MAJOR PROJECTS AND NEWS ITEMS INDUSTRY NEWS (Houston, TX) – Columbia Gas Transmission, LLC, a subsidiary of Columbia Pipeline Group, Inc. and Columbia Pipeline Partners LP, has filed a customer agreement with the Federal Energy Regulatory Commission to extend its long-term system modernization program. Columbia Transmission has requested FERC's approval of the customer agreement by March 31, 2016, which will allow critical planning and scoping work to commence in a timely manner. The filing extends and ex- pands the first-of-its-kind customer agreement, initially ap- proved by the FERC in January 2013. The program will be extended three years, through 2020, and will provide for approximately $1.1 billion of additional investment. The agreement also expands the scope of facility invest- ments covered by the program. “We are pleased to extend our Modernization Program, which continues a collaborative partnership with our customers to enhance the safety and reliability of the Columbia Transmission system," said CPG President Glen Kettering. "Further, we believe this agree- ment is fully consistent with the FERC's recently issued Modernization Policy Statement. "CPG has invested approximately $1.0 billion under the Modernization Pro- gram over the last three years, placing more than 100 pro- jects into service, including the: - Replacement of more than 130 miles of bare steel pipe lines and wrought iron facilities; - Installation or upgrading of approximately 116,000 horsepower of compression, including adding approxi- mately 80,000 horsepower of compression to its standby fleet; - Installation of an emerging technology, real-time preven- tive maintenance monitoring system to more than 80 per- cent of its existing compressor fleet. Investments in the Modernization Program have also en- abled CPG to reduce greenhouse gas emissions by approxi- mately 20,000 metric tons annually. Columbia Transmission is engaged in the transmission and storage of natural gas and operates approximately 12,000 miles of pipeline across 10 states. Customers include local gas distribution companies, natural gas producers, energy marketers, electric power generating facilities, as well as industrial and commercial end users. The company also owns and operates one of North Ameri- ca's largest underground natural gas storage systems. INDUSTRY NEWS (Houston, TX) – Black Hills Energy is committed to maintaining healthy, vibrant communities and has been working with the City of Norfolk to ensure our Northeast Nebraska communities have the natural gas sup- ply they need by adding a new natural gas line, the Northeast Nebraska Line. “Safe, reliable natural gas service from a dependable com- pany is imperative to attracting new businesses to northeast Nebraska,” said Scott Zaruba, operations manager for Black Hills Energy. “The increase in energy supply will make the Norfolk region a prime location for companies that want to expand or put down new roots. A recent example is OCT Pipe. This new supply of natural gas was a significant factor in OCT’s decision to build a new pipe manufacturing facility in Norfolk.” P.O. Box 1099 Missouri City, Texas 77459-1099 (281) 499-3131 FAX (281) 499-3223 3507 Plum Brook Ln., Missouri City, TX 77459 E-mail: [email protected] www.pipelineintelligence.com Continued on page 5 Volume XXVI, Number 9 January 1, 2016

MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Embed Size (px)

Citation preview

Page 1: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

1

MAJOR PROJECTS AND NEWS ITEMS

INDUSTRY NEWS (Houston, TX) – Columbia Gas Transmission, LLC, a subsidiary of Columbia Pipeline Group, Inc. and Columbia Pipeline Partners LP, has filed a customer agreement with the Federal Energy Regulatory Commission to extend its long-term system modernization program. Columbia Transmission has requested FERC's approval of the customer agreement by March 31, 2016, which will allow critical planning and scoping work to commence in a timely manner. The filing extends and ex-pands the first-of-its-kind customer agreement, initially ap-proved by the FERC in January 2013.

The program will be extended three years, through 2020, and will provide for approximately $1.1 billion of additional investment.

The agreement also expands the scope of facility invest-ments covered by the program. “We are pleased to extend our Modernization Program, which continues a collaborative partnership with our customers to enhance the safety and reliability of the Columbia Transmission system," said CPG President Glen Kettering. "Further, we believe this agree-ment is fully consistent with the FERC's recently issued Modernization Policy Statement. "CPG has invested approximately $1.0 billion under the Modernization Pro-gram over the last three years, placing more than 100 pro-jects into service, including the:

- Replacement of more than 130 miles of bare steel pipe lines and wrought iron facilities;

- Installation or upgrading of approximately 116,000 horsepower of compression, including adding approxi-mately 80,000 horsepower of compression to its standby fleet;

- Installation of an emerging technology, real-time preven-tive maintenance monitoring system to more than 80 per-cent of its existing compressor fleet.

