36
Alberta Infrastructure School Facilities Branch School Facility Evaluation Project Part II - Physical Condition School: Malmo Elementary School Date: 10 March 2000 Malmo Elementary School School District: Edmonton Public School District No.7 Location: 4716 115 Street Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 1

Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Malmo Elementary School

School District: Edmonton Public School District No.7Location: 4716 115 Street

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 1

Page 2: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

EXECUTIVE SUMMARY

In March 2000, Alberta Infrastructure engaged R.L.Wilkin Architects Ltd. to evaluate the conditions of a number of schools within Edmonton Public School District No.7. The evaluation process and the forms provided were developed by Alberta Infrastructure and reviewed with the consultant prior to visiting this facility on 10 March 2000.

Little information was available from Edmonton Public Schools in terms of recent studies, roof inspections, etc., thus evaluations have been based primarily on the site visit and discussions with staff.

Malmo Elementary School was constructed in 1963 and had a major expansion built in 1969. The school was built on unique soils

repairs. The interior is very well maintained although showing its age in terms of floor finishes and wall finishes. The primary concern and/or deficiencies requiring attention, are the mechanical and electrical systems which both need significant upgrading to up-grade them to current standards.

Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing and brick wall cladding. As noted above, there is concern regarding the structural movement/shifting that occurs regularly, and its effect on other building components.

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 2

Page 3: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

EXECUTIVE SUMMARY cont'dSummary of Observations and Recommendations

As noted previously, the major items requiring attention are the mechanical systems and the electrical systems. A review of the soils conditions, the structural condition of the building, and how these two are related is also a high priority item.

Evaluation Ratings 3 or Less

The following estimates apply to items that were rated 1, 2, or 3 as described in the evaluation guidelines:

1. Site related work $ 68 000.2. Building Exterior 48 000.3. Building Interior 95 660. *costs may increase depending on outcome of items noted for further investigation4. Mechanical items 559 000.5. Electrical items 312 000. Total Estimated Costs $ 1 082 660.*

7. Space Adequacy AssessmentBased upon equivalent areas for a non-core school with a capacity of 500 elementary students (using guidelines provided by Alberta provided by Alberta Infrastructure) this school is slightly over (41.7 m2) the suggested area.Further InvestigationIt is recommended that further investigation be done in the following areas:1. A roof investigation to determine extent of roof repairs/replacement required.2. A thorough energy efficiency study should be completed prior to the necessary electrical upgrading.3. A hazardous materials evaluation is required prior to any repairs/upgrading. There is a concern re lead based paints.4. A thorough soils test and structural review should be completed to determine cause and possible solutions to the problems evident.

School Data/Plan Information

to outside agencies. These agencies have renovated areas within the leased spaces and this information should be noted.

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 3

Page 4: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

School Name: Malmo Elementary School School Code: 7186Location: 4716 115 Street, Edmonton Facility Code: 1212

Region: NORTH Superintendent: Dr. Emery DosdallJurisdiction: EDMONTON PUBLIC SCHOOLS Contact Person: Bob Clark, Acting Facilities Director

DISTRICT #7 Telephone: (780) 429-8511

Grades: K-6 School Capacity: 500

Year of Compl.

No. of Floors

Gross Bldg Area (Sq.M.)

Type of Construction (i.e., structure, roof, cladding)

Description of Mechanical Systems (incl. major upgrades) Comments/Notes

1963 1 2424.7 Masonry, precast roof structure, brick cladding.

Boilers with perimeter univent force flows. No building wide ventilation system.

1969 1 1600.01 As above.Same as 1963.

Evaluator's Name: Gordon Franklin& Company: R.L.Wilkin Architects Ltd.

Building SectionOriginal Building

Additions/ Expansions

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 4

Page 5: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

N/A

N/A

Edmonton Public School Maintenance Department Roof Inspecting 1997

List of Reports/ Supplementary Information

Portable Struct. (identify whether attached/perman. or free-standing/ relocatable)

Upgrading/ Modernization (identify whether minor or major)

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 5

Page 6: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Evaluation Components Summary Assessment Estim. Cost

1 Site ConditionsRegrading and/or new asphalt at several locations.New concrete sidewalk at main entrance. $68 000.

2 Building Exterior Roof investigation required, evidence of leaking around perimeter.Structural investigation is required; major settlement/movement/cracking of concrete block structure.Repainting of exterior.

