time of the performance of the work, this report is not intended, nor is it able to provide a totally comprehensive review of present or past site environmental conditions.

This report has been prepared solely for the internal use of Scott Hill Development, pursuant to the agreement between Keystone Environmental Ltd. and Scott Hill Development. A copy of the general terms and conditions associated with this agreement is attached at the end of this report. By using the report, Scott Hill Development agrees that they will review and use the report in its entirety. Any use which other parties make of this report, or any reliance on or decisions made based on it, are the responsibility of such parties. Keystone Environmental Ltd. accepts no responsibility for damages, if any, suffered by other parties as a result of decisions made or actions based on this report.

3. APPLICABLE STANDARDS

The applicable provincial regulations used for comparison of analytical results are contained in the following documents:

Environmental Management Act (EMA), ([SBC 2003], Chapter 53 assented to October 23, 2003)

Contaminated Sites Regulation (CSR) (BC Reg. 375/96 O.C. 1480/96, includes amendments up to B.C. Reg. 286/2010, October 4, 2010)

Hazardous Waste Regulation (HW) (BC Reg. 63/88 O.C. 268/88, including amendments up to B.C. Reg. 63/2009, April 1, 2009)

Page 3: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Report of Findings – Phase 2 Environmental Site Assessment

7000 and 6976 Scott Road, Surrey, BC

3 Project 11272 / March 2012

3.1 Soil Standards

The CSR provides generic and matrix numerical soil standards for different land use categories. The matrix numerical soil standards provide standards for potential contaminants based on several site-specific factors (e.g., intake of contaminated soil, toxicity to soil invertebrates and plants). To determine the appropriate standard for a contaminant, the applicable factors for a site are first selected. The lowest standard of those for applicable factors for the site is then defined as the standard that will apply.

The Site is comprised of two properties (7000 and 6976 Scott Road, Surrey BC) are currently vacant and forested that covers an area of approximately 18,977m2. The current land zoning is residential; therefore the CSR standards for Residential land use (RL) would be applicable to the Site.

3.2 Groundwater Standards

The CSR standards for the protection of aquatic life (AW) apply to groundwater located within 500 m of a surface water body containing freshwater or marine aquatic life. Aquatic life water use also applies at sites where the potential for contaminated groundwater to flow through preferential pathways that discharge to within 500 m of a surface water body containing aquatic life. The closest freshwater surface water body to the Site is an unnamed pond adjacent to Cougar Creek, which is located approximately 140 m southeast of the Site.

Sufficient hydrogeological data has not been compiled for the Site to determine potential preferential pathways between the Site and the nearest water bodies. Based on the distance from the Site to the nearest surface water bodies, the CSR standards for the protection of freshwater aquatic life have been conservatively applied to the Site.

The CSR DW standards are based on current use and protection for the potential future use of drinking water in the area of the Site. The drinking water standards are considered applicable to a site unless the groundwater meets the following conditions:

If groundwater or surface water intake wells are not located at, or within, 100 m up-gradient or 500 m down-gradient of the outer edge of contamination at the site

If a suitable aquifer (hydraulic conductivity greater than 1 x 10-6 m/s and aquifer yield greater than 1.3 L/min) is not located beneath the site

If the natural quality of groundwater in the aquifer is unsuitable for drinking water (total dissolved solids (TDS) are greater than 4,000 mg/L, or is contained within organic soils or muskeg)

If there is a confining geological unit that adequately protects the aquifer (greater than or equal to 5 m thick, bulk hydraulic conductivity less than or equal to 1 x 10-7 m/s, relatively uniform and free of fractures, is continuous across the extent and predicted migration pathway of the shallow subsurface contamination, and the lower 5 m has not been penetrated by contamination from the above units).

Page 4: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Report of Findings – Phase 2 Environmental Site Assessment

7000 and 6976 Scott Road, Surrey, BC

4 Project 11272 / March 2012

The BC Water Resource Atlas, which displays groundwater management information for the Province of BC, shows that water wells are not located within 500 m of the Site. The groundwater in the area of the Site is therefore not currently used for drinking water purposes.

Based on the subsurface conditions observed during drilling at the Site, it is considered likely that the groundwater conditions required to exclude the CSR DW standards, considering the potential future use for drinking water, will not be met. Confining units and organic soil layers were not observed in the geology at the Site. Based on the observed geology, the hydraulic conductivity for the Site is estimated to be approximately 1x10-6 (Freeze and Cherry, 1979). Therefore, to be conservative, the CSR DW standards have been applied to the Site groundwater.

4. INVESTIGATIVE PROGRAM

The Keystone Environmental Phase 2 ESA field work was conducted from March 2 through March 5, 2012. The objective of this Phase 2 ESA was to determine if potential constituents of concern (PCOCs) associated with the APECs identified in the previous Stage 1 PSI completed by Keystone in February 2012 are present in Site groundwater and Soil vapour at concentrations greater than the applicable standards outlined in the CSR.

The following table presents the APECs, the corresponding investigative locations, and the associated potential constituents of concern. The on-Site investigative locations and off-Site APECs are shown on Figure 1.

Table 4-1 List of APECs and Investigative Locations

Area of Potential Environmental Concern

Phase 2 ESA Investigative

Locations

Potential Constituents of Concern

Soil Groundwater Soil Vapour

On-Site APEC #1 Potential for historic heating oil UST, at the northwest corner of the Site

EF scan in former building

footprint

None if heating oil tank Is not present

None if heating oil tank Is not present

None if heating oil tank Is not

present

On-Site APEC #2 Service Station located at 11996 70th Avenue

MW12-1, SV12-1

none LEPHw, HEPHw, PAH, VOC, VPH, dissolved metals

VPHv, BTEX, Naphthalene

BTEX – Benzene, Toluene, Ethylbenzene and Xylene PAH – Polycyclic Aromatic Hydrocarbons EF – Electro-frequency VOC – Volatile Organic Compounds GPR – Ground Penetrating Radar VPH – Volatile Petroleum Hydrocarbons HEPH – Heavy Extractable Petroleum Hydrocarbons v – in vapour LEPH – Light Extractable Petroleum Hydrocarbons w – in water

The scope of work for the Phase 2 ESA consisted of the following tasks:

Completing a BC One call to register the drilling program and obtain utility locate information

Performing an electro-frequency (EF) survey on-Site to identify the potential presence of underground utilities and potential underground USTs;

Page 5: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Report of Findings – Phase 2 Environmental Site Assessment

7000 and 6976 Scott Road, Surrey, BC

5 Project 11272 / March 2012

Drilling one borehole on the Site (between the boundary of 7000 and 6976 Scott Road) and completion of the borehole as a groundwater monitoring well

Installing one soil vapour well

Sampling groundwater and vapour at the test location (MW12-1)

Documenting the results of the investigation in this letter report

4.1 Electro-Frequency Survey

Prior to the drilling investigation, an underground utility locate was conducted on March 2, 2012. The utility contractor, Helux Environmental Services (Helux), was contracted to identify the potential for underground utilities at the proposed drilling location. The utility contractor determined that utilities were not located within a two metre radius of the proposed borehole location between 7000 and 6976 Scott Road with an electro-frequency survey.

The use of ground penetrating radar at the site was precluded as the dense vegetation and debris was present in the area of the former residence. As a result, an electro-frequency survey was completed in the area of the former residence to search for underground evidence that may be indicative of the presence of USTs.

Subsurface anomalies potentially indicative of USTs were not conclusively identified in the areas surveyed. Based on the redevelopment plans of the Site, it is anticipated that there is a low potential for a heating oil UST to be an area of environmental concern, as the contamination, if any, would likely be isolated based on the geology observed and the contamination would be dealt with during the site preparation phase of the development.

4.2 Borehole Drilling and Soil Sampling

Drilling was performed for the Phase 2 ESA on March 3, 2012 by Blue Max Environmental Drilling Co. Ltd. (Blue Max) of Port Coquitlam, BC. A truck-mounted rig equipped with solid stem augers was used to advance the borehole.

Soil samples were collected directly from the solid stem augers by first removing the outer 10 mm of soil in order to obtain a representative sample. One sample (laboratory sample) was placed in two glass jars (125 mL each) with minimal headspace and sealed. A second sample (field sample) was placed and sealed in a Ziploc® polyethylene bag to an approximate 50% volume for measurement of soil headspace vapours.

Field samples were screened for volatile constituents using a portable photo-ionization detector (MiniRAE). This instrument cannot be used to directly quantify the concentrations of volatile constituents as determined by the laboratory. However, it does provide an indication of volatile compounds and hydrocarbons to assist in sample selection for laboratory analysis. The headspace vapour screening procedure is described as follows:

Field soil samples were allowed to warm for approximately 120 minutes to allow the release of any hydrocarbon vapours into the headspace of the polyethylene bag

Following the one hundred and twenty minute holding period, a hole was punctured into the polyethylene bag using the MiniRAE instrument to obtain the headspace vapour concentration measurements

Page 6: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Report of Findings – Phase 2 Environmental Site Assessment

7000 and 6976 Scott Road, Surrey, BC

6 Project 11272 / March 2012

The soil sample depth intervals, headspace measurements and lithology were recorded on the field monitoring well logs. Soil samples were not submitted for analysis as elevated headspace readings were not observed in the soils and on-Site activities did not warrant soil investigations.

4.3 Monitoring Well Construction and Groundwater Sampling

Monitoring wells MW12-1 was constructed using stem augers since the soil conditions maintained the integrity of the borehole walls while installing the well and annular materials. The placement of monitoring well screen was dependent on the depth of the apparent water table and the potential constituents of concern associated with the off-site service station.

A Schedule 40 PVC screen with 0.25 mm slot width and 3.0 m in length were used during the construction of the monitoring well. Solid PVC riser pipes extended from the top of the 3 m screen to the well head. Filter sand was placed as a filter pack around the well screen and to at least 0.15 m above the top of the screen. To provide a seal above the sand pack and reduce the potential for vertical migration of groundwater or infiltration of surface waters into the well, bentonite chips overlined the sand pack. The monitoring wells were finished with a PVC stick up with a J-plug.

Following construction, the monitoring well was measured for water level and well headspace vapour level. The monitoring well was developed prior to sampling using dedicated WaterraTM tubing, a surge block and a footvalve in order to remove fine-grained sediments from the well and filter pack in preparation for groundwater sampling. The volume of water in the wells was calculated prior to developing, and a minimum of six times the well volume of water was removed or the well was developed dry three consecutive times.

Following well development on March 5th, 2012, purging was conducted on using a peristaltic pump to remove standing water within the well column and enable sampling of representative formation groundwater. Groundwater was monitored for pH, specific conductance, temperature and oxidation-reduction potential (ORP). Well purging was considered complete when the values of pH, specific conductance, temperature and ORP were within 0.1 units, 10%, 1oC and 10 mV of the previous measurements.

The monitoring well was sampled using a peristaltic pump and the low-flow sampling procedure for the analysis of LEPHW, HEPHW, PAH, and dissolved metals. The low-flow sampling procedure was used to minimize the amount of sediment entrained in the water column for sampling. WaterraTM tubing with a footvalve was used to collect samples from the monitoring wells for VOC and VPHw analysis. Groundwater samples were placed in chilled coolers, and were transported to the laboratory (Maxxam Analytics in Burnaby, BC) under standard chain of custody procedures.

4.4 Soil Vapour Well Installation and Soil Vapour

One soil vapour monitoring well (SV12-1) was installed approximately 1 m distance from MW12-1 using soild stem augers. A 150 mm by 6.4 mm soil vapour screen was installed below a bentonite seal and filter sand pack. The soil vapour well screen was positioned within a 0.3 m thick layer of 10/20 filter sand. Nylon tubing was connected to the top of the soil vapour well screen and extended to the surface. Finely ground bentonite powder was placed above the filter

Page 7: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Report of Findings – Phase 2 Environmental Site Assessment

7000 and 6976 Scott Road, Surrey, BC

7 Project 11272 / March 2012

sand and around the nylon tubing, and then hydrated to seal the well screen from external air sources from the ground surface (ambient air) or from soil layers located above the well screen. The nylon tubing was crimped to prevent water and ambient air from entering the tubing prior to sampling. The soil vapour screens were installed at depths of approximately 1.0 mbg for monitoring.

