Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
R.O. Evans, K.L. Bass, M.R. Burchell, R.D. Hinson, R. Johnson, and M. Doxey
Key words: BMPs-constructed wetlands-drainage-hydrology-water quality
Management alternatives to enhancewater quality and ecological function ofchannelized streams and drainage canals
Abstract: Drainage practices in humid regions historically focllSed on straightening anddeepening natural channels to increase their hydraulic capacity and minimize upstream flooding. In most cases, traditional channel improvements disassociated the channel from the natural floodplain, especially for smaller storms, degrading water quality and ecological functionsassociated with the riparian floodplain. Pilot studies were implemented to denlOnstrate andevaluate alternative channel management strategies and design geometries to identifY alternatives that might enhance water quality functions while maintaining the necessary drainagefunction. Channel alternatives included: establishment of in-stream and riparian wetlands,lowering of the floodplain to reconnect the channel with the floodplain, redesign of channels using natural channel design principles, and establislU11ent of conservation easementsto encourage establishment of perennial riparian buffer vegetation. This paper summarizesseven projects that were in1plemented between 1995 and 2006 to provide better management of drainage water in order to enhance water quality and other ecological functions inlarge drainage canals. Hydrology and water quality were monitored fi:om two to four yearsat five sites. In addition, plant conu11unities and macro-invertebrates were nlOnitored at threesites. Nitrogen concentrations and transport were reduced by 20% to 70% with in-stream andconstructed storm water wetlands. Reconnecting the channel with the floodplain damvenedthe hydrograph peak and reduced the "out-of-floodplain" risks outside the project area. Thealternative practices were more expensive and resulted in two to three tin1es more land areabeing taken out of production compared to conventional drainage practices. However, thebenefits were improved water quality, lower peak outflow stage, and enhanced habitat forwildlife. Practices described here are beginning to demonstrate that there are multipurpose,environmentally friendly alternatives to traditional practices of routinely cleaning and mowing trapezoidal ditch channels for the sole purpose of satisfYing drainage requirements.
Robert O. Evans is a professor, Kris L. Bass isan extension associate, and Mike R. Burchell isan extension assistant professor in the Department of Biological and Agricultural Engineering,North Carolina State University. R. Dwane Hinson is a district conservationist for the USDANatural Resources Conservation Service (NRCS).Rodney Johnson is a retired Albemarle resourceconservation and development coordinatorfor the USDA NRCS. Mike Doxey is a districttechnician for the Currituck Soil and WaterConservation District.
to the drainage formula Q = 0.013CiVj5/",where Q = discharge (m3 S-1 [ft3 S-I]),
M = watershed area (km2 [mi2]), and C = a
regional coefficient determined through localexperience (USDA Soil Conservation Service1971; Schwab et at 1993). Coefficients typically range from 10 to 45 depending on landlISe, crop, rainfall, topography, and desiredlevel of flood protectionValues for row cropsalong the Atlantic and Gulf Coast typicallyrange from 30 to 45. These result in bankfullflow frequencies of 2 to 5 year recurrenceintervals (Schwab et al. 1993), which areapproaching an order of magnitude less thanthe natural frequencies reported by Sweetand Geratz (2003).
Few unchannelized streams remain in thelower and middle coastal plain regions of theAtlantic and Gulf States. This has becomewidely apparent to stream restoration consultants who have experienced difficultylocating reference reaches in coastal plainareas for establishment of natural channeldesign criteria. In most cases, traditionalchannel improvements have straightened anddeepened natural channels to increase theirhydraulic capacity. This altered the hydraulic connection between the channel and thenatural floodplain thereby degrading riparianzone water quality and ecological functions.Woody riparian vegetation along the sidesof the streams have been removed and ditchbanks routinely mowed to provide access forperiodic clean-out and removal of silt (Lilly1981). In many channelized streams, moststorm flows are confined predominately tothe channel. The riparian floodplain thatonce routinely remained soaked or inundatedduring the winter and spring for months at atime only flood during large storms (stormsgreater than 2 to 3 year recurrence interval)following channelization. In addition to thedecline in the frequency of out-of-bank flow,water table levels both within the riparian
1992; Lowrance et al. 1984). This rIparIanzone function is one of the primary justifications for the USDA Conservation ReserveEnhancement Program initiative to restoreriparian buffers (Cowan 2007; Mayer et al.2005; USDA Farm Service Agency 2007).
Drainage has been an important component of land management in humid regionsof the US for the past 200 years (Beauchamp1987; Fausey et al. 1987; Lilly 1981).Natural processes affecting the connectivity of a stream channel and its floodplain areseverely altered by past drainage practices.Over the past century, drainage improvements in most humid regions were sized toconvey flows within the channel according
Natural channels typically experiencebankfull flows at a recurrence interval of1 to 1.5 years (Rosgen 1996). In flat areaswith wide river valleys representative oflowercoastal plain landscapes, bankfull flows mayoccur more frequently-on the order ofseveral times per year (Sweet and Geratz 2003).When a channel overflows its bank, a portionof the flow is stored in the riparian floodplain thus dampening the peak of the hydrograph. Flows stored in or passing throughthe riparian floodplain typically undergobiochemical processes that improve the quality of the water prior to it being returned tothe stream (Dukes and Evans 2003; Dukes etal. 2002, 2003; Gilliam et al. 1997; Lowrance
~L-_JO_U_R_N_A_L_O_F_S_O_IL_A_N_D_W_A_T_ER_C_O_N_S_E_R_VA_T_IO_N__
Table 1Summary of data collection, project durations, and citations to original references.
Project Data collected Reference{s) Duration
lull Creek, Currituck County
Liza's Bottom, Edenton, Chowan County
Newland Ditch, Pasquotank County
Guinea Mill, Currituck County
Edenton Airport, Chowan County
Chowan Golf Course, Chowan County
Core Creek, Craven County
Continuous stream stage
Outflow (stage wi weir eq.r
Monthly grab WQ
Plant surveys
Continuous stream stage
Outflow (stage wi weir eq.)
Automatic WQ samplers
No data collected
No data collected
Continuous stream stage
Outflow (stage wi weir eq.)
Riparian zone WL
Automatic WQ samplers
Benthic macro-invertebrates
Continuous stream stage
Outflow (stage wi weir eq.)
Groundwater WL
Automatic WQ samplers
Benthic macro-invertebrates
Continuous stream stage
Outflow (stage wi weir eq.)
