31
Canaveral Port Authority Major Capital Projects Update

Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

Canaveral Port Authority

Major Capital Projects Update

Page 2: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT-5 Inaugural Vessel Turn 6/4/2016

Passenger Debark: 3516 

Passenger Embark: 3554

70 Ticket Counters Stations

5 Security Lanes

1200 Ch i i G l 1200 + Chairs in General Boarding and VIP

Page 3: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

Rear of CT 5 Pier and Gangway Area

Page 4: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 5 Parking Garage

Page 5: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 5 Site and Roadway Network

Page 6: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 5 Elevated Pedestrian Access Bridge

Page 7: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 5 Elevated Pedestrian Access Bridge

Page 8: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 5 Elevated Pedestrian Access Bridge

Page 9: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

PROJECT DESCRIPTIONCOMMISSION MEETING

 ENCUMBERED AMOUNT  ETC PROJECT DESCRIPTION

COMMISSION MEETING

 ENCUMBERED AMOUNT  ETC 

Cruise Terminal 5 Cost Report

CT5 Renovation Design/Survey/Testing Various 1,562,178$       Construction 8/26/2015 17,400,000$    Project Management / Owner's Representative 8/26/2015 314,062$          Change Order ‐ CBP, Civil & Utilities packages 3/23/2016 985,000$          Purchase Order to CBP for CBP Purchased Equipment & Systems 3/23/2016 457,133$          Project Closeout Settlement (Acceleration CBP Changes) Pending 506 000$

CT5 Renovation Design/Survey/Testing Various 1,562,178$       Construction 8/26/2015 17,400,000$    Project Management / Owner's Representative 8/26/2015 314,062$          Change Order ‐ CBP, Civil & Utilities packages 3/23/2016 985,000$          Purchase Order to CBP for CBP Purchased Equipment & Systems 3/23/2016 457,133$          Project Closeout Settlement (Acceleration CBP Changes) Pending 506 000$Project Closeout Settlement (Acceleration, CBP Changes) Pending 506,000$         

CT5 Mobile Gangways Design/Survey/Testing 4/15/2015 89,764$            Construction (Includes $190,920 of Uncommitted Contingency) 8/26/2015 4,000,000$       Project Closeout Deductive Change Order for Contingency Pending (190,920)$         

CT5 Pi E t i D i /S /T ti 6/24/2015 132 491$

Project Closeout Settlement (Acceleration, CBP Changes) Pending 506,000$         

CT5 Mobile Gangways Design/Survey/Testing 4/15/2015 89,764$            Construction (Includes $190,920 of Uncommitted Contingency) 8/26/2015 4,000,000$       Project Closeout Deductive Change Order for Contingency Pending (190,920)$         

CT5 Pi E t i D i /S /T ti 6/24/2015 132 491$CT5 Pier Extension Design/Survey/Testing 6/24/2015 132,491$         Construction (Includes $334,767 of Uncommitted Contingency) 9/23/2015 3,896,500$       Project Closeout Deductive Change Order for Contingency Pending (334,767)$         

CT5 Garage  Design Build Construction (Includes $872,534 of Uncommitted Allowances) 8/26/2015 12,600,000$    Change Order #01 to Add 3rd Floor (350 Spaces) 9/23/2015 2,200,000$       

CT5 Pier Extension Design/Survey/Testing 6/24/2015 132,491$         Construction (Includes $334,767 of Uncommitted Contingency) 9/23/2015 3,896,500$       Project Closeout Deductive Change Order for Contingency Pending (334,767)$         

CT5 Garage  Design Build Construction (Includes $872,534 of Uncommitted Allowances) 8/26/2015 12,600,000$    Change Order #01 to Add 3rd Floor (350 Spaces) 9/23/2015 2,200,000$       Change Order #02 to Construct surrounding the Areas of CT5 Parking Garage 1/20/2016 2,497,771$      Pending Tenant Requests ‐ 2nd Floor Elevated Bridge 3/23/2016 996,001$          Budget Adjustment Pending (506,000)$         Project Closeout Deductive Change Order for Allowances Pending (366,534)$         