Soil vapour samples were collected on March 5, 2012 using laboratory-supplied pumps to extract soil vapour through thermal desorption tubes. The sampling was conducted at least 48 hours after installation of the soil vapour probes to allow for the vapour within the probe to equilibrate with the vapours in the surrounding soils. Purging of the soil vapour probe and tubing was conducted at each of the locations with approximately one litre of soil vapour expelled.

Leak testing was conducted at each soil vapour well using isopropanol to ensure the integrity of the soil vapour probe from exposure to ambient or other air sources. Samples were collected for analyses of VOCs, VPH, naphthalene and isopropanol, based on the APEC.

The sampling train was connected; and one to three soil vapour well volumes of air were purged to expel non-representative vapour prior to sampling. Purging and sampling was monitored by vacuum and flow testing at soil vapour well. Once purging was completed, vapour samples were drawn by a laboratory-calibrated pump into laboratory-supplied sample tubes. Samples were submitted in thermal desorption sampling tubes under a chain of custody to Maxxam for laboratory analysis of the vapour potential constituent of concern (PCOC).

5. INVESTIGATIVE RESULTS

5.1 Surficial Geology and Field Observations

The soil profile was logged by observation of the soil retrieved from the augers. The soil was classified using the Unified Soil Classification System. Top soil was encountered at the surface of the borehole location. The following is a general description of the stratigraphy encountered beneath the surface at the Site.

Unit A: Top Soil – Organic brown to black top soil with plant roots was present from surface to approximately 0.1 mbg.

Unit B: This unit consists of grey silty clay with minor sand and gravel components. Rootlets were present. The soil was soft, damp to moist, with medium plasticity. Odours or staining were not observed. This unit was encountered near surface and extended to a depth of 2.2 mbg.

Unit C: This unit consists of grey fine sandy and silty clay, with minor orange coloured gravel. The soils were soft, damp to moist, with medium plasticity. Odours or staining were not observed. This unit was encountered below Unit B to a depth of 3.5 mbg

Unit D: This native unit consists of blue-grey clay. The soils were soft and wet, with medium plasticity. Odours or staining were not observed. This unit was encountered below Unit C to the final drilling depth of 3.5 mbg

The soil headspace vapour measurements ranged from 3 parts per million by volume (ppmv) to 7.9 ppmv, and were not consider elevated.

Page 8: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Report of Findings – Phase 2 Environmental Site Assessment

7000 and 6976 Scott Road, Surrey, BC

8 Project 11272 / March 2012

5.2 Hydrogeology and Field Observations

Local groundwater flow direction cannot be determined within the scope of this investigation. Based on elevation contours derived from the Energy, Mines and resources 1:50000 Topographical map, the site groundwater is expected to follow local topography toward the south west toward Cougar Creek.

The depth to groundwater was measured at approximately 0.8m below top casing (TOC) relative to the 0.1 m stick up casing at MW12-1. Well casing headspace vapour measurement was 25 ppm using the GastechTor 1238 ME. This well headspace measurement is not considered elevated.

5.3 Groundwater Analytical Results

A groundwater sample from MW12-1 was collected and submitted to the laboratory for analysis for constituents LEPHw, HEPHw, PAH, VOC, VPHw, and dissolved metals.

The analytical results indicated the concentrations of LEPHw, HEPHw, PAHs, VOC and VPHw were less than the reported laboratory detection limits and therefore less than the CSR AWFW and DW standards for the sample analyzed.

The analytical results indicated the concentrations of dissolved metals were less than the CSR AWFW and DW standards for the sample analyzed.

The groundwater analytical results are presented in Tables 1 to 5, and are summarized on Figure 1. The laboratory analytical results are attached at the end of this report.

5.4 Soil Vapour Analytical Results

The analytical results for vapour are presented in Table 6 and on Figure 1. Laboratory reports are attached in at the end of this report.

The applicable attenuation factors were applied to the Keystone Environmental vapour analytical results to estimate breathing zone concentrations in indoor and outdoor air. The application of attenuation factors is described in the following calculation:

Cindoor air = Cvapour * α

Where:

Cair ( µg/m3) is the estimated indoor or outdoor air concentration of the PCOC

Cvapour is the measured vapour concentration of the PCOC

α is the vapour attenuation factor (Table 1 – BCMOE, 2010)

Page 9: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Report of Findings – Phase 2 Environmental Site Assessment

7000 and 6976 Scott Road, Surrey, BC

9 Project 11272 / March 2012

Attenuation factors are location-specific and dependent on the vapour sample depth. For vapour samples collected at 1.0 mbg, the applicable outdoor attenuation factor is 0.0000015 and the applicable indoor residential attenuation factor is 0.0028. The attenuation factors applied to the measured results are listed in Table 6. The attenuation factors are used to predict concentrations of vapour PCOCs in indoor and outdoor air. Vapour investigation and sampling was conducted in general accordance with Technical Guidance 4 (BCMOE, 2010).

With the exception of benzene, non-attenuated soil vapour concentrations of PCOCs did not exceed the CSR RL standards outlined in Schedule 11. Application of the applicable attenuation factors noted in the Ministry of Environment (MOE) Technical Guidance Document #4 resulted in estimated concentrations of constituents in the predicted indoor and outdoor breathing zones which were also less than their applicable CSR RL standards given the potential future and present Site conditions (Table 6).

6. SUMMARY AND DISCUSSION

Keystone Environmental conducted a Phase 2 ESA in March 2012 for the properties located at 7000 and 6976 Scott Road, Surrey, BC. The Phase 2 ESA was conducted to determine if potential constituents of concern (PCOCs) associated with the APECs identified in the previous Stage 1 PSI are present in Site groundwater and/or vapour at concentrations greater than the applicable standards outlined in the CSR.

Keystone Environmental drilled one borehole and completed the borehole as a monitoring well on the property at 6976 Scott Road, Surrey, BC. During the investigation, sheens, stains and odours were not observed in the soil or groundwater at the Site. The underlying geology at the Site generally consisted of grey silty clay with minor sand and gravel.

APEC 1 – Potential Residential Heating Oil Tank

Ground penetrating radar use on site was not possible due to dense vegetation and debris in the area of the former residence. As a result, an electro-frequency survey was completed in the area of the former residence to search for underground evidence that may be indicative of the presence of USTs.

Subsurface anomalies potentially indicative of USTs were not conclusive identified in the area surveyed. However, based on the redevelopment plans of the Site, there is considered to be a low potential for an heating oil UST to be an area of environmental concern as the contamination, if any, would likely be isolated based on the geology observed and would be dealt with during the site preparation phase of the development.

APEC 2 –Off-Site Service Station at 11996 70th Avenue

Various service stations have been located at 11996 70th Avenue, approximately 30 m to the west of the Site, since the early 1970s. This property is listed in the MOE Site Registry as 11996 70th Avenue (Site ID: 369).

Groundwater analytical results indicated that concentrations of LEPHw, HEPHw, PAHs, VOC and VPHw were less than the reported laboratory detection limits and therefore less than the CSR AWFW and DW standards for the sample analyzed.

Page 10: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Report of Findings – Phase 2 Environmental Site Assessment

7000 and 6976 Scott Road, Surrey, BC

10 Project 11272 / March 2012

The analytical results indicated the concentrations of dissolved metals were less than the CSR AWFW and DW standards for the sample analyzed.

Soil vapour from the newly-installed soil vapour wells were analyzed for VOCs, BTEX, styrene, VPHv, naphthalene and isopropanol on March 5, 2012. The concentrations of predicted indoor soil vapour for benzene at MW12-1 did exceed the CSR RL standards prior to attenuation factors were applied. However, the concentrations of predicted indoor soil vapour PCOCs did not exceed the applicable CSR RL standards after an attenuation factor was applied.

7. CONCLUSIONS

Constituents of concern associated with the off-Site service station was not present in Site groundwater or vapour at concentrations greater than the CSR RL, DW and AW standards in the locations investigated.

The electro-frequency survey was not sufficient to conclude that an underground tank was not present. However it is considered to be a low potential for concern, as the contamination, if present from a residential heating oil tank, would likely be isolated based on the geology observed and would be dealt with during the site preparation during the development of the Site.

We trust this is the information you require at this time. Please contact us should you have any questions.

Sincerely,

Keystone Environmental Ltd. Iori Kokotailo Andrew Lam, B.Sc. Geol. Environmental Scientist Project Manager 11272 120313 FINAL Phase 2 ESA Letter Report.doc

ATTACHMENTS: Figure 1: Groundwater and Soil Vapour Results Tables 1 to 6: Groundwater and Vapour Analytical Results Borehole Logs Maxxam Ltd. Analytical Reports Keystone Environmental Ltd. General Terms and Conditions for Services

labundo
Orignal Signed By
labundo
Orignal Signed By
Page 11: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

FIGURE

Page 12: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site
Page 13: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

TABLES

Page 14: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

1127202 120310 Water Analytical Tables.xlsx

Table 1 (1 of 1)Groundwater Analytical Results

Extractable Petroleum Hydrocarbons uncorrected for Polycyclic Aromatic Hydrocarbons (EPH) and corrected

for Polycyclic Aromatic Hydrocarbons (LEPH/HEPH)7000 Scott Rd. Surrey BC

Scott Hill DevelopmentProject No. 11272-02

Sample ID RDL MW12-1 CSR CSRLab Sample ID CW5220 AW DW

Date Sampled 05-Mar-12EHw (C10-C19) 200 < 5000 5000EHw (C19-C32) 200 < n/s n/sLEPHw 200 < 500 n/sHEPHw 200 < n/s n/s

NOTES:All concentrations in micrograms per litre (ug/L)

RDL Reported Detection LimitCSR Contaminated Sites Regulation, effective April 1, 1997AW Aquatic Life StandardDW Drinking Water standardNW No Water Use

LEPH Light Extractable Petroleum HydrocarbonsHEPH Heavy Extractable Petroleum Hydrocarbons

n/s No standard for this constituent< Less than reported detection limit- Not analyzed.* CSR LEPH/HEPH standards used for comparison

Bold Exceeds CSR (AW) standard for this sampleUnderline Exceeds CSR (DW) standard for this sample

Bold Italic Exceeds CSR (NWU) standard for this sample

Page 15: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

1127202 120310 Water Analytical Tables.xlsx

Table 2 (1 of 1)Groundwater Analytical Results

Polycyclic Aromatic Hydrocarbons (PAHs)7000 Scott Rd. Surrey BC

Scott Hill DevelopmentProject No. 11272-02

Sample ID RDL MW12-1 CSR CSRLab Sample ID CW5220 AWFW DW

Date Sampled 05-Mar-12Naphthalene 0.05 < 10 n/s2-MethylNaphthalene 0.05 < n/s n/sAcenaphthylene 0.05 < n/s n/sAcenaphthene 0.05 < 60 n/sFluorene 0.05 < 120 n/sPhenanthrene 0.05 < 3 n/sAnthracene 0.01 < 1 n/sAcridine 0.05 < 0.5 n/sTotal LMW-PAHs - < n/s n/sFluoranthene 0.02 < 2 n/sPyrene 0.02 < 0.2 n/sBenzo(a)anthracene 0.01 < 1 n/sChrysene 0.05 < 1 n/sBenzo(b+j)fluoranthene 0.05 < n/s n/sBenzo(k)fluoranthene 0.05 < n/s n/sBenzo(a)pyrene 0.009 < 0.1 0.01Indeno(1,2,3-cd)pyrene 0.05 < n/s n/sDibenz(a,h)anthracene 0.05 < n/s n/sBenzo(g,h,i)perylene 0.05 < n/s n/sQuinoline 0.5 < 34 n/sTotal HMW-PAHs - < n/s n/sTotal PAHs - < n/s n/s

