Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
PCBs: Public Pools:
Keeping Kids Swimming
Presented by: Ileen Gladstone, P.E., LSP, LEED AP Vice President & Senior Practice Leader
Where are PCBs Found?
• Need to know prior to pool maintenance,
renovations, or replacement.
• Caulk in pool expansion joints, concrete
decking expansion joints, and surrounding
auxiliary structures.
• Paint used to coat pool surfaces.
• Mastic-like materials behind pool gutters.
• Adjacent concrete.
• Soils.
Potential Exposure Pathways
• Direct contact with decking materials.
• Direct contact with pool materials.
• Pool water.
• Construction workers during
maintenance, renovation, or
replacement.
TSCA Compliance
• Prohibition of the use of PCB products at levels > 50 ppm, as
well as the building materials that those products have
contaminated.
• Testing not required, but if PCB concentrations are detected in
the materials above the regulatory limit, then the regulations
require the removal and proper disposal of those materials.
• Once removal is initiated, PCBs must be cleaned up to less than
1 ppm in the remaining materials, unless a deed restriction is
placed on the property.
• PCB-remediation waste is managed at its "as-found" PCB
concentration and it is characterized based on in situ sampling
rather than post-excavation or demolition composite samples
collected from waste piles and roll-off containers.
Disposal
• Waste PCBs > 50 ppm disposed of at a TSCA-permitted PCB
disposal facility or a federally-permitted hazardous waste landfill
in accordance with TSCA manifesting, reporting, and record
keeping requirements.
• Waste with PCBs < 50 ppm PCBs may be disposed of at TSCA-
permitted facility, a hazardous waste landfill, a permitted state-
municipal solid waste landfill or a state non-municipal non-
hazardous waste landfill.
• Unless it is assumed that all materials have concentrations of
PCBs greater than 50 ppm, TSCA provides for a very intensive
and prescriptive testing program to ensure that wastes
containing greater than 50 ppm do not end up in a solid waste
landfill.
Maintenance, Renovation, or
Replacement
• PCB remediation affects the schedule, planning, and
costs.
• Needs to be coordinated with the Capital
Improvement Program; often done prior to renovation
or reconstruction of the pools or integrated into
design package.
• General contractors for pool construction are typically
not experienced, equipped, or trained to conduct the
remediation; therefore, it may need to be performed
by a specialty contractor.
Maintenance, Renovation, or
Replacement
• The in situ characterization and cleanup plan
approval process can take months, which must be
factored into a total project schedule.
• Conducting characterization in the fall, once the
swimming season has ended in temperate climates,
will likely provide sufficient time for a spring
construction project.
• Once PCBs greater than 50 ppm are discovered at a
pool, the EPA may not allow its use until remediation;
therefore, conducting characterization in the late
winter or spring may result in closure of a pool over
the summer season.
Case Studies
• Shine Memorial Pool, Worcester
• Senator Casey Memorial Pool, Milford
• Allied Veterans Memorial Pool, Everett
Shine Memorial Pool
• Self-Implementing Cleanup Plan with a deviation for
verification sampling frequency.
• Remediated main and tot swimming pools and
decking surrounding pools prior to demolition.
• Remediated soil behind gutters and beneath decking
expansion joints.
• Re-graded the Site and constructed a zero-entry pool
and surrounding decking.
• Encapsulated impacted portions of pavilion and filter
building walls.
Shine Memorial Pool Pool Remediation
• Removal of: • Paint coating the pools;
• Gutters and a portion of the
pool walls from beneath the
gutters;
• Concrete adjacent to the
main pool expansion joints;
and
• The water seal behind the
main pool expansion joints.
• Dust Monitoring at Site
Perimeter.
Shine Memorial Pool Deck and Soil Remediation
• Removal of decking
adjacent to the pool
gutters and decking
expansion joints.
• Excavation of the PCB-
contaminated soil beneath
the decking expansion
joints and behind the pool
gutters
• PCB containing waste
paint chips disposed of on
Site along with the
comingled soil.
• Dust Monitoring.