$48 000.

3 Building InteriorReplace ceiling tiles in many locations.New flooring in many areas. $95 660.

4 Mechanical SystemsMechanical systems provide inadequate ventilation to building. Require new ventilation and heating system, school wide. $559 000.

5 Electrical SystemsMajority of electrical systems require upgrading to meet current standards. $312 000.

6 Portable BuildingsNo portables at this location.

7 Space Adequacy:7.1 Classrooms

Note that +/- 316 m2 presently leased to outside agencies. +233.8m2

7.2 Science Rooms/Labs-108.3m2

7.3 Ancillary Areas-27.1m2

7.4 Gymnasium-141.2m2

7.5 Library/Resource Areas-52.8m2

7.6 Administration/Staff Areas-251.3m2

7.7 CTS Areas

7.8 Other Non-Instructional Areas (incl. gross-up) 388.6m2

41.7m2 $1 082 660.Overall School Conditions & Estim. Costs

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 6

Page 7: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 1 Site Conditions Rating Comments/Concerns Estim. Cost1.1 General Site Condions

1.1.1 Overall site size.

5 Large site area shared with community facilities.

1.1.2 Outdoor athletic areas.

4 No apparent problems.

1.1.3 Outdoor playground areas, including condition of equipment and base.

3Generally in good condition with the exception of the asphalt play area on west side of school. This area low with ponding in the spring and uneven and cracking asphalt. Remove asphalt, regrade, repair. (Cost for asphalt only.)

$20 000.

1.1.4 Site landscaping.

4 Adequate.

1.1.5 Site accessories (i.e., perimeter and other fencing, guard rails, bike stands, flag poles).

4 In good condition.

1.1.6 Surface drainage conditions (i.e., drains away from building, signs of ponding).

2 Two areas of significant ponding and/or water collecting along school perimeter. Both areas to be regraded away from building and/or a catch basin/drainage system installed. (Cost for regrading only.) $10 000.

1.1.7 Evidence of sub-soil problems.

FIDiscussions with staff indicate that school (and surrounding housing) has been built on a unique clay that has high tendancy for swelling/shrinkage cycles throughout the year. School has many structural problems that seem to be a result of this. (See also 2.1)

1.1.8 Safety and security concerns due to site conditions.4 None apparent or noted in discussions with staff.

Other

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 7

Page 8: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 1 Site Conditions Rating Comments/Concerns Estim. Cost1.2 Access/Drop-Off Areas/Roadways/Bus Lanes

1.2.1 Vehicular and pedestrian access points (i.e., size, number, visibility, safety).

4 Four pedestrian access points from street, one vehicular access for parking and service. Can be congested at arrival/dismissal times.

1.2.2 Surfacing of on-site road network (note whether asphalt or gravel).

N/A No onsite roadways other than staff parking lot.

1.2.3 Bus lanes/drop-off areas (note whether on-site or off-site).

4 Bus drop-off along street in front of school.

1.2.4 Fire vehicle access.

4 Access on two sides from public street. Access to back of school via play tarmac.

1.2.5 Signage.

4 Signage for both bus and parent drop off areas adequate.

Other

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 8

Page 9: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 1 Site Conditions Rating Comments/Concerns Estim. Cost1.3 Parking Lots and Sidewalks

1.3.1 Number of parking spaces for staff, students and visitors (including stalls for disabled persons).

4 Sixteen parking stalls, no visitor parking or handicap stalls. Adequate on-street parking areas.

1.3.2 Layout and safety of parking lots.

4 Access point also pedestrian/student access, so safety is of some concern.

1.3.3 Surfacing and drainage of parking lots (note whether asphalt or gravel).

3Asphalt/gravel staff parking area. Substantial damage in one area due to refuse truck access to garbage containers. Also low in one area with significant ponding. Lot should be redone with design based on traffic using lot/access.

$32 000.

1.3.4 Layout and safety of sidewalks.

4 Adequate although an additional walk could be provided along east side of school at heavy traffic area across lawns.

1.3.5 Surfacing and drainage of sidewalks (note type of material).

2 Concrete walks in good condition except at main entrance access. Sidewalk to be replaced at this location. $6 000.

1.3.6 Curb cuts and ramps for barrier free access.

4 No apparent problems, at grade access to all school entrances.

Other

Overall Site Conditions & Estimated Costs $68 000.

