Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
MAJOR ACHIEVEMENTS DURING2013-14
1
Central Railway Construction Organisation
• Central Railway- Construction Organisation has been awarded IBCTrophy 2013 for New Administrative Building for IRICEN Pune.
• IRICEN Building got LEED Platinum Rating from IGBC with 61 creditpoints, highest ever for any Green Building in Maharashtra.
2
Central Railway Construction Organisation
2Godhani – Kalumna : The Rail level Goods Platform at Godhani,NGP Division, has been completed and commissioned. This willhelp in handling full length Rake at Godhani.
3
Central Railway Construction Organisation
3 Nasik: One vacant old Residential Type-II building has beenremodeling & renovated as New Supervisor hostel building with 8Rooms as part of sanctioned work of proposed SupervisorsTraining Center at IRIEEN Nasik.
4
Central Railway Construction Organisation
4 In Thane Yard Remodeling, extension of Platform No 5&6 by 210Mtrs with COP has been completed. This has avoided double haltof Mail/ Exp Trains.
5
Central Railway Construction Organisation
5 Warora ROB has been completed and commissioned.LC has been closed.
6
Central Railway Construction Organisation
6 Kalyan ROB in lieu of level crossing No.1/A, between Kalyan-Vithalwadi station in Kalyan- Lonavala section is commissionedfor Road traffic. LC has been closed.
7
Central Railway Construction Organisation
7 Construction of 2 Lane ROB at Outer Ring road at Kn 821/17-21in lieu of LC No 117 on Wardha Nagpur has been completed andcommissioned. LC has been closed. The work was done ondeposit term.
8
Central Railway Construction Organisation
8 Construction of ROB at km 57/16-58/1 in lieu of L-xing No.47/B in KYN-IGP Sec. – (Railway portion) has been completed
9
Central Railway Construction Organisation
9 G+12 stories of 24 units type V Special quarters at NirmalPark, Byculla has been completed.
10
Central Railway Construction Organisation
10 Amravati-New Platform has been completed and connected byyard remodeling. With this, additional entry to Amravati stationform west side has been started.
11
Central Railway Construction Organisation
11 On Trans Harbour Thane-VashiSection, the work of extensionof platforms with cover overplatform for 12 car rakes hasbeen completed at
•Koparkhairane
•Rabale
•AiroliRabale
Airoli
Koparkhairane
12
Central Railway Construction Organisation
12 On Harbour line, extension ofplatform for 12 car EMU rake hasbeen completed on all platforms.Now, the work of extension ofcover over platform has beencompleted on extended platformat
•Nerul
•Sanpada and
•Juinagar station.
Nerul
Juinagar
Sanpada
13
Central Railway Construction Organisation
13 On Pune Division, One Residential building of G+3 story of 16units type-II qtrs. have been completed at Tadiwala Road atPune.
14
Central Railway Construction Organisation
14 Nasik- Administrative Building of RPF training center having620 sq. mtrs on 2nd floor of existing building is completed.
15
Central Railway Construction Organisation
15 New PRS building of 260 sq.mts. having 6 booking counters andsurrounded by circulating area is completed at Amravati station.
16
Central Railway Construction Organisation
16 On Mumbai Division, On foot over bridge of width 3.66 mtr.connecting platform No1 to new platform has been completedat Pen station.
17
Central Railway Construction Organisation
17 On Mumbai Division, Extension of Heavy Repair Shed, LightRepair Shed, and Inspection shed over line No. 4 to 8 by 60mtrs each , and new running room of 12 beds in Sanpadacarshed have been completed
18
Central Railway Construction Organisation
18 Thakurli- Developed RPSF Parade Ground at size 125mtrs x90mtrs, saluting stage of 6mtrs x 4mtrs x 1.2mtrs height withsurface drainage arrangement has been completed. Republic Dayfunction and Parade was organized in new ground.
19
Central Railway Construction Organisation
19 The work of patients relatives Rest house at Byculla was sanctionedin 2007-08 at a cost of Rs.4.32 crs. as G+7 story building. In thefirst stage ground floor consisting of Ladies and Gents dormitory of20 beds has been completed and inaugurated by GM on26.01.2014.
20
THE LADIES DORMITORY(10 beds)
THE GENTS DORMITORY(10 beds)
Central Railway Construction Organisation
1 Kasara RRI – commissioned on 28.4.2013
2 Amla-Parasia-Replacement of signaling equipment by route settingtype control panel (8 stations) & colour light signaling (14 levelcrossing gates)- Bordhai panal interlocking commissioned on15.04.2013
3 Nagpur Division- The RRI works has been completed andcommissioned on 30.11.2013 at Naegaon on Amla-Parasia section.
4 Pandharpur (PVR) Yard panel interlocking and up gradation to std IIinterlocking has been completed and commissioned. Platform No.1 hasbeen extended by 150 mtr and One passenger loop line of 440 mtrlength have been commissioned.
21
Central Railway Construction Organisation
THANK YOU
Central Railway Construction Organisation