CT Road Demo Demo Elevated Road 7/29/2015 997,500$          

Change Order #02 to Construct surrounding the Areas of CT5 Parking Garage 1/20/2016 2,497,771$      Pending Tenant Requests ‐ 2nd Floor Elevated Bridge 3/23/2016 996,001$          Budget Adjustment Pending (506,000)$         Project Closeout Deductive Change Order for Allowances Pending (366,534)$         

CT Road Demo Demo Elevated Road 7/29/2015 997,500$          Project Closeout Deductive Change Order for Contingency 6/22/2016 (13,924)$           

Subtotal Encumbered: 48,128,400$Subtotal Estimate to Complete (ETC): (906,145)$     

Subtotal Estimate at Completion (EAC): 47,222,255$ Total Approved Budget for CT5: 48,378,400$  

Project Closeout Deductive Change Order for Contingency 6/22/2016 (13,924)$           Subtotal Encumbered: 48,128,400$

Subtotal Estimate to Complete (ETC): (906,145)$     Subtotal Estimate at Completion (EAC): 47,222,255$ 

Total Approved Budget for CT5: 48,378,400$  Difference: 1,156,145$   Difference: 1,156,145$   

Page 10: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

Cruise Terminal 5 Cost Report Continued

CONTRACTOR ORIGINAL AMOUNT CHANGES  SUBTOTAL CT5 Renovation Bid Tab

CONTRACTOR ORIGINAL AMOUNT CHANGES  SUBTOTAL CT5 Renovation Bid TabCT5 Renovation Bid Tab

HASKELL  $         20,302,287.00  (2,000,000)$    18,302,287$                

IVEY'S  $         21,106,696.45  (807,200)$        20,299,496$                

CT5 Renovation Bid TabHASKELL  $         20,302,287.00  (2,000,000)$    18,302,287$                

IVEY'S  $         21,106,696.45  (807,200)$        20,299,496$                

FINAL COST  $         17,400,000.00  1,491,000$      18,891,000$                FINAL COST  $         17,400,000.00  1,491,000$      18,891,000$                

Page 11: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 10 Prior to Renovation

Page 12: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

New CT 10 West-side Baggage Expansion

Page 13: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

New CT 10 East-side Entrance and Pax-Bridge Expansion

Page 14: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 10 Exterior Demolition

Page 15: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 10 Exterior Demolition

Page 16: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 10 Interior Demolition

Page 17: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 10 Interior Ramp and Baggage

Page 18: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

New CT 10 West-side Baggage Expansion

Page 19: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

Cruise Terminal 10 Cost Report

Page 20: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 8 As It Was

Page 21: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 8 New Roof Installation

Page 22: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 8 New Roof Complete

Page 23: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 8 New Roof Complete

Page 24: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

CT 8 New Roof Complete

Page 25: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

Cruise Terminal 8 Cost Report

PROJECT DESCRIPTIONCOMMISSION MEETING

 APPROVED BUDGET   PENDING 

Roofing Consultant Services and  5/15/2015 41,420$            Window & Door Penetration Leak Review 7/29/2015 6 600$

PROJECT DESCRIPTIONCOMMISSION MEETING

 APPROVED BUDGET   PENDING 

Roofing Consultant Services and  5/15/2015 41,420$            Window & Door Penetration Leak Review 7/29/2015 6 600$Window & Door Penetration Leak Review 7/29/2015 6,600$             Construction (Includes $125,000 of Uncommitted Contingency) 11/18/2015 1,800,000$       

Total Approved for CT8: 1,848,020$    

CT8 RenovationsWindow & Door Penetration Leak Review 7/29/2015 6,600$             Construction (Includes $125,000 of Uncommitted Contingency) 11/18/2015 1,800,000$       