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 9

Page 10: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 2 Building Exterior Rating Estim. Cost2.1 Overall Structure Bldg.

Section Description/Condition2.1.1 Floor structure and beams (i.e., signs of bending,

cracking, heaving, settlement, voids, rust, stains).

FI

1963

1969

Throughout school but primarily in the 1963 section, many areas of significant floor settling/shifting causing numerous other related problems. Recommend thorough soils and structural review to determine severity of problem and possible remedies.

2.1.2 Wall structure and columns (i.e., signs of bending, cracking, settlement, voids, rust, stains).

FI

1963

1969As per item 2.1.1 above.

2.1.3 Roof structure (i.e., signs of bending, cracking, voids, rust, stains).

FI

1963

1969As per item 2.1.1 above.

Other

Comments/Concerns

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 10

Page 11: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 2 Building Exterior Rating Estim. CostComments/Concerns2.2 Roofing and Skylights

Identify the availability of an up-to-date inspection report or roofing program. Note if roof sections are of different ages and/or in varying

Bldg. Section or Roof Section Description/Condition/Age

2.2.1 Based on the inspection report (and to the extent possible, direct observation), assess and rate roof conditions and estimate costs for required improvements (i.e., covering materials, membrane, insulation, other components).

FI 1963

1969

Evidence of roof leaks in many areas of the school. In-house EPS roof inspection in 1997 recommended numerous repairs. Staff do not recall any of these repairs having been done. Recommend a thorough independent roofing inspection.

2.2.2 Roof accessories (i.e., ladders, stairs, hatches, masts, exhaust hoods, chimneys, gutters, downspouts, splashpads). 4

1963 1969 No apparent problems.

2.2.3 Control of ice and snow falling from roof.

4 Not a concern.

2.2.4 Skylights (i.e., signs of distress, leaks, ice build-up, condensation, deteriorated materials/seals). N/A

Other

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 11

Page 12: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 2 Building Exterior Rating Estim. CostComments/Concerns2.3 Exterior Walls/Building Envelope Bldg.

Section Description/Condition2.3.1 Exterior wall finishes (i.e., signs of deterioration,

cracks, brick spalling, effluorescence, water stains).

31963

1969

Several areas where paint finish is peeling from exposed concrete structure. Areas that require patching of concrete structure at beam/column intersections. $5 000.

2.3.2 Fascias, soffits, parapets (i.e., signs of looseness, stains, rust, peeling paint).

31963

1969

School should be cleaned/patched/repainted on exterior non-brick/tile areas within the next 3 to 5 years. $18 000.

2.3.3 Building envelope (i.e., evidence of air infiltration/ exfiltration through the exterior wall or ice build up on wall, eaves, canopy).

4 Generally good condition.

2.3.4 Interface of roof drainage and ground drainage systems.

3 1963 Noted in EPS report that water appears to migrate through wall of mechanical/boiler room. This problem relates to site drainage problem and cost is covered in section 1.1.6. See 1.1.6.

2.3.5 Inside faces of exterior walls (i.e., signs of cracks, water stains, dust spots).

FI 1963 Evidence of possible roof leakage along perimeter of school in most rooms within 1963 portion of school. May be related to structural settlement problems.

Other

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 12

Page 13: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 2 Building Exterior Rating Estim. CostComments/Concerns2.4 Exterior Doors and Windows Bldg.

Section Description/Condition2.4.1 Doors (i.e., signs of deterioration, rusting metal, glass

cracks, peeling paint, damaged seals, sealed unit failure). 3 1963

1969 Most exterior doors should be repainted. $5 000.

2.4.2 Door accessories (i.e., latches, hardware, screens, locks, alarms, holders, closers, security devices).

3 1963 Original closers should be replaced. Several newer closers are damaged and need repair. Thresholds in two places need replacing. $10 000.

2.4.3 Exit door hardware (i.e., safety and/or code concerns).

3 1963 See note above regarding closers. Cost in 2.4.2.

