MAJESTIC TOWER Progress Report Date: 05/09/2014 A. Majestic Tower Residential Sale Building – (BUA – 22, 00,000 sft approx.) 2 basement + ground floor + 6 podium + 36 floors with 4 wings. 1. A wing : (2.5 BHK- 208 flats excluding Refuge area) 1 st typical floor slab completed. 2. B wing : (2.5 BHK- 140 flats, 2 BHK – 68 flats excluding Refuge area) Typical 10 th floor slab completed. Typical 11 th floor slab 25 % completed. Column above Typical 10 th floor is completed. Block work on 1 st Floor is started for Sample Flat. 3. C wing : (2.5 BHK- 64 flats, 2 BHK – 140 flats, 3 BHK – 72 flats excluding Refuge area) Typical 11 th floor slab completed. 4. D wing : (2 BHK – 132 flats, 3 BHK – 144 flats excluding Refuge area) Typical 13 th floor slab completed. Typical 13 th To 14 th floor column 35 % completed. Note: Drawing of 6 th podium slab of podium area is not finalized yet.

Majestic Progress Report - August

Embed Size (px)

DESCRIPTION

MIS FOR CONSTRUCTION SITE

Citation preview

Page 1: Majestic Progress Report - August

MAJESTIC TOWER

Progress Report Date: 05/09/2014

A. Majestic Tower Residential Sale Building – (BUA – 22, 00,000 sft approx.) 2 basement + ground floor + 6 podium + 36 floors with 4 wings.

1. A wing : (2.5 BHK- 208 flats excluding Refuge area)

1st typical floor slab completed.

2. B wing : (2.5 BHK- 140 flats, 2 BHK – 68 flats excluding Refuge area)

Typical 10th floor slab completed.

Typical 11th floor slab 25 % completed.

Column above Typical 10th floor is completed.

Block work on 1st Floor is started for Sample Flat.

3. C wing : (2.5 BHK- 64 flats, 2 BHK – 140 flats, 3 BHK – 72 flats excluding Refuge area)

Typical 11th floor slab completed.

4. D wing : (2 BHK – 132 flats, 3 BHK – 144 flats excluding Refuge area)

Typical 13th floor slab completed.

Typical 13th To 14th floor column 35 % completed.

Note:

Drawing of 6th podium slab of podium area is not finalized yet.

B. Majestic Tower Rehab building – (BUA 9, 50,000 sft approx.)

1. Building 1 : Ground floor + 17 floors with 6 wings.

a. A wing : No. of flats – 134 excluding refuge area , balwadi , society office and meter room.

RCC and Brick work completed External Plaster 80 % of periphery area completed. Gypsum Plaster 78/134 flats completed.

b. B wing: No. of flats – 134 excluding refuge area, balwadi, society office and meter room.

RCC and Brick work completed External Plaster 35 % of periphery area completed. Gypsum Plaster 78/134 flats completed.

Page 2: Majestic Progress Report - August

c. C wing : No. of flats – 134 excluding refuge area , balwadi , society office and meter room.

RCC and Brick work completed Casting of OHWT is completed. Gypsum Plaster 62/134 flats completed.

d. D wing: No. of flats – 134 excluding refuge area, balwadi, society office and meter room.

RCC and Brick work completed Fixing of marble frame on 17th floor is completed. Gypsum Plaster 54/134 flats completed.

e. E wing: No. of flats – 134 excluding refuge area, balwadi, society office and meter room.

RCC and Brick work completed External Plaster 25 % of periphery area completed. Gypsum Plaster 118/134 flats completed.

f. F wing: No. of flats – 134 excluding refuge area, balwadi, society office and meter room.

RCC and Brick work completed External Plaster 90 % of periphery area completed. Gypsum Plaster 118/134 flats completed. Basecoat in Bath & WC from 5th floor to 10th floor is completed.

2. Building 2: Ground floor + 16 floors with 4 wings.

a. A wing: No. of flats – 126 excluding refuge area, balwadi , society office and meter room.

RCC and Brick work completed External Plaster 80 % of periphery area completed. Gypsum Plaster 78/126 flats completed.

b. B wing: No. of flats – 126 excluding refuge area, balwadi, society office and meter room.

