BLAST FURNACE AREA 1 530 Cu.M BF - Structural fabrication VISL Client 6.5 2 600 Cu.M BF - Equipment & Structures erection NACAST Client 100 00 3 500 Cu.M BF - Equipment & Structures erection SJK Client 90.5 4 250 Cu.M BF - Equipment & Structures erection VISA Client 30.8 5 351 Cu.M BF 1 - Equipment & Structures erection JSPL Client 50 6 1250 Cu.M BF 1 - Equipment & Structures erection JSW Client 75 7 1680 Cu.M BF 2 - Equipment & Structures erection JSW Client 95 8 1680 Cu.M BF 2 - Equipment & Structures erection JSPL Client 135 9 1680 Cu.M BF 1 - Equipment & Structures erection BSSL Client 110 10 2000 Cu.M BF-7 - Dismantling, Supply & Erection BSP Danieli Corns 275 11 Sinter Fines Disposal System for BF-4 & 5 - Turnkey BSP Own 19.6 12 Sinter Transportation from SP3 to BFs - Turnkey BSP Own 118.8 13 Hot Blast Stoves for BF 4 - Dismantling & Erection DSP Client 53.5 14 Rotor Charging Unit for BF 3 - Supply & Installation BSP Totem, Russia 72 15 Iron Ore screening facilities for BF7 BSP Own 4 16 Disposal System for Granulated Slag from BF-4,5 & 6 - Turnkey BSP Own 144.2 17 BF 5 Stockhouse conveyorisation BSP Own 8.9 18 BF 2 Stockhouse conveyorisation BSP Own 10.8 19 Hot Blast Stoves for BF 2 - Dismantling & Erection BSL Client 189 20 250 Cu.M BF - Equipment & Structures erection Monnet Client 95 MILLS AREA 1 Water cooled Skid system for Reheating Furnaces in RSM - Dismantling, Supply & Erection BSP Cameron, UK 19.8 2 Walking Beam Cooling Bed, Roller Tables, Precambering, etc. for Lonq Rail Project - Supply & Erection incl. civil works BSP Siemens VAI 226 3 Transfer Beds, Roller Tables, Rail Handling System, etc. for Long Rail Project incl. civil works - Supply & Erection incl. civil works BSP Siemens VAI 268 4 NDT Station under Long Rail Project in RAIL & Structural Mill - PKG-III - Supply & Erection incl. civil works BSP NDT Tech., Canada 306.49 5 3 nos. Carbide Saws under Long Rail Project - Supply & Erection incl. civil works BSP Linsigner, Austria 6.5 6 3 Nos. Hydraulic Press under Long Rail Project - Supply & Erection incl. civil works BSP Berner, Germany 11.13 7 Long Rail Handling System for Rail Welding Plant - Supply & Erection BSP Siemens VAI 112.25 8 Equipment for Hydraulic automatic gauge control system in Plate Mill - Supply & Erection incl. civil works BSP Danieli India 30 9 Revamp of Hot Strip Mill - Dismantling, supply & erection BSL Siemens VAI 25 10 End Forging Plant for Thick Web Rail - Supply & Erection incl. civil works BSP Hydraulico, Denmark 82 11 Cooling Beds, Pilers & Other equipment for Plate Mill - Supply, erection, civil & structural works BSP Vitkovice, Czech 1,328.00 MAJOR CONSTRUCTION WORKS EXECUTED BY BEEKAY FOR STE SL. NO. NAME OF PROJECT CLIENT COLLABORATOR FOR TECHNOLOGY CONTRACT Value Rs. Million

MAJOR CONSTRUCTION WORKS EXECUTED BY · PDF file14 Rotor Charging Unit for BF 3 - Supply & Installation BSP Totem, ... 31.01.91 04.04.96-9,000 1,500 200 13.08.95 30.12.97 - 250 27.05.91

Embed Size (px)

