Upload
others
View
1
Download
1
Embed Size (px)
Citation preview
Management response to the evaluation of Evaluation of “Sumangali: Eradication of Extremely Exploitative Working Conditions in Southern India’s Textile Industry” (2019) Introduction - Context, background and findings “Sumangali – Eradication of Extremely Exploitative Working Conditions in Southern India’s Textile Industry” is a project supported by the German Ministry of Economic Cooperation and Development (BMZ) and C&A Foundation. This four-year project (April 2016–Dec 2019) is being implemented in 12 blocks of eight districts of the state of Tamil Nadu by terre des hommes Germany – India Program (tdh) and Community Awareness Research Education Trust (CARE-T), a Coimbatore based NGO. The total budget of the project is € 2,045,056. The project has the following four sub-goals at three levels of intervention: Level Sub goals Micro 1. Rehabilitation of 24,000 girls and young women as survivors of the Sumangali scheme in 12 blocks of Tamil Nadu 2. Prevention of recruitment of girls and young women under the Sumangali scheme in 12 direct blocks and 48 extended blocks Meso 3. Development and implementation of a universal code of conduct and recruitment guidelines by associations of spinning mills and exporters of garment manufacturers through multistakeholder dialogue process with support of German Textile Alliance Macro 4. Discussion of a draft bill (recruitment law) for the termination of the Sumangali scheme in Tamil Nadu State Assembly. The project commissioned the end-term evaluation as part of its accountability mandate and as a learning exercise to understand and inform pathways to eradicate the Sumangali1 system. The evaluation was conducted from mid-January 2019 to February 2019 and followed a qualitative and participative approach. The methodology included desk review, an evaluation workshop with project team, field visits involving discussions with beneficiaries and project team, and key informant interviews with other external stakeholders and experts. The evaluation also reconstructed project’s theory of change and developed a rating system for evaluation purposes. The evaluation used OECD-DAC criteria of assessing relevance, validity of design, effectiveness, efficiency, results and sustainability The evaluation team did not talk local language and had to rely on translators, which was in some cases seen as not satisfactory by beneficiaries.
Recommendations and Action Plan
Recommendation Management Response: (Accepted, Partially Accepted, Not accepted)1: If recommendation is rejected or partially accepted, state reasons:
Action Planned Expected Completion Date
1 The options for response are: • Accepted, meaning Fully Accepted: the organisation thinks that this recommendation should be completely implemented, and the response should
show how and by when that is to be done. • Partially Accepted: the organisation thinks part of the recommendation is in error or not applicable and will not be responding to it,but
1. Rehabilitation strategy: The project should aim to
develop a comprehensive rehabilitation strategy to
provide quality rehabilitation services in a need
based and holistic manner. Some of the specific
recommendations are:
a) Rehabilitation service must follow case
management approach wherein the support
services are provided as per the identified needs
of the survivors.
b) The current need assessment tool must be
revised to assess physical and mental health
status of survivors at the time of identification.
Relevant technical experts must approve the
need assessment tool before its application.
c) The project should adopt life skill building
approach, instead of psychosocial counselling, as
it is more relevant to the beneficiaries and is
also within the delivery capacities of the field
team. The life skills module can be delivered on
a weekly basis over four to six months. The
project should consider a need-based approach
to assess if the life skills training and vocational
training can be delivered simultaneously or one
after the other. Appropriate tools should be
Accepted
The project has accepted to develop the
comprehensive rehabilitation in order to
make the services more need based and
improve it on a holistic manner. The
specific recommendations are accepted
and the following measures are taken up:
-
a) The rehabilitation strategy is
redesigned to follow the Case
management. Therefore, the
rehabilitation service reassess,
plans, implements, coordinates,
monitors and evaluates the options
and services required to meet the
health and human service of the
young girls’ assessed needs.
b) The current need assessment tool
will be revised. It is to assess
physical and mental health status of
survivors at the time of
identification. The technical support
will be obtained from NIMHANS.
Surveys for baseline,
migrant study, end line
study and case
management
There are two surveys,
the base line survey is to
assess the pre-project
stage and situation and
the end line survey is to
measure the progress
made in the fixed
indicators. There are two
parts and the part one of
each of the two surveys
will cover the vulnerable
villages in 9 blocks.