RCC and Brick work completed. External Plaster 10 % of periphery area completed. Gypsum Plaster 102/126 flats completed.

c. C wing: No. of flats – 127 excluding refuge area, balwadi, society office and meter room.

RCC and Brick work completed External Plaster 60 % of periphery area completed. Gypsum Plaster 80/127 flats completed.

d. D wing: No. of flats – 126 excluding refuge area, balwadi, society office and meter room.

RCC and Brick work completed External Plaster 90 % of periphery area completed. Gypsum Plaster 118/126 flats completed.

Page 3: Majestic Progress Report - August

3. Building 3: Ground floor + 16 floors with 3 wings.

a. A wing: No. of flats – 90 excluding refuge area, balwadi, society office and meter room.

RCC work completed excluding OHWT. Brick work up to 9th floor completed. Gypsum Plaster 40/90 flats completed.

b. B wing: No. of flats – 124 excluding refuge area, balwadi, society office and meter room.

RCC and Brick work completed. Gypsum Plaster 70/14 flats completed.

c. C wing: No. of flats – 142 excluding refuge area, balwadi, society office and meter room.

RCC work completed excluding OHWT. Brick work up to 8th floor completed. Gypsum Plaster 67/142 flats completed.

4. Building 4: Ground floor + 16 floors with 3 wings.

a. A wing: No. of flats – 94 excluding refuge area, balwadi, society office and meter room.

Typical 11th floor slab completed. Brick work on 3rd, 4th, 5th & 6th floor completed.

b. B wing: No. of flats – 108 excluding refuge area, balwadi, society office and meter room.

Casting of Typical 12th floor slab completed. Brick work on 3rd, 4th, 5th & 6th floor completed.

c. C wing: No. of flats – 134 excluding refuge area, balwadi, society office and meter room.

RCC work completed. Brick work up to 16th floor completed. Fixing of Marble in Door & window frames is going on.

Description August -14 July-14 June-14 May -14

1 Labor strength per day 452 nos 351 nos 313 nos 300 nos

2 Average concreting per day 45 cum 23 cum 32 cum 18 cum

3 Average steel consumption per day 6.5 T 6.5 T 7.2 T 3.36 T

Page 4: Majestic Progress Report - August
Page 5: Majestic Progress Report - August
Page 6: Majestic Progress Report - August
Page 7: Majestic Progress Report - August