Citation preview

BLAST FURNACE AREA

1 530 Cu.M BF - Structural fabrication VISL Client 6.5

2 600 Cu.M BF - Equipment & Structures erection NACAST Client 100 00

3 500 Cu.M BF - Equipment & Structures erection SJK Client 90.5

4 250 Cu.M BF - Equipment & Structures erection VISA Client 30.8

5 351 Cu.M BF 1 - Equipment & Structures erection JSPL Client 50

6 1250 Cu.M BF 1 - Equipment & Structures erection JSW Client 75

7 1680 Cu.M BF 2 - Equipment & Structures erection JSW Client 95

8 1680 Cu.M BF 2 - Equipment & Structures erection JSPL Client 135

9 1680 Cu.M BF 1 - Equipment & Structures erection BSSL Client 110

10 2000 Cu.M BF-7 - Dismantling, Supply & Erection BSP Danieli Corns 275

11 Sinter Fines Disposal System for BF-4 & 5 - Turnkey BSP Own 19.6

12 Sinter Transportation from SP3 to BFs - Turnkey BSP Own 118.8

13 Hot Blast Stoves for BF 4 - Dismantling & Erection DSP Client 53.5

14 Rotor Charging Unit for BF 3 - Supply & Installation BSP Totem, Russia 72

15 Iron Ore screening facilities for BF7 BSP Own 4

16 Disposal System for Granulated Slag from BF-4,5 & 6 - Turnkey BSP Own 144.2

17 BF 5 Stockhouse conveyorisation BSP Own 8.9

18 BF 2 Stockhouse conveyorisation BSP Own 10.8

19 Hot Blast Stoves for BF 2 - Dismantling & Erection BSL Client 189

20 250 Cu.M BF - Equipment & Structures erection Monnet Client 95

MILLS AREA

1 Water cooled Skid system for Reheating Furnaces in RSM -

Dismantling, Supply & Erection

BSP Cameron, UK 19.8

2Walking Beam Cooling Bed, Roller Tables, Precambering, etc. for

Lonq Rail Project - Supply & Erection incl. civil works

BSP Siemens VAI 226

3 Transfer Beds, Roller Tables, Rail Handling System, etc. for Long

Rail Project incl. civil works - Supply & Erection incl. civil works

BSP Siemens VAI 268

4 NDT Station under Long Rail Project in RAIL & Structural Mill -

PKG-III - Supply & Erection incl. civil works

BSPNDT Tech., Canada

306.49

5 3 nos. Carbide Saws under Long Rail Project - Supply & Erection

incl. civil works

BSP Linsigner, Austria 6.5

6 3 Nos. Hydraulic Press under Long Rail Project - Supply &

Erection incl. civil works

BSP Berner, Germany 11.13

7 Long Rail Handling System for Rail Welding Plant - Supply &

Erection

BSP Siemens VAI 112.25

8 Equipment for Hydraulic automatic gauge control system in Plate

Mill - Supply & Erection incl. civil works

BSP Danieli India 30

9 Revamp of Hot Strip Mill - Dismantling, supply & erection BSL Siemens VAI 25

10 End Forging Plant for Thick Web Rail - Supply & Erection incl.

civil works

BSP Hydraulico,

Denmark

82

11 Cooling Beds, Pilers & Other equipment for Plate Mill - Supply,

erection, civil & structural works

BSP Vitkovice, Czech 1,328.00

MAJOR CONSTRUCTION WORKS EXECUTED BY BEEKAY FOR STEEL INDUSTRY

SL. NO. NAME OF PROJECT CLIENT

COLLABORATOR

FOR

TECHNOLOGY

CONTRACT

Value Rs.