Groundwater WL
Automatic WQ samplers
Benthic macro-invertebrates
Channel cross sections
Evans and Smith 2000
Bass 2000
Bass and Evans 2000
Smith and Evans 2004
Graduate study in progress
Graduate study in progress
Smeltz 2004
Smettz et al. 2004
Lindow et al. 2007
Graduate study in progress
1995 to 1999
1997 to 2000
1998 to 2003
1999 to 2003
2000 to 2006
2003 to present
1999 to present
'Flow computed from stage data and appropriate weir formula.
Notes: WQ ~ water quality samples for chemical analysis. WL ~ water level measurement.
zone and considerable distance (50 to 100 m(150 to 300 ft)) upslope perpendicular to theriparian zone have been lowered (Gilliam andSkaggs 1981; Skaggs et al. 1994). In bypassing the floodplain, there is less opportunityfor potential pollutants in the drainage waterto be filtered and assimilated. Restoration ofriparian zones has become a major initiativequalifYing for costs share assistance throughnumerous federal and state incentive programs. WIllie water quality and habitatrestoration have become priorities for thegeneral public, wetness is still a concern tomany landowners. However, intensive drainage systems sometimes remove more waterthan necessary to satisfY agricultural requirements, especially on sandy soils during drierperiods, which may lead to the problem of"over drainage" (Doty et al. 1982).
Early Attempts to Address AgriculturalDrainage Water QualityControlled drainage has been implemented ineastern orth Carolina to address the issueof over drainage and agricultural drainage
water quality. Controlled drainage involvesthe use ofadjustable, flow-retarding structuresplaced in drainage outlets to allow the waterlevel in the outlets to be artificially set. Manytypes of structures can be used depending onthe layout of the drainage system (Evans andSkaggs 1985; Evans et al. 1992; Evans 2003).When properly managed, controlled drainagehas been documented to reduce the transportof nitrogen in agricultural drainage watersby as much as 40% (Evans et al. 1995; Fauseyet al 2004). In 1985, controlled drainage wasadopted as a best management practice byNorth Carolina and as such qualified for costshare assistance to landowners under the NorthCarolina Agricultural Cost-Share Programadministered by the North Carolina Divisionof Soil and Water Conservation (Evans andSkaggs 2004). Since 1985, approximately 3500water control structures have been implemented on about 120,000 ha (300,000 ac)across eastern North Carolina. The practiceofcontrolled drainage is now being promotedby the Agricultural Drainage ManagementSystems Task Force-a multi state, multi
agency work group-as a practical means toreduce the transport ofnitrogen originating inthe upper Mississippi Valley ii-om getting intowaterways and contributing further to thehypoxic zone in the Gulf of Mexico (ADMS2003).
The rate of implementation of controlleddrainage peaked in North Carolina at about10,000 ha yc l (25,000 ac yr- I
) in 1991 (Evansand Skaggs 2004). Resurgence in public concern and interest in water quality arose in theearly 1990s following several major fish killsin the lower Neuse River and Albem.arle/Pamlico Sound Estuary. Controlled drainagewas one of several practices reconU11endedfor agricultural lands to address this problem;however, significant increase in controlleddrainage implementation did not occur. As aresult, the authors initiated a variety of demonstration practices to be used in addition to,or in conjunction with, controlled drainageto further reduce the transport of nutrients,especially nitrogen, in agricultural drainage.Seven demonstration projects are discussedin this paper.
I JULY IAUGUST 2007 VOLUME 62, NUMBER 4 ~
Figure 1In-stream wetland reach ofTull Creek project.
-e
Figure 2Schematic of water management treatments and sample locations, lull Creek project.
e Stage recorder and water sample locations
) Water control structure locations
bankfull Q was within an acceptable range.No increase in the water smface profile wasconsidered acceptable within urban watersheds while about a 50 mm (2 in) rise in thewater surface profile was considered acceptable for agricultural watersheds. Practicalapplications of this design rationale are discussed for several of the following projects.
Tull Creek ProjectThe first drainage alternative project wasinitiated in the Tull Creek watershed inCurrituck County, North Carolina, in 1995.The project involved a 1.6 km (1 mi) reachof the main canal system draining approximately 80 ha (200 ac)of cropland. Onereach of the canal (530 m [1,750 ft]) wasmanaged in the traditional "free" drainage
r---
-Controlled
Conventional Controlled drainage widrainage drainage wetland plantssection section section
e • e. eJ1'1 1500ft -I
Earthen plug
1
what it was prior to the project. HEC-RAS,Hydrologic Engineering Center's RiverAnalysis System (USACE 2002), was used toevaluate the impact of the channel alternatives and!or design parameters on the watersmface profile before and after the implementation of each project. The hydraulic designprocedure involved evaluating the existingcondition for each channel using HEC-RASand determining bankfull Q.The HEC-RASanalysis was then repeated incorporating thechannel alternative (weir, in-stream wetland, floodplain, etc.) and the water smfaceprofile re-com.puted and compared to thepre-project condition. Appropriate channeldimension, for example cross sectional area,was adjusted (sized) in HEC-RAS until thenew water sur£1Ce profile for the pre-project
Drainage Canal Alternatives EvaluatedPilot studies were begun in 1995 to demonstrate and evaluate alternative managementstrategies and channel design geometries thatmight enhance water quality and ecologicalfunctions while maintaining the necessarydrainage function of channelized streams.Channel alternatives included the following:
• Establishment of in-stream. wetlands.• Restoration of riparian wetlands and
buffers.• Re-design of channels using natural
channel design principles to reconnect thechannel with the existing natural floodplain(priority I restoration).A priority I restorationtypically retains the original floodplain elevation and moves the channel laterally withinthe existing floodplain and raises the channelbed elevation to accomplish reconnectionwith the existing floodplain. The new channel bottom is established at approximatelythe pre-drainage!channelization elevation.This results in a more natural channel-floodplain system, but upslope (perpendicular tochannel) and upstream lands may becomesusceptible to pre-drained flooding orwetness conditions.
• Lowering of the floodplain to reconnectthe floodplain to the existing channel (priority II restoration). A priority II restorationestablishes both the channel and floodplainat a new "lower" elevation than occurrednaturally. This is a more"engineered" system,is more costly to construct, but maintains thepost-drainage capacity of the system and protection of both upslope and upstream. lands.
• Establishment ofconservation easementsto eliminate traditional ditch bank mowing and facilitate establishment of perennialriparian vegetation.
It is beyond the scope of this paper toprovide detailed descriptions of each project including methodology used to monitorand evaluate each practice's effectiveness toaddress water quality and ecological goals.Instead, only general observations thataddress project characteristics and performance are presented herein. The reader isdirected to original publications for detailedproject descriptions, explanation ofmonitoring methodology, and scientific analysis andresults (table 1).
