4 th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 1 of 35 MAHARASHTRA POLLUTION CONTROL BOARD Minutes of 4 th Consent Appraisal Committee Meeting of 2017-2018 held on 23.08.2017 at 3:00 p.m. at at MHADA Office, Grihanirman Bhavan, Kalanagar, Bandra (East), Mumbai, Maharashtra 40005. The Consent Appraisal Committee meeting of the Board was held on 23.08.2017. Following members of the Consent Appraisal Committee were present: 1. Shri. Milind Mhaiskar, Chairman CEO, MHADA and Chairman, MPCB, Mumbai. 2. Dr. P. Anbalagan Member Member Secretary, MPC Board, Mumbai 3. Shri. P. Y. Neve Member Advisor (Environment), MIDC, Mumbai 4. Shri. Tuhin Banerjee, Member Scientist, NEERI 5. Shri. P. K. Mirashe Member Convener Assistant Secretary (Technical), MPC Board, Mumbai Additional Chief Secretary, Home (Transport) Dept., Mumbai and Shri. Rakesh Kumar, Director, NEERI, Mumbai could not attend the meeting. Leave of absence was granted to them. Following Officer of MPCB were present for the meeting: 1. Shri. V. M. Motghare, JD (APC), Mumbai 2. Shri. Y. B. Sontakke, JD (WPC), Mumbai

MAHARASHTRA POLLUTION CONTROL BOARD · 2017-09-15 · 4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 1 of 35 MAHARASHTRA POLLUTION CONTROL BOARD Minutes

  • Upload
    lytruc

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 1 of 35

MAHARASHTRA POLLUTION CONTROL BOARD

Minutes of 4th Consent Appraisal Committee Meeting of 2017-2018 held on 23.08.2017 at 3:00 p.m. at at MHADA Office, Grihanirman Bhavan, Kalanagar, Bandra (East), Mumbai, Maharashtra 40005. The Consent Appraisal Committee meeting of the Board was held on 23.08.2017. Following members of the Consent Appraisal Committee were present:

1. Shri. Milind Mhaiskar, Chairman CEO, MHADA and Chairman, MPCB, Mumbai.

2. Dr. P. Anbalagan Member

Member Secretary, MPC Board, Mumbai 3. Shri. P. Y. Neve Member

Advisor (Environment), MIDC, Mumbai 4. Shri. Tuhin Banerjee, Member

Scientist, NEERI

5. Shri. P. K. Mirashe Member Convener Assistant Secretary (Technical), MPC Board, Mumbai

Additional Chief Secretary, Home (Transport) Dept., Mumbai and Shri. Rakesh Kumar, Director, NEERI, Mumbai could not attend the meeting.

Leave of absence was granted to them. Following Officer of MPCB were present for the meeting:

1. Shri. V. M. Motghare, JD (APC), Mumbai

2. Shri. Y. B. Sontakke, JD (WPC), Mumbai

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 2 of 35

Chairman of the committee welcomed the members of the committee and allowed proceeding of the meeting to start. The meeting thereafter

deliberated on the fresh agenda items (Book-let no. 4) placed before the committee and following decisions were taken.

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

Consent to Renewal 1 0000013871 Vasantdada

Shetkari Sahakari Sakhar Karakhana Ltd., 173,156,167,181 Madhavanagar Road, Sangli Miraj Tal- Miraj, Dist- Sangli

APPROVED

Renewal of consent

31.05.2018 It was decided to grant renewal of consent by imposing following condition: - 1] PP shall install and operate CPU before starting crushing season. Consent shall be issue after receipt of verification report from SRO regarding queries communicated.

2 0000008411 Siddhanath Sugar Mills Ltd. 167/1,167/2 Tirhe North Solapur, Dist. Solapur

APPROVED

Renewal of consent

31.07.2018 It was decided to grant renewal of consent by imposing following condition: 1. Existing BG of Rs. 5 lakhs submitted towards provision of CPU

shall be forfeited as PP has failed t install CPU in time and top up the double amount of BG i.e. Rs. 10 Lakhs for installation of CPU before upcoming crushing season.

Consent shall be issue after:- 1. Verification report from SRO regarding installation of CPU. 2. Submission of requisite additional consent fee.

3 0000008295 Udgiri Sugar and Power Ltd. 586, 587, 588 A/p - Bamani Tal - Khanapur Dist - Solapur

APPROVED

Renewal of consent

31.07.2018 It was decided to grant renewal of consent by imposing following condition: -

1. Industry shall submit Bank Guarantee of Rs. 5 lakh towards Operation & maintenance of pollution control systems and compliance of consent conditions.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 3 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

Consent shall be issue after:-

1. After receipt of requisite additional consent fee.

4 0000009594 Jagruti Sugar And Allied Industries Ltd; 81,101,102,103,105,111 Talegaon(Bh) Devni, Dist. Latur

APPROVED

Renewal of consent

31.08.2018 It was decided to grant renewal of consent by imposing following condition :- 1. Existing BG of Rs. 15 lakhs submitted towards up-gradation of ETP

shall be forfeited as exceed JVS results and top up the double amount of BG i.e. Rs. 30 Lakhs for O&M of pollution control so as to achieve consented standards.

Consent shall be issued:-

1. After receipt of requisite additional consent fee.

5 0000008607 Fabtech Sugar Ltd, 639/2, 639/3, 639/4, 651/2, 651/3, 651/4, 671/1, Nandur Mangalwedha Dist - Solapur

APPROVED

Renewal of consent to

operate

31.07.2018 It was decided to grant consent for renewal of consent by imposing following conditions:- 1. PP shall install Condensate Polishing Unit (CPU) before

upcoming crushing season and extend the BG submitted. 2. Existing BG of Rs. 5 lakhs submitted towards O & M shall be

forfeited as exceed JVS results and top up the double amount of BG i.e. Rs. 10 Lakhs for O & M of pollution control so as to achieve consented standards and Compliance of Consent Conditions.

Consent shall be issued:-

1. After receipt of requisite additional consent fee so as to grant consent period as per Sectorial approach circular.

6 0000009692 Konkan Mitra Mandal Medical Trust's Sahyadri Speciality Hospital 30 C,Plot. No. 30C,

APPROVED Combined Consent to

Operate and BMW

30.06.2018 It was decided to grant Combined Consent to Operate and BMW Authorization (CCA) under renewal of combined consent to operate and authorisation for 202 beds on total plot area of 1975.85 sqm and total construction BUA of 8639 sqm by imposing BG as per BG regime of HCE following conditions:

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 4 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

Erandawane, Karve Road, Pune, Dist. Pune.

Authorization (CCA)

1. PP shall provide OWC for treatment of bio degradable municipal solid waste within 4 months’ time period.

2. HCE has provided STP therefore it was decided to return back the BG of Rs 2 Lakh.

7 0000009427 Fabtech Sugar Ltd (Distillery Division), 651,671At/P Nandur Mangalwedha Dist - Solapur

APPROVED

Renewal of consent to

operate

31.08.2018 It was decided to grant renewal of consent to operate for 65 KLPD capacity molasses based Distillery unit, by imposing following conditions: 1. PP shall submit Bank Guarantee of Rs. 5 lakh towards O & M of

pollution control systems and compliance of consent conditions. Consent shall be issued after:- 1. Verification report from SRO regarding online monitoring system

connectivity to CPCB & MPCB server.

8 0000009510 RattanIndia Nasik Power Limited Plot No. A1, Additional Sinnar Industrial Area, Sinnar SEZ, Dist. Nashik.

NOT APPROVED

Renewal of consent to

operate

- Committee noted that the said power plant is not in operation since commissioning of the unit. Hence, it was decided to issue final refusal of renewal of consent.

