History of MRP-II
y In 1960-80 manufacturing industry face a problem of material
ordering ,purchasing, delivery on basis of and labour timeneeded and customer demand.
y So EOQ and Inventory models where developed.
y Then the problem was of resource utilization for productionsystem based on sales and forecast.
y Solved by calculating raw material requirement and lead time,with some model which is MRP-1
y Future integration of MRP-1 with feedback came to be knownas closed loop MRP-1.
y When close loop MRP-I with computer based materialpurchasing and scheduling with other dep. is known as MRP-II.
y Then MRP-II integration leads to SCM and ERP.
8/7/2019 Manufacturing Resource Planning-II - Copy
3/18
MRP-II Evolution
EOQ
Closed Loop
MRP
MRP II
ERP
Planning Materials
Schedule MaterialsIncorporate Feedback
MRP
Schedule & Purchase
Materials Coordinate w/
Mfg Resources
Inventory manag.
8/7/2019 Manufacturing Resource Planning-II - Copy
4/18
MRP-II General Concept.
y MRP-II aims at coordination of entire manufacturingproduction process like material, finance and human resource.
y The goal of MRP-II is to provide all necessary data to all
managers as product flows through production line.
y
Definition given by APICS-:``Effective planning of allmanufacturing resources in a company.
y Its an incremental information integration business process
strategies that are implemented using hardware and modular
software applications linked to a central database that stores
and delivers business data and information.
y MRP-II is not a software but technique or tool.
y But software are available for inhouse and customize for
implementation of MRP-II.
8/7/2019 Manufacturing Resource Planning-II - Copy
5/18
Basic structure of MRP-II
8/7/2019 Manufacturing Resource Planning-II - Copy
6/18
Working of MRP-IIy MRP-II begins with MRP-1 and MPS.y MRP-1 allows inputs from sales, marketing to MRP-II. This
gives forecast of material.
y MRP-II makes MPS & breaks down the product as
preproduction line process.MRP allows for raw materialpurchase.
y MRP-II then develops a detail schedule for manufacturing as
per M/C tool and manpower capacity as material arrives.
y All the cost study related to product like M/C tool cost, labor
material cost and allied cost is given to finance dept. to process
it.
8/7/2019 Manufacturing Resource Planning-II - Copy
7/18
Inputs to MRP-IIy Business plan
y Aggregate planning.
y Bill of material.
y Master production schedule.
y
Capacity planning, and Actual capacity.y Inventories and orders.
y Purchasing management
y MRP-I
y Shop flour control (sfc)y Standard coasting.(COST CONTROL).
8/7/2019 Manufacturing Resource Planning-II - Copy
8/18
Aggregate production plan:-
y It is a planning for next 6-18 months in which production,
inventory and capacity are taken due care for planning .
y By varying inventories and manpower we can achieve monthly
targets. Cost study is also important so that our planning is feasible.
y It uses forecast,capacity,inventory files as input .
8/7/2019 Manufacturing Resource Planning-II - Copy
9/18
MASTER PRODUCTION SCHEDULE.(MPS)
y This is a macro level document which set a top level
priorities for what will be manufactured and when,
looking at the material and production cycle.
y
It takes in account the capacity and forecast to prepareit.
y It can be as long as aggregate production plan.
8/7/2019 Manufacturing Resource Planning-II - Copy
10/18
MATERIAL REQUIREMENT PLANNING.y Material needed for each workcentre inorder to meet the
production schedule.
y MRP is heart of a manufacturing control system.
y It uses information from BOM,forecast,inventory,purchase order.y MRP determines total gross requirements and compares against
current inventory and schedule.
8/7/2019 Manufacturing Resource Planning-II - Copy
11/18
CAPACITY REQUIREMENT PLANNING.y MRP does not consider capacity and often plans
production which is not possible.
y So CRP takes care of it and plans order from MRP
and release as per capacity to full fill the schedule.
y CRP consider many factors while planning like man
power,m/c tool , internal material handling time etc.
y
CRP compares the i/o and o/p for a work centre andcompare it with standard and control the workcentre.
8/7/2019 Manufacturing Resource Planning-II - Copy
12/18
SHOP FLOOR CONTROL
yThe sfc monitors all activities and communicates status informationon manufacturing orders and workcentre back to respective
managers.
y SFC determines what orders are released ,when and their routing,
when operation to be started and finished.
y It also maintain all paper work of order and reacts to changes in
schedule if priority changes.
y It also interacts with CRP component and provide i/o and o/p data
for capacity planning purpose.
8/7/2019 Manufacturing Resource Planning-II - Copy
13/18
PURCHASE ORDER AND RECEIVIVNG
y In order to reduce cost and to keep inventory at a minimum, this componentaccounts for delivery lead times, projected inventory and cost trends.
y MRP-I provides as input about inventory use and generates planned requisitions
for purchased parts.
y It mainly emphasis on reduction of inventory and more flow of parts.
y Purchase order and receiving's is an efficient time saving tool for creating andmaintaining purchase records and ensuring the quality accuracy and promptness
of delivers of purchased materials.
COSTINGy It is an effort to maintain profitability and to meet goals with some control .
y Depending on manufacturing product, various types of costing may required and
cost accounting control should accommodate other factors.
y The major costing elements include material labour and variable overheads.
8/7/2019 Manufacturing Resource Planning-II - Copy
14/18
Implementation of MRP-II
y Give basic knowledge of MRP-II to workers.
y Evaluation of BOM and routing process.
y Establish and implement a programme to bring all BOM and
routing documents to actual practice with an accuracy of99%.
y Document the cycle time for each step of routing to establish
actual capacity of plant.
y
Establish a relationship on and how all departmentscoordinate in your organization.
y Investigate available MRP-II package as per company need.
y Apply on a pilot location.
y
When results are positive spread it all over the company.
8/7/2019 Manufacturing Resource Planning-II - Copy
15/18
Benefits of MRP-IIy Better control over inventories.
y Improved scheduling.
y Better priority planning .
y For engineering and design
Improved design control
Better quality control
Accurate inventory record
y For finance and coasting
Improved cash flow through quicker deliveries.
Cash control decision can be taken.
8/7/2019 Manufacturing Resource Planning-II - Copy
16/18
COMPARISION BETWEEN MRP,MRP-II AND ERP
Consider MRP-I and MRP-II as tools and not softwarepackages.
8/7/2019 Manufacturing Resource Planning-II - Copy
17/18
Conclusiony MRP is a planning activity while MRP-II is a scheduling activity.y MRP is a push type of system while MRP-II is a pull type of
system.
y MRP-II is a management tool and not a software.
y MRP-II when run on paper based method in an industry itproduces a lot of mistakes so computers are used to avoid it.
y MRP-II works with data base management as one input.
y If new component comes then MRP-II will not work properly
because data is not available to produce a detail format of MRP-II.y For a dynamic system a MRP-II with CIM model is a best
combination.
8/7/2019 Manufacturing Resource Planning-II - Copy
18/18
THANKYOU.