Investments in the Modernization Program have also en-abled CPG to reduce greenhouse gas emissions by approxi-mately 20,000 metric tons annually.

Columbia Transmission is engaged in the transmission and storage of natural gas and operates approximately 12,000 miles of pipeline across 10 states. Customers include local gas distribution companies, natural gas producers, energy marketers, electric power generating facilities, as well as industrial and commercial end users.

The company also owns and operates one of North Ameri-ca's largest underground natural gas storage systems.

INDUSTRY NEWS (Houston, TX) – Black Hills Energy is committed to maintaining healthy, vibrant communities and has been working with the City of Norfolk to ensure our Northeast Nebraska communities have the natural gas sup-ply they need by adding a new natural gas line, the Northeast Nebraska Line.

“Safe, reliable natural gas service from a dependable com-pany is imperative to attracting new businesses to northeast Nebraska,” said Scott Zaruba, operations manager for Black Hills Energy. “The increase in energy supply will make the Norfolk region a prime location for companies that want to expand or put down new roots. A recent example is OCT Pipe. This new supply of natural gas was a significant factor in OCT’s decision to build a new pipe manufacturing facility in Norfolk.”

P.O. Box 1099 Missouri City, Texas 77459-1099 (281) 499-3131 FAX (281) 499-32233507 Plum Brook Ln., Missouri City, TX 77459 E-mail: [email protected]

www.pipelineintelligence.com

Continued on page 5

Volume XXVI, Number 9January 1, 2016

Page 2: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 2

New Listings

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

Black Hills Energy Rapid City, SD

50 mi. 24” “Northeast Nebraska Line” located near Norfolk, NE.

Construction 2016

Tennessee Gas Pipeline Houston, TX

5.8 mi. 30” “Delhi Laterals” located in Madison, Franklin & Richland parishes, LA.

Construction 4th quarter 2016

Williams-Northwest Pipeline Salt Lake City, UT

3.1 mi. 24” “Kalama Lateral” to be located in Cowlitz county, WA.

Construction early 2017

Williams-Transco Houston, TX

1,050’ 42” “New York Bay Expansion Project” lo-cated in Middlesex county, NJ. Also in-cludes upgrades to meter & regulator stations and lowering a lateral.

Construction 2016

Page 3: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 3

Updated Listings(A bold listing indicates a change)

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

AGL Resources Atlanta, GATallgrass Development Leawood, KS

140 mi. 36” or 42” “Prairie State Pipeline” will run from Douglas county, IL to the “Chicago Market Center.”

Construction could be 2017

AGL Resources Atlanta, GAWilliams-Transco Houston, TX

111 mi. 16”, 20”, 24” & 30”

The Dalton Expansion Project will begin at Station 115 in Murray county, GA and end near Holmesville, MS. Also includes new compressor facility in Carroll co, GA.

Filed w/FERC March 2015Construction could be 3rd quarter 2016

Algonquin Gas Transmission Houston, TX

27 mi. 16” “Access Northeast Project” to run from Grafton, MA to near Boylston, MA.

In planning stagesConstruction could be 2018

Algonquin Gas Transmission Houston, TX

1.2 mi. 16” “Salem Lateral” project to be located near Salem, MA.

Awaiting FERC approvalConstruction Summer 2015

Algonquin Gas Transmission Houston, TX

20.1 9.1 1.3 2.0 5.1

42”16”12”36”16” & 24”

“AIM” take up & relay & looping project would start north of Greeneville section of Norwich and continue SE to the RI bor-der. Will include 1.2 mi. directional drill of Hudson River.

Henkels & McCoy Norman, OKConstruction 2016

Page 4: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, May 1, 2015 - 4

Page 5: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 5

Black Hills Energy has determined the best, safest route for the 50-mile-long natural gas line and completed a preliminary environmental review and both archeological and historical assessments along this route.

The company is continuing to work with landowners and ag-ricultural producers along the route and anticipates beginning construction in the spring of 2016.

