    Managing

    Projects

    Project ManagementSoftware - Scheduling

    University of Sunderland - Managing Projects Lecturer: Annmarie Dookie

  • 8/15/2019 Managing Projects.pptx

    2/48

    PCs and Project Management Software

     The computer is now an integral part of the

    project manager’s information and control

    system.

    Software is used by managers to lan andcontrol projects.

     There is now complete acceptance of project

    management software to help project teamswith their tasks.

    Project management software cannot

    control or manage the project on its own.

  • 8/15/2019 Managing Projects.pptx

    3/48

    Project Management SoftwareProject Management Software is a term

    covering many types of software including!

    Scheduling " process of deciding how to commitresources between a variety of possible tasks.

    Cost control and #udget management

    $esource %llocation " assign the availableresources in an economical way.

    Collaboration Software " designed to help

    people involved in a common task achieve theirgoals.

    Communication and &uality Management

    'ocumentation or administration systems

    which are used to deal with the comple(ity of

  • 8/15/2019 Managing Projects.pptx

    4/48

    Project Management Software Tools

    % Project Management Tool )MSProject* should help accomplish thefollowing tasks!

     Track all the information you gatherabout the work duration costs andresource re+uirements for your

    project.,isuali-e and present your project

    plan in standard well"denedformats.

    Schedule tasks and resources

  • 8/15/2019 Managing Projects.pptx

    5/48

    Project Management Software Tools

    0(change project information withother Microsoft 12ce System

    applications.Communicate with resources and

    other stakeholders while you the

    project manager retain ultimatecontrol of the project.

    Manage projects using a program

    that looks and feels like other

  • 8/15/2019 Managing Projects.pptx

    6/48

    Scheduling

    1ne of the most common tasks

    is to schedule a series of events

    and the comple(ity of this taskcan vary considerably depending

    on how the tool is used.

  • 8/15/2019 Managing Projects.pptx

    7/48

    Some common challenges include!

    0vents which depend on one another in

    di/erent ways or dependencies

    Scheduling people to work on and resources

    re+uired by the various tasks commonly

    termed resource scheduling

    'ealing with uncertainties in the estimates of

    the duration of each task.%rranging tasks to meet various deadlines.

     3uggling multiple projects simultaneously to

    meet a variety of re+uirements.

    Scheduling

  • 8/15/2019 Managing Projects.pptx

    8/48

    Critical Path

    4n many comple( schedules therewill be a critical ath or series ofevents that depend on each otherand whose durations directlydetermine the length of the wholeproject.

     The Critical Path is the longestpath of planned activities to theend of the project.

  • 8/15/2019 Managing Projects.pptx

    9/48

    Critical Path Method

     The !ritical Path Method)CPM* calculates the longest

    path of planned activities to theend of the project and theearliest and latest that each

    activity can start and nishwithout making the projectlonger.

  • 8/15/2019 Managing Projects.pptx

    10/48

    Providing 4nformationProject planning software needs to provide a lot

    of information to various people to justify thetime spent using it. Typical re+uirements mightinclude!

     Tasks lists for people and allocationschedules for resources

    4nformation on how long tasks will take tocomplete

    0arly warning of any risks to the project

    4nformation on workload for planningholidays

    5istorical information on how projects havero ressed and in articular how actual and

  • 8/15/2019 Managing Projects.pptx

    11/48

    Criticisms of Project ManagementSoftware

    May not be derived from a soundproject management method. 0.g.displaying the "antt !hart view by

    default encourages users to focus ontask scheduling too early rather thanidentifying objectives and deliverables.

    Similar to PowerPoint project

    management software might shieldthe manager from importantinterpersonal contact.

  • 8/15/2019 Managing Projects.pptx

    12/48

    1/er complicated features to meet the needsof project management professionals whichmust be understood in order to e/ectively usethe product. Comple( task prioriti-ation andresource leveling algorithms can produceresults that make no intuitive sense and overallocation is often more simply resolvedmanually.

    Some people may achieve better results usingsimpler techni+ue )e.g. pen and paper* yetfeel pressured into using project managementsoftware by company policy.

    Criticisms of Project ManagementSoftware

  • 8/15/2019 Managing Projects.pptx

    13/48

    6hen there are multiple largerprojects project management

    software can be very useful.7evertheless one should probablydetermine whether using project

    management software for a singlesmall project is worthwhile .

    Criticisms of Project ManagementSoftware

  • 8/15/2019 Managing Projects.pptx

    14/48

    Microsoft ProjectMicrosoft Project is a project

    management software program which isdesigned to assist project managers indeveloping lans assigning resources totasks tracking rogress# managing$udgets and analy-ing workloads.

    Microsoft %&ce Project Server 

    leverages 6indows SharePoint Services asits foundation and utili-es both a we$interface and Microsoft Project as theclient application.

  • 8/15/2019 Managing Projects.pptx

    15/48

  • 8/15/2019 Managing Projects.pptx

    16/48

  • 8/15/2019 Managing Projects.pptx

    17/48

    Set Project Start 'ate

    •  Click on 8Project’ from the Menu bar andselect 8Project 4nformation’

  • 8/15/2019 Managing Projects.pptx

    18/48

    Set Project Start 'ate 9 ,ersion :;

  • 8/15/2019 Managing Projects.pptx

    19/48

    Set Project Start 'ate

    •  4n the 8Project 4nformation’ dialog enterthe start date as indicate.