Shine Memorial Pool Encapsulation and Post Remediation
• Coating the lower portions of
walls of the pavilion and the
filter building.
• Collecting soil, concrete, and
wipe verification samples.
• Dust monitoring at the
perimeter of the Site.
• Deed restriction.
• Long-term Monitoring Plan.
Coated Portion of Wall
Shine Memorial Pool Remediation Waste
• 137 tons of PCB-impacted material
(concrete, soil, and stainless steel
gutter) > 50 ppm PCBs disposed at a
hazardous waste landfill.
• 17 tons of concrete and 26 tons of paint
chip-impacted soil < 50 ppm PCBs were
disposed of at a non-municipal solid
waste facility.
Senator Casey Memorial Pool
• Self-Implementing Cleanup Plan
approved, completed as Risk-Based
Cleanup.
• Remediated main and tot swimming
pools and concrete decking.
• Two-phase cleanup, including Interim
Remedial Measure.
Senator Casey Memorial Pool Initial Remediation
• Removed paint from the surfaces of the main and tot pools.
• Removed caulk from the main pool and decking expansion
joints.
• Removed approximately 1.5 inches of concrete from both sides
of the main pool expansion joints to a depth of 1.5 inches.
• Pools were re-painted and the expansion joints were
reconstructed.
• PCB -impacted concrete in the main and tot pools remained,
and soil beneath the decking expansion joints were impacted
with PCBs from the caulk.
• Impacted concrete and soil could not be remediated before the
summer swimming season.
Senator Casey Memorial Pool Interim Remedial Measures
• To open the pool for the summer season,
EPA required implementation of an Interim
Measure.
• Goal: Eliminate the potential exposure
pathway to PCBs on accessible surfaces.
• Coating the main and tot pool surfaces.
• Collecting wipe samples from the coated
surfaces.
• Collecting two rounds of pool water samples.
Senator Casey Memorial Pool Final Remediation
• Concrete decking adjacent
to expansion joints.
• Concrete decking adjacent
to the pool gutters.
• Grout between the gutters
and the pool walls.
• Stainless steel gutters.
• The tot pool shell.
• The tot pool railing.
• Soil from beneath the
decking expansion joints
and from behind the
gutters.
Senator Casey Memorial Pool Final Remediation
• Collected soil and concrete verification samples.
• Performed dust monitoring at Site perimeter during remediation.
• Contractor unsuccessfully attempted to remove paint and
underlying PCB-impacted concrete from the main pool.
• Remediation strategy changed to meet the schedule for
reconstructing and opening the pool in time for the summer
2010 swimming season.
• Constructed new pool shell over the existing pool shell, thereby
encapsulating the existing PCB-impacted concrete shell with a
new concrete shell ranging in thickness from 6 to 8 inches.
• Deed restriction required.
Allied Veterans Memorial Pool
• Risk-Based Cleanup Plan.
• Pools, decking, and bath house
constructed in the late 1960s.
• Additional decking areas were
constructed in 2000 and 2008.
• PCBs present in caulking, concrete, and
paint.
• Utility tunnel surrounds the pool.
Allied Veterans Memorial Pool Risk-Based Cleanup Plan
• Underlying PCB-contaminated paint is classified as “excluded product.”
• Remove and replace caulking in the main pool and original decking
expansion joints.
• Coat the interior surfaces of the expansion joints prior to installing the
new caulking.
• Caulking removed from the decking expansion joints will be disposed of
as a greater than 50 ppm PCB-bulk product.
• Coat concrete adjacent to the original decking expansion joints.
• Coat the lower portion of the bath house wall.
• Maintain existing cap, which consists of decking and caulking, over soil.
• Perform long-term monitoring and maintenance of the coating and cap.
• Record a deed restriction.
PCBs: Public Pools:
Keeping Kids Swimming
Presented by: Ileen Gladstone, P.E., LSP, LEED AP Vice President & Senior Practice Leader
PCBs: Public Pools:
Keeping Kids Swimming
Presented by: Ileen Gladstone, P.E., LSP, LEED AP Vice President & Senior Practice Leader