2.4.4 Windows (i.e., signs of deterioration, rusting metal, glass cracks, peeling paint, damaged seals, sealed unit failure). 3 Original aluminum windows in acceptable condition. Many windows need caulking around exterior

opening. Several have failed sealed units that should be replaced. $10,000

2.4.5 Window accessories (i.e., latches, hardware, screens, locks, alarms, holders, closers, security devices).

4 Good condition for most items.

2.4.6 Building envelope (i.e., signs of heavy condensation on doors or windows).

4 No apparent problems.

Other

Overall Bldg Exterior Condition & Estim Costs $48 000.

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 13

Page 14: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 3 Building Interior - Overall Conditions Rating Estim. Cost3.1 Interior Structure Bldg.

Section Description/Condition3.1.1 Interior walls and partitions (i.e., signs of cracks,

spalling, paint peeling).

FI1963

1969See description in section 2.1.1

3.1.2 Floors (i.e., signs of cracks, heaving, settlement).

FI1963

1969See description in section 2.1.1

Other

3.2 Materials and Finishes Bldg. Section Description/Condition

3.2.1 Floor materials and finishes.

31963

1969

Several areas of carpet need to be replaced.

Flooring better quality/condition.$29 160.

3.2.2 Wall materials and finishes.

FIAlthough painted walls/trims are in fair condition with only a minor number of areas requiring repainting, there is a concern regarding the possibility of lead based paint. Recommend further investigation prior to any remedial work.

3.2.3 Ceiling materials and finishes.

1

3

1963

1963

Gym: clay tiles have been falling down. Tiles should be removed and new finish applied.

Several classrooms require removal of existing tiles and new acoustic ceiling tiles installed.

$8 000.

$35 000.

Comments/Concerns

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 14

Page 15: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 3 Building Interior - Overall Conditions Rating Estim. CostComments/Concerns3.2 Materials and Finishes (cont'd) Bldg.

Section Description/Condition3.2.4 Interior doors and hardware.

3 1963 1969 Some hardware requires replacement. Some doors need repair/paint. $8 000.

3.2.5 Millwork

3 1963 Window sills in most locations require refinishing/replacing. Millwork to be amended to accommodate revised heating system. $15 000.

3.2.6 Fixed/wall mounted equipment (i.e., writing boards, tackboards, display boards, signs).

4

3.2.7 Any other fixed/mounted specialty items (i.e., CTS equipment, gymnasium equipment).

4

3.2.8 Washroom materials and finishes.

3 1969 One washroom has damaged tile base, otherwise in good condition. $500.00

Other

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 15

Page 16: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 3 Building Interior - Overall Conditions Rating Estim. CostComments/Concerns3.3 Bldg.

Section Description/Condition

3.3.1 Building construction type - combustible or non-combustible, sprinklered or non-sprinklered.

4 19631969 Non combustible. Non sprinklered.

3.3.2 Fire separations (i.e., between buildings, wings, zones if non-sprinklered).

4 19631969 Appear to be in place.

3.3.3 Fire resistance rating of materials (i.e., corridor walls and doors).

4 19631969 Appears to conform.

3.3.4 Exiting distances and access to exits.4 1963

1969 Appear to conform.

3.3.5 Barrier-free access.

4 19631969 Appear to conform.

3.3.6 Availability of hazardous materials audit (i.e., evidence of safety concerns with respect to asbestos, PCB's, chemicals). F.I. 1963

1969As noted in 3.2.2, there is a concern regarding the possibility of lead based paint. Building requires painting in many areas and this concern should be addressed prior to any work proceeding.

3.3.7 Other health and safety concerns (i.e., evidence of excessive noise conditions, air quality problems) 4 No other concerns noted by staff.

Other

Overall Bldg Interior Condition & Estim Costs $95 660.

Health and Safety Concerns --- Intent is to identify renovations considered necessary to meet applicable codes, primarily due to safety concerns. Basis of evaluation should be an up-to-date inspection report from the authority having jurisdiction together with direct observations as appropriate. Evaluator should note if in his opinion a comprehensive code evaluation is

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 16

Page 17: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 4 Mechanical Systems Rating Estim. Cost4.1 Mechanical Site Services

4.1.1 Site drainage systems (i.e., surface and underground systems, catch basins).

4 ALL Interior courtyard has a catch basin installed. No problems reported or found.

4.1.2 Exterior plumbing systems (i.e., irrigation systems, hose bibs).

4 ALL No irrigation system. Non-freeze hose bibbs in good condition. No problems reported or found.

4.1.3 Outside storage tanks. N/A N/A

Other N/A N/A

4.2 Fire Suppression Systems Bldg. Sectio

Description/Condition

4.2.1 Fire hydrants and siamese connections. 4 1963 One fire hydrant is located along front street and is within 45 mm of the main entry and siamese connection.