9 0000012951 ADLABS ENTERTAINMENT LT, 30/31

Sangadewadi, Khopoli - Pali Road, Off Mumbai - Pune Express Highway, Pin 410203 Khalapur, Raigad

APPROVED

Renewal of consent to

operate with decrease in CI

31.08.2021 It was decided to grant renewal of consent for the Theme park for total plot area of 457780 sqm and total BUA of 52068 sqm by imposing following conditions: 1. PP shall extend the BG of Rs 10 lakh towards O & M of STP and

MSW facility. Consent shall be issued:-

1. Consent shall be issue after obtaining ADTP clarification report regarding BUA (FSI & Non FSI)

10 0000010834 Manganga Sahakari Sakhar

APPROVED

31.07.2018 It was decided to grant renewal of consent to operate by imposing following conditions :-

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 5 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

Karkhana Ltd. Sonarsidhanagar (Sugar Division) Tal-Atpadi ,Dist-Sangali-41530.1

Renewal of consent to

operate

1. Existing BG of Rs. 5 Lakhs submitted towards up-gradation of ETP shall be forfeited as JVS results are exceeding the consented standards and top up the double amount of BG i.e. Rs. 10 Lakhs for O & M of pollution control so as to achieve consented standards.

11 0000011215 Jawaharlal Nehru Medical college Sawangi (Meghe), Dist. Wardha

NOT APPROVED combined

Consent and BMW

Authorization with increase

in bedded capacity

- It is noted that application is made for combined Consent and BMW Authorization with increase in bedded capacity from 1206 to 1280 beds. PP submitted that BUA of the building of College is 52,537 sq.m. and construction BUA of hospital 69,460 sq.m. PP submitted that educational institutes are not falls in purview of Environment clearance. Hence, it was decided to call report from SEIAA, Environment Department, Mumbai regarding applicability of Environment Clearance. It was also decided to direct PP not to operate captive incinerator for incineration of MSW & BMW. To obtain membership for disposal of BMW on regular basis.

12 0000012199 ITTC KANJUR PVT. LTD. CTS No. 657/A (pt), 1293, 1293/1 to 5, 1294/3 to 7 Village Kanjurmar (East) Kurla

APPROVED

Renewal of consent to

operate for IT buildings A &

B

28.02.2018 It was decided to grant renewal of consent to operate for IT buildings A & B project M/s Lodha Developers Pvt Ltd on plot bearing CTS No 657/A(pt), 1293,1293/1 to 5, 1294/3 to 7 of Village Kanjurmarg (E), Mumbai on total plot area of 71278 sqm and construction BUA of 69244.12 sqm out of total construction BUA OF 269416.26 SQM as per EC dated 07.06.2011 by imposing following conditions:- 1. PP shall extend/top-up BG of Rs 5 lakh towards O &M of Pollution

Control Systems. 2. PP shall provide OWC within 4 months period and submit BG of

Rs 5 lakh towards the compliance of the same. 3. PP shall achieve the BOD standard of 30 mg/L within a period of

6 months and submit BG of Rs 10 lakh towards the compliance of the same.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 6 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

4. PP shall install online monitoring system for the parameters Flow, BOD, TSS at the outlet of STP and shall submit BG of Rs 5 lakh towards the compliance of the same.

13 0000009333 Peninsula Business Park C.S. No. 243 Dawn Mill Compound, Lower Parel Mumbai

APPROVED

Renewal of Consent to

Operate for IT Park Project

31.10.2018 It was decided to grant Renewal of Consent to Operate for IT Park Project on total plot area of 27,551.68 sq.m. and total construction BUA area of 1,92,941 sq.m., by imposing following conditions:- 1. PP shall extend/ top up the BG to form total sum of Rs. 25 lakh

towards O&M of pollution control system. 2. PP shall achieve the treated domestic effluent standard for the

parameter BOD- 10 mg/lit. within 6 months’ time period and shall submit BG of Rs. 10 lakhs for the same.

3. The treated domestic effluent shall be 60% recycled for secondary purposes such as toilet flushing, air conditioning, cooling tower make up, firefighting etc. and remaining shall be utilized on land for gardening and connected to the sewerage system provided by local body.

4. PP shall submit Board Resolution from company Board, towards continuing the operation of the project without obtaining consent to operate from the MPC Board thus violated the provisions of Environmental Laws and in future, they will not do such violations and BG of Rs. 2 lakh towards submission of Board resolution within one month of issue of consent.

Consent shall be issued after the receipt of additional fees.

14 0000010503 Nath Pulp And Paper Mills Ltd 142 143 144 WAHEGAON PAITHAN, Aurangabad

NOT APPROVED

Renewal of consent to

operate

-- It is noted that application is made for Kraft paper manufacturing activity with Electricity -3.5 MW. Applied for renewal of Consent to Operate. SRO, Aurangabad reported that CPCB issued Closure Direction on 30.08.2016 for not installing online monitoring system.

In view of above, It was decided to issue final refusal of Consent due to not received restart / withdrawal order from CPCB about installation of online monitoring system, partially treated effluent reuse in the process and excess disposal on land for irrigation.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 7 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

15 0000012957 Bhusawal Thermal Power Station, Deepnagar The Chief Engineer Bhusawal Thermal Power Station Deepnagar, Tal- Bhusawal Dist Jalgaon

APPROVED

Renewal of consent to

operate

31.08.2019 It was decided to principally approve the application for renewal of consent to operate with increase in CI for coal based power plant of unit IV & V- 1000 MW the period upto 31.08.2019 by imposing following conditions:- 1. Industry shall submit the BG of Rs. 10 lakh towards use of

blended/beneficiated coal with ash content less than 34%. 2. Industry shall comply the installation of Automatic real time

monitoring system for coal ash analysis. Consent shall be issued after receipt of BG compliance report from SRO along with latest JVS results accordingly, proportionate BG will be forfeited, if non-compliance reported and after submission of additional requisite consent fee.

16 0000013975 Earnest Tower Pvt Ltd, C54&55 BKC Mumbai

APPROVED

Renewal of consent to

operate with decrease in CI

31.10.2019 It was decided to grant renewal of consent to operate with decrease in CI by imposing following conditions: 1. Forfeit the 50% BG of Rs. 5 lakh out of BG Rs. 10 lakh obtained

towards O&M of pollution control system and obtain top-up BG of Rs. 25 lakh towards O&M of pollution control system as SRO reported that PP has not provided OWC for disposal of bio degradable waste also Environment statement not submitted. record not maintain of used oil, disposal of treated effluent not done properly as per consent condition.

2. PP shall submit the BG of Rs. 5 lakh towards installation of OWC within 03 months.

3. PP shall provide OWC within 4 months period and submit BG of Rs 5 lakh towards the compliance of the same.

4. PP shall install online monitoring system for the parameters Flow, BOD, TSS at the outlet of STP and shall submit BG of Rs 5 lakh towards the compliance of the same.

Consent shall be issued after the receipt of additional fees

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 8 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

17 0000015106 Maharashtra State Power Generation Company Ltd., Nashik Thermal Power Plant Eklahare, Nashik Road

APPROVED

Renewal of consent to

operate with increase in C

31.08.2019 It was decided to grant renewal of consent to operate with increase in CI for Coal based thermal Power plant of 210 MW x 3 Nos.= 630 MW for the period upto 31.08.19 by imposing following conditions:- 1. Industry shall submit the BG of Rs. 10 lakh towards use of

blended/beneficiated coal with ash content less than 34%. 2. Industry shall comply the installation of Automatic real time

monitoring system for coal ash analysis. Consent shall be issued after receipt of BG compliance report from SRO along with latest JVS results accordingly, proportionate BG will be forfeited, if non-compliance reported. and after submission of additional requisite consent fee.

18 0000014806 IndoSpace Rohan Industrial Park Pune Pvt. Ltd., Mahalunge Sr. No. 428, Mahalunge Ingle, Tal.Khed, Dist. Pune

APPROVED

Renewal of of two consent

to operate and amalgamation

of both consents of Logistic Park

31.03.2022 It was decided to grant renewal of two consent to operate and amalgamation of both consents of Logistic Park with total plot area of 377902 sqm and total construction BUA of 127331.54 sqm out of total construction BUA of 167128 sqm as per EC dated 19.11.2011 by imposing following conditions: 1. PP shall extend/top up BG of Rs 25 lakh towards O & M of

Pollution Control System. 2. PP shall install online monitoring system for the parameters flow,

BOD, TSS at the outlet of STP within a period of three months and submit BG of Rs 5 lakh towards compliance of the same.

3. PP shall achieve BOD standard of 10 mg/l within a period of 6 months and submit BG of Rs 10 lakh towards compliance of the same.