Maintenance of pre-project high flowdrainage capacities were a design requirement on all projects. That is, the capacity ofeach channel (Q) under high flow conditions (bankfull) could not be reduced below
~,-__JO_U_R_N_A_L_O_F_S_O_IL_A_N_D_W_A_T_ER_CO_N_S_E_R_VA_T_IO_N__
Table 2Outflow and water quality characteristics. Tull Creek project. January 19.1996. to September 29. 1999 (after Evans and Smith 2000)
Treatment
Controlled drainage w/plants
Controlled drainage
Conventional drainage
Outflow NOiN
2.3a
1.6ab
O.8b
Mean concentrations (mg L-')
NH.-N TN TP OP
O.6a 4.la O.09b O.04b
O.8a 4.4a O.13b O.04b
O.5a 2.6b O.3la O.26a
Outflow (mm yr-') and mean mass transport (kg ha-' yr-')
Sediment
5.lb
8.8ab
l2.3a
Controlled drainage w/plants 330ab 7.4a 1.9a l3.6a O.29b
Controlled drainage 229b 3.6b 1.8a 9.9a O.29b
Conventional drainage 500a 3.9b 2.3a l3.0a 1.56a
Note: Values followed by the same lower case letter vertically (within groups) are not significantly different at the 5% level.
O.13b
O.09b
1.30a
l5b
l8b
55a
mode, a second reach was managed in the"controlled" drainage mode, and the thirdreach was planted with a variety of wetlandplants (figure 1) to provide a combination instream wetland/controlled drainage system.Approximately 4,500 plants were planted inthe wetland section. Based on visual observations made during September 1996 and plantsurveys conducted at the end of the secondgrowing season, over 90% of all species,except cattail, survived. Annual re-growth ofwetland vegetation was excellent throughout the evaluation period (1996 to 1999).The outlet of each reach was instrumentedto continuously measure outflow (figure 2).Grab samples were collected monthly toevaluate treatment effects on water quality.In general, nitrogen (N) concentrations werehigher while phosphorus (P) concentrations were lower with drainage control bothwith and without the addition of wetlandplants (table 2). Total flow, P, and sedimenttransport were significantly lower with bothcontrolled drainage treatments.
The addition of plants did not appear toprovide an additional water quality benefitother than an improvement in water clarity over drainage control alone. Habitat
. benefits may have been enhanced by theplants, but habitat benefits were not evaluated. This initial project demonstrated thatit was possible to maintain wetland plants indrainage ditches without frequent mowingor adversely impacting the drainage performance of the ditch.
Liza's Bottom ProjectThe Edenton urban project, initiated in1997, involved construction to lower theold floodplain along approximately 400 m(1,320 ft) of stream known as Liza's Bottomand create approximately 1 ha (2.5 ac) ofin-stream wetlands. The stream carnesdrainage waters from agricultural lands and
runoff from commercial and urban sourcessuch as a solid waste transfer site and aformer farm supply facility. The channel wasinitially channelized prior to 1900 and wasroutinely cleaned out thereafter such thatthe riparian floodplain was rarely functional.A 1 ha (2.5 ac) wetland was constructedin April to May in 1997. The wetland wasbuilt by excavating the existing hydraulicallydisconnected floodplain down to the streambase-flow level and raising the streambottom (figure 3). The soils found in thefloodplain and used for the wetland substrate were variable, with some reduced andhigh in organic matter and others clayey incontent. Islands were built in the interior tominimize transportation of cut/fill material and create a more sinuous flow path. Alow head, wooden bulkhead was installedat the outlet to maintain water depths of0.1 m to 0.5 m (6 to 18 in). The wetlandbottom was graded for a mixture of shallowand deeper pool areas. Native plants wereused in the wetland and transplanted on a1 m x 1 m (3 ft x 3 ft) spacing. The wetlandintercepts drainage waters fi'om approximately 240 ha (600 ac) of surroundingwatershed. One hundred and sixty hectares(400 ac) are attributed to agricultural andnatural forested area, 60 ha (150 ac) to urbanarea, and 20 ha (50 ac) to intensive conllilercial areas. The resulting watershed/wetlandarea ratio is 100:1, which is less than half theminimum size typically reconllilended in theliterature (Scheuler 1992).
The wetland was instrumented tocontinuously measure inflow and outflow(figure 4). Flow measurements were made atthe two main inlet streams (E2 and E3) andat the wetland outlet (E1) using continuouswater level recorders. Stage measurementswere combined with weirs and calibrateddischarge curves to generate a continuousmass flow record at E1 and E3. However, no
weir was installed at the agricultural inlet,E2. Instead, a stage-discharge curve wasdeveloped at E2 by computing flow usingManning's formula from continuously measured stage and flow velocity at the nearbyculvert (Bass 2000). As a check, drainageoutflow from the agricultural watershed wasalso simulated using DRAINMOD (Skaggs1978) and compared to the wetland inflowestimate at E2. Good agreement (estimatedversus simulated water balance closed within5%) was observed between the estimatedand simulated inflow to the wetland atE2 so it was concluded that the overall flowsobserved were reasonable for use with concentration data to predict nutrient masstransport (Bass 2000). Background grabsamples were acquired bi-weekly upstreamand downstream of the planned wetlandreach from January 1996 until constructionbegan in May 1997. For a six month periodfollowing construction of the wetland, flowproportional water samples were collected atthe wetland inlets and outlet using automaticsamplers. Twice daily time based samplingoccurred thereafter.
During base flow conditions, attenuationwithin the Liza Bottom constructed wetland was approximately seven days with nosignificant attenuation during large stormflows. Prior to 'wetland construction, therewere no changes in ammonium (NH
4-N)
concentrations between up and downstreammonitoring locations while nitrate-nitrogen(N0
3-N) showed a 40% decrease indicat
ing some nitrate was likely being removedalong the stream by denitrification. itrogenconcentrations were consistently lowerand P concentrations consistently higher atthe wetland outlet compared to the inlet(table 3).Yearly and seasonal means indicatedthat significant improvements in N0
3-N and
NH.-N concentrations can be achieved withrelatively small wetlands. Initially, total- and
I JULY IAUGUST 2007 VOLUME 62, NUMBER 4 ~
Figure 3Liza's Bottom in-stream wetland, Edenton, construction completed May 1997.
Figure ItSchematic of monitoring locations at Liza's Bottom in-stream wetland, Edenton.