NOTES:All concentrations in micrograms per litre (µg/L)Parameters listed in order of increasing molecular weight

RDL Reported Detection LimitCSR Contaminated Sites Regulation, effective April 1, 1997AW Aquatic Life standardDW Drinking Water standardn/s No standard for this constituent< Less than reported detection limit- Not analyzed

Bold Exceeds CSR (AW) standard for this sampleUnderline Exceeds CSR (DW) standard for this sample

Page 16: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

1127202 120309 Water Analytical Tables.xlsx

Table 3 (1 of 1)Groundwater Analytical Results

Volatile Petroleum Hydrocarbons(VPH)7000 Scott Rd. Surrey BC

Scott Hill DevelopmentProject No. 11272-02

Sample ID RDL MW12-1 CSR CSRLab Sample ID CW4334 AWFW DW

Date Sampled 05-Mar-12VH 300 < 15000 15000VPH 300 < 1500 n/s

NOTES:All concentrations in micrograms per litre (µg/L)

RDL Reported Detection LimitCSR Contaminated Sites Regulation, effective April 1, 1997AW Aquatic Life standardDW Drinking Water standardn/s No standard for this constituent< Less than reported detection limit- Not analyzed

Bold Exceeds CSR (AW) standard for this sample

Underline Exceeds CSR (DW) standard for this sampleBold Italic Exceeds CSR (NWU) standard for this sample

Page 17: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

1127202 120309 Water Analytical Tables.xlsx

Table 4 (1 of 1)Groundwater Analytical Results

Volatile Organic Compounds7000 Scott Rd. Surrey BC

Scott Hill DevelopmentProject No. 11272-02

Sample ID RDL MW12-1 CSR CSRLab Sample ID CW4334 AWFW DW

Date Sampled 05-Mar-12Benzene 0.5 < 4000 5Bromodichloromethane 1 < n/s 16Bromoform 1 < n/s 100Bromomethane 1 < n/s 512-Butanone 10 < n/s 22000Carbon Tetrachloride 0.5 < 130 5Chlorobenzene 0.5 < 13 30Chloroethane 1 < n/s 46Chloroform 1 < 20 100Chloromethane 1 < n/s 9501,2-Dibromoethane 0.2 < n/s 0.34Dibromomethane 0.9 < n/s 370Dichlorodifluoromethane 2 < n/s 73001,2-Dichlorobenzene 0.5 < 7 31,3-Dichlorobenzene 0.5 < 1500 n/s1,4-Dichlorobenzene 0.5 < 260 11,1-Dichloroethane 0.5 < n/s 37001,2-Dichloroethane 0.5 < 1000 51,1-Dichloroethene 0.5 < n/s 14cis-1,2-Dichloroethene 1 < n/s 370trans-1,2-Dichloroethene 1 < n/s 7301,2-Dichloropropane 0.5 < n/s 9.9cis-1,3-Dichloropropene 1 < n/s 6.7trans-1,3-Dichloropropene 1 < n/s 6.7Toluene 0.5 < 390 244-Methyl-2-pentanone 10 < n/s 2900Methylene Chloride 2 < 980 501,1,2,2-Tetrachloroethane 0.5 < n/s 3.4Tetrachloroethene 0.5 < 1100 30Ethylbenzene 0.5 < 2000 2.41,1,1-Trichloroethane 0.5 < n/s 100001,1,2-Trichloroethane 0.5 < n/s 12Trichloroethene 0.5 < 200 5Trichlorofluoromethane 4 < n/s 11000Vinyl Chloride 0.5 < n/s 2Xylenes 1 < n/s 300Styrene 0.5 < 720 n/sBromobenzene 2 < n/s n/s1,3- Butadiene 5 < n/s n/s

NOTES:All concentrations in micrograms per litre (µg/L)

RDL Reported Detection LimitCSR Contaminated Sites Regulation, effective April 1, 1997AW Aquatic Life standardDW Drinking Water standardn/s No standard for this constituent< Less than reported detection limit- Not analyzed

Bold Exceeds CSR (AW) standard for this sampleUnderline Exceeds CSR (DW) standard for this sample

Bold Italic Exceeds CSR (NWU) standard for this sample

Page 18: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

1127202 120309 Water Analytical Tables.xlsx

Table 5 (1 of 1)Groundwater Analytical Results

Metals7000 Scott Rd. Surrey BC

Scott Hill DevelopmentProject No. 11272-02

Sample ID RDL MW12-1 CSR CSRLab Sample ID CW4334 AWFW DW

Date Sampled 05-Mar-12Aluminum 3 9.8 n/s 9500Antimony 0.5 < 200 6Arsenic 0.1 0.33 50 10Barium 1 41.8 10000 1000Beryllium 0.1 < 53 n/sBoron 50 < 50000 5000Cadmium 0.01 0.051 0.1-1.3a 5Chromium 1 < 10 50Cobalt 0.5 1.13 40 n/sCopper 0.2 1.17 20-90a 1000Iron 5 < n/s 6500Lead 0.2 < 40-160a 10Magnesium 50 44500 n/s 100000Manganese 1 72.7 n/s 550Mercury 0.05 < 1 1Molybdenum 1 < 10000 250Nickel 1 3.8 250-1500a n/sSelenium 0.1 0.78 10 10Silver 0.02 < 0.5-15a n/sSodium 50 18600 n/s 200000Strontium 1 277 n/s 22000Thallium 0.05 < 3 n/sTin 5 < n/s 22000Titanium 5 < 1000 n/sUranium 0.1 0.37 3000 20Zinc 5 < 75-3150a 5000Bismuth 1 < n/s n/sCalcium 50 41500 n/s n/sLithium 5 10.4 n/s n/sPotassium 50 2330 n/s n/sSilicon_Si 100 11400 n/s n/sVanadium 5 < n/s n/sZirconium 0.5 < n/s n/s

Conventional ParameterspH 0.1 6.4Hardness_CaCO3 287

NOTES:All concentrations in micrograms per litre (µg/L) except pH (unitless) and Hardness (mg/L) METALS NOTES: AWFW

RDL Reported Detection Limit Cd 0.1 @ H<30 Cu 20 @ H<50 Zn 75@ H<90CSR Contaminated Sites Regulation, effective April 1, 1997 0.3 @ H=30-<90 30 @ H=50-<75 150 @ H=90-<100AW Aquatic Life standard 0.5 @ H=90-<150 40 @ H=75-<100 900 @ H=100-<200DW Drinking Water standard 0.6 @ H=150-<210 50 @ H=100-<125 1650 @ H=200-<300

a CSR standard is hardness dependent 0.8 @ H=210-<270 60 @ H=125-<150 2400 @ H=300-<400n/s Standard not available for this constituent 0.9 @ H=270-<330 70 @ H=150-<175 3150@ H=400-<500< Less than reported detection limit 1.1 @ H=330-<390 80 @ H=175-<200- Not analyzed 1.2 @ H=390-<450 90 @ H>=200* Back Ground Criteria for Metals Analysis of Water Samples (Cobalt) 1.3 @ H=450-<500

Bold Exceeds CSR (AW) standard for this sampleUnderline Exceeds CSR (DW) standard for this sample Ni 250 @ H<60 Pb 40 @ H<50 Ag 0.5 @ H<=100

Metals Notes 650 @ H=60-<120 50 @ H=50-<100 15 @ H>1001100 @ H=120-<180 60 @ H=100-<2001500 @ H>=180 110 @ H=200-<300

160 @ H>=300

Page 19: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Sample ID SV12-1

Predicted Indoor Air

Concentration Based on

default attenuation

factors

Predicted Outdoor Air

Concentration Based on

default attenuation

factors

Sample Depth (m) 1.00

Date Sampled 06-Mar-12Attenuation Factor 2.80E-03 1.50E-06

Pump Time (min) 177Flow Rate (L/min) 0.08Diesel ListBenzene 1.9 0.0053 0.000003 1.5Ethylbenzene <0.8 <0.00224 <0.0000012 1,000n-decane <2 <0.0056 <0.000003 2,500Naphthalene <0.8 <0.00224 <0.0000012 3Toluene 1.1 0.0031 0.000002 5,0001,3,5-trimethylbenzene <0.8 <0.00224 <0.0000012 61,2,4-trimethylbenzene <2 <0.0056 <0.000003 6VPHv <40 <0.112 <0.00006 1,000Xylenes <2 <0.0056 <0.000003 100Gasoline ListBenzene 1.9 0.01 0.000003 1.51,3-butadiene <0.8 <0.00224 <0.0000012 21,2-Dibromoethane <0.4 <0.00112 <0.0000006 11,2-dichloroethane <0.2 <0.00056 <0.0000003 0.4n-decane <2 <0.0056 <0.000003 2,500Ethylbenzene <0.8 <0.00224 <0.0000012 1,000n-hexane 11 0.03 0.00002 700Isopropylbenzene (cumene) <2 <0.0056 <0.000003 400Methylcyclohexane <2 <0.0056 <0.000003 3,000MTBE <8 <0.0224 <0.000012 3,000Naphthalene <0.8 <0.00224 <0.0000012 3Toluene 1.1 0.00 0.000002 5,0001,2,4-trimethylbenzene <2 <0.0056 <0.000003 61,3,5-trimethylbenzene <0.8 <0.00224 <0.0000012 6VPHv <40 <0.112 <0.00006 1,000Xylenes <2 <0.0056 <0.000003 100Isopropanol (tracer) <8 - - 116319

CSR PL/RL

Table 6 (1 of 1)Soil Vapour Analytical Results

Volatile Organic Hydrocarbons (VOCs), Volatile Petrolem Hydrocarbons (VPHV) and Naphthalene

7000 Scott Rd. Surrey BCScott Hill Development Project No. 11272-02

NOTES:Concentrations in micrograms per litre (µg/m3)

RDL Reported Detection LimitCSR Contaminated Sites Regulation, effective April 1, 1997

RL/PL Residential and Urban Park Land Use Standard* Reported as total µg

n/s No standard for this constituent< Less than reported detection limit

Bold Exceeds CSR (RL/PL) standard for this sample

Page 20: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

BOREHOLE LOGS

Page 21: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site
Page 22: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site
Page 23: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

MAXXAM LTD. ANALYTICAL REPORTS

Page 24: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Your Project #: 11272 Your C.O.C. #: K010186

Attention: Andrew LamKEYSTONE ENVIRONMENTAL LTDSUITE 3204400 DOMINION STREETBURNABY, BCCANADA V5G 4G3

Report Date: 2012/03/08

CERTIFICATE OF ANALYSIS

MAXXAM JOB #: B218427Received: 2012/03/05, 16:10

Sample Matrix: Water# Samples Received: 1

Date DateAnalyses Quantity Extracted Analyzed Laboratory Method Analytical MethodHardness (calculated as CaCO3) 1 N/A 2012/03/07 BBY7SOP-00002 Calculated ParameterNa, K, Ca, Mg, S by CRC ICPMS (diss.) 1 N/A 2012/03/07 BBY7SOP-00002 EPA 200.8 Elements by CRC ICPMS (dissolved) 1 N/A 2012/03/06 BBY7SOP-00002 EPA 6020A Filter and HNO3 Preserve for Metals 1 N/A 2012/03/06 BBY6WI-00001 EPA 200.2 CSR VH C6-C10 in Water by HS GC/MS 1 N/A 2012/03/07 BBY8SOP-00011 EPA 8260B Extra VOCs in Water by HS GC/MS 1 N/A 2012/03/06 BRN SOP 00302 R8.0 EPA 8260C VOCs in Water by HS GC/MS 1 2012/03/07 2012/03/07 BBY8-SOP-0009 EPA 8260C Volatile HC-BTEX 1 N/A 2012/03/08

* RPDs calculated using raw data. The rounding of final results may result in the apparent difference.* Results relate only to the items tested.

