Managing Project Resources 1227191402446602 9

Embed Size (px)

Citation preview

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    1/38

    MANAGING PROJECT RESOURCES

    PRESENTED BY

    Toyin Osunlaja

    Gozde Kilinc

    And

    Ercin Sen

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    2/38

    OBJECTIVES

    After this presentation you will be able to:

    Understand what resources are, and the types

    of resources that are typically available

    Appreciate the importance of managing

    project resources, and their effect on the

    project duration

    Apply project resource management tools and

    techniques for managing project time.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    3/38

    What are Resources?

    Resources are commonly thought of as sources

    of supply or support, such as money, people,

    materials, technology, and space. For

    information system projects, more specific

    resources may include system developers,

    project managers, system analysts,

    stakeholders, development environments andinformation.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    4/38

    Types of Resources

    There are two primary types of resources used

    in information system projects namely:

    Human Resources

    Capital Resources

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    5/38

    Human Resources

    Human resources :is personnel pool available to

    an organization. The most important

    resources in any organization its human

    resources. Appropriate human resources

    assure an organization that the right number

    and kind of people are available at the right

    time and place so that organizational needscan be met.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    6/38

    Human Resources (Cont)

    Human Resources include all project

    stakeholders, such as customers, project team

    members, support staff, project suppliers and

    end users. In Information Technology, human

    resources consist of :

    System Analysts

    System Developers

    System Programmers..etc.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    7/38

    Human Resource Management

    Human Resource Management: is the

    strategic function performed in an

    organization that facilitates the most effective

    use of people(employees) to achieve

    organizational and individual goals.

    The person that manages Human resources is

    called Human Resource Manager orPersonnel Manager.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    8/38

    Role of a Human Resource

    Manager.

    The role of a HRM is:

    Acquiring Human Resources

    Maintaining Human Resources.

    Note: You can find more information about Human resources on

    our page!!

    Human resources

    planning

    Recruitment

    Selection and

    ScreeningOrientation.

    Training and

    Development

    Performance

    Appraisal

    Rewards andrecognition

    Retention and

    Replacement.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    9/38

    Capital Resources

    Capital Resources can be defined as the tools

    and infrastructure used to produce other

    goods and services.

    While the range of assets that can be

    considered to be a capital resource is very

    broad, it is important to note that not all

    assets are capital resources. There are a fewbasic qualifications that govern what assets

    can properly be referred to as a capital

    resource.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    10/38

    Capital Resources(cont.)

    One of the basic criteria for an asset to be

    considered a capital resource relates to the

    long-term use of the asset in the production

    of goods and services. In general a capital

    resource will be anticipated to aid in the

    creation of products for an extended period of

    time.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    11/38

    Capital Resources (cont.)

    The management of capital resources is

    particularly important when considering

    opportunity costs.

    Opportunity costs are a measure of the

    alternative opportunities forgone in the chose

    of one good or activity over others.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    12/38

    Managing Resources

    Efficient and effective use of resources

    can often make or break a project.

    Because resources are limited some hard

    to be obtain ,expensive or both.

    The allocation of resources can have a

    major influence on project schedules.

    For ex: limited programmers effects time,

    cost , quality , risk management.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    13/38

    Implications of Failure

    To correct a delay error, project manager

    can assign aditional resources to the task

    to get back on schedule this is known as

    crashing, but even this helps cost toomuch sometimes.

    When planning a project , managers first

    decide on the deliverables of the projectand the activities needed to produce them.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    14/38

    Implications of Failure(cont.)

    The next step is to estimate resources

    needed. Combination of resource needs

    and availability helps to determine the time

    needed for entire project.

    It should be considered during the

    initiation, planning, execution, and close-

    out phases of a project.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    15/38

    Duration vs Effort

    Effort is the actual time spend on working

    on an activity.

    Duration is elapsed time between the start

    and finish of an activity.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    16/38

    Activity Resource Estimating

    The goal of activity resource estimating , is

    to estimate the resources needed for each

    activity so they can be deployed in the

    most effective manner.

    Activity sequencing

    Resource availability

    Copmleted project schedule

    with durations

    Resource needs

    Managing resources

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    17/38

    Resource Estimation Techniques

    One of the primary tools of pj resourceestimating is expert judgement.

    Expert judgement is estimation based on the

    experience of one or more experts on theparticular activity or project.

    Another source of hard data is publishedestimating datahard data from specific

    activities carried out on previous projects thatmay be used to more accurately estimateresource needs.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    18/38

    Resource Estimation

    Techniques(cont.)

    When estimating activity resources, it is

    often advisable to conduct some form of

    alternatives analysis

    an estimating technicals in which trade ofs

    between the time needed the resources

    invested and the desired quality of the final

    deliverable are examined.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    19/38

    Resource Estimation

    Techniques(cont.)

    Also bottom up estimating is a technique

    applied when the resource needs of an

    activity can not be easily estimated.