19 0000012435 India Steel Works Ltd. Zenith compound Khopoli, Tq. Khalapur, Raigad

Not APPROVED

1st consent to Operate

--- Committee noted that industry has not obtained consent to establish for proposed expansion and directly applied for 1st operate for expansion. Also there is no clarity about scientific disposal of slag generated from existing unit, performance of pollution control system and also not complied with the Interim Direction issued by the Board.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 9 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

Hence, it is decided not to consider the case for 1st consent to operate for Profile Mill- 3250 MT/M and revert back to CAC after obtaining verification report from SRO.

20 0000012768 LMMF's Deenanath Mangeshkar Hospital & Research Centre, 8+13/2, 8+13/2, Erandawane, Nr. Mhatre Bridge, Pune,

NOT APPROVED

Combined

consent and authorization

- It was decided to defer the case and revert back to CAC after obtaining reply from PP in respect of SROs query letter.

21 0000001142 Telwasa Open Cast Coal Mine Expansion Project Project Telwasa OC Sub Area Po.+ Ta.-Bhadrawati, Dist.-Chandrapur

APPROVED

Renewal of Consent to

Operate

31.03.2019 It was decided to grant renewal of Consent to Operate by imposing following conditions:- 1. PP shall submit the BG as per BG regime towards O & M of

pollution control system, Compliance of Consent Conditions, Environment Clearance Conditions.

Consent shall be issued after submission of – 1. Verification regarding adequacy of sedimentation Tank, STP, ETP

capacity from SRO, Chandrapur. 2. After receipt of additional consent fees for increased investment

so as to meet period as per sectorial approach.

22 0000017648 Penganga Opencast Mine Office of the project officer, Penganga OC Project, Ghugus, Dist. Chandrapur

APPROVED

Renewal of consent to

operate with decrease in CI

31.03.2022 It was decided to grant Consent to Operate by imposing following conditions:- 1. PP shall submit the BG as per BG regime towards O & M of

pollution control system, Compliance of Consent Conditions, EC conditions.

Consent shall be issued after submission of – 1. Verification regarding adequacy of sedimentation Tank.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 10 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

2. Decision regarding release of BG may be decided after receipt of verification report from SRO. (i.e. Rs. 5 lakh each towards installation of CAAQMS & STP).

23 0000016729 Umicore Autocat India Pvt. Ltd., Survey Nos. 1295/1296/1122B/1129B/1140, Plot No.03, Mauje-Shirwal Khandala, Satara

APPROVED

Renewal of consent to

operate

31.01.2022 It was decided to grant renewal of Consent to Operate by imposing following conditions: 1. Industry shall submit the Board Resolution from company

towards increasing CI by Rs 56.8 Crs without obtaining permission from the MPC Board thus violated the provisions of Environmental Laws and in future, they will not do such violations and BG of Rs. 2 lakh towards submission of Board resolution within one month of issue of consent.

2. Industry shall extend the BG of Rs 5 lakhs towards O & M of Pollution Control System.

3. Industry shall submit the BG of Rs. 25 lakh for not to violate the conditions of existing consent and not carried out any expansion without prior permission from the board.

Consent shall be issued after submission of additional requisite consent fee.

24 0000012851 DR. Ulhas Patil Medical College & Hospital, GAT NO.315,316,321 & Part of 305, Gat No. 315,316,321 & 305 Jalgaon Bhusawal Road NH6 Jalgaon ,Jalgaon.

NOT APPROVED

Renewal of combined

consent and BMW

authorization

- It is noted that application is made for combined Consent and BMW Authorization with increase in capital Investment by Rs. 16 Cr. and BUA increase from 14,923 sq.m. to 61,534.5 sq.m. Hence, it was decided to issue SCN for refusal of consent and call the report from SEIAA, Environment Department, Mumbai regarding applicability of Environment Clearance (due to Previous BUA was 14923 sq.m. and increases up to 61,534.5 sq.m.).

25 0000019603 Bosch Chassis Systems India

APPROVED

28.02.2022 It was decided to grant renewal of consent to operate with increase in CI and removal of two Nos. of products such as 1] Calipers & 2]

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 11 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

Pvt. Ltd. Gat No 306 Nanekarwadi Chakan Pune

Renewal of consent to

operate with increase in CI and removal

of two Nos. of products

Rotor without electroplating activity by imposing following conditions:- 1. PP shall submit the BG of Rs. 5 lakh towards O&M of pollution

control system. Consent shall be issued after – 1. Submission of additional consent fee as per sectorial approach

circular and after receipt of clarification regarding increased CI.

26 0000019444 Privi Organics Ltd. C-3,4,5,6,6/1,7,8,9, 33/1 & X-9,10,11, 11/1 MIDC Mahad, Raigad

APPROVED

1st operate (remaining part) and

renewal of consent to

operate

28.02.2022 It was decided to grant consent to 1st operate (remaining part) and renewal of consent to operate by imposing following conditions:

1. Industry shall comply with the conditions stipulated in EC granted by GoM.

2. Industry shall extend the existing BGs as per the previous consent.

3. Industry shall install flow meter to monitor the quantity of treated water recycled back in the process/utilities and flow meter to the outlet of ETP to monitor the discharge to CETP.

4. Industry shall install online monitoring system to monitor the parameters such as COD, BOD, SS, pH and also install online flow meter within 03 months period.

Consent shall be issued after submission of requisite consent fee.

27 0000019323 Clariant Chemicals India Limited, 113/114, MIDC Industrial Park, AVPO Dhatav, AV Roha, Tal Roha, Dist Raigad

APPROVED

Renewal of Consent to

Operate

31.01.2022 It was decided to grant renewal of Consent to Operate by imposing following conditions: 1. PP shall submit Board Resolution from company towards

increasing CI by Rs 45.93 Crs without obtaining permission from the MPC Board thus violated the provisions of Environmental Laws and in future, they will not do such violations and BG of Rs. 2 lakh towards submission of Board resolution within one month of issue of consent.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 12 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

2. To Forfeit BG of Rs 10 lakh for exceeding JVS results and top-up double amount of BG i.e. Rs 20 Lakh.

3. PP shall submit feasibility report from NEERI, Nagpur within a period of 3 months and submit BG of Rs 5 lakh towards the compliance of the same.

4. PP shall install online monitoring system to monitor the parameters such as COD, BOD, SS, pH and also install online flow meter.

Consent shall be issued after – 1. Submission of additional consent fee as per sectorial approach

circular.

28 0000015269 Ordnance Factory, SURVEY NO. 91, 92, 93 NEAR VARANGAON VILLAGE, NH - 6 BHUSAWAL

APPROVED

Renewal of Consent to

Operate

30.10.2021 It was decided to grant renewal of Consent to Operate by imposing following conditions:- 1. Forfeit the BG of Rs 1.25 lakh out of Rs 5 lakh towards exceeding

JVS results and top up double amount of BG i.e Rs 5 lakh to make the total sum of Rs 6.25 lakh.

2. PP shall submit Board Resolution of Plant head stating that they have increased the production quantity without the permission of the Board and shall not violate any Environmental Laws in future within a period of one month and shall submit BG of Rs 2 lakh towards the compliance of the same.

Consent shall be granted after receipt of additional fees.

29 0000015775 Wockhardt Ltd, Biotech Park. H-14/2,MIDC,Walu, Aurangabad

NOT APPROVED

Renewal of Consent to

Operate with increase in CI and increase

--- Board has issued SCN for refusal of consent including initiation legal action as industry has increased the quantity of two products i.e. Insulin and Insulin Analogs by 195 Kg/A and Erythropoietin by 0.08 Kg/A without obtaining consent to establish from the Board. Committee noted the PP’s reply in respect of SCN issued by the Board as :-

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 13 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

in quantity of two products

1. Industry has not increased the current production levels above the consented capacities and requested for enhanced production capacity by utilization as well as with up-gradation of technology & excellence in production capacities.

2. The Biotech Manufacturing activity does not come under the purview of EC as per EIA Notification, 2006.

3. The increase in CI is to meet the regulatory and GMP (Good Manufacturing practices) requirements of pharmaceutical manufacturing.

The reply of the industry is not satisfactory and being a reputed industry carried out expansion without consent from the Board. Hence, it is decided to issue final refusal of renewal of consent to operate with increase in CI and stop work to the expansion activity.

30 0000020265 Tetra Pak India Pvt. Ltd, Plot No-B-53, Midc chakan, Phase no II, Village- Vasuli, Taluka Khed, Pune..