Encryption Key

Please direct all questions regarding this Certificate of Analysis to your Project Manager.

Jennifer Exter, Burnaby Project ManagerEmail: [email protected]# (604) 639-2627

====================================================================Maxxam has procedures in place to guard against improper use of the electronic signature and have the required "signatories", as per section5.10.2 of ISO/IEC 17025:2005(E), signing the reports. For Service Group specific validation please refer to the Validation Signature Page.

Total cover pages: 1

Maxxam Analytics International Corporation o/a Maxxam Analytics Burnaby: 4606 Canada Way V5G 1K5 Telephone(604) 734-7276 Fax(604) 731-2386

Page 1 of 10

Page 25: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218427 Client Project #: 11272Report Date: 2012/03/08

Sampler Initials: IKRESULTS OF CHEMICAL ANALYSES OF WATER

Maxxam ID CW4334Sampling Date 2012/03/05

Units MW12-1 RDL QC BatchCalculated ParametersFilter and HNO3 Preservation N/A LAB N/A 5653578

VOLATILE ORGANICS BY GC-MS (WATER)

Maxxam ID CW4334Sampling Date 2012/03/05

Units MW12-1 RDL QC BatchVolatiles2-Butanone (MEK) ug/L <10 10 56547874-Methyl-2-pentanone (MIBK) ug/L <10 10 5654787Surrogate Recovery (%)4-BROMOFLUOROBENZENE (sur.) % 100 5654787D4-1,2-DICHLOROETHANE (sur.) % 98 5654787

N/A = Not ApplicableRDL = Reportable Detection Limit

Page 2 of 10

Page 26: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218427 Client Project #: 11272Report Date: 2012/03/08

Sampler Initials: IKCSR DISSOLVED METALS IN WATER (WATER)

Maxxam ID CW4334Sampling Date 2012/03/05

Units MW12-1 RDL QC BatchMisc. InorganicsDissolved Hardness (CaCO3) mg/L 287 0.5 5649254Dissolved Metals by ICPMSDissolved Aluminum (Al) ug/L 9.8 3.0 5655366Dissolved Antimony (Sb) ug/L <0.50 0.50 5655366Dissolved Arsenic (As) ug/L 0.33 0.10 5655366Dissolved Barium (Ba) ug/L 41.8 1.0 5655366Dissolved Beryllium (Be) ug/L <0.10 0.10 5655366Dissolved Bismuth (Bi) ug/L <1.0 1.0 5655366Dissolved Boron (B) ug/L <50 50 5655366Dissolved Cadmium (Cd) ug/L 0.051 0.010 5655366Dissolved Chromium (Cr) ug/L <1.0 1.0 5655366Dissolved Cobalt (Co) ug/L 1.13 0.50 5655366Dissolved Copper (Cu) ug/L 1.17 0.20 5655366Dissolved Iron (Fe) ug/L <5.0 5.0 5655366Dissolved Lead (Pb) ug/L <0.20 0.20 5655366Dissolved Lithium (Li) ug/L 10.4 5.0 5655366Dissolved Manganese (Mn) ug/L 72.7 1.0 5655366Dissolved Mercury (Hg) ug/L <0.050 0.050 5655366Dissolved Molybdenum (Mo) ug/L <1.0 1.0 5655366Dissolved Nickel (Ni) ug/L 3.8 1.0 5655366Dissolved Selenium (Se) ug/L 0.78 0.10 5655366Dissolved Silicon (Si) ug/L 11400 100 5655366Dissolved Silver (Ag) ug/L <0.020 0.020 5655366Dissolved Strontium (Sr) ug/L 277 1.0 5655366Dissolved Thallium (Tl) ug/L <0.050 0.050 5655366Dissolved Tin (Sn) ug/L <5.0 5.0 5655366Dissolved Titanium (Ti) ug/L <5.0 5.0 5655366Dissolved Uranium (U) ug/L 0.37 0.10 5655366Dissolved Vanadium (V) ug/L <5.0 5.0 5655366Dissolved Zinc (Zn) ug/L <5.0 5.0 5655366Dissolved Zirconium (Zr) ug/L <0.50 0.50 5655366Dissolved Calcium (Ca) mg/L 41.5 0.050 5649255Dissolved Magnesium (Mg) mg/L 44.5 0.050 5649255Dissolved Potassium (K) mg/L 2.33 0.050 5649255Dissolved Sodium (Na) mg/L 18.6 0.050 5649255Dissolved Sulphur (S) mg/L 34.2 3.0 5649255

RDL = Reportable Detection Limit

Page 3 of 10

Page 27: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218427 Client Project #: 11272Report Date: 2012/03/08

Sampler Initials: IKCSR VOC + VPH IN WATER (WATER)

Maxxam ID CW4334Sampling Date 2012/03/05

Units MW12-1 RDL QC BatchVolatilesVPH (VHW6 to 10 - BTEX) ug/L <300 300 5649818Volatile HydrocarbonsVH C6-C10 ug/L <300 300 5658400VolatilesChloromethane ug/L <1.0 1.0 5658257Vinyl chloride ug/L <0.50 0.50 5658257Chloroethane ug/L <1.0 1.0 5658257Trichlorofluoromethane ug/L <4.0 4.0 56582571,1,2Trichloro-1,2,2Trifluoroethane ug/L <2.0 2.0 5658257Dichlorodifluoromethane ug/L <2.0 2.0 56582571,1-dichloroethene ug/L <0.50 0.50 5658257Dichloromethane ug/L <2.0 2.0 5658257trans-1,2-dichloroethene ug/L <1.0 1.0 56582571,1-dichloroethane ug/L <0.50 0.50 5658257cis-1,2-dichloroethene ug/L <1.0 1.0 5658257Chloroform ug/L <1.0 1.0 56582571,1,1-trichloroethane ug/L <0.50 0.50 56582571,2-dichloroethane ug/L <0.50 0.50 5658257Carbon tetrachloride ug/L <0.50 0.50 5658257Benzene ug/L <0.50 0.50 56582571,2-dichloropropane ug/L <0.50 0.50 5658257cis-1,3-dichloropropene ug/L <1.0 1.0 5658257trans-1,3-dichloropropene ug/L <1.0 1.0 5658257Bromomethane ug/L <1.0 1.0 56582571,1,2-trichloroethane ug/L <0.50 0.50 5658257Trichloroethene ug/L <0.50 0.50 5658257Chlorodibromomethane ug/L <1.0 1.0 56582571,2-dibromoethane ug/L <0.20 0.20 56582571,3-Butadiene ug/L <5.0 5.0 5658257Tetrachloroethene ug/L <0.50 0.50 5658257Bromodichloromethane ug/L <1.0 1.0 5658257Toluene ug/L <0.50 0.50 5658257Ethylbenzene ug/L <0.50 0.50 5658257m & p-Xylene ug/L <1.0 1.0 5658257Bromoform ug/L <1.0 1.0 5658257Styrene ug/L <0.50 0.50 5658257

RDL = Reportable Detection Limit

Page 4 of 10

Page 28: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218427 Client Project #: 11272Report Date: 2012/03/08

Sampler Initials: IKCSR VOC + VPH IN WATER (WATER)

Maxxam ID CW4334Sampling Date 2012/03/05

Units MW12-1 RDL QC Batcho-Xylene ug/L <0.50 0.50 5658257Xylenes (Total) ug/L <1.0 1.0 56582571,1,1,2-tetrachloroethane ug/L <0.50 0.50 56582571,1,2,2-tetrachloroethane ug/L <0.50 0.50 56582571,2-dichlorobenzene ug/L <0.50 0.50 56582571,3-dichlorobenzene ug/L <0.50 0.50 56582571,4-dichlorobenzene ug/L <0.50 0.50 5658257Chlorobenzene ug/L <0.50 0.50 5658257Dibromomethane ug/L <0.90 0.90 5658257Bromobenzene ug/L <2.0 2.0 5658257Surrogate Recovery (%)4-BROMOFLUOROBENZENE (sur.) % 85 5658257D4-1,2-DICHLOROETHANE (sur.) % 90 5658257

RDL = Reportable Detection Limit

Page 5 of 10

Page 29: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218427 Client Project #: 11272Report Date: 2012/03/08

Sampler Initials: IK

General Comments

Page 6 of 10

Page 30: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218427 Client Project #: 11272Report Date: 2012/03/08

Sampler Initials: IKQUALITY ASSURANCE REPORT

Spiked Blank Method Blank RPD QC StandardQC Batch Parameter Date % Recovery QC Limits Value Units Value (%) QC Limits % Recovery QC Limits5654787 4-BROMOFLUOROBENZENE (sur.) 2012/03/06 98 70 - 130 100 %5654787 D4-1,2-DICHLOROETHANE (sur.) 2012/03/06 95 70 - 130 99 %5654787 2-Butanone (MEK) 2012/03/06 87 70 - 130 <10 ug/L NC 405654787 4-Methyl-2-pentanone (MIBK) 2012/03/06 91 70 - 130 <10 ug/L NC 405655366 Dissolved Aluminum (Al) 2012/03/06 99 80 - 120 <3.0 ug/L NC 205655366 Dissolved Antimony (Sb) 2012/03/06 100 80 - 120 <0.50 ug/L NC 205655366 Dissolved Arsenic (As) 2012/03/06 98 80 - 120 <0.10 ug/L NC 205655366 Dissolved Barium (Ba) 2012/03/06 99 80 - 120 <1.0 ug/L 0.4 205655366 Dissolved Beryllium (Be) 2012/03/06 99 80 - 120 <0.10 ug/L NC 205655366 Dissolved Bismuth (Bi) 2012/03/06 97 80 - 120 <1.0 ug/L NC 205655366 Dissolved Cadmium (Cd) 2012/03/06 97 80 - 120 <0.010 ug/L NC (1) 205655366 Dissolved Chromium (Cr) 2012/03/06 99 80 - 120 <1.0 ug/L NC 205655366 Dissolved Cobalt (Co) 2012/03/06 98 80 - 120 <0.50 ug/L NC 205655366 Dissolved Copper (Cu) 2012/03/06 97 80 - 120 <0.20 ug/L NC 205655366 Dissolved Iron (Fe) 2012/03/06 101 80 - 120 <5.0 ug/L 2.9 205655366 Dissolved Lead (Pb) 2012/03/06 97 80 - 120 <0.20 ug/L NC 205655366 Dissolved Lithium (Li) 2012/03/06 101 80 - 120 <5.0 ug/L NC 205655366 Dissolved Manganese (Mn) 2012/03/06 94 80 - 120 <1.0 ug/L 2.4 205655366 Dissolved Mercury (Hg) 2012/03/06 97 80 - 120 <0.050 ug/L NC 205655366 Dissolved Molybdenum (Mo) 2012/03/06 93 80 - 120 <1.0 ug/L 0.5 205655366 Dissolved Nickel (Ni) 2012/03/06 100 80 - 120 <1.0 ug/L NC 205655366 Dissolved Selenium (Se) 2012/03/06 103 80 - 120 <0.10 ug/L 12.9 205655366 Dissolved Silver (Ag) 2012/03/06 98 80 - 120 <0.020 ug/L NC 205655366 Dissolved Strontium (Sr) 2012/03/06 102 80 - 120 <1.0 ug/L 1.5 205655366 Dissolved Thallium (Tl) 2012/03/06 102 80 - 120 <0.050 ug/L NC 205655366 Dissolved Tin (Sn) 2012/03/06 106 80 - 120 <5.0 ug/L NC 205655366 Dissolved Titanium (Ti) 2012/03/06 98 80 - 120 <5.0 ug/L NC 205655366 Dissolved Uranium (U) 2012/03/06 95 80 - 120 <0.10 ug/L 1.8 205655366 Dissolved Vanadium (V) 2012/03/06 96 80 - 120 <5.0 ug/L NC 205655366 Dissolved Zinc (Zn) 2012/03/06 103 80 - 120 <5.0 ug/L NC 205655366 Dissolved Boron (B) 2012/03/06 <50 ug/L NC 205655366 Dissolved Silicon (Si) 2012/03/06 <100 ug/L 0.2 205655366 Dissolved Zirconium (Zr) 2012/03/06 <0.50 ug/L NC 205658257 4-BROMOFLUOROBENZENE (sur.) 2012/03/07 93 70 - 130 85 %5658257 D4-1,2-DICHLOROETHANE (sur.) 2012/03/07 90 70 - 130 93 %5658257 Chloromethane 2012/03/07 98 60 - 140 <1.0 ug/L5658257 Vinyl chloride 2012/03/07 112 60 - 140 <0.50 ug/L5658257 Chloroethane 2012/03/07 97 60 - 140 <1.0 ug/L5658257 Trichlorofluoromethane 2012/03/07 115 60 - 140 <4.0 ug/L5658257 Dichlorodifluoromethane 2012/03/07 103 60 - 140 <2.0 ug/L