The engineering process for the Northeast Nebraska Line be-gan shortly after the project was announced in late January 2014 and the company plans to complete construction in the fall of 2016.

INDUSTRY NEWS (Tulsa, OK) – Williams recently an-nounced that John Seldenrust has been appointed Senior Vice President of Engineering & Construction, effective Jan. 1. Seldenrust will report directly to Williams President and Chief Executive Officer Alan Armstrong.

Seldenrust has more than 25 years industry experience and is responsible for ensuring the delivery of best-in-class engi-neering, design, and project and construction management activities and processes across all of Williams’ businesses. He previously served as Senior Vice President – Eastern Opera-tions for Williams and Access Midstream.

“Superior project development and execution is foundational to the success of our company,” said Armstrong. “I’m confi-dent in John’s ability to lead our talented E&C teams through a complex, challenging and exciting time for our industry. His breadth of knowledge, his passion for consistent excellence and his commitment to meeting the needs of our customers and shareholders will serve him well in this role.”

As the E&C lead, Seldenrust succeeds Fred Pace, who has chosen to retire mid-year 2016 after a 30-plus-year career. In the interim, Pace will continue to report directly to the CEO, assisting with transition and integration activities until a final retirement date is set.

“Under Fred’s steadfast leadership, Williams has executed on a tremendous volume of projects while implementing sweep-ing enhancements to our E&C processes,” said Armstrong. “We appreciate his help in facilitating a smooth transition with John in 2015 and 2016 and we wish him well in retire-ment.”

Prior to joining Williams, Seldenrust held a variety of engi-neering and operations leadership roles with Access Mid-stream, Chesapeake Energy, BP America, Vastar Resources and ARCO Oil & Gas.

Seldenrust holds a degree in Chemical Engineering from Texas A&M University, a Master of Divinity degree from Columbia International University and he currently serves on the boards of the Construction Industry Institute and TeenPact Leadership Schools.

Page 6: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 6

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

American Midstream Partners Denver, CO

50 mi. Undet. Crude oil gathering & transportation sys-tem located in McKenzie co., ND.

Open season ended June 22, 2015

American Midstream Partners Denver, CO

52 mi. 12” “Midla-Natchez” take up & relay an old 8” line to run from near Winnsboro, LA to near Natchez, MS.

Awards pendingConstruction Spring/Summer 2016

Ascension Pipeline Company Dallas, TX (EnLink & Marathon)

30 mi. Undet. Project located near Garyville, LA. Construction planned for late 2016

Atlanta Gas Light Atlanta, GA

17 mi. 16” “Newman Bypass Project” will be located near Coweta, GA.

Construction Fall 2015

BakkenLink Pipeline Houston, TX

37 mi. 16” Project runs from Dry Creek to Beaver Lodge near Tioga, ND.

Awaiting the BLM environmental assessment.

Bayou Bridge Pipeline, LLC Houston, TX

160 mi. 30” “Bayou Bridge” expansion will run from Lake Charles, LA to St. James, LA.

Construction could be mid 2017

Blueknight Energy Partners Tulsa, OK

160 mi. 12”, 16” “Knight Warrior Pipeline” project will run from Madisonville, TX to the Hor-ton Ship Channel.

On holdConstruction late 2016 or early 2017

Page 7: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 7

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

Cheniere Energy Houston, TX

23 mi. 48” Project located near Corpus Christi, TX. Construction could be Summer 2016

Columbia Pipeline Group Houston, TX

150 mi. 36” “Mountaineer XPress” will be located in the Appalachia with deliveries near Leach, KY.

Construction could be mid 2017

Columbia Pipeline Group Houston, TX

7 mi. 24”, 36”, 42” “Gulf Xpress Project” to be located near Ceredo, WV.

Construction could be 1st or 2nd quarter 2017

Columbia Pipeline Group Houston, TX

34 mi. 30”, 36” “Cameron Access Project” will be located in Cameron Parish, LA & will include a new comp station.

FERC approvedConstruction will be Spring 2016

Columbia Pipeline Group Houston, TX

5.1 mi. 24” “Utica Access” project will be located in Kanawha county, WV. Will include upgrades to existing comp. stations.

Awards pending

Columbia Pipeline GroupHouston, TX

16 mi. 36” “The Gilbralter Pipeline” will run from Claysville, PA to a point near Columbia’s Majorville comp. station. Line will run adjacent to line 1758.