Million

MINES AREA

1 Cold Bonded Pellet Plant for Iron Ore Fines at Gua Mines - TK RDCIS Own 69.8

2 Crushing, Screening, Washing & Slurry Disposal Plant for Iron

Ore at Dalli Mines - 4 Pacakqes - Turnkey

BSP Own 202

3 Crushing & Screening Plant for Limestone at ILQ Satna - TK RSP Own 55.2

4 Teritary Crushing & Screening System for Iron Ore at Rajhara - TK BSP Own 7930

5 Primary Crushing & Conveying Facilities at Dalli Mines - TK BSP Own 398.8

COKE OVEN AREA

1Quenching System for Coke Oven Battery No.5 - Dismantling,

Supply & Erection of eguipment incl. civil works

BSL Giprokoks 115

2Partial Briquette Coal Charging Plant for Coke Ovens - Supply &

Erection of equipment incl. civil works on Turnkey basis

RSP CdF Ing. France 537.4

3 Independent Coke Route for Coke Oven Battery 9 & 10 - Supply

& Erection of equipment incl. civil works

BSP Own 36.6

4 Revamping of By Product Plant - Supply & Erection of equipment

incl. civil works

BSP Own 102

5 Rebuilding of Coke Oven Battery No.5 - Dismantling, Supply &

Erection of equipment incl. civil works

BSP Giprokoks 620

6 Rebuilding of COB-6 (Works Pkg.2) - Dismantling, Supply &

Erection of equipment incl. civil works

BSP Own 213

7 Quenching System (Pkg-2A) COB-1 - Dismantling, Supply &

Erection of equipment incl. civil works

BSL Hutni, Czech 280

8 Coke Ovens & Aux. shops - Structural Fabrication & Erection VSP Own 74.8

SMS AREA

1 4 strand Bloom Caster - Supply & Erection of Equipment DSP Danieli & C 210

2 130T RH Deqasser - Supply & Erection of equipment BSP Siemens VAI 100

3 130T Ladle Furnace - Supply & Erection of equipment incl. civil

works

BSP Danieli & C 80

4 Hot Metal Desulphurisation for SMS-II - Supply & Erection of

equipment incl. civil works

BSP ESM INC. USA 285

5 Slab Caster - Supply & Erection of equipment BSP Danieli & C 510

6 Hot Metal Desulphurisation Unit Plant - Supply & Erection of

equipment

VSP ESM INC. USA 270

7 Hot Metal Desulphurisation Plant SMS-III - Supply & Erection of

equipment

BSP ESM INC. USA 291

OTHERS

1 Complete Conveyor System for RMHS of SP 3 - Supply &

erection

BSP L&T 67

2 Hydroblast unit for Grey Iron Foundry at RSP - Supply & erection

incl. civil works

RSP OWN 16.9

3 Gas Cleaning Plant - Structural fabrication & Erection VSP OWN 24

4 Stacker & Reclaimer - Erection & Commissioning L&T OWN 2.09

SL. NO. NAME OF PROJECT CLIENT

COLLABORATOR

FOR

TECHNOLOGY

CONTRACT

Value Rs.

Million

8,461

Page 1

M3 T T T

22.01.92 30.05.94 2,000 -

09.02.95 30.09.96 - 6,000 1,500

02.09.96 31.03.99 - - 4,500 1,500

26.11.03 22.03.05 - - 3,300 1,400

15.01.01 09.04 02 - - 4,500 2

21.02.03 31.12.04 - 5,100 1.995

16.09.04 10.08.06 - 10,000 1,610

30.07.04 15.10.06 - 13,800 3,500

18.10.05 under execution - 12,550 1,650

21.03.05 8.06.07 1,700 5,000 1,000 4,000

05.09.89 05.02.90 650 - 375 225

08.01.99 03.04.2000 1,280 - 1,000 300

31.01.91 04.04.96 - 9,000 1,500 200

13.08.95 30.12.97 - - 250

27.05.91 12.08.91 - - 100

12.08.91 18.12.93 5.2 2,200 350

12.08.91 12.0592 - 200 200

19.0393 20.08.93 200 200

27.05.08 under execution 325 8,250 800 -

31.01.08 under execution - 4, BOO 2,400

04.07.86 06.06.88 2,100 300 100

18.10.02 18.04.04 12,000 - - 2,200

18.10.02 18.06.04 8,000 - 800 2,400

06.05.03 20.11.04 400 - - 200

22.11.02 29.09.04 100 - - 100

27.11.02 29.09.04 100 150

30.09.03 31.03.05 - 1,000 200

22.02.05 30.06.08 200 100 500

15.08.05 under execution - - 100 500

20.12.07 NOV. '08 600 100 500

24.07 08 under execution 10,000 - 700 3,000

MAJOR CONSTRUCTION WORKS EXECUTED BY BEEKAY FOR STEEL INDUSTRY

CONTRACT

DATE

COMPLETION

DATE

VOLUME OF SITE WORKS

Concrete | Refractory | Structures | Equipment

27 07.87 15.12.90 6,375 - 900 450

21.11.88 30.09.91 10,000 - 1,050 2,100

06.06.91 01.10.94 3.25 - 500 400

21.10.91 07.06.94 1,150 - 200 240

08.05.95 30.12.97 10,500 - 650 820

2.05.05 12.10.07 3,000 - 300 500

03.12.92 27.11.96 6,200 - 3,000 2,500

04.01.95 11.11.96 350 - 450 150

22.01.05 30.09.08 100 - 250 650

26.02.05 12.02.09 7,000 12,700 1,800 5,000

01.09.08 under execution 1,000 12,700 450 3,000

19.09.08 under execution 3,000 - 100 200

29.05.82 30.05.90 - 10,000 -

03.09.04 2.08.07 - 500 3,000

23.08.05 3.05.08 - 500 - 1.5

02.09.05 2.06.08 2,000 300 700 500

18.02.06 30.08.08 2,400 300 700 600

05.12.05 OCT. '08 700 - 4,500

17.01.08 under execution - 300 700 300

06.10.08 under execution - 300 700 400

16.12.97 30.04.00 - - 1,900 1,700

23.07.90 30.06.92 300 - 100 250

24.06.86 31.07.88 - - 1,500 -

24.11.97 31.10.99 - - - 600

VOLUME OF SITE WORKS

Concrete

CONTRACT

DATE

COMPLETION

DATE

97,180 52,650 82,575 56,190