4.2.2 Fire suppression systems (i.e., pumps, sprinklers, piping, reservoirs, hoses, stand pipes, CO2 systems).

5 ALL Fire hose cabinets are installed throughout the building.

4.2.3 Hand extinguishers, blankets and showers (i.e., in CTS areas).

5 ALL Fire blanket and eyewash are not installed. None required. Water type fire extinguishers in corridors. Dry chemical is other area.

4.2.4 Other special situations (e.g., flammable storage areas, science labs, CTS areas).

N/A N/A

Other N/A N/A

Comments/Concerns

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 17

Page 18: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 4 Mechanical Systems Rating Estim. CostComments/Concerns4.3 Water Supply and Plumbing Systems Bldg.

Sectio Description/Condition

4.3.1 Domestic water supply (i.e., pressure, volume, quality - note whether municipal or well supply).

4 ALL Domestic cold water from taps gets hot at times. No check valve noted at water heater.

4.3.2 Water treatment system(s). N/A N/A

4.3.3 Pumps and valves (including backflow prevention valves).

5 1963 Bell & Gossett pumps. No problems reported or found.

4.3.4 Piping and fittings. 3 1963 Gas entry is below ground. This is a potential explosion hazard. 800$

4.3.5 Plumbing fixtures (i.e., toilets, urinals, sinks) 4

4

ALL

1963

Some flush valve recently upgraded and new ball valve for isolation installed.

Urinals are flush tank c/w motion sensor for solenoid.

4.3.6 Domestic hot water system (i.e., heater, storage tanks, failure alarms, pressure, volume, recirculation).

4 1963 Rheem water heater. Tag is not legible. 324 MBH, 75 gallon storage (good condition).

4.3.7 Sanitary and storm sewers, including sumps and pits (note whether sewage system is municipal or septic).

4 ALL Municipal sewer system. No problems reported or found.

Other N/A N/A

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 18

Page 19: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 4 Mechanical Systems Rating Estim. CostComments/Concerns4.4 Heating Systems Bldg.

Sectio Description/Condition

4.4.1 Heating capacity and reliability (including backup capacity).

4 1963 (1) Beaver boiler BG2-2752, 2475/1980 MBH.(1) Beaver boiler BG3000, 2700/2160 MBH.100% standby system. No problems to report on boilers.

4.4.2 Heating controls (including use of current energy management technology.

3 1963 Thermostats do not have a night setback. Thermostats in music, library and some classrooms do not work. Indoor/outdoor boiler controls are a Barber Coleman system.

1,750$

4.4.3 Fresh air for combustion and condition of the combustion chimney.

4 1963 Combustion air in mechanical room is installed at 18" above finished floor. No problems reported or found.

4.4.4 Treatment of water used in heating systems. 4 ALL No sidestream filter or site glass. Heating water is tested yearly.

4.4.5 Low water cutoff/pressure relief valves and failure alarms (i.e., hot water heating).

4 1963 Boiler controls are functioing properly.

4.4.6 Heating air filtration systems and filters. N/A N/A

4.4.7 Heating humidification systems and components. N/A N/A

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 19

Page 20: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 4 Mechanical Systems Rating Estim. CostComments/Concerns4.4 Heating Systems (cont'd) Bldg.

Sectio Description/Condition

4.4.8 Heating distribution systems (i.e., piping, ductwork) and associated components (i.e., diffusers, radiators).

3 ALL Radiation valves are operational. Herman Nelson units presently provides heat at perimeter walls. The heating system should be changed to a fin radiation system.

259,800$

4.4.9 Heating piping, valve and/or duct insulation. 4 ALL Distribution system is black steel piping. No leaks reported.

4.4.10 Heat exchangers. N/A N/A

4.4.11 Heating mixing boxes, dampers and linkages. 3 ALL Herman Nelson wall heat/ventilation units, outside dampers are troublesome. Fan belts loosen quickly. If these units are not replaced (see 4.4.8) the unit will need maintenance work.