Construction could be early 2016

Page 8: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 8

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

Columbia Pipeline Group Houston, TX

26 mi.2 mi.4,800”

26”12”36”

“WB Xpress Project” will be a take-up & relay, new lay, and compressor sta-tions upgrades located in Fairfax co., VA and New Kanawha co., WV.

Construction early 2017

Columbia Pipeline GroupHouston, TX

9 mi. 36” “Buffalo Creek Pipeline” will run from Claysville, PA to near Houston, PA. Line will run adjacent to line 1758.

Construction late 2016

Crestwood EquityHouston, TX

165 mi. Undet. Delaware Takeaway crude pipeline sys-tem, known as Delta will be located in Reeves county, TX near Orla, TX.

Open Season ends Dec 7, 2015

Denbury Resources Plano, TX

87 mi. 36” “Conroe Lateral-Green Project” located near Conroe, TX.

Construction could be Summer 2016

Dominion Carolina Gas Richmond, VA

28 mi. 8” Project will begin at the DAK Americas facility in Calhoun county, NC.

Construction Spring 2016

Dominion TransmissionDuke EnergyPiedmont Natural GasAGL Resources

560 mi. 20”, 36” & 42”

“Atlantic Coast Pipeline” would run from Harrison county, WV to near Lumberton, NC.

Will file w/FERC Summer 2015Construction could be 2017-2018

Page 9: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 9

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

Dominion Transmission Richmond, VA

39 mi. 30” & 36” “Supply Header Project” consists of 2 loops located in Westmoreland co, PA & Harrison, Doddridge, Tyler & Wet-zel co WV.

Will file w/FERC Summer 2015Construction could be 2016-17

Dominion TransmissionRichmond, VA

55 mi.5 mi.

12”4”

“Transco to Charleston” project will run from Moore, SC to near Chappells, SC. Includes comp. station upgrades.

Construction could be late 2016 or early 2017

DTE Energy - Ann Arbor, MIEnbridge Energy - Houston, TXSpectra Energy - Houston, TX

250 mi. 36” or 42” “Nexus Gas Transmission System” to run from the Utica Shale to markets in the Midwest & Eastern Canada.

Delayed construction could be 2017

Downeast Pipeline, LLC Robbinston, ME

30 mi. 30” Project located near Baileyville, ME. Still awaiting approval. Could be 2016 or 2017

Dow Pipeline Company Houston, TX

140 mi. Undet. Project would run from Freeport, TX to Mont Belvieu, TX.

Wood Group Mustang - engr.Houston, TX - Could be mid 2016

Eastern Shore Natural Gas Camden, DE

10 mi. 16” “Reliability Project System” located in New Castle, Kent & Sussex co., DE.

Construction mid 2016

East Tennessee Natural Gas Houston, TX

10 mi. 12” “Loudon Expansion Project” will be lo-cated in Bradley & Loudon co., TN.

Summer 2016 Construction

Page 10: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 10

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

Enbridge Energy Houston, TX

364 mi. 36” “Line 3” is a take up & relay that will run from Neche, ND to the Superior terminal.

Construction could be late 2016

Enbridge Energy Houston, TX

616 mi. 24”, 30 “Sandpiper Pipeline” will run from near Beaver Lodge south of Tioga, ND to Superior, WI. Half to be done 2016 & other half in 2017

DelayedConstruction will be 2016 & 2017

Energy Transfer Houston, TX

100 mi. 24” & 30” “The Revolution Pipeline” will begin in Butler county, PA and extend to the Revolution Plant in Western PA.

Construction could be 2017

Enterprise Products Houston, TX

65 mi. 10” RGP Pipeline and rail terminal expan-sion will begin near Sorrento, LA and end near Breaux Bridge, LA.

Construction late 2016 or early 2017

Enterprise Products Houston, TX

416 mi. 24” Pipeline will run from Midland, TX to Sealy, TX.

Delayed until late 2016

EQT Midstream Pittsburgh PA

32 mi. 20” & 24” “Maco Pipeline” Natural Gas Header Sys-tem located in southwestern PA.

Construction 3rd Quarter 2016

Page 11: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 11

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

EQT Pittsburgh, PANextEra Miami, FL

301 mi. 42” “Mountain Valley Pipeline” will run from Equitrans transmission system inWV to delivery points in Pittslavania county, VA. Will be done in 2 phases.