Second part is to status
and training needs of
workers through Human
Resources staffs of textile
mills. Team of staff with
Hired consultant for
guiding the surveys is to
carry out the surveys. A
accepts and will take action for the other part. Note that the reason for a partial acceptance must be given. • Not Accepted: the organisation thinks the recommendation is based on
inaccurate findings or does not address the findings in the appropriate way. The reason for non-acceptance must be stated.
developed and applied to measure the progress
of the beneficiaries. The tools must essentially
include trainer manual to conduct life skill
trainings.
d) Survivors who require clinical attention for
mental health should be referred to
professionals such as clinical psychologists and
psychiatrists. Innovative and cost-efficient
methods such as phone-based therapy can be
explored for this purpose.
e) Selection of trades for alternate livelihood
should be based on block level feasibility
studies. The feasibility studies must focus on
identifying trades and vocational skills based on
market demand, their absorption potential,
salary levels and ability to provide decent
working conditions. The project’s placement
support must ensure issuance of contract letters
detailing terms of employment and benefits.
Adopting a centralised web-based information system to manage opportunities can strengthen the project’s placement strategy. Further, partnership with local placement agencies can be explored. Since employers pay placement agencies for recruitment services, this strategy can be significantly cost effective. Finally, the project team at the RRC level should be given flexibility to innovate and implement strategies to facilitate placement of survivors.
c) The process of building life skill
approach is already carried out to
build the capacities of the
beneficiaries. As per the
recommendations, one more special
life skill education camps will be
conducted for all the needy
beneficiaries before the end of the
project period.
d) The feasibility study for selecting the
appropriate trade will be taken up
during the next phase of the project.
Placement services will be
strengthened.
e) Selection of trades for alternate
livelihood will be based on block
level feasibility studies. It is a good
recommendation for improving our
work. It is planned to be conducted
after the end of the project while
strengthening the existing activities.
The outcome of the feasibility study
will be used for the changed course
of action in the follow up activities.
The recommendations especially on
the identified feasible trade for the
activity groups of young women will
be implemented.
comprehensive baseline
survey is the basis for
monitoring and the
reference for the end line
survey. The baseline
survey is expected to
analyse the basic profile,
emotional level of the
survivors, medical and
trauma related status,
emotional coping level,
skill and educational
level, family conditions
and the vulnerability of
the family. The external
evaluation of the current
project is setting a good
base when deciding what
kind of data is necessary
and how to manage the
data throughout the
project. Two surveys will
be conducted: one in the
project villages and the
second in the mills.
Furthermore, as
recommended in the
evaluation, a feasibility
f) Adopting a centralised web-based
information system to manage
opportunities will be initiated during
the pendency of this project. It is a
good recommendation. As per the
recommendations, one more update
on emotional status before the end
of the project.
As per the recommendations, Profile of
the beneficiaries will be again updated
based on the present economic status.
Medical camp records of the girls and
young women with abnormal HB count
and serious illness are documented. It is
documented and made available in
regional resource centre.
Partially Accepted
Survivors who require clinical attention through innovative and cost efficient methods such as phone therapy is a good recommendation. So far the phone based therapy is not likely to be feasible. This imperative aspect is to considered based on the unwillingness of young women survivors. There are cultural barriers of young women in opening up their mind and sharing it to clinical psychologist whom they don’t know in person. Moreover, even the
study on the status of
female migrants is
conducted. Digital coding
of the beneficiaries,
documentation of their
status at the beginning of
the intervention and at
the end is required to
map the life changing
progress of the
beneficiaries due to the
project intervention.
Periodic data collection
on their psychological,
physical, attitudinal,
educational and
livelihood changes are
recorded and
documented in digital
formats.
Life skill education
Girls are trained in ten
types of life skill
education promoted by
the World Health
Organisation (WHO).
Beneficiaries are selected
by field staff based on
general preference of the clinical psychologists is not in favour of this imperative aspect. Therefore, the existing referral services shall be continued for the time being.
the criteria formulated by
key staff of the project.
The existing training
materials on Life skill
education will be
screened and refined to
suit our project’s target
Life skill education will
be conducted by the
project staff based on a
trainings manual within
the Resource Centres
(RRCs), which were
established in the
previous phase and serve
as a contact point and
training centre for the
victims. Life skill
education is the first step
in the rehabilitation
process of the girls and
sets the ground for
further training. After the
training tailor-made
measures for the
individual development
then it will be offered to
the girls
Feasibility study on job
market, skill
development and micro
enterprises
As recommended in the evaluation, a feasibility study on market demands and employment opportunities is to be conducted by the project team to design the skill development activities for decent employment and educational support. A special look will be given to the emerging developments in organic cotton processing and circular economy approaches with regard to job opportunities and needs for training. There is a need to enhance the capacities in tune with reality. Dynamics of the job market will be analysed in the feasibility study. The study will provide a clearer direction on the current job market situation.