9,650$

4.4.12 Heating distribution/circulation in larger spaces (i.e., user comfort, temperature of outside wall surfaces).

2 1969 Interior library is cold in mornings, no direct heating source. 5,500$

4.4.13 Zone/unit heaters and controls. 4 ALL Controls are in good condition.

Other N/A N/A

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 20

Page 21: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 4 Mechanical Systems Rating Estim. CostComments/Concerns4.5 Ventilation Systems Bldg.

Sectio Description/Condition

4.5.1 Air handling units capacity and condition. 2 ALL Herman Nelson heat/ventilation units.See 4.5.2

See 4.5.2

4.5.2 Outside air for the occupant load (if possible, reference CFM/occupant).

2 ALL No air balancing reports available. The Herman Nelson wall heat/ventilation units do not meet current ventilation standards. A new system is required.

281,500$

4.5.3 Air distribution system (if possible, reference number of air changes/hour).

N/A N/A

4.5.4 Exhaust systems capacity and condition. 4 ALL Exhaust systems are operating properly.

4.5.5 Separation of out flow from air intakes. 4 ALL Outside air intakes are near groung elevations. No exhaust outlets nearby.

4.5.6 Special/dedicated ventilation and/or exhaust systems (i.e., kitchen, labs, CTS areas).

N/A N/A

Other N/A N/A

4.5 Ventilation Systems (cont'd) Bldg. Sectio

Description/Condition

Note: Only complete the following items if there are separate ventilation and heating systems.

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 21

Page 22: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 4 Mechanical Systems Rating Estim. CostComments/Concerns4.5.7 Ventilation controls (including use of current energy

management technology).4 1963 Gym AHU Trane 12TMZ.

No capacity data available. Heating coil data not available.

4.5.8 Air filtration systems and filters. 4 1963 STANDARD EFFICIENCY FILTERS INSTALLED (30%).

4.5.9 Humidification system and components. N/A N/A

4.5.10 Heat exchangers. N/A N/A

4.5.11 Ventilation distribution system and components (i.e., ductwork, diffusers, mixing boxes, dampers, linkages).

4 1963 Systems are all functioning properly.

Other N/A N/A

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 22

Page 23: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 4 Mechanical Systems Rating Estim. CostComments/Concerns4.6 Cooling Systems Bldg.

Sectio Description/Condition

4.6.1 Cooling system capacity and condition (i.e., chillers, cooling towers, condensers).

N/A N/A

4.6.2 Cooling distribution system and components (i.e., ductwork, diffusers, mixing boxes, dampers, linkages)

N/A N/A

4.6.3 Cooling system controls (including use of current energy management technology).

N/A N/A

4.6.4 Special/dedicated cooling systems (i.e., labs, CTS areas).

N/A N/A

Other N/A N/A

4.7 Building Control Systems Bldg. Sectio

Description/Condition

4.7.1 Building wide/system wide control systems and/or energy management systems.

4 ALL Barbar Coleman 8000 Controls: Gym AHU, heating pumps, domestic recirculation, pump, day/night boiler control, indoor/outdoor controller. DDC control is not required.

Overall Mech Systems Condition & Estim. Costs $ 559 000

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 23

Page 24: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 5 Electrical Systems Rating Estim. Cost5.1 Site Services

5.1.1 Primary service capacity and reliability (i.e., access, location, components, installation, bus sizes - note whether overhead or underground). 3

120/208V, 3 phase, 4 wire, 800A panel, underground service to Mechanical Room. 70 kVA demand load. 4 spaces in main distribution panel for breakers. 800A main breaker. Old

equipment should be tested.$5,000.00

5.1.2 Site and building exterior lighting (i.e., safety concerns).

3 Generally metal halide floods light up playground. Front entrances lit with incandescent par lamps. Recommend metal halide at front and add one fixture at parking lot. $5,000.00

5.1.3 Vehicle plug-ins (i.e., number, capacity, condition).

4 12 car plugs on timer and relay cab control. All operate and in good condition.

Other

5.2 Life Safety Systems Bldg. Section Description/Condition

5.2.1 Fire and smoke alarm systems (i.e., safety concerns, up-to-date technology, regularly tested).

1 Edwards 6616 fire alarm panel in Office (9 zones used). Remote annunciator at main entrance. Sprinkler zone not supervised. No smoke detectors in classrooms or hallways. $40,000.00

5.2.2 Emergency lighting systems (i.e., safety concerns, condition).

1Emergency generator tied to emergency lighting, exit signs, fire alarm and sound located in Mechanical Room (Code violation regarding fuel supply and location). Fluorescent fixtures (1962 vintage).