Wetland outlet
E1•
A
Solid wastetransfer station
E31150 ac:urban
Side ditch
400 ac agricultural500 ac commercial
ortho- P concentrations were unchangedby the wetland. However, by the end of yeart\;yO, P concentrations began to increase.The P increase at the wetland outlet mayhave resulted from reduction of iron-Pcomplexes as the aerable soils used for substrate became reduced, solublizing the iron(Vepraskas and Faulkner 2001). However,redox measuren"lents were not made, so
[ ~'-~JO-U-R-N-A-L-O-F-5-0-1L-A-N-D-W-A-T-ER-C-0-N-5-E-R-VA-T-IO-N~-
Pre-constructionA
Post-construction
there is no conclusive explanation for theP increase. Over the four-year monitoring period which ended December 2000,N0
3-N concentrations were reduced by 60%,
NH"- by 30%, and TK by 9.5% resultingin a flow-weighted total nitrogen reductionof 20% (table 4). During the last two yearsof monitoring, there was a net increase in Pdischarge fi-om the wetland of 55%.
Implementation of Water ManagementService Districts: Case Study ExamplesThe Newland Ditch watershed project(7,000 ha [17,000 ac]) and Guinea Millwatershed project (2,000 ha [5,000 ac])were initiated in 1998 and 1999, respectively, to address drainage and waterquality issues arising from rapid urbanization ofpredominately rural counties. Resultsof the Liza Bottom project previously presented showed potential for using in-streamwetlands to reduce the transport of nitrogen. The Newland Ditch and Guinea Millprojects represent the implementation of thispractice on a large watershed basis. Neitherof these watershed projects were instrumented to collect quantitative water qualitydata. However, they are important to the discussion in this paper in that they representdeviation fi-om traditional "drainage only"land management practices to multi-purposeprojects that address regional water management and water quality issues. They alsodemonstrate willingness of local landownersto adopt new water management alternativesfor goals other than just drainage.
A significant component of the NewlandDitch and Guinea Mill projects was formation of tax-supported Water ManagementService Districts, the first in North Carolina.Historically, federal legislation such as theDrainage Districts Acts of 1885 and 1903established authority for states and countygovernments to organize drainage districtsfor the purpose of draining agricultural landsand to reclaim swamps and other wet lands(Beauchamp 1987). While drainage districtlaw has been effective for providing authority to drain lands, it can be prohibitive forimplementation of practices within drainagedistrict's jurisdiction for purposes other thandrainage improvement. For example, underdrainage district law, penalties can be assessedfor activities such as addition of weirs orstructures to control flow for the purposeof improving drainage water quality. Thisconstraint has prevented the installation ofwater control structures in North Carolinawithin drainage district right-of-waysfor the purpose of providing controlleddrainage (based on authors' frequentexperiences).
Under North Carolina Statute, a servicedistrict operates similarly to a drainage districtin terms of establishment, taxation and governance. The advantage of a service district isthe ability to incorporate multiple objectives
Table 3Constituent concentrations at Liza's Bottom in-stream wetland inlets and outlets (after Bass and Evans 2000).
Mean concentrations (mg L-1)
Nutrient Inlet
1997
Outlet Inlet
1998
Outlet Inlet
1999
Outlet Inlet
Overall
Outlet
N03-N 0.6a 0.5a 0.7a 0.2b 0.6a 0.2b
NH.-N OAa OAa 0.6a OAb 0.5a OAb
TKN 1.3a 1.2a 2.0a 1.9a 2Aa 2.1a
TP 0.31a 0.36a 0.32b 0.56a OA7b 0.64a
OP 0.20a 0.28a 0.24b OAla 0.34b OA5a
Note: Values followed by the same lower case letter (horizontally within years) are not significantly different at the 5% level.
Source: After Bass (2000).
0.6a
0.6a
2.1a
0.37b
0.27b
0.2b
OAb
1.9b
0.57a
OA2a
Table IfOverall nutrient reductions on concentration and mass basis, Liza's Bottom wetland, Edenton.
in the charter whereas a drainage district byNorth Carolina Statute has one objective,that being drainage or flood protection. Inthe case of a Service District, it becom.es theresponsibility of the leadership to determineon a case by case basis what activities achievethe overall goals of the District. For example,a service district can have an objective ofproviding flood protection but at the sametime allowing installation of a water controlstructure to enhance water quality. If it isdeemed that water quality is more imp01'-
tant to the District than drainage, drainagecan be compromised for the benefit of waterquality. This has major implementations formulti-use projects in watersheds traditionallygoverned by drainage districts.
Guinea Mill Project. The Guinea Millwatershed resulted in 289 parcel owners, theInajority in eight major subdivisions, executing taxation easements to maintain theproject. Permanent conservation easementsinvolving 20 ha (50 ac) along both sides ofthe canal were purchased and are managed by
Concentration basis
Mass basis
N03 N
60%
55%
30%
16%
TKN
9.5%
6%
TN
20%
18%
TP
-55%
-50%
OP
-55%
-50%
the county utilizing an advisory board comprised of five landowners in the watershed.The advisory board is charged with the dutyof investigating, studying and making recommendations to the Board of Conmussionerspertaining to the construction, enlargement,improvement, maintenance, operation andregulation of the service district. A countyordinance was established requiring all newsubdivisions and any landowners encroaching on the easement and canal to submit aplan for that encroachment (i.e., culvert,drainage swale, etc) to the service districtprior to installation.
Fourteen kilometers (9 nu) of riparianbuffers were established along the GuineaMill canal. Where f.1rnung used to occurnext to the stream bank, buffers are established with vegetation maintained 0.3 to1 m (1 to 3 ft) high. In-stream constructed
Figure 5Lower section of Guinea Mill after installation of riparian buffer andinstream wetland.
Note: Path was moved away from canal bank.
Figure 6Rock weir raises upstream water level at base flow enhancinghydrologic function of upstream swamp, Guinea Mill project.
Note: Upstream water level is raised about 1 m.
JULY IAUGUST 2007 VOLUME 62, NUMBER 4
Figure 7Section of Shepard Ditch during dry period after establishment ofwetland plants on constructed ledge (right bank), NewlandDitch project.
Figure 8Vegetative buffers were established along ditch banks and thechannel was widened to maintain capacity at the rock structures,Newland Ditch project.
In additionManagement
Figure 9View of lower floodplain after third growing season, Edenton Airport project.
wetlands (figure 5) were installed on3.4 ha (8 ac) within the Guinea Mill canal.In the wetland section, the canal was widened from 10 to 20 m (30 to 70 ft). Thewidened channel section increased the crosssectional area of the channel to offset theincreased flow resistance resulting from thewetland plants. Two in-stream wetland cellswere constructed, one approximately 2 km(1.3 nil) and the second about 1 km (0.6 milin length.