    The primary output of the activity resource

    estimating process is a detailed listing of

    the resource requirements.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    20/38

    Resource Estimation Outputs

    Activity resource requiements is a very

    detailed listing of the resource

    requirements for the individual activities.

    Resource breakdown structure is a

    hierarchical ,graphical representation of all

    needed resources ordered by type or

    category.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    21/38

    Resource Estimation

    Outputs(cont.)

    Resource calender is a specific type of

    project calender that is used to track the

    hours when certain resources are

    available.

    Activity duration estimation is the process

    of estimating the duration of the project

    activities using both project scope andresource information.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    22/38

    Duration Estimating Techniques

    Analogous estimating is the estimation of

    activities durations based upon the duration of

    similar activities.

    Parametric estimating is the estimation ofactivities durations using some type of

    mathematical process.

    Three- point estimates- are the estimation of

    activities durations by averaging the

    optimistic,pessimistic and most likely estimates .

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    23/38

    Reserve Analysis

    Reserve analysis technique used to

    establish contingency reserves during a

    project to guard against potential risk.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    24/38

    Schedule development:

    Schedule development : is an iterative process

    designed to determine start and finish dates

    for project activities.

    During the process of schedule development

    activity duration estimates combination with

    the activity sequences are used to establish

    the final project schedule.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    25/38

    Input Schedule Development

    Input Schedule Development includes:

    -organizational process assets

    -project scope statement - Activity list (which also includes activity)

    - Activity attributes

    -Project network diagrams - Resource requirements

    - Resource calendars

    - Activity duration estimates and Risk Register

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    26/38

    Organizational Process Assets

    Organizational process assets can be as

    simple as a project calendar and easily

    calculate working and non working days.

    Example: in holidays, personal time off,overtime or standard working time..

    For this often developed using Microsoft

    project or collaboration tools ex: outlook orshare point such as Microsoft project can be

    used to record and display resource.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    27/38

    Risk Register

    Risk register specifies how control measures

    will be implemented to identify potential risks

    to project schedule. For example ,if the risk is

    high that a new mainframe computer will notbe installed on time.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    28/38

    Schedule development techniques

    The Schedules Developments Techniques

    includes:

    network analysis

    critical path analysis

    schedule compression

    what-if scenario analyze critical chain method.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    29/38

    Schedule network analysis

    Schedule network analysis: aids to managers in

    determining when activities can be performed

    given resources and constraints so network

    diagrams have to be analyze for any errors innetwork.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    30/38

    Critical Path Analysis

    -Critical path analysis: critical path is to

    established have quickly a project can be

    completed given the tasks, durations and

    dependencies in network diagram.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    31/38

    Critical Path (cont.)

    critical path method uses the 2 concepts

    Free float: the time an activity can be delayed

    without affecting the immediately following

    activity

    Total float: the time an activity can be delayed

    without affecting the overall completion of

    project

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    32/38

    Schedule Compression

    Schedule compression: in schedule

    compression use mathematical techniques to

    shorten project`s duration

    These techniques are known as

    Crashing: dedicated extra resources to

    particular activity.

    Fast-tracking: This looks at possibility of

    performing activities.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    33/38

    What-if Analyses

    What-if analyses: This method is a process of

    evaluating alternative strategies by observing

    how changes to selected factors affect other

    factors so take advantage of logic network byscenarios.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    34/38

    Critical Chain Method

    Critical chain method: the longest path

    through a network diagram, considering both

    task dependencies and resource dependencies

    and when using the critical chain method, thecritical path is first identifies, independent of

    resource availability.

    When using any of these techniques, aproject manager should always monitor

    project and resource calendars (times)

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    35/38

    Schedule Development Outputs

    Outputs include updates to resources

    requirements, project calendar, or the project

    management plan and schedule management

    plan, supporting details and resourcerequirements updates.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    36/38

    The schedule development outputs

    process include:

    A preliminary project schedule: Show the

    start and finish dates for each activity so it

    contains schedule network diagrams.

    Schedule model data: Provide managers with

    additional information about resource

    requirements and alternative schedules.

    Schedule baseline: Once the schedule hasbeen finalized and approved, it becomes the

    schedule baseline. This baseline, which shows

    the set of original start and finish dates.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    37/38

    Schedule Control

    The last process within the Project Time

    Management knowledge area is schedule

    control. In schedule control, the process of

    putting rules in place for controlling changesto the project schedules and schedule control

    process include updates to the schedule

    model data, schedule baseline , the activity listor project management plan.

  • 7/30/2019 Managing Project Resources 1227191402446602 9

    38/38

    Conclusion

    We have discussed the fundamentals,

    characteristics challenges, related to allocating

    resources, estimating activity, and project

    durations and developing the schedule withstart and end dates.

    In addition, we also identified types of

    resources and how they influence theestimation of task durations