Filed w/FERC Oct. 2015Phase I - Spring 2017Phase II - Spring 2018

EQT Midstream Pittsburgh, PA

4 mi.5 mi.

30”30”

Project located in Greene, Allegheny & Washington counties, PA.

Construction could be late 2016 or early 2017

Fairway Energy Partners Houston, TX

21 mi. Dual 24” “Pierce Junction Crude Oil” storage facil-ity will be near Houston TX.

Awards pendingConstruction early 2016

Florida Southeast Connection, LLC Juno Beach, FL

77 mi.49 mi.

36”30”

“Florida Southeast Connection Project” to be located in Osceola, Okeechobee, Polk, St. Lucie & Martin counties, FL in two phases.

Rockford Corp. Hillsboro, ORConstruction will be 2016

Genesis Energy Houston, TX

135 mi. Undet. Crude oil line that would run through Campbell, Converse, Niobrara & Platte counties, WY. This will tie into the Camp-bell Station near Wright, WY. “

Open season ended Dec 1, 2015Construction could be early 2016

Page 12: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 12

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

Gulf South Houston, TX

64 mi. 36” Coastal Bend Header Project” to be located in Wharton & Brazoria coun-ties, TX. Will also include 3 compres-sor stations and 7 meter stations.

Construction could be early 2017

Howard Midstream San Antonio, TX

200 mi. 30” “The Nueva Era P/L” will begin in Webb co, TX and run to Escobedo, MX.

Construction late 2016 or early 2017

Kinder Morgan Houston, TX

240 mi. 12” “UTOPIA West & East” pipelines would run from Harrison county, OH to near Riga, MI from there it would run to near Windsor, ON, Canada. Added another line of 240 mi. 12”.

Construction could be late 2016

Kinder Morgan Houston, TX

360 mi. Undet. “Palmetto Project” will begin near Belton, SC & end near Jacksonville, FL.

Construction could be early 2017

Kinder Morgan Houston, TX

320 mi. Undet. “Utica Marcellus Texas Pipeline” would convert 964 mi. of natural gas service, the construction of 200 mi. of new pipe from LA to TX. 120 miles of new laterals in Ohio to provide basin connectivity.

Open Season ended Dec. 1, 2015Construction could be late 2018

Page 13: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 13

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

Louisville Gas & Electric Louisville KY

9 mi. 12” Project located near Louisville, KY. Awards pendingConstruction 1st quarter 2016

Kinder Morgan Houston, TX

176 mi. 24” The “Trans Pecos Pipeline” will run from Ward county, TX and end in Hudspeth county, TX.

Construction mid 2016

Magellan Midstream Houston, TXTransCanada Corp. Houston, TX

9 mi. 24” Project located east of Houston, TX. Construction late 2015

Marathon Petroleum Houston, TX

49 mi. 16” “Cornerstone” will run from near Cadiz, OH to Leesville, OH. Located in the Utica Shale. April 2016 start date.

Price GregoryHouston, TX

Medallion Pipeline Company Irving, TX

55 mi. Undet. “The Santa Rita Lateral” will be located in Reagan county, TX.

Construction early 2016

Millennium Pipeline Pearl River, NY

7.8 mi. 16” “Valley Lateral Project” to be located in Orange county, NY.

Construction Summer 2016

Page 14: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 14

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

National Fuel Gas Supply Williamsville, NY

97 mi. 24” “Northern Access 2016 Project” will run from Sergant Township, PA to Elma, NY. Will also include 2,500 HP additional compression.

Construction to begin late 1st quarter 2016

New Jersey Natural Gas Wall, NJ

28 mi. 30” “Southern Reliability Line” would run from Chesterfield Township, NJ to near Man-chester Township, NJ.

Construction to begin Fall 2015

Northern Border Pipeline Houston, TX

64 mi. 16” “Bakken Header Supply Lateral” will be located in Northwestern ND.

Construction could be 2017

North Star Express The Woodlands, TX

23 mi. 12” “NST Express” is located near East Fair-view, ND.

Construction early 2016

Northwest P/L Salt Lake City, UTVeresen, Inc. Calgary, Alberta

232 mi. 36” “The Pacific Connector” project starts near Jordan Cove, OR & runs to Marling, OR southeast of Klamath Falls, OR.