A rock weir water control structure wasinstalled to enhance hydrologic function atlow flows in the main channel.The rock weir(1 m high by 1.2 m top width by 21 m length[3 ft high by 4 ft top width by 70 ft length])was located just downstream ofa 15 ha (40 ac)hardwood swamp (figure 6). The hydrologyof the swamp had been significantly altered(water table lowered) by channelization ofGuinea Mill canal. The rock weir raised thebase flow elevation by approximately 1 m(3 ft), restoring some hydrologic function tothe riparian swamp in terms of raised watertable level and more frequent overflow intothe swamp. In addition, a scour pool formeddownstream of the rock weir which has thepotential to enhance aquatic habitat. As inprevious examples, the channel was widenedin the vicinity of the rock weir to offset thereduction in flow depth resulting from theweir. Annual inspections of all conservationeasements are made by the Advisory Boardand the Currituck SWCD Board withtheir respective reports submitted to theCounty commissioners.
Newland Ditch Project.to establishment of a Water
Service District, this project involved excavation of the two nuin channels (158 Canaland Sheppard Ditch) to stabilize streambanks. The ditch bottoms were excavated tocreate a ledge for establishment of just over1 ha (2.5 ac) of in-stream constructed wetlands (figure 7). Five associated rock weirwater control structures (figure 8) wereinstalled to enhance base flow hydrology andecological function. At each rock weir, thechannel was widened to maintain the sainecross sectional area as existed prior to theproject so that the channel capacity will not
be reduced at high flows. Vegetative bufferswere established along 4.2 km (2.6 nil) of the158 Canal and 3.6 knl (2.3 mil on SheppardDitch. Annual inspections are nude by theadvisory board and the Pasquotank SWCDBoard with their respective reports submitted to the county cOlnnussioners.
Edenton Airport ProjectThe Edenton Airport and Industrial Parkrestoration and enhancement project inChowan County was initiated in 2000. Aspart of the construction and developn"lent
JOURNAL OF SOIL AND WATER CONSERVATION~IL-- ___=_~
Figure 10Constructed stream and floodplain of small headwater stream, upper reach of Edenton Airport project.
Figure 11Constructed storm water wetland in series in drainage system, midreach of Edenton Airport project.
of the Edenton Army Base in the 1930s,the lower stream reach of the watershedwas channelized with the spoil deposited inthe adjacent floodplain and a short circuitcutoff constructed that shortened the flowpath of drainage water to the AlbemarleSound by more than one km (0.6 nul. Thisproject involved three hydrologic enhancements. The first involved restoration ofstream and riparian floodplain functions inthe lower stream segment. Spoil piles wereremoved to restore hydrologic functionsin terms of more frequent diffuse overlandflow and raised water table elevations withinthe floodplain. Re-growth maples werereplaced with cypress and mixed bottomland hardwood species. At several locations,the straightened, channelized stream wasre-routed back through existing floodplain(figure 9) at its original elevation (priorityI restoration). Priority I restoration involvesraising the streambed elevation to re-connectthe stream to the existing floodplain.
The second hydrologic enhancementinvolved construction of a 300 m (1,000 ft)reach of stream and riparian floodplain(priority II). Priority II restoration involveslowering the floodplain (stream valley) elevation to an appropriate elevation based on theexisting stream bed elevation. Final designconsisted of a 250 m (800 ft) stream/wetland valley with floodplain width varyingfrom 7 to 10 m (20 to 30 ft).The stream wasdesigned to meander within the wetlandvalley (figure 10). The resulting sinuosity is1.25 (stream length divided by valley length).The stream/wetland system was designedto be from 0.5 to 1.5 m (1.5 to 5 ft) beloworiginal grade. Lastly a series of two stormwater wetlands were constructed between theconstructed and restored stream reaches(figure 11). A schematic of the flow pathand monitoring locations for this project areshown in figure 12.
Water quality monitoring showed meanpollutant concentrations for all samplinglocations (table 5) were lower than typicalagricultural watersheds (Evans et al. 1995;Skaggs et al. 1994). The relatively undeveloped status of the watershed was mostlikely a causative factor for the low concentrations. All constituent concentrationsdecreased through the constructed stream/floodplain reach of the system (uppermostcomponent of the project). Nitrate-N wasreduced through the constructed stormwaterwetland (midreach) but other constituents
were unaffected or increased. All N speciesdecreased through the further most downstream component of the project (restoredfloodplain swamp) but both P and sedimentconcentrations increased. The increase insediment concentration in the stormwater and restored swamp wetlands was likelythe result of muskrat (Ondatra zibethicus) and
nutria (lVJ.yocaster coypus) disturbance of thebottom sediments. Both species were common in areas of standing water. Disturbanceof the sediments might also account forthe increase in total phosphorus. Wetlandprocesses were likely the primarily causeof nitrate reduction throughout the system.Nitrate reduction on a concentration basis
I JULY IAUGUST z007 VOLUME 6z, NUMBER 4 GiJ
Figure 12Schematic of Edenton Airport project showing surface water sampling locations.
Industrial parkwas relatively high, likely due to the relativelylow inflow concentrations.
Outlet to Albermarie Sound
Location TKN NH4N N0
3N TN TP Sediment
Golf Course ProjectAn innovative approach was initiated in 2003to manage poor drainage and storm water atthe Chowan Golf Course. Existing drainage ditches were redesigned utilizing natural channel design concepts (Rosgen 1995)along with HEC-RAS hydrologic analysisand were then interconnected to a networkof twelve constructed storm water wetlands(figures 13 and 14) ranging in size from 0.1to 2 ha (0.25 to 5 ac). On this project, theratio of watershed area to wetland area is10: 1. All storm water conveyance channelsand wetlands are protected by a permanentconservation easement under the control ofthe county commissioners.
The golf course wetland system wasdesigned to store and treat the first 50 nU11(2 in) of runoff which is recycled back ontothe course through irrigation resulting in anearly "closed" system except for very largeevents. Evaluation of the hydrologic andwater quality pet{ormance of this system isin progress. Inflow samples to each wetlandare collected for chemical determinationusing passive composite samplers installedin fain¥ay catch basins. Water level stage ismeasured in each wetland using continuouswater level data loggers. Outflow rate fromeach wetland is controlled by a small, Vnotch, orifice type weir such that dischargeis relatively constant.
