Manufacturing Strategy – Lean Lot Sizing
Capacity Optimization with Lean Lot Sizing for high-volume assemblies
RT
SMT Run-rate = 0.375 mins per piece.
SMT Operations Run-rate
Consider a 20hrs run per day. Number of units produced at SMT = 20*60/0.375 = 3200 pcs
HLA Operations Run-rate
HLA Run-rate = 0.333 mins per piece.
Consider a 20hrs run per day. Number of units produced at HLA = 20*60/0.333 = 3600 pcs
Lean Lot Sizing to optimize capacity at ATE for assemblies
Average ATE capacity per day ~ 2400 pcs
SMT capacity per day = 3200HLA capacity per day = 3600
Lean Lot Size = 3000 (minimum)
When you feed 3000pcs per day into the ATE Testers, you ensure Full Efficiency is achieved at the ATE Test each day of the week.
Thank You
Negative Effects of non-optimized Manufacturing Line
Quality: Rush jobs on weeks with high-loading affecting quality of PWAs.
On-Time-Delivery (OTD): Uneven load-leveling means no shipment during some weeks and affects delivery commitments to customers.