  • 8/15/2019 Managing Projects.pptx

    20/48

    Change 6orking Time

     Click on 8Tools’ from the Menu bar andselect 8Change 6orking Time’

  • 8/15/2019 Managing Projects.pptx

    21/48

    Change 6orking Time 9 ,ersion :;

  • 8/15/2019 Managing Projects.pptx

    22/48

    Change 6orking Time

    •  4n the 8Change 6orking Time’ dialoghighlight Saturdays and Sundays andselect 8non"working’ for a ve"day workweek

  • 8/15/2019 Managing Projects.pptx

    23/48

    0nter Project Properties

    •  Click on 8=ile’ from the Menu bar andselect 8Properties’

  • 8/15/2019 Managing Projects.pptx

    24/48

      9:;4nfo?@ then Click>Project 4nformation? and select >%dvanced Properties?

  • 8/15/2019 Managing Projects.pptx

    25/48

    0nter Project Properties

    •  4n the 8Properties’ dialog enter theproject Title Subject %uthor etc.

  • 8/15/2019 Managing Projects.pptx

    26/48

    Creating a task list

    •  0nter Tasks as indicated.

  • 8/15/2019 Managing Projects.pptx

    27/48

    'uration and Predecessor 4nformation

      Duration and Predecessorinformation is entered in the Columns asindicated to indicate se'uencing ofactivities.

  • 8/15/2019 Managing Projects.pptx

    28/48

    1rgani-ing Tasks into Phases

    (o-down lanning identies majorphases or products of the project beforelling in the tasks re+uired to completethose phases.

    )ottom-u lanning identies asmany of the bottom level detailed tasks

    as possible before organi-ing them intological groups called phases orsummary tasks. This approach worksfrom specic to general.

  • 8/15/2019 Managing Projects.pptx

    29/48

    Ainking Tasks•  Select the tasks to be linked and click onthe link tasks button as shown.

  • 8/15/2019 Managing Projects.pptx

    30/48

    1rgani-ing Tasks into Phases•

       To create a 8summary task’ select theactivities and click the *ndent button asshown.

  • 8/15/2019 Managing Projects.pptx

    31/48

    7etwork 'iagram ,iew

    •  Click on 8,iew’ from the Menu bar andselect 87etwork 'iagram’

  • 8/15/2019 Managing Projects.pptx

    32/48

    7etwork 'iagram ,iew

    •  Click on 8,iew’ from the Menu bar and select 87etwork

    'iagram’

  • 8/15/2019 Managing Projects.pptx

    33/48

    7etwork 'iagram ,iew•   The 7etwork 'iagram is shown asindicated from where you -oom in andout as necessary

  • 8/15/2019 Managing Projects.pptx

    34/48

    %ssigning $esources in MS Project

    Bo to $esources Sheet 9 Select 8,iew’ andclick on 8$esource Sheet’@ enter resources asshown.

  • 8/15/2019 Managing Projects.pptx

    35/48

    %ssigning $esources in MS Project To assign resources to a Task in the $esource column double"click the

    relevant activity )task*. The Task 4nformation dialog is shown.Select the $esources tab and enter the resources

  • 8/15/2019 Managing Projects.pptx

    36/48

    %ssigning $esources in MS Project

     The $esources will be displayed against therelevant activity as shown.

  • 8/15/2019 Managing Projects.pptx

    37/48

    %djusting Print ,iew on page

    'ouble"click the Timescale bar as shown

  • 8/15/2019 Managing Projects.pptx

    38/48

    %djusting Print ,iew on page

    Click the 8Middle Tier’ and 8#ottom Tier’ tab toadjust accordingly to compress the bars.

  • 8/15/2019 Managing Projects.pptx

    39/48

    Bantt Charts

    • Bantt Charts are another tool for creatingproject network. 4t established a time"phasednetwork which links project activities to aproject schedule baseline.

    • Some benets are!• 0asy to read and comprehend• 4dentify the project network coupled with

    its schedule baseline•

    %llow for updaing and project control• seful for identifying resource needs and

    assignments• 0asy to create

    $ead Chapter

  • 8/15/2019 Managing Projects.pptx

    40/48

    Microsoft ,isioMicrosoft +isio is diagramming software

    for Microsoft 6indows.

    Microsoft +isio provides a wide range of

    templates E business process Fowchartsnetwork diagrams workFow diagramsdatabase models and softwarediagrams E you can use to visuali-e and

    streamline business processes trackprojects and resources chartorgani-ations map networks diagrambuilding sites and optimi-e systems.

  • 8/15/2019 Managing Projects.pptx

    41/48

    Microsoft ,isio

    Select the Pert Chart Template asindicated to begin drawing your7etwork 'iagram

  • 8/15/2019 Managing Projects.pptx

    42/48

    Microsoft ,isio

    % new 'rawing Page is displayed asshown with the tools located to theleft.

  • 8/15/2019 Managing Projects.pptx

    43/48

    'rag and drop the nodes on the pageto begin drawing the 7etwork 'iagram

    Microsoft ,isio

  • 8/15/2019 Managing Projects.pptx

    44/48

    Microsoft ,isio

    'rag and drop the connectors to link thenodes.

  • 8/15/2019 Managing Projects.pptx

    45/48

    Microsoft ,isio

    7ote you should rst have yourdiagram completed )sketched* beforetransferring to ,isio in order to get thebest layout the nodes.

  • 8/15/2019 Managing Projects.pptx

    46/48

    Microsoft ,isio

     To begin inputting data select therelevant node to enter the 8Task 7ame’as shown )7ote the green border*

  • 8/15/2019 Managing Projects.pptx

    47/48

     To input the data in the other sections of the nodeselect the relevant section to enter the informatione.g. 80arly Start’ )7ote the grey border*

    Continue selecting the other sections to complete

    the information as re+uired and do the same for allnodes.

    Microsoft ,isio

  • 8/15/2019 Managing Projects.pptx

    48/48

    ,uestions