Storm water retention durations in thewetlands have ranged fron1 3 to 30 daysdepending on storm size and the watershedto wetland area ratio. After three growingseasons, there has been no visible adverseeffect on wetland plants from large fluctuations (30 to 50 cm) in water levelswithin the wetlands resulting from thelarge range in stormwater retention time.Nitrogen concentrations spiked brieflyfollowing heavy fertilization applied toestablish the fairways in 2003 which werebeing established at the same time the wetlands were establishing (data not shown). Asa result, the inunature wetlands did not havethe capacity to assimilate the initial pulse ofN in the runoff. After the initial growingseason (establishment phase), concentrationsof the various species of Nand P have beenreduced by the six wetland cells from 16%to 56% on average (table 6). There is considerable variation from wetland to wetland.
Restored swamp floodplain
Outflow sampler
Constructedfloodplain valley
Outflow sampler
I '-..IL--,?" Restored swamp channel
/ Inflow sampler
Constructedheadwater natural
channel design
"' Undergrounddrainage conduit
Stormwater wetland 1Conventional
ditch
Upperproject reach
Inflow sampler
Middleprojectreach
Lowerproject reach
0.5 ha mid-reach constructed wetland
Inflow (mg L-ll 1.51 0.39 0.07 1.58 0.24 33
Outflow (mg L-ll 1.66 0.39 0.02 1.67 0.24 48
Reduction -10% 0% 71% -6% 0% -45%
Downstream 600 m restored floodplain swamp
Table 5Mean inflow and outflow concentrations in three wetland components of the Edenton Airportproject, October 1999 to January 2004 (after Evans and Smith 2004).
Upstream 300 m reach of constructed stream and associated constructed floodplain
Inflow (mg L-ll 2.87 0.37 0.08 2.94 0.40 229
Outflow (mg L-ll 1.48 0.18 0.02 1.50 0.24 42
Reduction 48% 51% 75% 49% 40% 82%
Inflow (mg L-ll 3.88 3.58 0.45 4.03 0.30 39
Outflow (mg L-ll 3.49 2.53 0.03 3.51 0.56 101
Reduction 10% 29% 93% 13% -87% -160%
Note: Reduction (%l = (inflow concentration - outflow concentration)/inflow concentration x 100.
JOURNAL OF SOil AND WATER CONSERVATION~'---------------
Figure 13Constructed stream channel with riparian floodplain immediatelyafter construction, Chowan Golf Course project.
Figure 11tConstructed stream and wetland six months after planting, ChowanGolf Course project.
Table 6Summary of mean inflow and outflow concentrations in six stormwater wetland cells on theChowan Golf Course project. Values are for calendar years 2005 and 2006.
Location TKN NH4N N0
3N/N02N TP OP
Wetland cell number 1
Inflow concentration (mg L") 3.10 0.19 0.05 1.67 1.17
Outflow concentration (mg L") 2.50 0.17 0.09 1.23 1.03
Reduction 19% 11% -80% 26% 12%
Wetland cell number 3
Inflow concentration (mg L") 3.42 0.21 0.05 1.77 1.23
Outflow concentration (mg L") 1.33 0.03 0.00 0.53 0.19
Reduction 61% 86% 100% 70% 85%
Wetland cell number 6
Inflow concentration (mg L") 2.19 0.08 0.03 2.42 1.81
Outflow concentration (mg L") 1.20 0.09 0.00 0.77 0.48
Reduction 45% -13% 100% 68% 73%
Wetland cell number 9
Inflow concentration (mg L") 3.60 0.17 0.06 1.82 1.29
Outflow concentration (mg L") 2.26 0.11 0.02 0.83 0.48
Reduction 37% 35% 67% 54% 63%
Wetland cell number 18
Inflow concentration (mg L") 3.60 0.20 0.18 2.12 1.83
Outflow concentration (mg L") 2.58 0.27 0.18 1.13 0.87
Reduction 28% -35% 0% 47% 52%
Wetland cell number 19
Inflow concentration (mg L") 2.91 0.12 0.05 1.73 1.19
Outflow concentration (mg L") 2.62 0.14 0.02 1.01 0.70
Reduction 10% -17% 60% 42% 41%
Mean six wetland cells
Inflow concentration (mg L") 3.14 0.16 0.07 1.92 1.42
Outflow concentration (mg L") 2.08 0.14 0.05 0.92 0.63
Reduction 34% 16% 26% 52% 56%
Note: Reduction (%) = (inflow concentration - outflow concentration)/inflow concentration x 100.
This is due in part to differences in watershed to wetland area ratio, which has not yetbeen accounted for in table 6. Wetlands 18and 19 also have more open water which hasattracted geese, which could be an additionalsource of N which is not accounted for inthe inflow measuren'lents.
Core Creek ProjectThe Core Creek project consisted of relocation of an unnamed channelized streamwithin the Core Creek watershed that hadbeen significantly impacted by cattle access(figure 15). The degraded stream was a G5class (Rosgen classification system) channelized stream with severe bank erosion anddegraded water quality. Prior to construction, background monitoring showed therewas no significant difference in upstream anddownstream N concentrations (upstreamand downstream of the planned constructionreach) (table 7). Phosphorus concentrationsand fecal coliform levels downstream weresignificantly higher than upstream. Macroinvertebrate sampling indicated that thequality of the stream was severely stressed(Smeltz 2004).
A new channel was designed using a combination of analog, empirical, and analyticaldesign techniques (USACE 1995; Shieldset al. 2003). The relocated E5 channel wasconstructed using priority II methodologyin March of 2005. The constructed streamconsisted of a uniform dimensional section, meandering pattern, and 0.1% slope(figure 16).A 30 to 40 m (100 to 130 ft) wide
I JULY IAUGUST 2007 VOLUME 62, NUMBER 4 ~
Figure 15Cattle in Core Creek tributary stream prior to restoration.
Table 7Nutrient and suspended sedimentconcentrations in stream flow prior tocattle exclusions, Core Creek project.