2. Prevention strategy: The prevention strategy
must focus on addressing systemic issues at the
individual, family, societal and workplace levels to
eradicate exploitative conditions in the textile
industry.
a) The prevention strategy should continue to work
on filling the information gap related to
negative impact of the Sumangali system.
Additionally, the awareness must be created on
labour rights especially on minimum wages,
leaves, freedom of movement, anti sexual
harassment laws, and need for collectivisation.
b) The current strategy to promote two kinds of
groups needs to be revisited to ensure coverage
of all the villages, promotion of women and
youth leadership, and a linkage with block level
group using federation structure. The capacity
development of the groups must focus on
eradication of social norms, labour rights, and
participation in decentralised self-governance
mechanisms and also in policy advocacy
initiatives at the meso and macro levels. The
project must work out sustainability strategy of
the groups in consultation with survivors and
other key stakeholders.
The prevention strategy must include engagement with factories to improve working conditions and implementation of existing laws.. It can advocate for setting up of Village level systems to prevent
Partially accepted.
a) The prevention strategy is planned
to combine awareness on the
negative impact of Sumangali system
with continued awareness on labour
rights especially on minimum wages,
leaves, freedom of movement and
anti-sexual harassment laws.
Awareness on labour rights,
minimum wages and freedom of
movement is an ongoing process.
b) As per the recommendations of the
evaluation, one more round up of
explanation on roles and
responsibilities will be made to all
community structures before the end
of the project.
c) Resolutions are passed in programme
village councils on maintenance of
migration register. It is available in
many programme villages. Now, the
petitions on maintenance of
migration are submitted in other
villages where the programme is
implemented during the
Independence Day.
Engagement with factories will be initiated the engagement with the factories such as explaining the
Prevention work in
vulnerable source areas
Girls and women in
deprived areas will be
supported through
informal education on
child rights, gender and
labour rights to prevent
their drop out of school
and unfair recruitment
for exploitative work.
They will participate in
village council meetings
and speak out for girls’
rights to education and
for preventing
recruitment into
exploitative labour and
pass resolutions on
special public village
council meetings.
Children (aged 11 to 17)
will be supported with
proper education and as
they are vulnerable to
become early age workers
Strengthening groups of
girls and young women
unsafe migration and to raise voice against the exploitative conditions. For example: -Village level in maintenance of migration registers.
prevention methods to improve the working conditions are started. And in the due course it will be explained to other textile mills in upcoming project period.
Activity Groups (AG) will
create an action plan for
each group in defending
the rights of girl children
and young women. AG are
joining hands and support
each other on village
level and at block level
with the network of AGs.
They monitor the
prevention of unsafe
recruitment of forced
labour. It will lead to
structural sustainability.
Interaction by female
workers with village
They will meet with
labour brokers and the
communities to inform
about working and living
conditions in the spinning
mills. a) Organized as
activity groups will
establish contacts with
key persons in the
community; b) Once in a
month approach the key
persons; c) Then short list
the recruiters; d) Conduct
meetings with the
recruiters once in two
months and Follow up.
Knowledge building for peer workers on ICC, hostel law, Mill Codex: - Peers of the factory workers with articulation and potentials will be selected and trained in order to build knowledge on ICC, Hostel Law and Mill Codex.
3. Development of Mill Codex: The project must
initiate engagement with employer associations like
SIMA at the earliest with the overall goal of
developing universal code of recruitment in a
stakeholder driven manner.
a) The project needs to develop human resource
capacities to engage with employer associations
to facilitate multi-stakeholder dialogue process
either by bringing in relevant experts in the
team or by tdh playing a bigger role at this
level.
b) With the objective of building trust, the project
should also identify and disseminate good
practices of recruitment and working conditions.
The project must use existing platforms like Tamil Nadu Alliance (TNA) and Multi Stakeholder Initiative
Accepted
The project will initiate engagement
employers’ associations. Draft Mill Codex
is shared with the employers of large
textile manufacturing factory unit. Mill
Codex has identified and explained all the
good practices of recruitment and fair
treatment of workers by employers.
a) The engagement with employers
association will be carried out after
organizing the German level round
table with the select brands
representatives with textile supply
chain link in Tamil Nadu. The
positive outcome of the round table
Round table conferences
with the managers of the
textile supply chain
management staff
(responsible for human
resources) of the mills
are sensitized for the
importance of best
business practices in
recruitment and
employment, the
effective relationships
between sustainable
human resources, and the
productivity at workplace
and the progress in
–Tamil Nadu (MSI-TN), and engage with worker organisations to create larger demand for the universal Mill Codex.
will be helpful in advancing the
advocacy effort with the employers.