Page 7 of 10

Page 31: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218427 Client Project #: 11272Report Date: 2012/03/08

Sampler Initials: IKQUALITY ASSURANCE REPORT

Spiked Blank Method Blank RPD QC StandardQC Batch Parameter Date % Recovery QC Limits Value Units Value (%) QC Limits % Recovery QC Limits5658257 1,1-dichloroethene 2012/03/07 101 70 - 130 <0.50 ug/L5658257 Dichloromethane 2012/03/07 101 70 - 130 <2.0 ug/L5658257 trans-1,2-dichloroethene 2012/03/07 99 70 - 130 <1.0 ug/L5658257 1,1-dichloroethane 2012/03/07 100 70 - 130 <0.50 ug/L5658257 cis-1,2-dichloroethene 2012/03/07 98 70 - 130 <1.0 ug/L5658257 Chloroform 2012/03/07 98 70 - 130 <1.0 ug/L5658257 1,1,1-trichloroethane 2012/03/07 98 70 - 130 <0.50 ug/L5658257 1,2-dichloroethane 2012/03/07 94 70 - 130 <0.50 ug/L5658257 Carbon tetrachloride 2012/03/07 100 70 - 130 <0.50 ug/L5658257 Benzene 2012/03/07 101 70 - 130 <0.50 ug/L5658257 1,2-dichloropropane 2012/03/07 93 70 - 130 <0.50 ug/L5658257 cis-1,3-dichloropropene 2012/03/07 82 70 - 130 <1.0 ug/L5658257 trans-1,3-dichloropropene 2012/03/07 84 70 - 130 <1.0 ug/L5658257 Bromomethane 2012/03/07 90 60 - 140 <1.0 ug/L5658257 1,1,2-trichloroethane 2012/03/07 93 70 - 130 <0.50 ug/L5658257 Trichloroethene 2012/03/07 100 70 - 130 <0.50 ug/L5658257 Chlorodibromomethane 2012/03/07 93 70 - 130 <1.0 ug/L5658257 1,2-dibromoethane 2012/03/07 95 70 - 130 <0.20 ug/L5658257 Tetrachloroethene 2012/03/07 100 70 - 130 <0.50 ug/L5658257 Bromodichloromethane 2012/03/07 94 70 - 130 <1.0 ug/L5658257 Toluene 2012/03/07 99 70 - 130 <0.50 ug/L5658257 Ethylbenzene 2012/03/07 97 70 - 130 <0.50 ug/L5658257 m & p-Xylene 2012/03/07 101 70 - 130 <1.0 ug/L5658257 Bromoform 2012/03/07 94 70 - 130 <1.0 ug/L5658257 Styrene 2012/03/07 101 70 - 130 <0.50 ug/L5658257 o-Xylene 2012/03/07 98 70 - 130 <0.50 ug/L5658257 1,1,1,2-tetrachloroethane 2012/03/07 97 70 - 130 <0.50 ug/L5658257 1,1,2,2-tetrachloroethane 2012/03/07 99 70 - 130 <0.50 ug/L5658257 1,2-dichlorobenzene 2012/03/07 98 70 - 130 <0.50 ug/L5658257 1,3-dichlorobenzene 2012/03/07 101 70 - 130 <0.50 ug/L5658257 1,4-dichlorobenzene 2012/03/07 97 70 - 130 <0.50 ug/L5658257 Chlorobenzene 2012/03/07 96 70 - 130 <0.50 ug/L5658257 Dibromomethane 2012/03/07 91 70 - 130 <0.90 ug/L5658257 Bromobenzene 2012/03/07 99 70 - 130 <2.0 ug/L5658257 1,1,2Trichloro-1,2,2Trifluoroethane 2012/03/07 <2.0 ug/L5658257 1,3-Butadiene 2012/03/07 <5.0 ug/L

Page 8 of 10

Page 32: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218427 Client Project #: 11272Report Date: 2012/03/08

Sampler Initials: IKQUALITY ASSURANCE REPORT

Spiked Blank Method Blank RPD QC StandardQC Batch Parameter Date % Recovery QC Limits Value Units Value (%) QC Limits % Recovery QC Limits5658257 Xylenes (Total) 2012/03/07 <1.0 ug/L5658400 VH C6-C10 2012/03/07 <300 ug/L 110 70 - 130

N/A = Not ApplicableRPD = Relative Percent DifferenceDuplicate: Paired analysis of a separate portion of the same sample. Used to evaluate the variance in the measurement.QC Standard: A blank matrix to which a known amount of the analyte has been added. Used to evaluate analyte recovery.Spiked Blank: A blank matrix to which a known amount of the analyte has been added. Used to evaluate analyte recovery.Method Blank: A blank matrix containing all reagents used in the analytical procedure. Used to identify laboratory contamination.Surrogate: A pure or isotopically labeled compound whose behavior mirrors the analytes of interest. Used to evaluate extraction efficiency.NC (RPD): The RPD was not calculated. The level of analyte detected in the parent sample and its duplicate was not sufficiently significant to permit a reliable calculation.(1) - RDL raised due to sample matrix interference.

Page 9 of 10

Page 33: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Page 10 of 10

Page 34: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Your Project #: 11272 Site Location: 7000 SCOTT ROAD SURREY Your C.O.C. #: K000318

Attention: Andrew LamKEYSTONE ENVIRONMENTAL LTDSUITE 3204400 DOMINION STREETBURNABY, BCCANADA V5G 4G3

Report Date: 2012/03/08

CERTIFICATE OF ANALYSIS

MAXXAM JOB #: B218594Received: 2012/03/06, 09:09

Sample Matrix: Water# Samples Received: 1

Date DateAnalyses Quantity Extracted Analyzed Laboratory Method Analytical MethodExtrac. Pet HC when LEPH/HEPH required 1 2012/03/08 2012/03/08 BBY8SOP-00029 BCCSR Method 4 PAH in Water by GC/MS (SIM) 1 2012/03/08 2012/03/08 BBY8SOP-00021 EPA 8270D Total LMW, HMW, Total PAH Calc 1 N/A 2012/03/08 EPH less PAH in Water by GC/FID 1 N/A 2012/03/08

* RPDs calculated using raw data. The rounding of final results may result in the apparent difference.* Results relate only to the items tested.

Encryption Key

Please direct all questions regarding this Certificate of Analysis to your Project Manager.

Jennifer Exter, Burnaby Project ManagerEmail: [email protected]# (604) 639-2627

====================================================================Maxxam has procedures in place to guard against improper use of the electronic signature and have the required "signatories", as per section5.10.2 of ISO/IEC 17025:2005(E), signing the reports. For Service Group specific validation please refer to the Validation Signature Page.

Total cover pages: 1

Maxxam Analytics International Corporation o/a Maxxam Analytics Burnaby: 4606 Canada Way V5G 1K5 Telephone(604) 734-7276 Fax(604) 731-2386

Page 1 of 5

Page 35: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218594 Client Project #: 11272Report Date: 2012/03/08 Site Location: 7000 SCOTT ROAD SURREY

LEPH & HEPH FOR CSR IN WATER (WATER)

Maxxam ID CW5220Sampling Date 2012/03/05

Units MW12-1 RDL QC BatchPolycyclic AromaticsLow Molecular Weight PAH`s ug/L <0.50 0.50 5652958High Molecular Weight PAH`s ug/L <0.050 0.050 5652958Total PAH ug/L <0.50 0.50 5652958Naphthalene ug/L <0.050 0.050 56612232-Methylnaphthalene ug/L <0.050 0.050 5661223Quinoline ug/L <0.50 0.50 5661223Acenaphthylene ug/L <0.050 0.050 5661223Acenaphthene ug/L <0.050 0.050 5661223Fluorene ug/L <0.050 0.050 5661223Phenanthrene ug/L <0.050 0.050 5661223Anthracene ug/L <0.010 0.010 5661223Acridine ug/L <0.050 0.050 5661223Fluoranthene ug/L <0.020 0.020 5661223Pyrene ug/L <0.020 0.020 5661223Benzo(a)anthracene ug/L <0.010 0.010 5661223Chrysene ug/L <0.050 0.050 5661223Benzo(b&j)fluoranthene ug/L <0.050 0.050 5661223Benzo(k)fluoranthene ug/L <0.050 0.050 5661223Benzo(a)pyrene ug/L <0.0090 0.0090 5661223Indeno(1,2,3-cd)pyrene ug/L <0.050 0.050 5661223Dibenz(a,h)anthracene ug/L <0.050 0.050 5661223Benzo(g,h,i)perylene ug/L <0.050 0.050 5661223Surrogate Recovery (%)D10-ANTHRACENE (sur.) % 72 5661223D8-ACENAPHTHYLENE (sur.) % 69 5661223D8-NAPHTHALENE (sur.) % 67 5661223D9-Acridine % 63 5661223TERPHENYL-D14 (sur.) % 86 5661223Calculated ParametersLEPH (C10-C19 less PAH) mg/L <0.20 0.20 5653026HEPH (C19-C32 less PAH) mg/L <0.20 0.20 5653026Ext. Pet. HydrocarbonEPH (C10-C19) mg/L <0.20 0.20 5658631EPH (C19-C32) mg/L <0.20 0.20 5658631Surrogate Recovery (%)O-TERPHENYL (sur.) % 105 5658631

RDL = Reportable Detection Limit

Page 2 of 5

Page 36: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218594 Client Project #: 11272Report Date: 2012/03/08 Site Location: 7000 SCOTT ROAD SURREY

Package 1 3.3°CEach temperature is the average of up to three cooler temperatures taken at receipt

General Comments

Page 3 of 5

Page 37: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218594 Client Project #: 11272Report Date: 2012/03/08 Site Location: 7000 SCOTT ROAD SURREY