Downstreamof pasture
Upstreamof pastureNutrient
Summary and ConclusionsPilot studies were demonstrated and evaluated to investigate alternative channel designgeometries and management strategies toencourage water quality and ecologicalfunctions while maintaining the necessary drainage function. Channel alternatives included establishment of in-streamwetlands, lowering of the floodplain toreconnect the channel with the floodplain,redesign of channels using natural channeldesign principles to reconnect the channelwith the natural floodplain, and· establishment of conservation easements to eliminatetraditional ditch bank mowing to encourageestablishment of perennial riparian vegetation. Results to date indicate that alternativesexist that can be used to address drainage,water quality and ecological functions moreeffectively than have been achieved in thepast with conventional trapezoidal drainage canals. Of course, all of the alternativesevaluated are more costly than conventionaldrainage canals required to achieve just the
Total N (mg L-l) 2.45 2.45
N03-N (mg L-l) 0.33 0.32
NH.-N (mg L-1) 0.33 0.65
Total P (mg L-l) 0.38 0.50
Ortho-P (mg L-l) 0.11 0.25
TSS (mg L-l) 96.9 46.3
Note: Data from Smeltz (2004).
designed to meet expected channel hydraulics and regional geomorphology (Lindow etal. 2007). Bank mass wasting and slumpingoccurred during and inunediately followingconstruction. This was due to soil instability caused by a pressurized sand layer at theconstructed streambed elevation. This areastabilized as soon as bank vegetation becameestablished. Water quality monitoring andevaluation S111ce construction IS ongoing. Initial macro-invertebrate monitoringindicates improvement in aquatic habitatcompared to the original channel.The streamand associated floodplain appear to be stableand have the capacity to transmit greaterflood volumes than the original trapezoidalchannel without a floodplain (Lindow et al.2007).
(figure 17). Log vanes were used to holdgrade and root wads to armor banks. Flowhydraulics and design structures controlledrime/pool formation (figure 18).
Since construction, periodic cross sectionmeasurements indicate the re-located streamdimension, pattern, and profile were well
stream valley was constrllcted by stockpiling150 nun (6 in) of topsoil then removing 0.5to 0.6 m (1.5 to 2 ft) of subsoil. The topsoil was then redistributed across the valleyfollowed by construction of a 3.5 m (topwidth) by 0.5 m (depth) (14 ft by 1.5 ft)E5 channel with an average sinuosity of 1.3
Figure 16Schematic of Core Creek natural channel design.
318 JOURNAL OF SOIL AND WATER CONSERVATION
Figure 17Core Creek relocated stream just after construction.
Figure 18Core Creek relocated stream one year after construction.
drainage function. A conventional trapezoidal channel of comparable flow capacity(2 to 2.5 m 2 cross sectional area by 1.5 mdeep [80 ft2 by 5 ftJ) would costs about $35/linear meter ($1 a/linear ft) based on an earthmoving rate of $4/m3 ($3/yd3
). The projectcosts in these studies ranged from a low ofabout $7/linear m ($2/linear ft) for wetland
planting in the existing canal (Tull Creekproject), $130 to 200/linear m ($40 to 60/linear ft) of channel for weirs, channel excavation, and planting of in-stream wetlands(Edenton, Guinea Mill, and Newland Ditchin-stream. projects), to over $450/linear m($140/linear ft) of channel where floodplain construction was also required (Core
Creek project). Increased costs were associated with the initial costs of additional earthwork required to either widen channels orcreate artificial floodplains and the largerland areas being taken out of production.These projects accon'lplish the first step inthe evaluation process which is to demonstrate technical feasibility. The added costs arenot justified by increased drainage benefits tothe landowner.Therefore, it becomes incumbent on society to put a value on the waterquality and ecological functions achieved todetermine if public funds should be used tohelp landowners offset the costs of achievingthe additional water quality and ecologicalfunctions.
AcknowledgementsThe projects discussed herein were supported by a com
bination of grams from the North Carolina Clean Water
Management Trust Fund, North Carolina Department of
Environment and Natural Resources 319(h) Program, North
Carolina Agricultural Cost Share Program, North Carolina
Conservation Reserve and Enhancement Program, and
USDA farm bill along with local government and landownerin-kind contributions.
Portions of this work were presented and printed in the
Proceedings of the Alnerican Society of Agricultural
and Biological Engineers Specialty Conference "Self
Sustaining Solutions for Streams, Wetlands, and Watersheds,"
Sr. Paul, Minnesota, 2004, and in the Proceedings of rhe
19th International Congress on Irrigation and Drainage,
"Improving Water and Land Management for Increasing
Efficiency in Irrigated Agriculture," Beijing, China, 2005.
ReferencesADMS (Agriculture Drainage Management System). 2003.
Agricultural drainage water management systems for
improving \:vater quality and increasing crop produc
tion. Advanced Drainage Systems Management Task
Force Factsheet: www.agridrain.com/Literature/
Drainage%20Fact%20Sheer_posr-final%20version.pdf.
Bass, K.L. 2000. Evaluation of a small in-stream constructed
wetland in North Carolina's Coastal Plain. MS thesis.
North Carolina State University, Raleigh.
Bass, K.L., and R. O. Evans. 2000. Warer quality improve
ment by a small in-stream constructed wetland in
North Carolina's coastal plain. In Proceedings of the
Watershed Management 2000 SymposiU111: Science and
Engineering for the New Millennium, ed. M. Flug, and
D. Frevert.
Beauchamp, K.H. 1987. Chaprer 2: A hisrory of drainage
and drainage methods. In Farm Drainage in the United
States: History, Status and Prospects. ed. G.A. Pavelis.
USDA Miscellaneous Publication No. 1455.Washington,
DC: USDA Economic Research Service.
Cowan, T. 2007. Conservation Reserve Program: Status and
Current Issues. Congressional Research Service, The
Library of Congress. Order Code RS21613.
Doty, C.W, J.E. Parsons, A. Nassehzadeh-Trabizi, R.W
Skaggs, and A.W Badr. 1982. Deep ditch overd
rainage affects water table depth and crop yield. III
Environmentally Sound Water and Oil Management.
New York: American Society of Civil Engineering.
I JULY IAUGUST 2007 VOLUME 62, NUMBER 4 ~
Dukes, M.D., and R.O. Evans. 2003. Rip:1rian ecosystem
management model: hydrology performance and sensitivity in the North Carolina middle Coastal Plain.
Transactions of the ASAE. -\6(6): 1567-1579.Dukes, M.D., 1'..0. Evans,JW Gilliam, and S.H. Kunickis.
2002. facer of riparian buffer width and vegetation typeon shallow groundwater quality in the middle coastal
plain of North Carolina. TransJcrions of the ASAE
45(2):327-336.Dukes, MD., 1'..0. Evans,JW Gilliam, and S.H. Kunickis.
2003. lnreractive effects of controlled drJinage and
riparian buffers on shallow groundwater quality.journal of Irrigation and Drainage Engineering ASCE
129(2):82-91.Evans, R.O., and R.W Skaggs. 1985. Agriculrural water
management for coastal plain soils. N.C. AgriculruralExtension Service, Raleigh, AG-355.
Evans, R.o., JE. Parsons, K. Stone, and WB. Wells. 1992.
Water table managemenr on a watershed scale. journalorSoi! and Water Conservation 47(1):58-64.