$20,000.00

5.2.3 Exit lighting and signage (i.e., safety concerns, condition).

2 Incandescent exit signs to Code tied to generator. Recommend upgrade to LED style. Some lamps regularly out. $5,000.00

Other

Comments/Concerns

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 24

Page 25: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 5 Electrical Systems Rating Estim. CostComments/Concerns5.3 Power Supply and Distribution Bldg.

Section Description/Condition5.3.1 Power service surge protection.

2 None provided. $15,000.00

5.3.2 Panels and wireways capacity and condition.

2 Existing Square D panels are full. One panel added adjacent to existing panel to feed computers, subfed from existing panel, not main distribution panel. $20,000.00

5.3.3 Emergency generator capacity and condition and/or UPS (if applicable).

1 12 1/2 kVA, 120/208V, 3 phase, 4 wire, natural gas. Tied only to emergency lighting, exits, sound and boiler room lighting located in Boiler Room. Replace with separate fuel supply. $30,000.00

5.3.4 General wiring devices and methods.

2Conduit and wire throughout. 2 - 3 receptacles per classroom except 1 room where 8 outlets added (surface mounted). 2 classrooms have multiple computers tied to 1 extra outlet surface run. Require additional circuits for vending machines and computer outlets.

$20,000.00

5.3.5 Motor controls.

Loose magnetic and manual starters. Hard wired interlocks.

Other

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 25

Page 26: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 5 Electrical Systems Rating Estim. CostComments/Concerns5.4 Lighting Systems Bldg.

Section Description/Condition

5.4.1 Interior lighting systems and components (i.e., illumination levels, conditions, controls).

2

White opal, old inefficient lighting in west corridor - 15 FC. Balance of corridors have 2L wrap-around FL at 12' on centre (25 FC). Classrooms use suspended 2L F40 fluorescent old eggcrate style fixtures complete with magnetic ballasts. Lighting lenses low in classrooms (35 - 50 FC) due to de-lamping and removal of ballasts. Recommend complete lighting replacement with T8 electronic fixtures. Gym lighting consists of 48 - 2L, F40 strip lights (30 FC). Low lighting levels and inefficient. Recommend replacement with new metal halide energy efficient system. Library has 8' x 8' white opal fixtures; 50% shut off and de-lamped. Inefficient and under lit. Recommend replacement.

$80,000.00

5.4.2 Replacement of ballasts (i.e., health and safety concerns).

1 Some ballasts (20%) removed from building and fixtures de-lamped. Balance of ballasts date back to 1964 and may have PCB's. All are magnetic. $20,000.00

5.4.3 Implementation of energy efficiency measures and recommendations.

F.I. Exterior lighting on PEC control. Car plugs have a timer and relays. Fixtures de-lamped causing low lighting levels.

Other

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 26

Page 27: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 5 Electrical Systems Rating Estim. CostComments/Concerns5.5 Network and Communication Systems Bldg.

Section Description/Condition

5.5.1 Telephone system and components (i.e., capacity, reliability, condition).

4 Telephone system integrated with intercom. Communication from main office to all classrooms.

5.5.2 Other communication systems (i.e., public address, intercom, CCTV, satellite or cable TV).

4 Cable TV at main telephone panel not used. Intercom/telephone integrated and goes to each classroom. All page via speakers work.

5.5.3 Network cabling (if available, should be category 5 or better).

2 Computer cabling only in computer room. Surface mounted. $10,000.00

5.5.4 Network cabling installation (i.e., in conduit, secured to walls or tables).

2 Minimal cables run from 4 classrooms in corridor ceiling. $15,000.00

5.5.5 Wiring and telecommunication closets (i.e., size, security, ventilation/cooling, capacity for growth).

2 None provided. Consolidate wiring in closets. $5,000.00

5.5.6 Provision for dedicated circuits for network equipment (i.e., hubs, switches, computers).

2 None provided. Add panels throughout complete with circuits to computers. $20,000.00

Other

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 27

Page 28: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 5 Electrical Systems Rating Estim. CostComments/Concerns5.6 Miscellaneous Systems Bldg.