Therefore, the employers understand
more about the relationship between
our project and the international
business implications. The
recognition of our work by the
employers’ association also requires
some external business inputs from
the top level of the textile supply
chain.
The Mill Codex is already shared with the employers of large textile manufacturers. The employers have listened to the explanations on the various components of the Mill Codex. They have expressed their apprehension on the expected business value for implementation of all the components of the Mill Codex. They have agreed to implement the hostel laws and they have started registering their hostels as per the law. The evaluation was taken up in Jan-Feb 2019.Many activities were taken up after the evaluation.
business in textile supply
chain. Round Table
Conferences are related
to recruitment and
employment.
Engagement for revising SIMA guidelines in tune with Mill Codex The project will connect
with SIMA as they have
developed their own
guidelines to improve
working and living
conditions in the mills.
Multi-stakeholder
dialogues on the Mill
Codex and relevant
themes
Conference for managers will deal with the Ministry of Corporate Affairs New Delhi has developed National Action Plan on the UN Guidelines on Human Rights and Business. Periodic dialogue with the employers, government representatives is enhancing to create models of best social
practices in textile supply chain. In a participatory process the employers will be supported during the dialogue events to develop action plans for the improvement of working and living conditions. Best textile practise is assessed by the effective application of components of Mill Codex even if it takes place gradually and incrementally.
4. Policy advocacy at the macro level: The project
should explore alternate methods of policy advocacy
to address the legal loopholes in place formulating a
new law, which is a long-term and resource
intensive strategy. Few alternatives to be
considered are:
a) Advocacy for inclusion of textile industry
(including spinning mills) in the list of hazardous
industry through public interest litigation.
b) Adopt evidence based policy advocacy strategy
at the local, regional and state levels to
highlight the exploitative working conditions in
the textile industry. For this purpose, the
project can utilise needs assessment survey data
Agreed in principle but strategy varies.
Project network is founding member of
TNA. The project network is actively
participating and cooperating with TNA
since its inception in 2017 as a platform
of all networks including Ethical Trading
Initiatives of Tamil Nadu Multi Stake
Holder Initiative (TNMSI). ETI’s TNMSI is
founded since 2014 and is a founding
member of TNA. Already Tamil Nadu
Alliance has the engagement with TPF
(Tirupur Peoples Forum for environment
and labour rights), ETIs TNMSI (Tamil
Nadu Multi Stakeholder Initiative),
Migrant Workers forum,
Appraisal on the
incidence of violations
Appraisal on the
incidence of violations is
conducted by supporting
the victims. Evidences
are gathered and
submitted along with the
petitions seeking justice
and compensation.
Victims or families of
victims are provided
moral, operational
(petitions) and legal
support. Resolvable
and also further collect relevant data using
TPF’s network of community organisations.
c) Advocate for activating District Monitoring
Committee and implementation of its
recommendations in partnership with other
stakeholders like TNA.
d) Support the TNA’s efforts to develop policy for
women workers in textile industry government
bodies. It is to be noted that TNA is working
with State Commission for Women and
Department of Labour to develop this policy.
TPF’s support can be in form of creating
grassroot level demand for such a policy. It can
further support TNA to influence the state level
policy makers by providing evidence in form of
data and field stories to highlight the situation
of women workers.
Design and implement a communications and media
strategy to deliver the key messages around the
negative impacts of the Sumangali system, its
systemic factors and policy asks in a sustained and
consistent manner.
MSI-TN and Campaign against Camp
Coolie System (CACS.)This will be
strengthened for better policy advocacy.
a) Not accepted. Textile production
process was in the hazardous sector
in the past. But the government of
India has changed in to the non
hazardous sector
It is a good recommendation but the
advocacy on the inclusion of textile
industry is considered as a sensitive
and offending issue by the
employers. The project agrees the
importance of the listing the textile
industry as a hazardous industry at a
policy level but it is not immediately
possible only by a stakeholder like
our project in changing the mindsets
of the employers. It is a time bound
and long term advocacy work. Also,
it is not advisable for our project as
we are entering the phase of
intensively working on factory
engagement. The project should not
antagonize the employers at one side
and work with them on the other
side. Practically, the project is not
grievances are directed to
the management by
petitions and in case of
failures, other avenues
for justice are explored.