Evans, R.O.,j.W Gilliam, and R. W Skaggs. 1995. Conrrolled
versus conventional drainage effects on water quality. journal of Irrigation and Drainage Division ASCE
121 (4):271-276.Evans, R.O., and J-T. Smith. 2000. Performance of an on
farm-in ditch wetland in northeastern North Carolina.Factsheet No. EBAE 00-228. Biological and Agricultural
Engineering Cooperative Extension.
Evans, R.O. 2003. Controlled drainage. III Encyclopedia ofWater Science, 121-127. NcwYork: Marcel Dekker Inc.
Evans, R.O., and R.W. Skaggs. 2004. Development of controlled drainage as a BMP in North Carolina. III Drainage
VIII, Proceedings of the Eight International Drainage
Symposium, ed. R. Cooke. Sacramento, CA: AmericanSociety ofAgriculmral and Biological Engineers.
Fausey, N.R., E.J. Doering, and M.L. Palmer. 1987. CllJpter-k Purposes and benefits of drainage. 11/ Elrlll Drainage
in the United States: History, St:ltus and Prospects, ed.C.A. P:1Velis, 48-51 USDA Miscellaneous Publication
No. 1455. \Vashington, DC: USDA Economic Research
Service.Fausey, N.R., K.W King, B.J. Baker, alld R.L. Cooper. 2004.
Controlled drainage performance on Hoytville soilin Ohio. 11/ Drainage VIII, Proceedings of the Eight
International Drainage Symposiulll, ed. R. Cooke, 84
88. Sacramento, CA: Arnerican Society of Agriculturaland Biological Engineers.
Gilliam,j.W, and R.W Skaggs. 1981. Drainage and agricultural development: Effects on drainage waters. III Pocosin
Wetlands, ed. C.J. Richardson, 109-12-\. Stroudsburg, pA:Hutchinson Ross Publishing Company.
Gilliam,JW., D.L. Osmond, and R.O. Evans. 1997. Selected
Agricultural Best MJn~lgell1enr Practices ro Control
Nitrogen in the Neuse River Basin. North CarolinaAgriculntral Research Service Technical Bulletin 311.
Raleigh, NC: North Carolina State University.
Lilly, J.P. 1981. A history of swamp land development inNorth Carolina. III Pocosin Wetlands ed. C.J.lt.i.chardson,
20-42. Stroudsburg, PA: Hutchinson Ross Publishing
Company.Lowr:mce, R.R. 1992. Groundwater nitrate and denitri
fication in a coastal plain riparian forest. journal ofEnvironmental Quality 21 :40 1-405.
Lowrance, 1'..1'.., R.L. Todd, J Fail Jr., 0. Hendrickson Jr.,R. Leonard, and L. Asmussen. 1984. Riparian forests as
nutriem filters in agricultural watersheds. Bioscience
34:374-377.Lindow, N., R.O. Evans, and K.L. Bass. 2007. Channel evo
lution and sediment transport in a restored sand bedstream. In Restoring Our Natural Habitat. Proceedings
of the 2007 EWRI World Environmemal and Water
Resources Congress. Tampa·, FL: ASCE. May. Compact
Disk.Mayer, I'M., S.K. Reynolds, and T.J Canfield. 2005.
Riparian bufFer width, vegetative cover, and nitro
gen removal effectiveness: A review of current science
and regulations. Office of Research and Development,National Risk Managemem Research laborarory,
USEpA/600/R-05/1 18.
Rosgen, D.L. 1996. Applied River Morphology. PagosaSprings, CO: Wildland Hydrology.
Scheuler, Thomas R. '1992. Design of Stormwater Wetland
Systems: Guidelines for Creating Diverse and EffectiveStormwJter Wetlands in the Mid-Atlantic Region.
Washington, DC: Metropolitan Washington Council of
Governments.Schwab, G.O., D.D. Fangmeier, W.J. Elliot, and R.K. Frevert.
1993. Chapter 13: Open channels. 111 Soil and WaterConservation Engineering 265-286. New York: john
Wiley and Sons.
Sheilds, ED. Jr., R.R. Copeland, Pc. K.1ngeman, M.WDoyle, and A. Simon. 2003. Design for stream res
toration. journal of Hydraulic Engineering ASCE
123(8):575-58-\.Skaggs, R.W '1978. A Water Management Model for
Shallow Water Table Soils. Report No. 13-\. Raleigh,NC: University of North Carolina Water Resources
Research InstinHt'.
Skaggs, 1'..w., M.A. Breve,andJ W Gilliam. 1994. Hydrologicand water quality impacts of agricultural drainage.
Environmental Science and Technology 24(1): 1-32.
Smeltz, H.L. 200~. Water quality assessment of a degradedstream prior ro resroration and nitrate reduction through
controlled drainage. MS thesis, North Carolina State
University, Raleigh, NC.Smeltz, H.L., R.O. Evans, D.L. Osmond, and GD.
Jennings. 2005. Nitrate reduction through controlleddrainage and nutrient management plans. ASAE Paper
052236. Tampa, FL: American Society of Agricultural
Engineers.Smith, J.T., and P....G. Evans. 2004. Hydrologic and surf.lce
water quality changes in a coastal wJtershed resulting £i'om stream restoration and constructed wetlands.
Factshect EBAE-04-2xx. Biological and Agricultural
Engineering Extension.Sweet, William v., and Jens W. Geratz. 2003. Bankfull
Hydraulic Geometry Relationships and RecurrenceIntervals for North Carolina's Coastal Plain. journal
of the American Water Resources Association
39(-\):861-871.USACE (United States Army Corps of Engineers). 1995.
Engineering and design-sedimentation investigationsof rivers and reservoirs. US Army Corps of Engineers
Manual, Publicarion Number EM 1110-2-4000.
Washington, DC: USACE.USACE. 2002. HEC-KAS I<.iver Analysis System Hydraulic
Reference ManuaL Version 3.1 CPD-69. Washington,
DC:USACE.USDA Farm Service Agency 2007. Conservation Reserve
Enhancement Program. Washington. DC: USDA Farm
Service Agency. \vw\v.fsa.usda.gov/FSA/webapp?area=
home&subject=copr&topic=cep.USDA Soil Conservation Service. 1971. Chapter 5: Open
ditches for drainage design, construction and maintenance. III Drainage of Agriculrural Lands. National
Engineering Handbook, , Washington, DC: USDA SoilConservation Service.
Vepraskas, M.J., and S.P Faulkner. 2001. Redox chemistry
of hydric soils. 11/ Wetland Soils, ed. J L. Richardson andM.J. Vepraskas. Boca Raton, FL: CRC Press.
JOURNAL OF SOIL AND WATER CONSERVATION~--------------