Section Description/Condition

5.6.1 Site and building surveillance system (if applicable).

None

5.6.2 Intrusion alarms (if applicable).

4 Contronic security key pad at entrance and mechanical room. Motion sensors in hallways.

5.6.3 Master clock system (if applicable).

2 Standard time system. Most clocks work. A few are replaced with plug-in units. Central control in office area. Replace with new class signal controller tied to communication system. $2,000.00

Other

5.7 Elevators/Disabled Lifts (If applicable)5.7.1 Elevator/lift size, access and operating features (i.e.,

sensing devices, buttons, phones, detectors).None

5.7.2 Condition of elevators/lifts.

Not Applicable

5.7.3 Lighting and ventilation of elevators/lifts.

Not Applicable

Other

Overall Elect. Systems Condition & Estim Costs $312,000.00

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 28

Page 29: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Section 6 Portable Buildings Rating Comments/Concerns Estim. CostNote: Separate sheets can be completed, if necessary, for portable buildings of different ages and/or conditions.

There are no portables at this location.

6.1.1 Foundation and structure (i.e., signs of bending, cracking, settlement, rust, voids, stains).

6.1.2 Roof materials and components (i.e., signs of deterioration, leaks, ice build-up).

6.1.3 Exterior wall finishes (i.e., signs of deterioration, cracks, water stains).

6.1.4 Doors and windows (i.e., signs of deterioration, rusting hardware, glass cracks, peeling paint, damaged seals).

6.1.5 Interior finishes (i.e., floors, walls, ceiling).

6.1.6 Millwork (i.e., counters, shelving, vanities, cabinets).

6.1.7 Fixed/wall mounted equipment (i.e., writing boards, tackboards, display boards, signs)

6.1.8 Heating system.

6.1.9 Ventilation system.

6.1.10 Electrical, communication and data network systems.

6.1.11 Health and safety concerns (i.e., fire and smoke alarms, fire protection systems, exiting, fire resistance rating of materials).

6.1.12 Barrier-free access.

Overall Portable Bldgs Condition & Estim Costs

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 29

Page 30: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

No. Size Total Area No. Size Total Area

7.1 Classrooms8

2 7

79.9 80.8 79.0

1433.7 14 80 1120 233.8

7.2 Science Rooms/Labs

1 81.7 2 95 190 -108.3

7.3 Ancillary Areas (i.e., Art, Computer Labs, Drama, Music,) 5 Varies 372.9 1 3 130

90 400 -27.1

7.4 Gymnasium (incl. gym storage)

1 331.8 1 473 -141.2

7.5 Library/Resource Areas

1 167.2 1 220 -52.8

7.6 Administration/Staff, Physical Education, Storage Areas 259.7 511 -251.3

7.7 CTS Areas 7.7.1 Business Education

7.7.2 Home Economics

7.7.3 Industrial Arts

7.7.4 Other CTS Programs

7.8 Other Non-Instructional Areas (i.e., circulation, wall area, crush space, wc area)

1457.6 1069 388.6

Overall Space Adequacy Assessment 4024.7 3983 41.7

Section 7 Space Adequacy Comments/ConcernsSurplus/ Deficiency

This Facility Equiv. New Facility

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 30

Page 31: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Evaluation Component/ Sub-Component Additional Notes and Comments

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 31

Page 32: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Evaluation Component/ Sub-Component Additional Notes and Comments

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 32

Page 33: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Evaluation Component/ Sub-Component Additional Notes and Comments

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 33

Page 34: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Evaluation Component/ Sub-Component Additional Notes and Comments

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 34

Page 35: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Evaluation Component/ Sub-Component Additional Notes and Comments

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 35

Page 36: Malmo Elementary School - Alberta · Malmo School is primarily non-combustible concrete block wall construction with a pre-cast concrete roof structure, built-up membrane roofing

Alberta InfrastructureSchool Facilities Branch

School Facility Evaluation ProjectPart II - Physical Condition

School: Malmo Elementary SchoolDate: 10 March 2000

Evaluation Component/ Sub-Component Additional Notes and Comments

Condition Ratings: 1-Emergency/Critical 2-Poor/Unsatisfactory 3-Marginal 4-Good 5-Excellent F.I.-Further investigation required 36