Construction late 2016

Oneok Tulsa, OK

58 mi. 16” “Bakken Expansion II Loop Project” lo-cated near Alexander, ND & Ft. Laramie, FL.

Construction Spring 2016

Page 15: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 15

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

Oneok Tulsa, OK

40 mi. 8” “Bear Creek Crossing Project” located near Alexander, ND

Bids 4th quarterConstruction early 2016

Oregon Pipeline, LLC Warrenton, OR

85 mi. 36” Would begin near Warrenton, OR and end near Woodland, WA and tie into an existing Williams line.

DelayedCould be 2017

Oryx Midstream Services, LLC Midland, TX

100 mi. 16” “Oryx Trans Permian” pipeline will be located near Midland, TX.

Open Season ended Oct. 30, 2015

Paiute Pipeline Co. Las Vegas, NV

35 mi. 8” Project will be located near Elko, NV. This line will tie into the Ruby Pipeline.

BLM approved

Paradigm Midstream Dallas TXPhillips 66 Houston, TX

78 mi. 16” & 20” “Sacagawea Pipeline” project would run from McKenzie co. to Mountrail co., ND.

Will be rebid in early 2016

Penn East Pipeline Co. Wyomissing, PA

105 mi. 36” Project will run from Wilkes-Barre, PA to Trenton, NJ.

Construction could be 2017

Pilgrim Pipeline Palm Coast, FL

178 mi.178 mi.

16”20”

Line will run from near Albany, NY to the New York Harbour.

Filed state permits Nov. 2015Construction 2017

Page 16: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 16

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

Plains All American Houston, TX

60 mi. 16” “State Line” will run from Culberson co. to Wink, TX. Start Feb, 2016

Two Rivers PipelineOdessa, TX

Plains All American Houston, TX

9.5 mi. 8” Project will be located near Lake Sakakawea, ND.

Awaiting Approval

Plains All American Houston, TXDelek Logistics Brentwood, TN

80 mi. 12” “The Caddo Pipeline Project” will run from Longview, TX to near Shreveport, LA. 2016 start date.

Sunland ConstructionEunice, LA

Plains All American Houston, TX

32 mi. 12” “The Avalon Extension” will be located in Loving & Culberson counties, TX.

Construction Summer 2015

Plains All American Houston, TX

440 mi. 20” “Diamond Pipeline” will run from Cushing, OK to Memphis, TN.

Delayed (permitting issues)May be late 2016

PSNC Raleigh, NC

25 mi. Undet. Pipeline would run from Franklin, NC to Wendell, NC.

Early stagesConstruction 2016 or 2017

Rangeland Energy Sugar Land, TX

107 mi. Undet. Rio Pipeline is located in the Delaware Basin and will connect to the crude oil market in Midland, TX.

Culberson ConstructionGranbury, TX

Page 17: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 17

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

Red Rock Gathering South Denver, CO

21.4 mi. 12” & 16” “Winter Flats Pipeline Project” will be located near Grand Junction, CO.

Awaiting BLM approvalConstruction could be Fall 2015

Rio Grande LNG The Woodlands, TX

140 mi. Dual 42” “Rio Grande LNG Project” will begin near Kingsville, TX and end near Brownsville, TX. Will also include 3 compressor stations.

Construction could be Summer 2017

Saddlehorn Pipeline Tulsa, OK

50 mi. 16” “The Carr Extension Project” will run from Platteville, CO to Carr, CO. This is an extension of the 600 mi. 20” line to be built from Carr to Cushing.

Awards pendingConstruction early 2016

Saddle Butte Pipeline LLC Durango, CO

140 mi. Undet. Project located in northwestern New Mex-ico in the San Juan Basin.

Awaiting BLM approval

SemGroup Tulsa, OK

34.2 mi.35 mi.34 mi.

24”12”6”

The “Maurepas Pipelines” will connect to refineries in Southern Louisiana.

Construction Sumer 2016

Sempra Energy San Diego, CA

90 mi. 36” “North-South Project” will run from Adelanto, CA to Adelanto, CA then turn East to end near White-water, CA.