Total Approved for CT8: 1,848,020$    

CT8 Renovations

Page 26: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

43’ Federal Channel Widening and Deepening

Page 27: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

Canaveral Harbor Channel Deepening Cost Report

PROJECT DESCRIPTIONCOMMISSION MEETING

 APPROVED BUDGET   PENDING 

Canaveral Harbor Dredging channel depth to 46' deep (Includes  $291,143 of Uncommitted Contingency) 2/19/2014 28,614,000$    Channel Deepening Change Order #01 ‐ Dredging at NCP 1, 2, SCP 3 & 4 and West Channel 9/17/2014 700,000$          

PROJECT DESCRIPTIONCOMMISSION MEETING

 APPROVED BUDGET   PENDING 

Canaveral Harbor Dredging channel depth to 46' deep (Includes  $291,143 of Uncommitted Contingency) 2/19/2014 28,614,000$    Channel Deepening Change Order #01 ‐ Dredging at NCP 1, 2, SCP 3 & 4 and West Channel 9/17/2014 700,000$          

Change Order #02 ‐ Dredging at CT3 2/18/2015 60,800$           Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$          Change Order #04 ‐ Dredging at Middle Turning Basin to a depth of ‐43' + 1' 5/20/2015 1,657,985$       Change Order #05 ‐ Removal of Additional Dredged Material  3/24/2026 2,043,756$       

Change Order #02 ‐ Dredging at CT3 2/18/2015 60,800$           Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$          Change Order #04 ‐ Dredging at Middle Turning Basin to a depth of ‐43' + 1' 5/20/2015 1,657,985$       Change Order #05 ‐ Removal of Additional Dredged Material  3/24/2026 2,043,756$       

Subtotal Pending Costs: ‐$                 

Total Approved Budget for CT5: 33,326,541$    

Total Approved Budget and Pending Costs for CT5: 33,326,541$  

Subtotal Pending Costs: ‐$                 

Total Approved Budget for CT5: 33,326,541$    

Total Approved Budget and Pending Costs for CT5: 33,326,541$  

Page 28: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

Channel Widening Project (GLF)

• Total Contract with Change Orders = $9,873,488.00

• The Contract total following removal of ODP amounts = $7,921,189.09

• The Project was awarded Substantial Completion on 10/1/15

• GLF’s original change order request was: $2,915,598.77g g q , ,

• Following first round of comments from the forensic scheduler and claims analyst team, the revised amount received on 2/23/16 was reduced to $2 142 016 35$2,142,016.35.

• Negotiations continue...

Page 29: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

VSA 7 – Marine Terminal Phase II

Page 30: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

VSA 7 – Marine Terminal Phase II (9.8 Acre)

Page 31: Major Capital Projects Update - Port Canaveral · 2016. 8. 18. · Change Order #03 ‐ Dredging at USCG facility in the West Turning Basin 5/20/2015 250,000$ Change Order #04 ‐

Marlin Street Improvements:• Contractor: RUSH Construction

Upcoming Projects

Contractor: RUSH Construction• Purchase Order: $1,927,781• Schedule: Construction Complete January ‘17

Parish Medical Building:C t t RUSH C t ti• Contractor: RUSH Construction

• Purchase Order: $1,738,438• Schedule: Undergoing Site Design Revisions due to Location Change

North Cargo Berth 3 & 4 Reconstruction:North Cargo Berth 3 & 4 Reconstruction:• Contractor: (TBD)• Schedule: Currently Under Design and Permitting by Ch2m

Northside Cruise Terminal Roadway Network Improvements:• Contractor: (TBD) D/B Solicitation Anticipated December ‘16• Schedule: Currently Under Design by TransSystems

Port-Wide Wayfinding & Signage Project:• Contractor: (TBD) D/B Solicitation Underway Quals due 9/6 Shortlist &Contractor: (TBD) D/B Solicitation Underway, Quals due 9/6, Shortlist &

Presentations in October ‘16.• Schedule: Anticipated Completion by Summer ’17

New Cruise Berth Design and Permitting:RFQ S li it ti f P f i l S i P di• RFQ Solicitation for Professional Services Pending