APPROVED

Renewal of consent to

operate

28.02.2022 It was decided to grant renewal of Consent to Operate for manufacturing of packing material, straw, Machinery for dairy, beverage and cosmetic industry with printing and painting activity. by imposing following conditions:- 1. Industry shall extend the BG of Rs 5 lakh obtained towards O &

M of Pollution Control System.

31 0000020424 Varroc Engineering Pvt Ltd (Plant No. VIII) Plot No. M-191/3, MIDC Waluj, Dist. Aurangabad

APPROVED

Renewal of Consent to

Operate

28.02.2022 It was decided to grant renewal of Consent to Operate by imposing following conditions:- 1. Forfeit the BG of Rs. 3 lakh out of BG of Rs. 6 lakh obtained

towards O & M of pollution control system as out of 03 ETP outlet results, one ETP outlet result dtd 16.08.2016 are exceeding and to obtain top-up BG of Rs. 6 lakh to make the total BG amount of Rs. 9 lakh towards O & M of pollution control system.

Consent shall be issued after submission of additional requisite fees.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 14 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

32 0000020816 Magarpatta Township Development and Construction Co. Ltd. S. No. 115,116,126-130, 138-148, 149(P), 254, 288 (P), Hadapsar, Dist. Pune

APPROVED

Renewal for consent of operate for Township

(Residential & SEZ for IT)

31.01.2018 It was decided to grant renewal for consent of operate for Township (Residential & SEZ for IT) project of M/s Magarpatta Township Development and Construction Co. Ltd., & Magapatta City Township at S. No 115, 116,126-130,138-148,149 (P) 254,288 (p), Hadapsar, Pune on total plot area of 15,94,102.29 sq.m. and total construction BUA of 7,37,200 sq.m. by imposing following conditions:- 1. PP shall extend / Top up BG of Rs 25 lakh towards O & M of

Pollution Control System. 2. PP shall install online monitoring system for the parameters flow,

BOD, TSS at the outlet of STP within a period of three months and submit BG of Rs 5 lakh towards the compliance of the same.

3. PP shall achieve BOD standard of 10 mg/l within a period of 6 months and submit BG of Rs 10 lakh towards compliance of the same.

33 0000020536 Mahanagar Gas Limited, TAK-A Ambernath Industrial Area, Pin code 421506 Ambernath

APPROVED

Renewal for consent of

operate

31.07.2021 It was decided to grant renewal of Consent to Operate for City gate Station at Forest Naka (Ambernath West) and Transportation and Distribution of Natural Gas in Ambernath, Badlapur and Bhiwandi by imposing following conditions:-

1. PP shall submit BG as per BG regime for compliance of C to O conditions.

34 0000015200 Mungoli Opencast Coal Mine Wani Area, Sakhara, Tal. Wani, Dist. Yavatmal.

NOT APPROVED

Renewal for consent of

operate

-- Committee noted that SCN for refusal of Consent to Operate with increase in CI was issued by the Board. Mine authority submitted the reply which is not satisfactory. Committee also noted that industry failed to comply the consent condition No.(8) Consent No. CAC-1263 dtd. 28/01/2016 regarding provision of three CAAQMS. In view of above, It was decided to issue final refusal of renewal of Consent to operate.

35 0000017956 Times of India (Suburban Press), (M/s Bennett

APPROVED

Renewal for

31.12.2021 It was decided to grant renewal of consent to operate by imposing following conditions:-

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 15 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

Coleman & Co LTD) S.No.11B/1 Malad, 137-A Wadhwan,163 B Akurli Western Express Highway 0, Akurli Road, Kandivali(East)

consent of operate

1. PP shall submit the BG of Rs. 5 lakh towards O&M of pollution control system.

Consent shall be granted after receipt of verification report from SRO to return BG of Rs. 5 lakh obtained from PP towards installation of ETP & STP.

36 0000020955 Reliance Gas Transportation Infrastructure Limited (RGTIL), 1.Survey No. 189 (Jamgaon) 2.Survey No. 373/363 (Navhre) 3.Survey Nos. 110,111,113 (Vaholi) 1.Compressor Station No.06,Jamgaon 2.Compressor Station No.07, Navhre 3.Compressor Station No.08,Vah 1.Barshi 2.Shirur 3.Kalyan

APPROVED

Renewal for consent of

operate

31.03.2022 It was decided to grant renewal of Consent to Operate for Operation of Part of Hyderabad (Zahirabad)- Ahmedabad Gas/Hydrocarbon Pipeline located in Maharashtra with design capacity of 80 MMSCMD of Natural gas/Hydrocarbon having 48; diameter and having length of Pipeline in Maharashtra 584.92 km and passing through 7 districts in Maharashtra and Operation of Compressor Stations at 1. Jamgaon, near Barshi, Dist. Solapur (CS-06), 2 Kokadewadi, Near Shirur, Dist. Pune (CS-07) & 3.Village Vaholi, Tal Kalyan, Dist. Thane by imposing following condition:-

1. PP shall submit BG for O & M as per BG mentioned in BG regime.

Consent shall be issued after submission of requisite consent fee.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 16 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

37 0000020464 Jai Corp Limited - Sipta Coated Steels Division A-3/4 MIDC Industrial Area Nanded

APPROVED

Renewal for consent of

operate with decrease in CI

28.02..2019 It was decided to grant renewal of consent to operate with decrease in CI by imposing following conditions:

1. Industry shall extend the existing BG of Rs. 5 lakh towards O&M of pollution control system.

Consent shall be issued after submission of additional requisite consent fee and details of Stacks with APC systems.

38 0000018276 Shirpur Gold Refinery Ltd. 147 Gut 269/1/2/3, 270/1/2 & 271 Village Dahivad Shirpur, Dhule

APPROVED

Renewal of consent to

operate with increase in CI

28.02.2022 It was decided to grant renewal of consent to operate by imposing following conditions:- 1. PP shall extend the existing BG of Rs. 5 lakh towards O&M of

pollution control system. Consent shall be issued after submission of additional requisite consent fee.

39 0000020407 USV PRIVATE LIMITED CTS-320A,320(1TO3),321(1TO3),275 A-1 Arvind Vithal Gandhi Chowk Mumbai

APPROVED

Renewal of consent to

operate

30.04.2022 It was decided to grant renewal of consent to operate by imposing following conditions: 1. PP shall submit item wise information regarding R&D to be

carried out. 2. PP shall submit Board resolution from Company Board stating

that they have increased the CI of Rs. 42 crs without obtaining permission from the Board within period of one month and shall not do any shall environmental violations in future and shall submit BG of Rs 2 lakh towards the compliance of the same.

3. PP shall not use products mentioned in application form (i.e. R & D activity) for commercial purpose.

4. PP shall submit BG of Rs 5 towards O & M of Pollution Control systems.

5. PP shall submit BG of Rs 25 lakh towards not doing any further violations.

40 0000021698 Praxair India Pvt. Ltd. A-3 Murbad

APPROVED

31.03.2019 It was decided to grant renewal of Consent to Operate by imposing following conditions:-

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 17 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

MIDC Murbad, thane

Renewal of consent to

operate

1. PP shall extend the BG of Rs 5 Lakh obtained towards O & M of Pollution Control Systems.

41 0000022036 Sulzer India Private Limited Gat No. 304, A/P: Kondhapuri, Shirur, Pune

APPROVED

Renewal of consent to

operate with increase in CI and removal

of two nos. of products

30.04.2022 It was decided to grant renewal of consent to operate with increase in CI and removal of two nos. of products for the period upto 30.04.2022 by imposing following conditions:

1. PP shall extend the existing BG of Rs. 6 lakh obtained towards O & M of pollution control system.

2. PP shall treat the effluent including metal bearing effluent by providing adequate treatment facility including metal recovery plant so as to achieve consented standards and 100% reuse/recycle the total treated trade effluent including metal bearing effluent into the process within a period of three months. In no case treated trade effluent shall be used on land for gardening purpose and submit the BG of Rs. 5 lakh towards compliance of the same.

Consent shall be issued after receipt of latest JVS results from SRO and forfeiting proportionate BG towards exceed Consent standards, after additional requisite consent fee.

42 0000022279 Sudarshan Chemical Industries Limited Plot No A-19/1+2 MIDC, Mahad Dist. Raigad.