QUALITY ASSURANCE REPORT

Spiked Blank Method Blank RPDQC Batch Parameter Date % Recovery QC Limits Value Units Value (%) QC Limits5658631 O-TERPHENYL (sur.) 2012/03/07 114 50 - 130 111 %5658631 EPH (C10-C19) 2012/03/07 117 50 - 130 <0.20 mg/L NC 305658631 EPH (C19-C32) 2012/03/07 116 50 - 130 <0.20 mg/L NC 305661223 D10-ANTHRACENE (sur.) 2012/03/08 79 60 - 130 103 %5661223 D8-ACENAPHTHYLENE (sur.) 2012/03/08 73 50 - 130 100 %5661223 D8-NAPHTHALENE (sur.) 2012/03/08 69 50 - 130 107 %5661223 D9-Acridine 2012/03/08 74 50 - 130 96 %5661223 TERPHENYL-D14 (sur.) 2012/03/08 98 60 - 130 130 %5661223 Naphthalene 2012/03/08 84 50 - 130 <0.050 ug/L5661223 2-Methylnaphthalene 2012/03/08 81 50 - 130 <0.050 ug/L5661223 Quinoline 2012/03/08 118 50 - 130 <0.50 ug/L5661223 Acenaphthylene 2012/03/08 84 50 - 130 <0.050 ug/L5661223 Acenaphthene 2012/03/08 84 50 - 130 <0.050 ug/L5661223 Fluorene 2012/03/08 88 50 - 130 <0.050 ug/L5661223 Phenanthrene 2012/03/08 85 60 - 130 <0.050 ug/L5661223 Anthracene 2012/03/08 85 60 - 130 <0.010 ug/L5661223 Acridine 2012/03/08 81 50 - 130 <0.050 ug/L5661223 Fluoranthene 2012/03/08 91 60 - 130 <0.020 ug/L5661223 Pyrene 2012/03/08 91 60 - 130 <0.020 ug/L5661223 Benzo(a)anthracene 2012/03/08 90 60 - 130 <0.010 ug/L5661223 Chrysene 2012/03/08 88 60 - 130 <0.050 ug/L5661223 Benzo(b&j)fluoranthene 2012/03/08 87 60 - 130 <0.050 ug/L5661223 Benzo(k)fluoranthene 2012/03/08 85 60 - 130 <0.050 ug/L5661223 Benzo(a)pyrene 2012/03/08 87 60 - 130 <0.0090 ug/L5661223 Indeno(1,2,3-cd)pyrene 2012/03/08 85 60 - 130 <0.050 ug/L5661223 Dibenz(a,h)anthracene 2012/03/08 87 60 - 130 <0.050 ug/L5661223 Benzo(g,h,i)perylene 2012/03/08 87 60 - 130 <0.050 ug/L

N/A = Not ApplicableRPD = Relative Percent DifferenceSpiked Blank: A blank matrix to which a known amount of the analyte has been added. Used to evaluate analyte recovery.Method Blank: A blank matrix containing all reagents used in the analytical procedure. Used to identify laboratory contamination.Surrogate: A pure or isotopically labeled compound whose behavior mirrors the analytes of interest. Used to evaluate extraction efficiency.NC (RPD): The RPD was not calculated. The level of analyte detected in the parent sample and its duplicate was not sufficiently significant to permit a reliable calculation.

Page 4 of 5

Page 38: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Page 5 of 5

Page 39: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Your Project #: 11272 Your C.O.C. #: 25899520, 2589952001

Attention: Andrew LamKEYSTONE ENVIRONMENTAL LTDSUITE 3204400 DOMINION STREETBURNABY, BCCANADA V5G 4G3

Report Date: 2012/03/09This report supersedes all previous reports with the same Maxxam job number

CERTIFICATE OF ANALYSIS

MAXXAM JOB #: B218439Received: 2012/03/05, 16:20

Sample Matrix: Air# Samples Received: 1

Date DateAnalyses Quantity Extracted Analyzed Laboratory Method Analytical MethodPetroleum Hydrocarbon Analysis TD Tube 1 2012/03/06 2012/03/06 67-C-040 NIOSH 2549/EPA TO17 Petroleum Hydrocarbon Analysis TD Tube 1 2012/03/08 2012/03/08 67-C-040 NIOSH 2549/EPA TO17 Duration 1 N/A 2012/03/06 NA N A Flow Rate (L/min) 1 N/A 2012/03/06 Volatile Organic Compounds Plus 1 2012/03/05 2012/03/06 67-C-040 NIOSH 2549/ EPA TO17Volatile Organic Compounds Plus 1 2012/03/08 2012/03/08 67-C-040 NIOSH 2549/EPA TO17

* RPDs calculated using raw data. The rounding of final results may result in the apparent difference.* Results relate only to the items tested.

Encryption Key

Please direct all questions regarding this Certificate of Analysis to your Project Manager.

Jennifer Exter, Burnaby Project ManagerEmail: [email protected]# (604) 639-2627

====================================================================Maxxam has procedures in place to guard against improper use of the electronic signature and have the required "signatories", as per section5.10.2 of ISO/IEC 17025:2005(E), signing the reports. For Service Group specific validation please refer to the Validation Signature Page.

Total cover pages: 1

Maxxam Analytics International Corporation o/a Maxxam Analytics Burnaby: 4606 Canada Way V5G 1K5 Telephone(604) 734-7276 Fax(604) 731-2386

Page 1 of 11

Page 40: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218439 Client Project #: 11272Report Date: 2012/03/09

RESULTS OF CHEMICAL ANALYSES OF AIR

Maxxam ID CW4452Sampling Date 2012/03/05 15:00

Units SV12-1 RDL QC BatchField ParametersDuration min 177 N/A ONSITEFlow Rate L/min 0.075 N/A ONSITE

N/A = Not ApplicableRDL = Reportable Detection Limit

Page 2 of 11

Page 41: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218439 Client Project #: 11272Report Date: 2012/03/09

ORGANIC VAPOURS CALC'D (AIR)

Maxxam ID CW4452Sampling Date 2012/03/05 15:00

Units SV12-1 RDL QC BatchHydrocarbonsBenzene ug/m3 1.9 0.8 5653238Ethylbenzene ug/m3 <0.8 0.8 5653238Toluene ug/m3 1.1 0.8 5653238m & p-Xylene ug/m3 <2 2 5653238o-Xylene ug/m3 <2 2 5653238Xylenes (Total) ug/m3 <2 2 5653238Styrene ug/m3 <2 2 5653238n-Decane ug/m3 <2 2 5653238n-Hexane ug/m3 11 0.8 5653238C6-C13 Hydrocarbons (VHv) ug/m3 <40 40 5653238C6-C13 Hydrocarbons (VPHv) ug/m3 <40 40 56532381,2,3-Trimethylbenzene ug/m3 <0.8 0.8 56532381,2,4-trimethylbenzene ug/m3 <2 2 56532381,2-dibromoethane ug/m3 <0.4 0.4 56532381,2-dichloroethane ug/m3 <0.2 0.2 56532381,3,5-trimethylbenzene ug/m3 <0.8 0.8 56532381,3-Butadiene ug/m3 <0.8 0.8 5653238Isopropylbenzene ug/m3 <2 2 5653238Methylcyclohexane ug/m3 <2 2 5653238Methyl-tert-butylether (MTBE) ug/m3 <8 8 5653238Naphthalene ug/m3 <0.8 0.8 5653238Isopropanol ug/m3 <8 8 5653238VolatilesChlorobenzene ug/m3 3.6 0.8 56532391,3-dichlorobenzene ug/m3 <2 2 56532391,4-dichlorobenzene ug/m3 <2 2 56532391,1-dichloropropene ug/m3 <0.8 0.8 5653239cis-1,2-dichloroethene ug/m3 <0.8 0.8 56532391,2-dichlorobenzene ug/m3 <2 2 56532391,2,4-trichlorobenzene ug/m3 <0.8 0.8 56532391,2,3-trichlorobenzene ug/m3 <2 2 5653239Chloromethane ug/m3 <3 3 5653239Chloroform ug/m3 <0.3 0.3 56532391,1,1-trichloroethane ug/m3 <3 3 56532391,2-dichloropropane ug/m3 <0.2 0.2 5653239Vinyl chloride ug/m3 <2 2 5653239

RDL = Reportable Detection Limit

Page 3 of 11

Page 42: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218439 Client Project #: 11272Report Date: 2012/03/09

ORGANIC VAPOURS CALC'D (AIR)

Maxxam ID CW4452Sampling Date 2012/03/05 15:00

Units SV12-1 RDL QC Batchcis-1,3-dichloropropene ug/m3 <0.8 0.8 5653239trans-1,3-dichloropropene ug/m3 <0.8 0.8 56532391,1,2-trichloroethane ug/m3 <0.2 0.2 5653239Dibromochloromethane ug/m3 <0.8 0.8 56532391,1,2,2-tetrachloroethane ug/m3 <0.2 0.2 5653239Dichlorodifluoromethane ug/m3 <5 5 5653239Bromochloromethane ug/m3 <0.8 0.8 5653239Chloroethane ug/m3 <3 3 56532391,1-dichloroethene ug/m3 <0.8 0.8 5653239trans-1,2-dichloroethene ug/m3 <0.8 0.8 5653239Dichloromethane ug/m3 <5 5 5653239Tetrachloroethene ug/m3 7.1 0.8 5653239Trichloroethene ug/m3 <0.2 0.2 5653239Trichlorofluoromethane ug/m3 <2 2 56532391,1-dichloroethane ug/m3 <2 2 56532392-chlorotoluene ug/m3 <2 2 56532391,1,1,2-tetrachloroethane ug/m3 <0.2 0.2 56532391,2-dibromo-3-chloropropane ug/m3 <2 2 56532391,2,3-trichloropropane ug/m3 <0.8 0.8 56532391,3-dichloropropane ug/m3 <0.8 0.8 56532392,2-dichloropropane ug/m3 <4 4 5653239Bromobenzene ug/m3 <2 2 5653239Dibromomethane ug/m3 <2 2 5653239Hexachlorobutadiene ug/m3 <2 2 5653239n-Butylbenzene ug/m3 <2 2 5653239n-Propylbenzene ug/m3 <2 2 5653239p-Isopropyltoluene ug/m3 <2 2 5653239sec-Butylbenzene ug/m3 <2 2 5653239tert-Butylbenzene ug/m3 <2 2 56532394-chlorotoluene ug/m3 <2 2 56532392-Hexanone ug/m3 <8 8 56532394-Methyl-2-pentanone (MIBK) ug/m3 <8 8 56532392-Butanone (MEK) ug/m3 <8 8 5653239Carbon tetrachloride ug/m3 <0.4 0.4 5653239Bromodichloromethane ug/m3 <0.8 0.8 5653239Bromoform ug/m3 <2 2 5653239Bromomethane ug/m3 <6 6 5653239

RDL = Reportable Detection Limit

Page 4 of 11

Page 43: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218439 Client Project #: 11272Report Date: 2012/03/09

ORGANIC VAPOURS (AIR)

Maxxam ID CW4452Sampling Date 2012/03/05 15:00

Units SV12-1 RDL QC BatchHydrocarbonsBenzene ug 0.03 0.01 5661826Ethylbenzene ug <0.01 0.01 5661826Toluene ug 0.01 0.01 5661826m & p-Xylene ug <0.03 0.03 5661826o-Xylene ug <0.03 0.03 5661826Xylenes (Total) ug <0.03 0.03 5661826Styrene ug <0.02 0.02 5661826n-Decane ug <0.02 0.02 5661826n-Hexane ug 0.15 0.01 5661826C6-C13 Hydrocarbons (VHv) ug <0.5 0.5 5661826C6-C13 Hydrocarbons (VPHv) ug <0.5 0.5 56618261,2,3-Trimethylbenzene ug <0.01 0.01 56618261,2,4-trimethylbenzene ug <0.02 0.02 56618261,2-dibromoethane ug <0.005 0.005 56618261,2-dichloroethane ug <0.002 0.002 56618261,3,5-trimethylbenzene ug <0.01 0.01 56618261,3-Butadiene ug <0.01 0.01 5661826Isopropylbenzene ug <0.02 0.02 5661826Methylcyclohexane ug <0.02 0.02 5661826Methyl-tert-butylether (MTBE) ug <0.1 0.1 5661826Naphthalene ug <0.01 0.01 5661826Isopropanol ug <0.1 0.1 5661826VolatilesChlorobenzene ug 0.0480 0.0100 56620261,3-dichlorobenzene ug <0.0200 0.0200 56620261,4-dichlorobenzene ug <0.0200 0.0200 56620261,1-dichloropropene ug <0.0100 0.0100 5662026cis-1,2-dichloroethene ug <0.0100 0.0100 56620261,2-dichlorobenzene ug <0.0200 0.0200 56620261,2,4-trichlorobenzene ug <0.0100 0.0100 56620261,2,3-trichlorobenzene ug <0.0200 0.0200 5662026Chloromethane ug <0.0400 0.0400 5662026Chloroform ug <0.00400 0.00400 56620261,1,1-trichloroethane ug <0.0400 0.0400 56620261,2-dichloropropane ug <0.00200 0.00200 5662026Vinyl chloride ug <0.0200 0.0200 5662026