Staff and local activists
will approach the textile
mills along with
beneficiaries. Then, in
case of failures in
achieving the results then
it will be taken to
concerned authorities.
Legal advice in labour
disputes
Legal advice will be
facilitated for the
affected young women
workers in labour disputes
to claim the rights
(payments of
compensation in case of
sickness, suicides and
attempted suicides;
regular payment of
salaries). Identified cases
of mill owners trespassing
labour laws are discussed
making any immediate demand for
the inclusion of textile industry.
b) An evidence based policy advocacy is
already taken up and more will be
taken up during the next phase of
the project.
c) Advocating for activating District
Monitoring Committee and
implementation of its
recommendations in partnership with
other stakeholders will be done.
d) Designing and implementing a
communications and media strategy
to deliver the key messages around
the negative impacts of the
Sumangali system, its systemic
factors and policy asks in a sustained
and consistent manner.
The project is associated with Tirupur
Peoples Forum for environment and
labour rights. It is a founder member of
Tamil Nadu Alliance. Our project has
ddocumented unresolved cases and it has
produced it before the State Women
Commission and it is following up with the
State Women Commission jointly with the
Tamil Nadu Alliance. Majority of the
cases produced through Tamil Nadu
with advisory persons
from the legal advisory
institutions.
Engaging with free legal
aid authority and state
commissions for women
and children, and
others: - The project will
support the reported
victims by engaging with
Human Rights Instruments
and mechanism at state
level such as State Human
Rights, Women, Child,
Scheduled Caste,
Scheduled Tribes,
Backward Class and
Minority Commissions.
Proactive intervention by
the Judiciary has a
snowballing effect on
resolution of the cases.
There is an urgent need
to enhance the
engagement with free
legal aid authority for
comparatively faster
Alliance belongs to our project. The
intervention through State Women
Commission has resulted in immediate
justice to the survivors and the family of
the survivors. There will be more such
efforts besides follow ups to influence
the state level policy.
delivery of justice and
compensation.
Cooperation with District
law enforcement
mechanisms
Coordination meetings
with the district level
officials are conducted
with them for effective
implementation of laws
defending girls and
women at workplace and
hostels. Registration of
hostels run by the
spinning mills under the
law is pursued through
the pressures of the
officials. Officials at
State level with mandate
to work for the welfare of
labour, women, children,
marginalized
communities. Officials of
the relevant departments
of the district meet
project staff and AG
leaders.
District level workshops
for leaders of CSOs
district level workshops
for the leaders of
CSOs/trade unions and
Schools on engagements
with the enforcement
officials for the
implementation of legal
mechanisms to protect
children and women
officials for effective
implementation of laws
defending girls and
women in particular at
workplace, hostels and
schools are conducted. In
each workshop an action
plan is developed to
record next steps how the
stakeholder can support
decent working conditions
for girls and young
women. In the following
meetings the
implementation of the
action plans will be
monitored.
State level engagements
with administration
The state level
engagement team will
share information, hand
in petitions and follow up
with elected
representatives on topics
like prevention of school
dropout, ratio of high
school girls in government
schools and a faster
mechanism for licensing
hostels in textile mills.
The team will meet with
state departments of the
relevant ministry on
gender and labour issues
of garment industry,
developing policy for
adolescent girl children,
and state level
coordination with the
representatives of trade
unions, media advocacy
for the welfare of girls
and young women and
networking with CSO
working on gender issues.
Networking with Civil
Society Networks
CARE-T is the facilitator
of Tirupur Peoples Forum
for environment and
labour rights (TPF). It is
engaged in working for
the improvement in
working and living
conditions in the textile
supply chain. TPF acts in
association with more
than 41 civil society
organizations located in
21 districts. TPF is the
founding member of
Tamil Nadu Alliance
(TNA). TNA is a focal
point for advocacy
activities of CSOs to
advance the rights of
young women and
migrant workers at state
level. The project is in
direct communication
with the convenor of
TNA. There is a clear
distinction on the
activities proposed by this
project and the activities
proposed by TNA
coalition. Our project and
its network TPF has a
wider geographical
working area. There is a
good solidarity between
our project, TPF and the
TNA secretariat.
Networking with ETI’s
Tamil Nadu Multi
Stakeholder Initiatives
(TNMSI) is developed
further with workshops
for CSOs, employers’
associations and
government agencies for
convergence of relevant
officials on
implementation existing
legislations. TPF will
strengthen its networking
with Tamil Nadu Women
Movement (TNWM).