APPROVED

Renewal of consent to

operate

30.04.2022 It was decided to grant renewal of Consent to Operate by extending the existing BG of Rs 5 lakh towards O & M of Pollution Control System.

43 0000020969 Jawaharlal Nehru Port Trust, Sheva Navi Mumbai

APPROVED

Renewal of

---- It was decided to grant plain renewal of Consent to Operate by imposing following conditions:-

1. PP shall extend the existing BG as per BG regime.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 18 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

Administration Building, Sheva, Navi Mumbai

Consent to operate

The Consent shall be issued after receipt of verification report of SRO regarding deletion of specific conditions of EC and CRZ clearance as requested by JNPT and after receipt of opinion of legal wing, MPCB.

44 0000022084 Larsen & Toubro Limited, Gate No1. Saki Vihar Road, Powai (W), Mumbai

APPROVED

Renewal of consent to

operate with increase in CI

30.04.2022 It was decided to grant renewal of consent to operate with increase in CI by imposing following conditions:- 1. PP shall extend the existing BG of Rs. 5 Lakh submitted towards

O & M of pollution control system. Consent shall be issued after submission of additional requisite consent fee if any.

45 0000022429 Rhodia Specialty Chemicals India Ltd Plot No 103/104, 104 part,105 part I, II & 2 , MIDC Dhatav MIDC Dhatav Roha, Raigad

APPROVED

Renewal of consent to

operate with change in

name

30.04.2022 It was decided to grant renewal of consent to operate with change in name from M/s. Rhodia Specialty Chemicals India Ltd to M/s. Rhodia Specialty Chemicals India Pvt Ltd by imposing following conditions: 1. Forfeit BG of Rs 2.5 lakh out of Rs 5 lakh as JVS result of sample

dated 16.02.2016 is exceeding the consented limit and obtain top- up BG of Rs 5 lakh to make the total BG of Rs 7.5 lakh.

46 0000022957 SM SHIVAJIRAO NARAYANRAO NAGAWADE SSK LTD., SHRIGONDA FACTORY SHRIGONDA FACTORY, 52/2 AHMEDNAGAR

APPROVED

Renewal of consent to

operate

31.07.2018 The Committee noted that the PP has applied for renewal of Consent for the sugar industry of capacity 3500 TCD. Also, noted that the recent order passed by Hon'ble NGT (WZ) in the case filed by Shri Karim Jahangir Shaikh Vs. State of Maharashtra & Ors. which was transferred from Hon'ble High Court Bench, Aurangabad to Hon'ble NGT (WZ), Pune, The Hon'ble NGT, Pune vide order dated 18.08.2017 directed the MPCB that the consent application shall be duly considered and decision thereupon shall be taken within a fortnight in accordance with law for the reasons recorded therein.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 19 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

DOUND ROAD SHRIGONDA

The Committee deliberated the issue and noted that the industry have modified / upgraded the existing ETP so as to meet the consented norms. The modification / up-gradation is carried out in the form of arrangement of the ETP unit in the scientific manner as suggested by CPCB, modification in existing bar screen, Grit Chamber, O & G Chamber, Bagasse Trap, Mixing device in Equalization Tank, Proper Slope at Bottom of Primary Clarifier, Provision of uniform effluent arrangement to the units, proper media in tube settler, replacement of media, provision of distribution channel in trickling filter and uniform launder at the top of secondary clarifier for uniform overflow , removal of flexible pipelines including provision of 15 days storage tank etc. As Air Pollution Control system the industry has provided wet scrubber for 04 Nos. of Boiler. Since the industry has taken adequate measures towards up-gradation of 400 CMD capacity ETP for the treatment of effluent generated from sugar industry. It is decided to consider renewal of Consent to Operate by stipulating following conditions:- 1. Industry shall submit Board resolution by Company Board

towards increase in capital investment without permission of MPC Board within a period of one month & submit BG of Rs 2 lakh towards compliance of same.

2. Forfeit the BG of Rs. 10 Lakhs as JVS results are exceeding the consented standards and top up with double amount i.e. Rs. 20 Lakhs for O & M of pollution control system.

3. Industry shall extend existing BG of Rs. 5 Lakh submitted towards O & M of pollution control systems.

4. The said consent is issued without prejudice of the order passed or being passed by the Hon'ble NGT, Pune in the aforesaid application No. 70/2014 & application no. 51/2016.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 20 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

47 0000019531 Hindustan Organic Chemicals Ltd Sawale s.no.-137,136,135,134,143,144,131,132 Posari-11,12,13,18 Dapiwali-42,41,40,45 Rasayani Panvel

APPROVED

Renewal of Consent to

operate

28.02.2018 It was decided to grant renewal of Consent to Operate for Dinitrogen Teroxide Plant, by imposing following conditions :-

1. To forfeit Bank Guarantee of Rs. 5 Lakhs as unit has not provided STP till date and top-up with double amount i.e. Rs. 10 lakh towards provision of STP within 3 months period.

2. Industry shall submit Bank Guarantee of Rs. 5 lakh towards O & M of pollution control systems and compliance of consent conditions.

3. Industry shall take specific permission from RO, Raigad before re- starting other plants (except Dinitrogen Teroxide Plant)

48 0000021820 Smruthi Organics Limited A - 27, MIDC Chincholi, Tal-Mohol, Dist-Solapur

APPROVED

Renewal of Consent to

operate

30.04.2022 It was decided to grant renewal of Consent to Operate for manufacturing of basic drugs chemicals, by imposing following conditions: 1. Forfeit Bank Guarantee of Rs. 2.5 lakh out of Rs. 5 lakh obtain

towards O & M of Pollution Control System as JVS are exceeding consented standard and top-up with Rs. 5 lakh so as to make total BG of Rs. 7.5 lakh towards compliance of same.

49 0000022020 Tata Blue Scope Steel Ltd., Sr. No. 247 & 250, Hinjewadi Mulshi, Pune

APPROVED

Renewal of consent to

operate with increased CI

30.04.2022 It was decided to grant the case for renewal of consent to operate with increased CI by imposing following conditions:- 1. PP shall extend the existing Bg of Rs. 5 lakh obtained towards

O&M of pollution control system. It was also decided to return the BG of Rs. 2 lakh obtained towards carryout hazardous waste audit as industry has submitted the same. Consent shall be issued after submission of additional requisite consent fee and latest JVS results from SRO.

50 0000022624 Embio Limited E-21, 22/1/2/3, MIDC, Mahad, Raigad

APPROVED

Renewal of consent to

30.04.2022 It was decided to grant renewal of consent with increase in capital investment by imposing following conditions: 1. PP shall submit Board resolution by Company Board towards

increase in capital investment without permission of MPC Board

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 21 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

operate with increased CI

within a period of one month & submit BG of Rs 2 lakh towards compliance of same.

2. Regarding generation & dispose of 720 T/A sodium acetate mixture residue in hazardous waste category industry shall Carry out H.W. audit to authorized technical institute within 3 months & BG of Rs.5 lakh towards compliance of same.

3. PP shall extend the BG Rs. 10 Lakh towards O & M of Pollution Control System.

Consent shall be issued after the receipt of additional fees.

51 0000022317 Ghugus Open Cast Mine Post: Ghugus, Tal. & Dist. Chandrapur

NOT APPROVED

Renewal of consent to

operate

-- It was decided to issue SCN for refusal of renewal of consent to operate on the basis of non-compliances mentioned in SCN issued by Regional Officer, Chandrapur like :-

1. Not provided sedimentation tank for mine water discharge. 2. Water discharged on ground and colour of the mine water

found reddish. 3. Fixed type water sprinkling arrangement at Coal stock yard

not provided. 4. Coal dust found accumulated in CHP area. 5. Fugitive emission found during visit of Ghugus railway siding. 6. Water sprinkling arrangement provided at Ghugus railway

station which is not in operation. 7. Bank Guarantee Rs. 50 Lakhs not submitted by the applicant.

Also, it was decided that PP shall submit mining closure plan as per their submission about Coal reserve exhausted.

