43
Sr No Description Amount Remarks 1 Construction of First Floor of Main Building (Academic Block) 20384229 2 Construction of Training and Demonstration Free Rang / Backyard Poultry Shed 3246536 3 Construction of Conference Hall 23698044 4 Construction of First Floor of Boys Hostel 17718581 5 Construction of Parking Shed 1710457 66757847 3337892 70095739 70.096 Main Summary Estimates For the Civil Work "Strengthening of Capacity Building Facilities at Para Veterinary Institute, Karor Lal Eason, Layyah" UNIVERSITY OF VETERINARY & ANIMAL SCIENCES (UVAS) LAHORE Total Amount Add 05% PST Grand Total Cost in Million

Main Summary - eproc.punjab.gov.pk

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Main Summary - eproc.punjab.gov.pk

Sr No Description Amount Remarks

1Construction of First Floor of Main Building

(Academic Block)20384229

2Construction of Training and Demonstration Free

Rang / Backyard Poultry Shed3246536

3 Construction of Conference Hall 23698044

4 Construction of First Floor of Boys Hostel 17718581

5 Construction of Parking Shed 1710457

66757847

3337892

70095739

70.096

Main Summary

Estimates For the Civil Work "Strengthening of Capacity Building Facilities at

Para Veterinary Institute, Karor Lal Eason, Layyah"

UNIVERSITY OF VETERINARY & ANIMAL SCIENCES (UVAS) LAHORE

Total Amount

Add 05% PST

Grand Total

Cost in Million

Page 2: Main Summary - eproc.punjab.gov.pk
Page 3: Main Summary - eproc.punjab.gov.pk

Contractor University Executive Engineer

MEMORANDUM OF WORK

(To be filled by the Project Directorate of the University of

Veterinary & Animal Sciences, Lahore)

General Description _________________________________________________________

(if several sub works are included, they should be detailed in a separate sheet)

__________________________________________________________________________

__________________________________________________________________________

(a) Estimate cost Rs. ____________________________________________________________

_____________________________________________________________

(b) Amount of earnest money to accompany the tender Rs. ____________________________

(to be furnished by the tenderer in the shape of deposit at call from a scheduled Bank of

Pakistan)

(c) Percentage of security deposit to be retained from the bills.

i. On the amount of work done upto Rs. 5 million = ten (10) percent

ii. On the amount of work done beyond Rs. 5 million = five (5) percent

(d) Minimum amount of interim running bills Rs. _____________________________________

(e) Mobilization period ______________________________________________________days

(f) Time allowed to complete the work after the expiry of mobilization period ________ days.

(g) Amount of performance security of Rs ________________________________________ in

the form of Bank Guarantee (see contract conditions clause 7 and general direction 26 (A),

five (05) percent of the accepted tender price in case of tenders with cost exceeding Rs. 50

millions and as per condition 26(A) for all tenders.

(h) Period of maintenance (after the date of issuance of certificate of completion)

_______________________________________________

Page 4: Main Summary - eproc.punjab.gov.pk
Page 5: Main Summary - eproc.punjab.gov.pk
Page 6: Main Summary - eproc.punjab.gov.pk
Page 7: Main Summary - eproc.punjab.gov.pk
Page 8: Main Summary - eproc.punjab.gov.pk
Page 9: Main Summary - eproc.punjab.gov.pk
Page 10: Main Summary - eproc.punjab.gov.pk
Page 11: Main Summary - eproc.punjab.gov.pk
Page 12: Main Summary - eproc.punjab.gov.pk

Sr No Description Amount Remarks

1 Civil Work MRS Items 49865629 MRS

2 Civil Work Non Schedules items 9043923 N-S

3Public Health /Plumbing, Sanitary Installation &

Gas Fittings967208 MRS

4Public Health /Plumbing, Sanitary Installation &

Gas Fittings Non Schedules 1482368 N-S

5 Electric Installation MRS 2334175 MRS

6 Electric Installation Non Schedule 2038600 N-S

7 Road & Road Structure / External Development 1528023 MRS

67259926

Add 5 % PRA 3362996

Total Amount 70622923

Cost in Million 70.623

Subject .Estimate for Construction of Boys Hostel Building at Ravi

Campus Pattoki

UNIVERSITY OF VETERINARY & ANIMAL SCIENCES (UVAS)

RAVI CAMPUS PATTOKI

MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT KASUR

Page 13: Main Summary - eproc.punjab.gov.pk
Page 14: Main Summary - eproc.punjab.gov.pk

Contractor University Executive Engineer

MEMORANDUM OF WORK

(To be filled by the Project Directorate of the University of

Veterinary & Animal Sciences, Lahore)

General Description _________________________________________________________

(if several sub works are included, they should be detailed in a separate sheet)

__________________________________________________________________________

__________________________________________________________________________

(a) Estimate cost Rs. ____________________________________________________________

_____________________________________________________________

(b) Amount of earnest money to accompany the tender Rs. ____________________________

(to be furnished by the tenderer in the shape of deposit at call from a scheduled Bank of

Pakistan)

(c) Percentage of security deposit to be retained from the bills.

i. On the amount of work done upto Rs. 5 million = ten (10) percent

ii. On the amount of work done beyond Rs. 5 million = five (5) percent

(d) Minimum amount of interim running bills Rs. _____________________________________

(e) Mobilization period ______________________________________________________days

(f) Time allowed to complete the work after the expiry of mobilization period ________ days.