Construction 2018

Page 18: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 18

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

SourceGas Golden, CO

4.6 mi. Undet. “Rocky Mountain Gas” take up & relay project located near Town of Eagle, CO.

Out for bids early 2016

Southern Star Central Gas P/L Owensboro, KYNext Era Energy Juno Beach, FL

250 mi. 24” “Sooner Trails Project” will run from near Grady, OK to near Bryan, OK and will cross over into Lamar county, TX.

DelayedCould be 2018 or 2019

South Jersey Gas Folsom, NJ

22 mi. 24” Project will run from Maurice River Town-ship to Upper Township, NJ.

Awaiting permit approval

Spectra Energy Houston, TXEversource Energy Boston, MANational Fuel Williamsville, NY

27 mi. 16” “West Boylston Lateral” will run through Milford, Upton, Gafton, Sut-ton, Shrewsbury, Boylston & West Boylston, MA. Will tie into “Access Northwest.”

Construction could be 2018

Spectra Energy Houston, TX

10.910.42.610.12.2

42”36”36”30”12”

“Atlantic Bridge” will include take up & relays & new lays all located in Con-necticut, New York & Massachusetts. Will also include compressor station work.

Filed w/FERC February 2015Construction 2017

Page 19: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 19

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

Spectra Energy Houston, TXNextEra Energy Juno Beach, FL

465 mi. 36” “Sabal Trail” would run from mid Alabama thru Georgia & into Central Florida in Marion county. This would be part of the FP&L project.

Spd. 1, 4, 5 - Price GregorySpd. 2 - MPG P/LSpd. 3 - Troy ConstructionSpd. - 6, 7 Rockford Corp.

Sunoco Logistics Philadelphia, PA

350 mi.350 mi.

16”20”

“The Mariner East 2” project will move propane, butane & ethane. Will run through Ohio, WV and western PA.

Awards pending

Sunoco Logistics Philadelphia, PA

125 mi. Undet. Delaware Basin Extension will run from Loving, TX to Lee, NM turn & go east to near Midland, TX.

Spd. 1 & 2 - RebiddingSpd 3 - Pumpco Giddings, TXSpd 4 & 5 Pumpco Giddings, TX

Tennessee Gas Pipeline Houston, TX

8.2 mi. 36” “Orion Looping Project” located in Pike & Wayne counties, PA.

Filed w/FERC October 2015

Tennessee Gas Pipeline Houston, TX

7.6 mi. 36” The Abandonment & Capacity Restora-tion Project (ACR) will be located in Car-ter & Lewis counties, KY. Also includes a new compressor station in Mahoning county. 4 new compressors in Ohio.

Filed w/FERC Feb. 2015

Page 20: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 20

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

Tennessee Gas Pipeline Co. Houston, TX

7 mi. 36” “Triad Expansion Project” to be located near Lenox & Clifford Townships, PA.

Construction could be Spring 2017

Tennessee Gas Pipeline Houston, TX

30 mi. 30” or 36” “Southern Indiana Market Lateral” will begin near Robards, KY and end near Mount Vernon, IN.

Construction could be late 2015 or early 2016

Tennessee Gas Pipeline Houston, TX

13.26 mi. 24” & 36” “Connecticut Expansion Project” is a loop-ing project located in CT.

Awaiting FERC approvalConstruction Spring 2016

Tennessee Gas Pipeline Houston, TX

133 mi.41 mi.

30”36”

“Northeast Energy Direct Project” to upgrade its existing p/l system within NY, MA, CT & NH to run from Wright, NY to Dracut, MA.

Construction could be early to mid 2017

Tennessee Gas Pipeline Co. Houston, TX

8.2 mi. 36” “Susquehanna West Project” will be a looping project located in Tioga co., PA.

Filed w/FERC April 2015Const. early 2017

Texas Eastern Transmission Houston, TX

4.5 mi. 36” “Appalachian Lease Project” located in Monroe co, OH. Includes comp. station upgrades in Columbiana co, OH.

Could be late 2017

Texas Eastern Transmission Houston, TX

35 mi. 20” & 24” The SOLA project would be located near Assumption Parish, LA.

Construction late 2015 or early 2016

Page 21: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 21

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

Texas Gas Transmission Owensboro, KY

22.5 mi. 24” “The Western Kentucky Lateral Project” located in Muhlenberg co., KY.