52 0000023667 Minda Industries Ltd. Plot No. B-6 MIDC Chakan, Mhalunge (Ingale) Khed

APPROVED

Amendment in renewal of consent for

HW category

30.07.2021 It was decided to amend the existing consent to operate for addition of Haz. Waste category No. 5.2, 31.1 and 33.3 by imposing following conditions;-

1. To forfeit the BG of Rs. 2 lakh out of BG of Rs.5 lakh as JVS result of ETP outlet are exceeding the consented standards and obtain top-up BG of double amount i.e. Rs. 4 lakh towards O&M of pollution control system.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 22 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

Consent shall be issued after submission of latest audited balance sheet for verification and requisite fees .

53 0000022192 Gabriel India Limited29th Milestore, Pune Nashik Road, village- Kuruli, Tal- Khed , Dist – Pune.

APPROVED

Renewal of consent to

operate

30.04.2022 It was decided to grant the case for renewal of consent to operate by imposing following conditions :- 1. PP shall extend the existing BG of Rs. 5 lakh obtained towards

O & M of pollution control system.

It was also decided to return BG of Rs. 2 Lakh obtained towards submission of Board resolution as industry has submitted the same reported by Board Official. Consent shall be issued after submission of requisite consent fee, if any.

54 0000023312 Sai Life Sciences Ltd. Chrysalis Enclave, Building No. 1, Plot No. 2A; International Biotech park, Hinjewadi phsae 2, Pune

APPROVED

Renewal of consent to

operate

30.04.2022 It was decided to grant renewal of Consent to Operate for R & D Activity in the area of Medicinal Chemistry (Basic Lead Discovery, Contract Chemistry Research, Formulation and Analytical Development), Pharmaceutical Formulation Development & DMPK; Biology (Drug Metabolism Pharmaco Kinetics in animal house) by extending the BG of Rs 5 lakh towards O & M of Pollution Control System.

55 0000024400 Bekaert Industries Pvt. Ltd. B-1, MIDC, Ranjangaon, Taluka Shirur, Dist. Pune

APPROVED

Renewal of Consent to

Operate with increase in CI

30.04.2022 It was decided to grant renewal of Consent to Operate with increase in CI by imposing following conditions :- 1. PP shall extend the existing BG of Rs. 5 lakh obtained towards O

& M of pollution control system. Consent shall be issued after submission of additional requisite consent fee from industry.

56 0000021946 Eternis Fine Chemicals

NOT APPROVED

--- Committee noted that the production quantity mentioned in the EC and in renewal of consent and consent to establish after

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 23 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

Limited, D9/1, D9/2, D9/3, D-15 Kurkumbh MIDC Daund

1st Consent to

operate and renewal of

existing unit and their

amalgamation

amalgamation does not match. Deviation is observed in the consent application and amalgamated quantity of C to R and C to E for water budget, hazardous waste quantity and boiler details etc. In view of above, it was decided to defer the case and revert back to CAC along with details explanation from PP, verification from SRO, Pune-I with above details.

57 0000020999 The Manjri Stud Farm Pvt. Ltd. "SP Infocity"- Residential Project Shapoorji Pallonji And Company Pvt. Ltd. (Real Estate Division),SP Infocity, Survey No 209,Pune-Saswad Road, Phursungi, Haveli, Pune

APPROVED

Renewal of Consent to

Operate (part) for Residential

Project

31.01.2022 It was decided to grant renewal of Consent to Operate (part) for Residential Project on total plot area 3,19,900 sq. m. and Construction BUA of 19,433.94 sq. m. (Out of Total construction BUA of 1,05,565.23 sq. m. of entire project as per EC) by imposing following conditions:- 1. PP shall submit BG of Rs. 25 lakhs towards Operation &

Maintenance of pollution control system. 2. PP shall achieve the treated domestic effluent standard for the

parameter BOD- 10 mg/lit. and shall submit BG of Rs. 10 lakhs for the same.

3. The treated domestic effluent shall be 60% recycled for secondary purposes such as toilet flushing, air conditioning, cooling tower make up, firefighting etc. and remaining shall be utilized on land for gardening and connected to the sewerage system provided by local body.

4. PP shall obtain permission from Central ground water Board within 03 months from issuance of consent to operate, if source is from ground water.

Consent shall be issued after obtaining:- 1. After submission of reply by SRO regarding Queries

communicated vide E mail dtd. 12/08/2017 & 19/08/2017 & after receipt of verification report from SRO regarding adequacy of OWC (capacity), STP (capacity), disposal details.

2. PP shall submit details regarding BG submission (as per earlier consent) in case of non-submission reason of the same.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 24 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

58 0000024999 Wirtgen India Pvt. Ltd. Gat No. 301 & 302, village - Bhandgaon, Taluka - Daund, Dist. -Pune.

APPROVED

Renewal of consent to

operate with increased CI

and production

quantity

28.02.2022 It was decided to grant renewal of consent to operate with increased CI and production quantity and amalgamation of two consents by imposing following conditions:- 1. PP shall submit the BG of Rs. 10 Lakh towards O & M of pollution

control system. 2. PP shall submit Board Resolution from industry Board, due to

increase in investment without obtaining consent to establish from the MPC Board thus violated the provisions of Environmental Laws and in future, they will not do such violations and BG of Rs. 2 lakh towards submission of Board resolution within one month of issue of consent. Consent shall be issued after receipt of requisite consent fee.

59 0000023775 Kirloskar Ebara Pumps Limited Gat No. 904 Gat No. 904, Sawantpur Vasahat, Near Kirloskarwadi Palus Kirloskarwadi, Sangali

APPROVED

Renewal of consent to

operate with increase in CI and change in water budget

and stacks

30.04.2022 It was decided to grant renewal of consent to operate with increase in CI and change in water budget and stacks for the period upto 30.04.2022 by imposing following conditions: 1. PP shall extend the existing BG of Rs. 5 lakh towards O&M of

pollution control system. Consent shall be issued after submission of additional requisite consent fee, industries reply and latest JVS results from SRO.

60 0000016146 DR L H HIRANANDANI HOSPITAL HILL SIDE AVENUE, NEAR HIRANANDANI GARDENS, POWAI

APPROVED

Combined consent to

operate and BMW

authorization

30.08.2018 It was decided to grant combined consent to operate and authorization for 246 beds on total plot area of 6121.7 sqm and total construction BUA of 20372.24 sqm by imposing following conditions:

1. PP shall submit BGs as per the BG regime of the HCE. 2. PP shall provide OWC within a period of 4 months.

Consent shall be granted after submission of following documents:

1. BNH registration. 2. CBMWTSDF membership.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 25 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

3. Additional fees if any.

61 0000019992 Fortis Hospitals Pvt. Ltd, Mulund Goregaon Link Road,Bhandup (W) Mumbai 400078,Mumbai Suburban,Bhandup, Mumbai

NOT APPROVED

Combined consent to

operate and BMW

authorization

'-- Committee noted that application is made for combined Consent and BMW Authorization for 350 beds. Earlier BMW Authorization was granted for 263 Beds & Bombay Nursing Home registration certificate obtained for 440 beds. CI increases from 151.84 Cr to 472.28 Cr. Information called from PP. Reply is awaited. Hence, it was decided to issue Show Cause Notice for refusal of Consent for above non compliances

62 0000025732 BALKRISHNA PAPER MILLS LIMITED Ambivali, Post- Mohone, Tal- Kalyan Dist- Thane

APPROVED

Renewal of Consent to

Operate

30.06.2022 It was decided to grant of Renewal of Consent to Operate by imposing following conditions-

1. PP shall extend existing BG of Rs. 10 Lakh towards O & M of pollution control systems.

2. Bank Guarantee of Rs. 10/- Lakhs obtained against installation of ZLD to be released as SRO reported compliance of the same.

