Maintaining the Power Grid for 2010 Soccer World Cup

Q U A N T ASERVICES

BGEDr. Johan Enslin BGEJanuary 4, 2008

VP – International & Sustainable Energy Quanta Technology

[email protected]

Page 1© 2010 Quanta Technology LLC Page 1

November 2007

Overview

FIFA 2010 World Cup in South Africa

Status of Power Grid in South AfricaStatus of Power Grid in South Africa

Uprating and Conductor Analysis

Energized Solution to Uprate 88 kV SystemEnergized Solution to Uprate 88 kV System

Emergency Support during World Cup

Status of Uprating ProjectStatus of Uprating Project

Page 2© 2010 Quanta Technology LLC Page 2

FIFA World Cup 2010

Page 3© 2010 Quanta Technology LLC Page 3

FIFA World Cup 2010

Page 4© 2010 Quanta Technology LLC Page 4

Status of Power Grid in South Africa

Installed Capacity - 45 GW with Reserve Margin < 10%

Johannesburg Old 88kV Network (1950 vintage)Johannesburg Old 88kV Network (1950 vintage)

Last few years had rolling Blackouts

Existing electrical transmission and distributionExisting electrical transmission and distribution infrastructure have no or limited N-1 reliability

System cant support an outage nor alternative route is

Namibia

BotswanaMozambique

2009

Matimba 2009/10 for

integration of project

AlphaMarang

Dinaledi

y pp gavailable

Restricted ROWsNamibia

SwazilandMercury

Perseus

Hydra

Kudu

2009

2009

2010

AlphaMarang

Eros202

Page 5© 2010 Quanta Technology LLC Page 5

y

Gamma

Omega

765 kV400 kV

Grassridge

DelphiNeptune20

10

007Juno 2

009

2009

Energized Solution to Uprate 88 kV System

Re-conductor the City Power 88kV system:Uprade to High Temperature ACSS conductorsIncrease individual circuit capacity – 100% targetIncrease individual circuit capacity 100% target.Mechanically harden transmission system, extend life. Enhance system economic performance and end-customer satisfaction

Energized Techniques and Robotic Technology: Safe and economic solution to a complex operation.Shorter project timelineShorter project timelineSecurely holding energized lines/equipment intact during upgradesIncreasing personnel safety Increasing utilization of existing transmission assetsSafely reconductoring, rebuilding and replacing/adding lines and equipment while not taking system out of service

Page 6© 2010 Quanta Technology LLC Page 6

Better asset maintenance and upgrade in restricted right-of-ways

Uprating and Conductor Selection

R i 50 100% i 88kV tRequire 50-100% power increase on 88kV system

Provides power throughput from 100 MW to 200 MVA

Select High Temperature ACCC Conductors

Replaced UPAS and WOLF conductors with the ACCC Lisbon and ACCC Copenhagen conductorsLisbon and ACCC Copenhagen conductors

28% More Aluminum

Greater StrengthGreater Strength

Lower Coefficient of Thermal

Expansion

Less Sag at Higher Temp.

Page 7© 2010 Quanta Technology LLC Page 7

ACCC uses a carbon fiber core that is 25% stronger and 60% lighter than a traditional steel core

Conductor Thermal Rating Comparison

Page 8© 2010 Quanta Technology LLC Page 8

Approximate Sag for Spans of 200m ‐ ACCC vs. ZTACIR

Page 9© 2010 Quanta Technology LLC Page 9

Kelvin – Cydna

Kelvin – Cydna:16.8 km, 88kV, 100MVA to 150/200MVA

Page 10© 2010 Quanta Technology LLC Page 10

K l i C d

Kelvin – Cydna

Kelvin – Cydna:16.8 km, 88kV, 100MVA to 150/200MVA

Page 11© 2010 Quanta Technology LLC Page 11

Kelvin – Cydna

Kelvin – Cydna:16.8 km, 88kV, 100MVA to 150/200MVA

Page 12© 2010 Quanta Technology LLC Page 12

Quanta Energized Services Team

Page 13© 2010 Quanta Technology LLC Page 13

South Africa - Re-conductoring

Page 14© 2010 Quanta Technology LLC Page 14

88 kV Energized Uprating using LineMasterTM with an additional delta circuit

South Africa - Re-conductoring

Equipotential string technique used in South Africa to increase

Page 15© 2010 Quanta Technology LLC Page 15

efficiency – necessary safety measures in place

Emergency Support During World Cup Support was provided during the World cupSupport was provided during the World-cup

Emergency repairs and standby

Q i k t b k dQuick response to break downsProspect - Robertsham (stabilize tower)

Orlando - Fordsburg (conductor down)Orlando - Fordsburg (conductor down)

Live-Line inspections / Audits

Section of Kelvin – Delta upgradedSection of Kelvin – Delta upgraded

Distance Cond. Type Voltage New

Cond. SOWyp

Str 1-52 Upas 88kV Lisbon Line Reconductor

Page 16© 2010 Quanta Technology LLC Page 16

Phase II - Delta – Rosebank

Delta – Rosebank: 1.3km, 88kV, 60MVA to 150/200MVA

Page 17© 2010 Quanta Technology LLC Page 17

Phase II - Kelvin – Sandringham

Kelvin – Sandringham: 8.6km, 88kV, 100MVA to 150/200MVA

Page 18© 2010 Quanta Technology LLC Page 18

Phase II - Kelvin – Greswold

Kelvin – Greswold: 11.4km, 88kV, 100MVA to 150/200MVA

Page 19© 2010 Quanta Technology LLC Page 19

Thank You –Questions?For more information about our services please contact: