MANAGING CONTRACT PARTNERSHIPS Webinar Hosted by Pharmaceutical Manufacturing Wednesday, November 7 2012 Presented by Hedley Rees, Biotech PharmaFlow

MANAGING CONTRACT PARTNERSHIPS

  • Upload
    gannon

  • View
    39

  • Download
    0

Embed Size (px)

DESCRIPTION

MANAGING CONTRACT PARTNERSHIPS. Webinar Hosted by Pharmaceutical Manufacturing Wednesday, November 7 2012 Presented by Hedley Rees, Biotech PharmaFlow. Agenda. What is behind the ‘supply chain heat’ Where do contractors fit in? Management strategies based on segmentation - PowerPoint PPT Presentation

Citation preview

Page 1: MANAGING CONTRACT PARTNERSHIPS

MANAGING CONTRACT PARTNERSHIPSWebinar Hosted by Pharmaceutical Manufacturing

Wednesday, November 7 2012

Presented by Hedley Rees, Biotech PharmaFlow

Page 2: MANAGING CONTRACT PARTNERSHIPS

Agenda

What is behind the ‘supply chain heat’Where do contractors fit in?Management strategies based on

segmentationThe procurement cycleBuilding a foundation for the future

Page 3: MANAGING CONTRACT PARTNERSHIPS

Supply chain ‘heat’

Page 4: MANAGING CONTRACT PARTNERSHIPS

Where is the heat coming from?

Shortages……Economically motivated adulteration……Recalls…..Cost of Goods issues…Counterfeiting…..Theft…..Diversion…..

Page 5: MANAGING CONTRACT PARTNERSHIPS

The fall-out….

Crippling impacts in the areas of patient safety, brand image and reputation, costs of remediation, customer service and investor confidence.

A UNIVERSAL CRY FOR CHANGE!From regulators, governments, other

competent authorities and patient advocacy groups.

5

Page 6: MANAGING CONTRACT PARTNERSHIPS

Stakeholders pile in….

…EU implements Falsified Medicines Directive.…EMA consults on dramatic tightening of GDP/GMP…FDA pens “Pathway to Global Safety and Quality”.…President Obama wades in on drug shortages.…US HELP Congressional Committee consults.…US Pharmacopeia consults on new Chapter < 1083 >.…PEW Charitable Trust writes report “After Heparin”.…GS1 Global Traceability Standard for Healthcare

(GTSH).…FDA Safety and Innovation Act (FDASIA), Title VII

Page 7: MANAGING CONTRACT PARTNERSHIPS

Where do contractors fit in?

Page 8: MANAGING CONTRACT PARTNERSHIPS

Roles in the Pharma Supply Chain

Responsible for supply

chain

Page 9: MANAGING CONTRACT PARTNERSHIPS

The Scope of Contractual Relationships•Qualification/validation work for premises• Maintenance /calibration of equipment• Storage and distribution• Artwork generation and print ready material• Assessment and sourcing of starting and packaging materials

•QP and other professional services such as GMP audits of suppliers Washing/depyrogenation/sterilisation of packaging materials used in manufacture.• Hosting of IT functions• Document archiving and storageRef: GMP/GDP INSPECTORS WORKING

GROUP GMP/GDP IWGDocument Ref: EMEA/INS/GMP/648678/2009

Page 10: MANAGING CONTRACT PARTNERSHIPS

Dis-integration of the supply chain

PatientsOutsourcing begins in earnest…..

Page 11: MANAGING CONTRACT PARTNERSHIPS

Contractor Management in Context

Immensely complex interactions.Relationships are 3rd party.Contractually driven.Power and dependence.Management by Segment.

Page 12: MANAGING CONTRACT PARTNERSHIPS

Strategies based on segmentation

Page 13: MANAGING CONTRACT PARTNERSHIPS

Procurement Portfolio

Leverage Strategic

Routine

BottleneckPortfoli

o

Many Suppliers Single SupplierComplexity of Supply Market

Financial Relevance

High

Low

Based on Kraljic Matrix, HBR 1983

Page 14: MANAGING CONTRACT PARTNERSHIPS

Procurement Portfolio Management

LeverageExploit

Negotiate hardRegular tendering Strategic

Build relationshipsSeek innovation

Joint investments

RoutineAutomate

StandardiseEmpower users

BottleneckMitigate risk

Change designAlternate source

PORTFOLIO

Many Suppliers Single SupplierComplexity of Supply Market

Financial Relevance

High

Low

Figure 1 A segmentation approach based on Kraljic Matrix

Page 15: MANAGING CONTRACT PARTNERSHIPS

The procurement cycle

Page 16: MANAGING CONTRACT PARTNERSHIPS

The Procurement Cycle – Strategic Segment

Specify

•User Driven•Team based•Request for Proposal

Select •Involvement of stakeholders•Decision making process•Business benefits

Commit

•Agreements – Supply, Quality & Technical, Service level•Processes for working together•Information sharing

Perform

•Regular reviews•Metrics•Continuous improvement

Page 17: MANAGING CONTRACT PARTNERSHIPS

Building a foundation for the future

Page 18: MANAGING CONTRACT PARTNERSHIPS

It starts in early stage development…

Analytical Methods

Supply chain

thinking?

Page 19: MANAGING CONTRACT PARTNERSHIPS

Building successful contractor partnerships

Robust Supply Base

• cGXP compliant

• Capable processes

• Commercially viable

• Organisationally mature

• Culturally congruent

Inclusive planning process

• Defined envelope of uncertainty

• Adequate capacity

• Appropriate scale

• Thorough risk assessments

• Sourcing and Inventory policy

Sound Agreements

• Procurement cycle

• Supply• QTA• Service level

Process Driven

• End-to-end• Allocation of responsibilities

• Change control

• Metrics