3. Industry shall provide online effluent quality monitoring system as per the directives of CPCB before 31.12. 2017.

63 0000025881 Pride Purple Properties- 210,211,214,215,217,218,219,220,221,222,224,225 Wakad , Pune

NOT APPROVED

renewal of Consent to Operate for

Construction of residential

Buildings

- It is noted that application is made for renewal of Consent to Operate for Construction of residential Buildings, Commercial Building with BUA 271671.9 Sq.M on total Plot area 289189 Sq.M. SRO, Pimpri-Chinchwad submitted copies of latest visit report of Board Official. On scrutiny of the same it is observed that- 1. Organic waste Convertor not found in operation during visit. 2. STP provided for Ruby Park, Ivory Park found non-operational

during visit. 3. Untreated effluent discharged in to drainage line. 4. Information regarding Bank guarantee, OWC capacity, STP

capacity not received from SRO & PP. It was decided to issue Show Cause Notice for refusal of Consent on the basis of non-compliances submitted by SRO.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 26 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

64 0000020570 Jubilant Life Sciences Ltd G.No.25,26,27,28,32,45,Village Nimbut Nira, Tal.Baramati, Dist. Pune

APPROVED renewal of consent to

operate

31.08.2022 Committee noted that industry has applied for renewal of consent to operate without any increase in production quantity. Industry has also provided online monitoring system. NEERI has made the visit and submitted the recommendations as per court Order. Industry has submitted the compliance of recommendations of NEERI. In view of above, it was decided to grant renewal of consent to operate for chemical plant. The consent is issued without prejudice to the order passed or being passed by the Hon’ble NGT and Hon’ble High Court. SRO shall submit the verification report of compliance made by the industry as per recommendations of NEERI and Hon’ble NGT direction.

65 0000027412 Brahmacrop Ltd. (Sheraton Grand) 100/101, R.B.M. Road, Sangamwadi, Pune-411001.

APPROVED

Renewal of Consent to

operate

31.05.2022 It was decided to grant renewal of Consent to operate by imposing following conditions:- 1. PP shall submit the BG of Rs. 25 lakhs obtained towards O & M

of pollution control system. 2. PP shall install online monitoring system for the parameters

BOD, SS and flow at the outlet of STP and submit BG of Rs 5 lakh for the compliance of the same.

3. PP shall achieve the treated domestic effluent standard for the parameter BOD- 10 mg/lit.

4. The treated effluent shall be 60% recycled for secondary purposes such as toilet flushing, air conditioning, cooling tower make up, firefighting etc. and remaining shall be utilized on land for gardening and connected to the sewerage system provided by local body.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 27 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

Consent shall be issued after submission of 1. latest JVS results and verification report from SRO, Pune-I regarding adequacy of capacity of OWC and STP, submission of additional fees. 2. After verification of BG submission as per earlier consent to

operate i.e. BG Rs. 5 lakhs.

66 0000025704 Radisson Blue Hotel, S. No. 136/1 Behind Mercedes Benz International School, Phase-I, Hinjewadi, Tal. Mulshi, dist. Pune Mulshi

APPROVED

Renewal of Consent to

operate

31.05.2022 It was decided to grant renewal of Consent to Operate by imposing following conditions: 1. Project Proponent shall submit the BG of Rs. 25 lakhs towards O

& M of pollution control system. 2. PP shall achieve the treated domestic effluent standard for the

parameter BOD- 10 mg/lit. 3. The treated effluent shall be 60% recycled for secondary purposes

such as toilet flushing, air conditioning, cooling tower make up, firefighting etc. and remaining shall be utilized on land for gardening and connected to the sewerage system provided by local body.

4. PP shall install online monitoring system for parameters BOD, TSS & flow at the outlet of STP with a period of three months and submit BG of Rs 5 lakh towards the compliance of the same.

5. PP shall submit Board Resolution from industry Board, due to increase in investment by 51 Cr without obtaining consent to establish from the MPC Board thus violated the provisions of Environmental Laws and in future, they will not do such violations and BG of Rs. 2 lakh towards submission of Board resolution within one month of issue of consent.

Consent shall be granted after submission of following:-

1. After receipt of verification report of SRO regarding adequacy of STP and OWC.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 28 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

67 0000008394 Sharda Shree Ispat Limited Plot No. E-12, MIDC, Butibori, Nagpur

NOT APPROVED

Renewal of consent to

operate with increase in CI

and production

quantity

-- Committee deliberated the issue that an appeal is pending with Hon'ble Additional Chief Secretary, Environment against refusal of 1st consent to operate for expansion and renewal of existing consent with amalgamation of consent issued by the Board vide letter dtd 10.05.2016,

In the view of above, It was decided to keep the case in abeyance till the decision of appeal and issue SCN.

68 0000027768 DEFIANCE KNITTING INDUSTRIES PVT. LTD. K-6, Addl.MIDC Ambernath, Anand Nagar, Ambernath (E)

APPROVED

Renewal of Consent to

operate

30.06.2018 It was decided to grant renewal of consent to operate, by imposing following conditions :-

1. PP shall submit Bank Guarantee of Rs. 5 lakh towards O & M of Pollution control systems and compliance of consent conditions.

2. PP shall obtain specific permission from the RO, Kalyan before re- starting the operation.

69 0000027046 Chalet Hotels Pvt. Ltd. 71 A, 72 B/A, 72 B/C, 72 A/B, 72 B/B and 71B, Vill. Passpoli Near Chainmayananda Ashram Saki Vihar Road, Powai, Mumbai - 400072.

APPROVED

Renewal of Consent to

operate

31.05.2022 It was decided to grant renewal of Consent to Operate by imposing following conditions:- 1. PP shall submit the BG of Rs. 25 lakhs towards O & M of

pollution control system. 2. PP shall achieve the treated domestic effluent standard for the

parameter BOD- 10 mg/lit. 3. The treated effluent shall be 60% recycled for secondary

purposes such as toilet flushing, air conditioning, cooling tower make up, firefighting etc. and remaining shall be utilized on land for gardening and connected to the sewerage system provided by local body.

4. PP shall install online monitoring system for parameters BOD, TSS & flow at the outlet of STP with a period of three months

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 29 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

and submit BG of Rs 5 lakh towards the compliance of the same.

Consent shall be granted after submission of following:- 1. Requisite additional consent fees for increase investment. 2. Certificate from Architect or Undertaking on 100 Rs. Stamp

Paper stating that PP has not done expansion (built up area) in hotel building after issuance of last consent to operate dated 03.11.2014.

70 0000022284 BASF India Pvt. Ltd. Plot No-12, Thane-Belapur Road, TTC Area, Turbhe, Navi Mumbai

APPROVED

Renewal of Consent to

operate

31.03.2022 It was decided to grant renewal of consent to operate for manufacturing of Leather chemicals, Leather Auxillaries, Automotive coolants, Polyurethene System House, Engineering Plastic, R&D centre(Fine and Performance chemicals & Polyetether Polylol blends ( by physical mixing & without any chemical reaction),& Research Centre for chemicals up to 31.03.2022, by imposing following conditions: 1. PP shall submit Bank Guarantee of Rs. 5 lakh towards O & M of

pollution control systems.

71 0000027996 Konecranes Private Limited Plot D 16 Jejuri MIDC, Pune

APPROVED

Renewal of Consent to

operate with decrease in CI

30.04.2022 It was decided to grant renewal of consent to operate with decreased Capital Investment and name change from M/s. WMI Konecranes India Pvt. Ltd., to Konecranes Pvt. Ltd. for the period upto 30.04.2022 by imposing following conditions:

1. Considering the non-compliance reported by SRO for non-operation of secondary system of STP, It was decided to forfeit the BG of Rs. 5 lakh obtained towards O&M of pollution control system and obtain top-up double amount of BG Rs. 10 Lakh towards compliance of the same.

Consent shall be issued after submission of additional requisite consent fee.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 30 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

72 0000028098 NIPRO INDIA CORPORATION Pvt. Ltd. Plot No.E-1 MIDC Kesurdi Khandala Dist. Satara

APPROVED

Renewal of Consent to

Operate

31.07.2022 It was decided to grant renewal of Consent to Operate with amalgamation with 1st consent to operate expansion, by imposing following conditions:

1. Industry shall submit Bank Guarantee of Rs. 5 lakh towards O & M of pollution control systems.

Consent shall be issued after submission of RO reject disposal details from PP and verification report from SRO.

73 0000025001 Cipla Ltd. A-42 MIDC Patalganga Tal. Khalapur, Dist. Raigad , 410220, Maharashtra, India. Tal. Khalapur, Raigad

APPROVED

Renewal of consent to

operate

30.04.2022 It was decided to grant renewal of consent to operate by imposing following conditions:-

1. PP shall submit BG of Rs 5 lakh towards O & M of Pollution Control System.

Consent shall be issued after submission of Undertaking that they have not carried out any expansion activity. Also, PP shall submit item wise expenditure towards increase in Capital investment.