MAJESTIC TOWER PROGRESS REPORT

DATE : 05 / 09 / 2014

TOTAL PROJECT COMPLETED TILL DATE IN % =

25.05%

SR.NO

DESCRIPTION% WISE

CONTRIBUTIO

N IN PROJECT

A WIN

G

B WIN

G

C WIN

G

D WIN

G

COMPLETED%

WISE

CONTRIBUTION

1 EXCAVATION 5% 100%100.00

%

100.00

%

100.00

%

100.0

%5.00%

2 R.C.C. 45%29.57

%42.86% 49.67% 56.14%

44.6

%20.05%

3 BRICKWORK 10% 0.00% 0.00% 0.00% 0.00% 0.0%

4INTERNAL

PLASTER10% 0.00% 0.00% 0.00% 0.00% 0.0%

5EXTERNAL

PLASTER8% 0.00% 0.00% 0.00% 0.00% 0.0%

6WATERPROOFI

NG3% 0.00% 0.00% 0.00% 0.00% 0.0%

7 PLUMBING 5% 0.00% 0.00% 0.00% 0.00% 0.0%

8 FIRE FIGHTING 1% 0.00% 0.00% 0.00% 0.00% 0.0%

9ELECTRICAL

WORK3% 0.00% 0.00% 0.00% 0.00% 0.0%

10 TILING 6% 0.00% 0.00% 0.00% 0.00% 0.0%

11 PAINTING 2% 0.00% 0.00% 0.00% 0.00% 0.0%

12`MISCLLEANEO

US2% 0.00% 0.00% 0.00% 0.00% 0.0%

13 TOTAL 100% 0.0% 25.05%

Page 8: Majestic Progress Report - August

NAHUR REHAB PROGRESS REPORT

TOTAL PROJECT COMPLETED TILL DATE IN % = 63 %

SR.NO

ACTIVITY

% W

ISE

CON

TRIB

UTI

ON

IN

PRO

JECT

BLD

G.N

O.1

BLD

G.N

O.2

BLD

G.N

O.3

BLD

G.N

O.4

ACTI

VITY

CO

MPL

ETED

IN

%

COM

PLET

ED%

WIS

E

CON

TRIB

UTI

ON

REM

ARKS

1 EXCAVATION 5% 100% 100% 100% 100% 100% 5%

2 R.C.C. 45% 100% 100% 100% 81% 95% 43%

3 BRICKWORK 10% 94% 94% 64% 46% 75% 7%

4 INTERNAL GYPSUM 10% 71% 71% 47% 0% 45% 5%

5EXTERNAL PLASTER

8% 40% 61% 0% 0% 25% 2%

6 WATERPROOFING 3% 0% 0% 0% 0% 0% 0%

7 PLUMBING 5% 0% 0% 0% 0% 0% 0%

8 FIRE FIGHTING 1% 0% 0% 0% 0% 0% 0%

9 ELECTRICAL WORK 2% 94% 94% 58% 20% 67% 1%

10ELECTRICAL WORK

SWITCH FITTING1% 0% 0% 0% 0% 0% 0%

11 TILING 6% 0% 0% 0% 0% 0% 0%

12 PAINTING 2% 0% 0% 0% 0% 0% 0%

12 MISCELLANEOUS 2% 0% 0% 0% 0% 0% 0%

13 TOTAL 100% 38% 40% 28% 19% 31% 63% SALE & REHAB STEEL OPENING SCHEDULE

DIA. RECEIVED USE BALANCE      MT.

8mm 2203.99 2148.99 5510mm 362.352 341.352 2112mm 982.22 940.22 4216mm 955.755 929.755 2620mm 1537.72 1496.72 4125mm 1857.085 1790.085 6732mm 813.13 751.13 62

       TOTAL 8712.252 8398.252 314

Page 9: Majestic Progress Report - August

RMC CONSUMPTIONREHAB

SR. NO. CONCRETE PREVIOUS TODAY' S CUMML.  GRADE QUANTITY QUANTITY QUANTITY        CU.M.1 M15 1195 0 11952 M20      3 M25 15548.75 0 15548.754 M30 15108.75 0 15108.755 M35      6 M40      7 M45      8 M50                                 

TOTAL   31852.5 0 31852.5

RMC CONSUMPTIONSALE

SR. NO. CONCRETE PREVIOUS TODAY' S CUMML.

Page 10: Majestic Progress Report - August

  GRADE QUANTITY QUANTITY QUANTITY        CU.M.1 M15 54 0 542 M20 45 0 453 M25 4.5 0 4.54 M30 38.45 0 38.455 M35 8673.4 0.75 8674.156 M40 0 0 07 M45 506.5 0 506.58 M50 435.05 8.05 443.139 M55 7326.55 6.7 7333.2510 M60 91.5 0 91.511 M65 55.5 0 55.5

TOTAL   17230.45 15.5 17245.95

CEMENT CONSUMPTIONSALE AND REHAB

MATERIAL OPC 53 BULKER PPC    GRADE    

         

TOTAL RECEIVED 111465 15167.295 44718TOTAL CONSUMED 111260 15106.274 43908

TODAY' S RECEIVED 0 0 0OPENING BALANCE 205 61.021 810

TODAY' S CONSUMPTION 25 6.816 150

BALANCE ON SITE 180 54.205 660

Page 11: Majestic Progress Report - August
Page 12: Majestic Progress Report - August
Page 13: Majestic Progress Report - August
Page 14: Majestic Progress Report - August
Page 15: Majestic Progress Report - August
Page 16: Majestic Progress Report - August
Page 17: Majestic Progress Report - August
Page 18: Majestic Progress Report - August
Page 19: Majestic Progress Report - August
Page 20: Majestic Progress Report - August
Page 21: Majestic Progress Report - August
Page 22: Majestic Progress Report - August