Cancelled

Texas Gas Transmission Owensboro, KY

30 mi. 24” “The Southern Indiana Market Lateral Project” will run through Henderson county, KY and Posey county, IN.

Construction could be early 2016

TransCanada Corp. Calgary, Alberta Canada

200 mi. Undet. The Upland Pipeline will run from near Williston, ND and end across border in Saskatchewan, Canada.

Very early stagesCould be 2020

UGI Wyomissing, PA

35 mi. 20” “Sunberry Pipeline” to run from Lycoming county to a plant near Shamokin Dam, in Snyder co., PA.

Construction could be early 2016

Venture Global LNG Washington, DC

23.8 mi.18.3 mi.

42”42”

“TransCameron Pipeline” Two lines to be built. One near Grand Chenier, LA & the other near Johnson’s Bayou, LA.

Filed w/FERC late Summer 2015Construction could be 2019

WBI Energy Glendive, MT

27 mi. 24” “Demicks Lake” pipeline project will be located in McKenzie co., ND. Also in-cludes meter station.

Will file w/FERC January 2016Construction could be Spring 2017

Page 22: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 22

Company Length Diameter Location/DescriptionApprox. Bid Date/Awarded Contractor

WBI Energy Glendive, MT

95 mi. 16” “Wind Ridge Pipeline” will run from near Zeeland, ND to Spiritwood, ND.

Construction planned for late 2015 or early 2016

Western Gas Partners The Woodlands, TX

53 mi.26 mi.

36”42”

Project to be located in Reeves, Loving & Ward counties, TX.

Open Season ended Sept. 30, 2015Construction planned for late 2016

Western Refining El Paso, TX

40 mi. 12” “Delaware Basin” project to be located in Reeves & Winkler co., TX.

Construction mid 2016

WGL MidstreamWilliams-Transco

177 mi. Undet. “Central Penn Line” will run from Susquehanna co. to Lancaster co. PA.

Construction mid 2017

William Field Services Tulsa, OK

9.5 mi. 16” “New York Mainline Loop” located in Broome co, NY.

Otis EasternWellsville, NY

Williams-Transco Houston, TX

8.28 mi. 4”-10” “Promesa Pipeline” to run from near Mont Belvieu to the Houston Ship Channel. Will include 27 mi. of existing line.

Construction late 2015

Williams - Transco Houston, TX

8 mi. 36” “The Gulf Trace” project will tie into the new Sabine Pass LNG facility located near Cameron Parrish, LA.

Construction could be 2nd quarter 2016

Williams-Transco Houston, TX

178 mi. 36” “Atlantic Sunrise” will run from Pennsyl-vania, Maryland, Virginia, North Carolina and end in South Carolina. Also includes comp. station work and replacement of some existing lines.

Awards pendingConstruction Summer 2016

Williams-Transco Houston, TX

4 mi. 24” “Virginia Southside Expansion Project II” to be located in Brunswick & Geensville counties, VA. Also includes compressor station upgrades.

Filed w/FERCConstruction could be Jan 2017

Williams - Transco Houston, TX

4.6 mi.15.5 mi.

48”42”

“Hillabee Expansion” Phase I will consist of 4 loops located in Autauga, Chilton, Coosa & Tallaposia co., AL. Starts early 2016

Price GregoryHouston, TX

Williams - Northwest Pipeline Salt Lake City, UT

140 mi. 36” “The Washington Expansion Project” will begin in Whatcom co, WA & end near Woodland, WA.

Construction could be 2016 or 2017

Wolverine Pipe Line Co. Portage, MI

35 mi. 16” “The Detroit Metro Access Project” will run from Freedom, MI to Romulus, MI.

Construction late 1st quarter 2016

Zydeco Pipeliine Co., LLC (Shell) Houston, TX

40 mi. 24” Take up & relay of 18” line would be-gin near Houma, LA & end near St. James Parish.

Open Season Ended December 11Construction could be 2018

Page 23: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 23

Page 24: MAJOR PROJECTS AND NEWS ITEMS - Pipeline · PDF fileMAJOR PROJECTS AND NEWS ITEMS ... "CPG has invested ... Construction Spring/Summer 2016 Ascension Pipeline Company Dallas, TX (EnLink

Pipeline Intelligence Report, January 1, 2016 - 24