RDL = Reportable Detection Limit

Page 5 of 11

Page 44: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218439 Client Project #: 11272Report Date: 2012/03/09

ORGANIC VAPOURS (AIR)

Maxxam ID CW4452Sampling Date 2012/03/05 15:00

Units SV12-1 RDL QC Batchcis-1,3-dichloropropene ug <0.0100 0.0100 5662026trans-1,3-dichloropropene ug <0.0100 0.0100 56620261,1,2-trichloroethane ug <0.00200 0.00200 5662026Dibromochloromethane ug <0.0100 0.0100 56620261,1,2,2-tetrachloroethane ug <0.00200 0.00200 5662026Dichlorodifluoromethane ug <0.0600 0.0600 5662026Bromochloromethane ug <0.0100 0.0100 5662026Chloroethane ug <0.0400 0.0400 56620261,1-dichloroethene ug <0.0100 0.0100 5662026trans-1,2-dichloroethene ug <0.0100 0.0100 5662026Dichloromethane ug <0.0600 0.0600 5662026Tetrachloroethene ug 0.0940 0.0100 5662026Trichloroethene ug <0.00200 0.00200 5662026Trichlorofluoromethane ug <0.0300 0.0300 56620261,1-dichloroethane ug <0.0300 0.0300 56620262-chlorotoluene ug <0.0200 0.0200 56620261,1,1,2-tetrachloroethane ug <0.00200 0.00200 56620261,2-dibromo-3-chloropropane ug <0.0200 0.0200 56620261,2,3-trichloropropane ug <0.0100 0.0100 56620261,3-dichloropropane ug <0.0100 0.0100 56620262,2-dichloropropane ug <0.0500 0.0500 5662026Bromobenzene ug <0.0200 0.0200 5662026Dibromomethane ug <0.0200 0.0200 5662026Hexachlorobutadiene ug <0.0200 0.0200 5662026n-Butylbenzene ug <0.0200 0.0200 5662026n-Propylbenzene ug <0.0200 0.0200 5662026p-Isopropyltoluene ug <0.0200 0.0200 5662026sec-Butylbenzene ug <0.0200 0.0200 5662026tert-Butylbenzene ug <0.0200 0.0200 56620264-chlorotoluene ug <0.0200 0.0200 56620262-Hexanone ug <0.100 0.100 56620264-Methyl-2-pentanone (MIBK) ug <0.100 0.100 56620262-Butanone (MEK) ug <0.100 0.100 5662026Carbon tetrachloride ug <0.00500 0.00500 5662026Bromodichloromethane ug <0.0100 0.0100 5662026Bromoform ug <0.0200 0.0200 5662026Bromomethane ug <0.0800 0.0800 5662026

RDL = Reportable Detection Limit

Page 6 of 11

Page 45: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218439 Client Project #: 11272Report Date: 2012/03/09

General Comments

Page 7 of 11

Page 46: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218439 Client Project #: 11272Report Date: 2012/03/09

QUALITY ASSURANCE REPORT

Spiked Blank Method BlankQC Batch Parameter Date % Recovery QC Limits Value Units5661826 Benzene 2012/03/08 120 60 - 140 <0.01 ug5661826 Ethylbenzene 2012/03/08 101 60 - 140 <0.01 ug5661826 Toluene 2012/03/08 131 60 - 140 <0.01 ug5661826 m & p-Xylene 2012/03/08 137 60 - 140 <0.01 ug5661826 o-Xylene 2012/03/08 131 60 - 140 <0.01 ug5661826 Xylenes (Total) 2012/03/08 135 60 - 140 <0.03 ug5661826 Styrene 2012/03/08 109 60 - 140 <0.01 ug5661826 n-Decane 2012/03/08 104 60 - 140 <0.02 ug5661826 n-Hexane 2012/03/08 74 60 - 140 <0.01 ug5661826 1,2,3-Trimethylbenzene 2012/03/08 119 60 - 140 <0.01 ug5661826 1,2,4-trimethylbenzene 2012/03/08 109 60 - 140 <0.02 ug5661826 1,2-dibromoethane 2012/03/08 73 60 - 140 <0.005 ug5661826 1,2-dichloroethane 2012/03/08 123 60 - 140 <0.002 ug5661826 1,3,5-trimethylbenzene 2012/03/08 111 60 - 140 <0.01 ug5661826 Isopropylbenzene 2012/03/08 132 60 - 140 <0.02 ug5661826 Methylcyclohexane 2012/03/08 90 60 - 140 <0.02 ug5661826 Methyl-tert-butylether (MTBE) 2012/03/08 83 60 - 140 <0.1 ug5661826 Naphthalene 2012/03/08 88 60 - 140 <0.01 ug5661826 Isopropanol 2012/03/08 95 60 - 140 <0.1 ug5661826 C6-C13 Hydrocarbons (VHv) 2012/03/08 <0.5 ug5661826 C6-C13 Hydrocarbons (VPHv) 2012/03/08 <0.5 ug5661826 1,3-Butadiene 2012/03/08 <0.01 ug5662026 Chlorobenzene 2012/03/08 <0.0100 ug5662026 1,3-dichlorobenzene 2012/03/08 <0.0200 ug5662026 1,4-dichlorobenzene 2012/03/08 <0.0200 ug5662026 1,1-dichloropropene 2012/03/08 <0.0100 ug5662026 cis-1,2-dichloroethene 2012/03/08 <0.0100 ug5662026 1,2-dichlorobenzene 2012/03/08 <0.0200 ug5662026 1,2,4-trichlorobenzene 2012/03/08 <0.0100 ug5662026 1,2,3-trichlorobenzene 2012/03/08 <0.0200 ug5662026 Chloromethane 2012/03/08 <0.0400 ug5662026 Chloroform 2012/03/08 <0.00400 ug5662026 1,1,1-trichloroethane 2012/03/08 <0.0400 ug5662026 1,2-dichloropropane 2012/03/08 <0.00200 ug5662026 Vinyl chloride 2012/03/08 <0.0200 ug5662026 cis-1,3-dichloropropene 2012/03/08 <0.0100 ug5662026 trans-1,3-dichloropropene 2012/03/08 <0.0100 ug5662026 1,1,2-trichloroethane 2012/03/08 <0.00200 ug5662026 Dibromochloromethane 2012/03/08 <0.0100 ug5662026 1,1,2,2-tetrachloroethane 2012/03/08 <0.00200 ug

Page 8 of 11

Page 47: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTDMaxxam Job #: B218439 Client Project #: 11272Report Date: 2012/03/09

QUALITY ASSURANCE REPORT

Spiked Blank Method BlankQC Batch Parameter Date % Recovery QC Limits Value Units5662026 Dichlorodifluoromethane 2012/03/08 <0.0600 ug5662026 Bromochloromethane 2012/03/08 <0.0100 ug5662026 Chloroethane 2012/03/08 <0.0400 ug5662026 1,1-dichloroethene 2012/03/08 <0.0100 ug5662026 trans-1,2-dichloroethene 2012/03/08 <0.0100 ug5662026 Dichloromethane 2012/03/08 <0.0600 ug5662026 Tetrachloroethene 2012/03/08 <0.0100 ug5662026 Trichloroethene 2012/03/08 <0.00200 ug5662026 Trichlorofluoromethane 2012/03/08 <0.0300 ug5662026 1,1-dichloroethane 2012/03/08 <0.0300 ug5662026 2-chlorotoluene 2012/03/08 <0.0200 ug5662026 1,1,1,2-tetrachloroethane 2012/03/08 <0.00200 ug5662026 1,2-dibromo-3-chloropropane 2012/03/08 <0.0200 ug5662026 1,2,3-trichloropropane 2012/03/08 <0.0100 ug5662026 1,3-dichloropropane 2012/03/08 <0.0100 ug5662026 2,2-dichloropropane 2012/03/08 <0.0500 ug5662026 Bromobenzene 2012/03/08 <0.0200 ug5662026 Dibromomethane 2012/03/08 <0.0200 ug5662026 Hexachlorobutadiene 2012/03/08 <0.0200 ug5662026 n-Butylbenzene 2012/03/08 <0.0200 ug5662026 n-Propylbenzene 2012/03/08 <0.0200 ug5662026 p-Isopropyltoluene 2012/03/08 <0.0200 ug5662026 sec-Butylbenzene 2012/03/08 <0.0200 ug5662026 tert-Butylbenzene 2012/03/08 <0.0200 ug5662026 4-chlorotoluene 2012/03/08 <0.0200 ug5662026 2-Hexanone 2012/03/08 <0.100 ug5662026 4-Methyl-2-pentanone (MIBK) 2012/03/08 <0.100 ug5662026 2-Butanone (MEK) 2012/03/08 <0.100 ug5662026 Carbon tetrachloride 2012/03/08 <0.00500 ug5662026 Bromodichloromethane 2012/03/08 <0.0100 ug5662026 Bromoform 2012/03/08 <0.0200 ug5662026 Bromomethane 2012/03/08 <0.0800 ug

N/A = Not ApplicableSpiked Blank: A blank matrix to which a known amount of the analyte has been added. Used to evaluate analyte recovery.Method Blank: A blank matrix containing all reagents used in the analytical procedure. Used to identify laboratory contamination.

Page 9 of 11

Page 48: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Page 10 of 11

Page 49: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

Page 11 of 11

Page 50: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

KEYSTONE ENVIRONMENTAL LTD. GENERAL TERMS AND CONDITIONS FOR SERVICES

Page 51: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

1

KEYSTONE ENVIRONMENTAL LTD. GENERAL TERMS AND CONDITIONS FOR SERVICES

The terms and conditions set forth below govern all work or services requested by CLIENT as described and set forth in the Proposal of Keystone Environmental Ltd. ("Keystone") attached hereto, any Purchase Order issued by CLIENT or Agreement between Keystone and CLIENT. The provisions of said Proposal or Agreement govern the scope of services to be performed, including the time schedule, compensation, and any other special terms. The terms and conditions contained herein shall otherwise apply expressly stated to the contract or inconsistent with said Proposal or Agreement. 1. COMPENSATION Unless otherwise stated in Keystone's Proposal, CLIENT agrees to compensate Keystone in accordance

with Keystone's published rate schedules in effect on the date when the services are performed. Copies of the schedules currently in effect are attached hereto. Keystone's rate schedules are revised periodically; and Keystone will notify CLIENT of any such revisions and the effective date thereof which shall not be less than thirty (30) days after receipt of such notice. As to those services for which no schedule exists, Keystone shall be compensated on a time and materials basis as set forth in any change order executed pursuant to this Agreement.

2. PAYMENT

Unless otherwise agreed to in writing, invoices will be submitted monthly. Payment of invoices is due within thirty (30) days of receipt of the invoice. Invoices not paid within (30) days after date of receipt shall be deemed delinquent.

3. INDEPENDENT CONTRACTOR Keystone shall be an independent contractor and shall be fully independent in performing the services of

work and shall not act or hold themselves out as an agent, servant or employee of CLIENT. 4. KEYSTONE'S LIMITED WARRANTY The sole and exclusive warranty which Keystone makes with respect to the services to be provided in the

performance of the work is that they shall be performed in accordance with generally accepted professional practices and CLIENT's standards and specifications to the extent accepted by Keystone and shall be performed in a skillful manner.

In the event Keystone's performance of work, or any portion thereof, fails to conform with the above stated

limited warranty, Keystone shall, at its discretion and its expense, proceed expeditiously to reperform the nonconforming, or upon the mutual agreement of the parties, refund the amount of compensation paid to Keystone for such nonconforming work. In no event shall Keystone be required to bear the cost of gaining access in order to perform its warranty obligations.