5. Project management: The project management
systems must focus on developing appropriate tools
to efficiently monitor, to facilitate internal learning,
adaptive management and enhancing the
effectiveness of the implementation strategies. The
recommendations in this direction are:
a) The project should develop a manual for the
project team to develop common understanding
of the objectives, strategies, terminologies,
processes, quality control measures, indicators
and targets. This shall also contribute to
standardisation of activities across blocks.
Better remuneration structure for project staff
should be considered to enable the partners to hire
staff with required capacity and skills.
Partially Accepted.
a) The project will develop a manual
for the project team to develop
common understanding of the
objectives, strategies, terminologies,
processes, quality control measures,
indicators and targets, training
manuals for all key trainings to the
direct and indirect beneficiaries and
it will contribute the standardisation
of activities across blocks. It is an
ongoing process
b) The existing remuneration structure
for the project staff is not adequate
considering their experience and
dedication.
Capacity building programmes for the
existing staff and new staff for the future
Staff training in PCM,
project concept,
baseline, end line
survey, data
management,
engagement with
stakeholders: - Project
staffs are trained in the
project cycle
management, the project
concept, implementation
strategy, baseline design
and implementation, data
management and analysis
planning and reporting.
Residential training of
key staffs of the project
on engagements to
prepare and conduct
engagement meetings
with government
representatives.
Negotiating skills will be
trained in the regard to
the Mill Codex as
practical example.
Manuals on career
guidance, labour and
human resources
training: - Therefore
uniform capacity building
among the target group
takes place. Personnel
costs: -Better
remuneration structure
for the project staff is
developed.
6. Validity of project design The project design is weak in terms of logical connect between the levels of results (i.e. the connect between outputs, outcomes and overall goal).
Not accepted. The project design was
developed by experts from BENGO and
BMZ, C&A Foundation and TdH Germany
in cooperation with the partner Care-T
7. Under sub-goal 2, the project targeted to stop recruitment under Sumangali scheme in all the 12 project blocks completely, however, the strategy and corresponding activities are inadequate to comprehensively cover the entire project area. The prevention strategy focused on filling the information gap related to negative impacts of the Sumangali system and overlooked other systemic issues like safety concerns for girls in the villages, economic deprivation, social norms. Further, the operational strategy to organise survivors and stakeholders into groups is not clear. There is an absence of interrelatedness between the different activities, which makes it ambiguous as to how the overall objective of eradicating the Sumangali scheme in the entire block shall be achieved.
Partially accepted,
There is absolutely no reference to .
Under sub-goal 2, that the project
targeted to stop recruitment under
Sumangali scheme in all the 12 project
blocks completely.
8.To develop the recruitment guidelines under sub-goal 3, the project design rightly suggested of a multi-stakeholder approach. However, the design made assumptions about participation of different stakeholders and did not identify challenges and risks of the dialogue process adequately. The project design to draft the new law under sub-goal 4 is not stakeholder driven and is inadequate to having the law discussed in the Tamil Nadu State Assembly.
Partially accepted.
This effort is driven by concerns at the grass root level activists and subsequently it is a concern of the families of victims. It is not easy to expect the support of employers on a draft bill and discussion at the legislative assembly. Gaining political support for this work is an attempt to bring structural change on this prolonged issue. It is an attempt to bring a legal change. (Draft bill is now ready and meeting with political and administrative set up has been planned in2019). Yes, there was no stakeholder driven advocacy towards the draft bill, as during the project it turned out to be not possible to include employers association and/or politicians right now, as there is a lot of political repression and the TN government is denying the existence of contemporary form of modern slavery practices. Nevertheless we drafted the bill – to have a draft at hand for future work. In next phase the difficulties are reflected and the speed is much more humble. Tdh Germany is not directly involved in drafting the bill, but supporting the Mill Codex and the issue through advocacy on with relevant stakeholders in Germany,
like the Sustainable Textile Alliance and its business members, sourcing in TN.
10. Effectiveness and results The project achieved outcome level results only at the micro level. At the meso level, the recruitment guidelines is drafted, however, it is yet to be introduced to employer associations. At the macro level, the proposed anti-Sumangali law is yet to be drafted. The key findings related to effectiveness and results are as below:
Not accepted.
The evaluation took place a year before
the project phase ends. Subsequently,
activities have to be continued to reach
the planned results. For example: As
reported in the Half Yearly Report on
the period from January 1st to June
30th, introduction to employers took
place.