MAINTENANCE, REPAIR, REHABILATATION, REFRUBISHMENT,
UPGRADE AND ADDITION
National/Provincial Road showsJuly/ August 2009
1
Classification Circular 3
Classification of own account and outsourced Maintenance and Repairs (M&R), Upgrade and
Additions (U&A) and Rehabilitation and
Refurbishment (R&R) of all asset types
Presented by: SCOA Technical Committee
National Treasury
3
Important principles
• Why record asset related payments?
– Infrastructure reporting
– Asset management and costing
– Recording own account transactions
– Correctly present spending on contractors
– Monitoring total maintenance cost
4
Definitions
• Own Account maintenance, upgrade and rehabilitation
– Department engages in project in its own capacity
• Outsourced maintenance, upgrade and
rehabilitation – Project is outsourced to an external service
provider
• Only difference is in Item segment
5
Definitions continued
• Maintenance and repairs – Maintaining the capacity and effectiveness of
an asset at its designed level
• Upgrades and additions – Improving the capacity and effectiveness of
an asset above that of the initial design purpose
• Rehabilitation and refurbishment– Required due to neglect, unsatisfactory
maintenance or degeneration of an asset
6
Relevant transaction types
• Owned and leasehold property – Residential and non-residential buildings
either owned or leased by government
– To get a full picture of spending on property
• Machinery and equipment
• All other asset types
• Either own account or outsourced
7
Item Asset
Maintenance &
repair (M&R)
Project
Owned and leasehold property
Owned & leasehold
property: Contracted
property M&R
Upgrade &
additions (U&A)
Rehab &
refurbishment
(R&R)
Owned & leasehold
property: Contracted
property R&R
Owned & leasehold
property: Contracted
property U&A
Relevant property
asset category
Relevant property
asset category
Relevant property
asset category
Projects: Existing
infrastructure: M&R
Current
Projects: Existing
infrastructure: U&A
Capital
Projects: Existing
infrastructure: R&R
Capital
8
Item Asset
Maintenance &
repair (M&R)
Project
Machinery and equipment
Contractors: M&R of
machinery & equipment
Upgrade &
additions (U&A)
Rehab &
refurbishment
(R&R)
Contractors: R&R of
machinery & equipment
Contractors: U&A to
machinery & equipment
Relevant asset
category
Relevant asset
category
Relevant asset
category
Projects: Not related to
infrastructure: M&R
Current
Projects: Not related to
infrastructure: U&A
Capital
Projects: Not related to
infrastructure: R&R
Capital
9
Item Asset
Maintenance &
repair (M&R)
Project
Other asset types
Contractors: M&R of
other asset types
Upgrade &
additions (U&A)
Rehab &
refurbishment
(R&R)
Contractors: R&R of
other asset types
Contractors: U&A to
other asset types
Relevant other asset
category
Relevant other asset
category
Relevant other asset
category
Projects: Existing or not
related to Inf: M&R
Current
Projects: Existing or not
related to Inf: U&A
Capital
Projects: Existing or not
related to Inf: R&R
Capital
10