5. CLIENT WARRANTY CLIENT warrants that: it will provide to Keystone all available information regarding the site, structures,

facilities, buildings, and land involved with the work and that such information shall be true and correct: it will provide all licences and permits required for the work; that all work which it performs shall be in accordance with generally accepted professional practices; and it has title to or will provide right of entry or access to all property necessary to perform the work.

6. INDEMNITY

a. Subject to the limitations of Section 7 below, Keystone agrees to indemnify, defend and hold harmless CLIENT (including its officers, directors, employees and agents) from and against any and all losses, damages, liabilities, claims, suits, and the costs and expenses incident thereto (including legal fees and reasonable costs of investigation) which any or all of them may hereafter incur, become responsible for or pay out as a result of death or bodily injuries to any person, destruction or damage to any property, private or public, contamination or adverse effects on the environment or any violation or alleged violation of governmental laws, regulations, or orders, to the extent caused by or arising out of: (i) Keystone's errors or omissions or (ii) negligence on the part of Keystone in performing services hereunder.

b. CLIENT agrees to indemnify and hold harmless Keystone (including its officers, directors, employees

and agents) from and against any and all losses, damages, liabilities, claims, suits and the costs and expenses incident thereto (including legal fees and reasonable costs of investigation) which any or all of them may hereafter incur, become responsible for or pay out as a result of death or bodily injuries to any person, destruction or damage to any property, private or public, contamination or adverse effects

Page 52: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

2

on the environment or any violation or alleged violation of governmental laws, regulations, or orders, caused by, or arising out of in whole or in part: (i) any negligence or willful misconduct of CLIENT, (ii) any breach of CLIENT of any warranties or other provisions hereunder, (iii) any condition including, but not limited to, contamination existing at the site, or (iv) contamination of other property arising or alleged to arise from or be related to the site provided, however, that such indemnification shall not apply to the extent any losses, damages, liabilities or expenses result from or arise out of: (i) any negligence or willful misconduct of Keystone; or(ii) any breach of Keystone of any warranties hereunder.

7. LIMITATION OF LIABILITY Keystone's total liability, whether arising from or based upon breach of warranty, breach of contract, tort,

including Keystone's negligence, strict liability, indemnity or any other cause of basis whatsoever, is expressly limited to the limits of Keystone's insurance coverage. This provision limiting Keystone's liability shall survive the termination, cancellation or expiration of any contract resulting from this Proposal and the completion of services thereunder. After three (3) years of completion of Keystone's services, any legal costs arising to defend third party claims made against Keystone in connection with the project defined in the Proposal or Agreement will be paid in full by the CLIENT.

8. INSURANCE Keystone, during performance of this Agreement, will at its own expense carry Worker's Compensation

Insurance within limits required by law; Comprehensive General Liability Insurance for bodily injury and for property damage; Professional Liability Insurance for errors omissions and negligence; and Comprehensive Automobile Liability Insurance for bodily injury and property damage. At CLIENT'S request, Keystone shall provide a Certificate of Insurance demonstrating Keystone's compliance with this section. Such Certificate of Insurance shall provide that said insurance shall not be cancelled or materially altered until at least ten (10) days after written notice to CLIENT.

9. CONFIDENTIALITY Each party shall retain as confidential all information and data furnished to it by the other party which relate

to the other party's technologies, formulae, procedures, processes, methods, trade secrets, ideas, improvements, inventions and/or computer programs, which are designated in writing by such other party as confidential at the time of transmission and are obtained or acquired by the receiving party in connection with work or services performed subject to this Proposal or Agreement, and shall not disclose such information to any third party.

However, nothing herein is meant to prevent nor shall it be interpreted as preventing either Keystone or

CLIENT from disclosing and/or using said information or data; (i) when the information or data is actually known to the receiving party before being obtained or derived from the transmitting party; or (ii) when the information or data is generally available to the public without the receiving party's fault; or (iii) where the information or data is obtained or acquired in good faith at any time by the receiving party from a third party who has the right to disclose such information or data; or (iv) where a written release is obtained by the receiving party from the transmitting party; or (v) as required by law.

10. PROTECTION OF INFORMATION Keystone specifically disclaims any warranties expressed or implied and does not make any representations

regarding whether any information associated with conducting the work, including the report, can be protected from disclosure in responses to a request by a federal, provincial or local government agency, or in response to discovery or other legal process during the course of any litigation involving Keystone or CLIENT. Should Keystone receive such request from a third party, it will immediately advise CLIENT.

11. FORCE MAJEURE Neither party shall be responsible or liable to the other for default or delay in the performance of any of its

obligations hereunder (other than the payment of money for services already rendered) caused in whole or in part by strikes or other labour difficulties or disputes; governmental orders or regulations; war, riot, fire, explosion; acts of God; acts of omissions of the other party; any other like causes; or any other unlike causes which are beyond the reasonable control of the respective party.

In the event of delay in performance due to any such cause, the time for completion will be extended by a

period of time reasonably necessary to overcome the effect of the delay. The party so prevented from complying shall within a reasonable time of its knowledge of the disability advise the other party of the effective cause, the performance suspended or affected and the anticipated length of time during which performance will be prevented or delayed and shall make all reasonable efforts to remove such disability as soon as possible, except for labour disputes, which shall be solely within said party's discretion. The party prevented from complying shall advise the other party when the cause of the delay or default has ended, the number of days which will be reasonably required to compensate for the period of suspension and the date

Page 53: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

3

when performance will be resumed. Any additional costs or expense accruing or arising from the delaying event shall be solely for the account of the CLIENT.

12. NOTICE Any notice, communication, or statement required or permitted to be given hereunder shall be in writing and

deemed to have been sufficiently given when delivered in person or sent by facsimile, wire, or certified mail, return receipt requested, postage prepaid, to the address of the party set forth below, or to such address for either party as the party may be written notice designate.

13. ASSIGNMENT/SUBCONTRACT Neither party hereto shall assign this Agreement or any part thereof or any interest therein without the prior

written approval of the other party hereto except as herein otherwise provided. Keystone shall not subcontract the performance of any work hereunder without the written approval of CLIENT. Subject to the foregoing limitation, the Agreement shall inure to the benefit of and be binding upon the successors and permitted assigns of the parties hereto.

14. ESTIMATES To the extent the work requires Keystone to prepare opinions of probable cost, for example, opinions of

probable cost for the cost of construction, such opinions shall be prepared in accordance with generally accepted engineering practice and procedure. However, Keystone has no control over construction costs, competitive bidding and market conditions, costs of financing, acquisition of land or rights-of-way and Keystone does not guarantee the accuracy of such opinion of probable cost as compared to actual costs or contractor's bid.

15. DELAYED AGREEMENTS AND OBLIGATIONS The performance by Keystone of its obligations under this Agreement depends upon the CLIENT performing

its obligations in a timely manner and cooperating with Keystone to the extent reasonably required for completion of the Work. Delays by CLIENT in providing information or approvals or performing its obligations set forth in this Agreement may result in an appropriate adjustment of contract price and schedule.

16. CONSTRUCTION PHASE To the extent the work is related to or shall be followed by construction work not performed by Keystone,

Keystone shall not be responsible during the construction phase for the construction means, methods, techniques, sequences or procedures of construction contractors, or the safety precautions and programs incident thereto, and shall not be responsible for the construction contractor's failure to perform the work in accordance with the contract documents. Keystone will not direct, supervise or control the work of the CLIENT'S contractors or the CLIENT'S subcontractors.

17. DOCUMENTATION, RECORDS, AUDIT Keystone when requested by CLIENT, shall provide CLIENT with copies of all documents relating to the

service(s) of work performed. Keystone shall retain true and correct records in connection with each service and/or work performed and all transactions related thereto and shall retain all such records for twelve (12) months after the end of the calendar year in which the last service pursuant to this Agreement was performed. CLIENT, at its expense and upon reasonable notice, may from time to time during the term of this Agreement, and at any time after the date the service(s) were performed up to twelve (12) months after the end of the calendar year in which the last service(s) were performed, audit all records of Keystone in connection with all costs and expenses which it was invoiced.

18. REPORTS, DOCUMENTS AND INFORMATION All field data, field notes, laboratory test data, calculations, estimates and other documents prepared by

Keystone in performance of the work shall remain the property of Keystone. If required as part of the work, Keystone shall prepare a written report addressing the items in the work plan including the test results. Such report shall be the property of CLIENT, Keystone shall be entitled to retain three (3) copies of such report for its internal use and reference.

All drawings and documents produces under the terms of this Agreement are the property of Keystone, and

cannot be used for any reason other than to bid and construct the project as described in the Proposal or Agreement.

19. LIMITED USE OF REPORT Any report prepared as part of the work will be prepared solely for the internal use of CLIENT. Unless

otherwise agreed by Keystone and CLIENT, parties agree that third parties are not to rely upon the report.

Page 54: March 13, 2012 15095 Royal Avenue - Chysik Project …...building was heated prior to the availability to natural gas. It is possible that heating oil could have been used at the Site

4

20. SAMPLE MANAGEMENT Ownership of all samples obtained by Keystone from the project site is maintained by the CLIENT. Keystone

will store such samples in a professional manner in a secure area for the period of time necessary to complete the project. Upon completion of the project, Keystone will return any unused samples or portions thereof to the CLIENT or at Keystone's option dispose of the samples in a lawful manner and bill the CLIENT for all costs related thereto. Keystone will normally store samples for thirty (30) days. Written notice will be given to the CLIENT before finally disposing of samples.

21. RECOGNITION OF RISK CLIENT recognized and accepts the work to be undertaken by Keystone may involve unknown conditions

and hazards. CLIENT further recognizes that environmental, geologic, hydrological, and geotechnical conditions can and may vary from those encountered by Keystone at the times and locations where it obtained data and information, and that limitations on available data results in some uncertainty with respect to the interpretation of these conditions, despite the use of due professional care by Keystone. CLIENT recognizes that the performance of services hereunder or the implementation of recommendations made by Keystone may unavoidably alter the existing site conditions and affect the environment in the area being studied.

22. DISPOSAL OF CONTAMINATED MATERIAL It is understood and agreed that Keystone is not, and has no responsibility as, a generator, operator or storer

of pre-existing hazardous substances or wastes found or identified at work sites. Keystone shall not directly or indirectly assume title to such hazardous or toxic substances and shall not be liable to third parties.

CLIENT will indemnify and hold harmless Keystone from and against all incurred losses, damages, costs

and expenses, including but not limited to attorneys' fees, arising or resulting from actions brought by third parties alleging or identifying Keystone as a generator, operator, storer or owner of pre-existing hazardous substances or wastes found or identified at work sites.

23. SUSPENSION OR TERMINATION In the event the work is terminated or suspended by CLIENT prior to the completion of the services

contemplated hereunder, Keystone shall be paid for: (i) the services rendered to the date of termination or suspension, (ii) the demobilization costs, and (iii) the costs incurred with respect to noncancelable commitments.

24. GOVERNING LAW This Agreement shall be governed by and interpreted pursuant to the laws of the Province of

British Columbia. 25. HEADINGS AND SEVERABILITY

Any heading preceding the text of sections hereof is inserted solely for convenience or reference and shall not constitute a part of the Agreement and shall not effect the meanings, context, effect or construction of the Agreement. Every part, term or provision of this Agreement is severable from others. Notwithstanding any possible future finding by duly constituted authority that a particular part, term or provision is invalid, void or unenforceable, this Agreement has been made with the clear intention that the validity and enforceability of the remaining parts, terms and provision shall not be affected thereby.

26. ENTIRE AGREEMENT The terms and conditions set forth herein constitute the entire Agreement and understanding or the parties

relating to the provision of work or services by Keystone to CLIENT, and merges and supersedes all prior agreements, commitments, representation, writings, and discussions between them and shall be incorporated in all work orders, purchase orders and authorization unless otherwise so stated therein. The terms and conditions may be amended only by written instrument signed by both parties.