Manufacturing Resource Planning -II

MANISH UTTAM

12MT07IND013

Page 2: Manish 13 mrp2

MRP II -- Manufacturing Resource Planning

• “A method for the effective planning of all resources of a manufacturing company”– Financial accounting incorporated– Sales– Operations Planning– Simulate capacity requirements of different possible

Master Production Schedules

Page 3: Manish 13 mrp2

The MRP II Hierarchy

Page 4: Manish 13 mrp2
Page 5: Manish 13 mrp2

Long-Range Planning• At the top of the hierarchy we have long-range

planning. • This involves three functions: resource planning,

aggregate planning, and forecasting.• The length of time horizon for long-range planning

ranges is around six months to five years. • The frequency for replanning varies from once per

month, to once per year, with two to four times per year being typical.

• The degree of detail is typically at the part family level.

Page 6: Manish 13 mrp2

Forecasting

• The forecasting function seeks to predict demands in the future.

• Long-range fore casting is important to determining the capacity, tooling, and personnel requirements.

• Short-term forecasting converts a long-range forecast of part families to short-term fore casts of individual end items.

• Both kinds of forecasts are input to-the intermediate-level function of demand management.

Page 7: Manish 13 mrp2

Resource planning

• Resource planning is process of determining capacity requirements over the long term.

• Decisions such as whether to build a new plant or to expand an existing one are part of the capacity planning function. .

• This information is fed as a parameter to the aggregate planning function.

Page 8: Manish 13 mrp2

Aggregate planning

• Aggregate planning is used to determine levels of production, staffing, inventory, overtime, and so on over the long term.

• The level of detail is typically by month and for part families. For instance, the aggregate planning function will determine whether we build up inventories in anticipation of increased demand (from the forecasting function), "chase" the demand by varying capacity using overtime, or do some combination of both.

• Optimization techniques such as linear programming are often used to assist the aggregate planning process.

Page 9: Manish 13 mrp2
Page 10: Manish 13 mrp2

Intermediate Planning

Included production planning functions:

• demand management

• rough-cut capacity planning

• master production scheduling

• material requirements planning

• capacity requirements planning

Page 11: Manish 13 mrp2

Demand management

• The process of converting the long-term aggregate forecast to a detailed forecast while tracking individual customer orders is the function of demand management.

• The output of the demand management module is a set of actual customer orders plus a forecast of anticipated orders.

• As time progresses, the anticipated orders should be "consumed" by actual orders.

Page 12: Manish 13 mrp2

Master production scheduling

• Master production scheduling takes the demand forecast along with the firm orders from the demand management module.

• Master production schedule contains an order quantity in each time bucket for every item with independent demand, for every planning date.

Page 13: Manish 13 mrp2

RCCP

• Rough-cut capacity planning (RCCP) is used to provide a quick capacity check of a few critical resources to ensure the feasibility of the master production schedule.

• Although more detailed than aggregate planning, RCCP is less detailed than capacity requirements planning (CRP), which is another tool for performing capacity checks after the MRP processing.

• RCCP makes use of a bill of resources for each end item on the MPS.

Page 14: Manish 13 mrp2
Page 15: Manish 13 mrp2

CRP

• Capacity requirements planning (CRP) provides a more detailed capacity check on MRP-generated production plans than RCCP.

. • In spite of its name, capacity requirements

planning does not generate finite capacity analysis. Instead, CRP performs what is called infinite forward loading.

Page 16: Manish 13 mrp2

Short-Term Control

• The plans generated in the long- and intermediate-term planning functions are implemented in the short-term control modules, of job release, job dispatching, and in put/output control.

Page 17: Manish 13 mrp2

Job release

• Job release converts planned order releases to scheduled receipts.

• One of the important functions of job release is allocation.

• When there are several high-level items that use the same lower-level part, a conflict can arise when there is an insufficient quantity on hand. By allocating parts to one job or another, the job release function can rationalize these conflicts.

Page 18: Manish 13 mrp2

Job Dispatching

The basic idea behind job dispatching is simple: Develop a rule for arranging the queue in front of each workstation that will maintain due date integrity while keeping machine utilization high and manufacturing times low. Many rules have been proposed for doing this.

Page 19: Manish 13 mrp2

Input/Output Control

• 1. Monitor the WIP level in each process center.• 2. If the WIP goes above a certain level, then

the current release rate is too high, so reduce it.• 3. If it goes below a specified lower level, then

the current release rate is too low, so increase it.• 4. If it stays between these control levels, the

release rate is correct for the current conditions.

Page 20: Manish 13 mrp2

Changes to Business Practices

Page 21: Manish 13 mrp2
Page 22: Manish 13 mrp2
Page 23: Manish 13 mrp2

THANK YOU