(g) Amount of performance security of Rs ________________________________________ in

the form of Bank Guarantee (see contract conditions clause 7 and general direction 26 (A),

five (05) percent of the accepted tender price in case of tenders with cost exceeding Rs. 50

millions and as per condition 26(A) for all tenders.

(h) Period of maintenance (after the date of issuance of certificate of completion)

_______________________________________________

Page 15: Main Summary - eproc.punjab.gov.pk
Page 16: Main Summary - eproc.punjab.gov.pk
Page 17: Main Summary - eproc.punjab.gov.pk
Page 18: Main Summary - eproc.punjab.gov.pk
Page 19: Main Summary - eproc.punjab.gov.pk
Page 20: Main Summary - eproc.punjab.gov.pk
Page 21: Main Summary - eproc.punjab.gov.pk
Page 22: Main Summary - eproc.punjab.gov.pk
Page 23: Main Summary - eproc.punjab.gov.pk
Page 24: Main Summary - eproc.punjab.gov.pk
Page 25: Main Summary - eproc.punjab.gov.pk
Page 26: Main Summary - eproc.punjab.gov.pk
Page 27: Main Summary - eproc.punjab.gov.pk
Page 28: Main Summary - eproc.punjab.gov.pk

Sr.

No. Description Amount Remarks

1 Civil Work MRS Items 49865629 MRS

2 Civil Work Non Schedules items 9043923 N-S

3Public Health /Plumbing, Sanitary Installation &

Gas Fittings967208 MRS

4Public Health /Plumbing, Sanitary Installation &

Gas Fittings Non Schedules 1482368 N-S

5 Electric Installation MRS 2334175 MRS

6 Electric Installation Non Schedule 2038600 N-S

7Construction Of Boundry Wall ,gates and Gate

Pillars 3121480 MRS

8 External Development Tuff paver 1202912 MRS

70056295

Add 5 % PRA 3502815

Total Amount 73559110

Cost in Million 73.559

Subject .Estimate for Construction of Girls Hostel Building at Ravi

Campus Pattoki

UNIVERSITY OF VETERINARY & ANIMAL SCIENCES (UVAS)

RAVI CAMPUS PATTOKI

MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT KASUR

Page 29: Main Summary - eproc.punjab.gov.pk
Page 30: Main Summary - eproc.punjab.gov.pk

Contractor University Executive Engineer

MEMORANDUM OF WORK

(To be filled by the Project Directorate of the University of

Veterinary & Animal Sciences, Lahore)

General Description _________________________________________________________

(if several sub works are included, they should be detailed in a separate sheet)

__________________________________________________________________________

__________________________________________________________________________

(a) Estimate cost Rs. ____________________________________________________________

_____________________________________________________________

(b) Amount of earnest money to accompany the tender Rs. ____________________________

(to be furnished by the tenderer in the shape of deposit at call from a scheduled Bank of

Pakistan)

(c) Percentage of security deposit to be retained from the bills.

i. On the amount of work done upto Rs. 5 million = ten (10) percent

ii. On the amount of work done beyond Rs. 5 million = five (5) percent

(d) Minimum amount of interim running bills Rs. _____________________________________

(e) Mobilization period ______________________________________________________days

(f) Time allowed to complete the work after the expiry of mobilization period ________ days.

(g) Amount of performance security of Rs ________________________________________ in

the form of Bank Guarantee (see contract conditions clause 7 and general direction 26 (A),

five (05) percent of the accepted tender price in case of tenders with cost exceeding Rs. 50

millions and as per condition 26(A) for all tenders.

(h) Period of maintenance (after the date of issuance of certificate of completion)

_______________________________________________

Page 31: Main Summary - eproc.punjab.gov.pk
Page 32: Main Summary - eproc.punjab.gov.pk
Page 33: Main Summary - eproc.punjab.gov.pk
Page 34: Main Summary - eproc.punjab.gov.pk
Page 35: Main Summary - eproc.punjab.gov.pk
Page 36: Main Summary - eproc.punjab.gov.pk
Page 37: Main Summary - eproc.punjab.gov.pk
Page 38: Main Summary - eproc.punjab.gov.pk
Page 39: Main Summary - eproc.punjab.gov.pk
Page 40: Main Summary - eproc.punjab.gov.pk
Page 41: Main Summary - eproc.punjab.gov.pk
Page 42: Main Summary - eproc.punjab.gov.pk
Page 43: Main Summary - eproc.punjab.gov.pk