74 0000027447 Mars Enterprises & Hospitality Private. Limited. 1425,1426,1428to 1431, 1432,14491451 to 14561475 to 1482 etc. Off. International Airport Approach Road, Marol, Andheri (E) Mumbai – 400 059. Andheri

APPROVED

Renewal of Consent to Operate for

hotel activity

31.05.2022 It was decided to grant renewal of Consent to Operate for hotel activity of 102 rooms, restaurant, swimming pool may be consider by imposing following conditions:- 1. PP shall extend/ top up the BG to form total sum of Rs. 25 lakh

towards O&M of pollution control system. 2. PP shall achieve the treated domestic effluent standard for the

parameter BOD- 10 mg/ltr. within 6 months’ time period. 3. The treated domestic effluent shall be 60% recycled for

secondary purposes such as toilet flushing, air conditioning, cooling tower make up, firefighting etc. and remaining shall be utilized on land for gardening and connected to the sewerage system provided by local body.

4. PP shall install online monitoring system for parameters BOD, TSS & flow at the outlet of STP with a period of three months and submit BG of Rs 5 lakh towards the compliance of the same.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 31 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

5. PP shall provide Organic Waste management system (OWC/Bio digester) for treatment of biodegradable waste within 03 months period from the date of issuance of consent to operate.

Consent shall be issued after verifying whether PP has submitted Bank Guarantee as per stipulated in earlier Consent.

75 0000028074 Loknete Baburao Patil Agro Industries Ltd Laxminagar – Angar, 310 Laxminagar - Angar, Tal - Mohol Dist - Solpaur Mohol

APPROVED

Renewal of Consent to

operate

31.07.2018 Committee noted that unit has provided ETP consists of primary, secondary treatment and treated effluent used on land for irrigation. Industry having 03 bagasse based Boilers, provided Wet Scrubber as Air Pollution Control System with 65 mtrs stack height for 02 Boilers one common wet scrubber, separate wet scrubber to remaining boiler, Common stack height 65 mtrs provided) In view of above, it was decided to grant renewal of consent to operate by imposing following conditions: 1. Forfeit the BG of Rs. 5 lakh as industry has not installing CPU in

time and also exceed JVS results and obtained top-up BG of Rs. 10 lakh towards compliance of the same.

Consent shall be issued after verification from SRO regarding installation of CPU and restart revocation order in case CPCB issued Closure Direction.

76 0000028095 Udagiri Sugar and Power Ltd A/P- Bamni (Pare), 587, 588 A/P Bamani Sangli.

APPROVED

Renewal of consent to

operate

31.08.2018 It was decided to grant renewal of consent to operate for Molasses based distillery, by imposing following conditions:

1. PP shall submit Bank Guarantee of Rs. 5 lakh towards O & M of pollution control systems and compliance of consent conditions.

77 0000027760 Shri Vighnahar Sahakari Sakhar Karkhana Ltd. At.

APPROVED

Renewal of

31.07.2018 It was decided to grant renewal of consent to operate for sugar unit 5000 TCD & Co-generation 18 MW by imposing following conditions:

1. PP shall extend existing Bank Guarantee of Rs. 10 lakh.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 32 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

Nivruttinagar, (Dhalewadi), Tal- Junnar, Dist-Pune.

consent to operate

Consent shall be issued after submission of Bank Guarantee of Rs. 3 lakh and requisite consent fee.

78 0000028737 India steel Works Ltd. Zenith compound Khopoli, Raigad

NOT APPROVED

Renewal of consent to

operate with increased

production quantity

--- Committee noted that industry has applied for renewal of consent with increased production quantity. Also there is no clarity about scientific disposal of slag generated from existing unit, performance of pollution control system and also not complied with the Interim Direction issued by the Board. Hence, it is decided not to consider the case for renewal of consent to operate and revert back to CAC after obtaining verification report from SRO.

79 0000027255 Gateway Hotel - P17, MIDC Ambad, Nashik.

APPROVED

Renewal of consent to

operate

31.10.2020 It was decided to grant renewal of Consent to Operate by imposing following conditions:-

1. PP shall submit the BG of Rs. 25 lakhs towards O & M of pollution control system.

2. PP shall achieve the treated domestic effluent standard for the parameter BOD- 10 mg/lit.

3. The treated effluent shall be 60% recycled for secondary purposes such as toilet flushing, air conditioning, cooling tower make up, firefighting etc. and remaining shall be utilized on land for gardening and connected to the sewerage system provided by local body.

4. PP shall install online monitoring system for parameters BOD, TSS & flow at the outlet of STP with a period of three months and submit BG of Rs 5 lakh towards the compliance of the same.

Consent shall be granted after submission of following:- 1. After receipt of verification report of SRO regarding adequacy

of STP and OWC.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 33 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

80 0000029488 Harman Finochem Limited Plot No. A-100, A-100/1, A-100/2, A-120 & D-1 Plot No. A-100, A-100/1, A-100/2, A-120 & D-1, Five star MIDC Shendra, Aurangabad 431 007, State Mah Aurangabad

APPROVED

Renewal of consent to

operate

30.04.2023 It was decided grant renewal with amalgamation of consent of API and pharmaceutical formation up to 30.04.2023, by imposing following conditions:-

1. Industry shall submit Bank Guarantee of Rs. 5 lakh towards O & M of pollution control systems and compliance of consent conditions.

81 0000028399 SHARAYU AGRO INDUSTRIES LTD KAPSHI at post-Kapshi , Tal-Phaltan Dist-Satara.

APPROVED

Renewal of consent to

operate

31.07.2018 It was decided to grant renewal of consent to operate for Sugar - 5000 TCD & Co-Generation capacity - 30 MW, by imposing following conditions: 1. PP shall submit Bank Guarantee of Rs. 5 lakh towards O & M of

pollution control systems and compliance of consent conditions.

82 0000023348 FERRING THERAPEUTICS PRIVATE LIMITED K-28/1 PLOT NO K-28/1, MIDC ADDITIONAL AMBERNATH, AMBERNATH

APPROVED

Renewal of consent to

operate with increase in CI

30.04.2022 It was decided to grant renewal of consent to operate with increased CI for MESALAZINE (API)-300 MT/A by imposing following conditions:- 1. PP shall extend all the existing BG as per earlier consent/

directions. It was decided not to allow conditional grant for discharging treated effluent to CETP during full- fledged operation in future & as earlier consent is granted with ZLD condition and industry is located in non performing CETP in additional Ambernath.

83 0000028757 Bhaurao Chavan SSK Ltd.(Unit No.4) Village

APPROVED Renewal of

31.07.2018 It was decided to grant renewal of Consent to Operate for sugar unit by imposing following conditions: -

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 34 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

Hadsani Tal Hadgaon Dist Nanded

consent to operate

1. PP shall submit BG of Rs. 5 Lakhs towards O & M of pollution control systems and compliance of consent conditions.

Consent shall be issued after submission of requisite fee for refusal period.

Table Item 84 Pune Zillha Dudh

utpadak Sangh Maryadit (katraj Dairy), Pune-Satara Road, Katrak, Pune

Approved

Renewal of Consent to

operate with increase in production

and CI

28.02.2021 It was decided to grant Renewal of Consent to operate with increase in production and CI by imposing following conditions 1. Forfeit the BG of Rs. 5 lakh obtained towards O&M of pollution

control system as JVS results are exceeding the consented standards and obtained top-up BG of Rs. 10 lakh towards O&M of pollution control system.

Consent shall be issued after submission of requisite consent fee.

85 0000010364 Natural Sugar & Allied Industries, Sainagar, A/p. Ranjani, Tq. & Dist. Osmanabad

APPROVED

Renewal of consent to

operate

31.07.2018 It was decided to grant renewal of consent to operate of Sugar unit- 5000 TCD and Co-gen unit-22 MW by imposing following condition: 1. Forfeit the BG of Rs. 5 lakh out of Bg of Rs. 10 lakh obtained

towards O&M of pollution control system as JVS results are exceeding the consented standards and obtained top-up BG of Rs. 10 lakh to make the total BG of Rs. 15 lakh towards O&M of pollution control system.

Consent shall be issued after submission of requisite consent fee.

86 0000023034 Ghatge Patil Industries Ltd., S. No. 362A/365A, 4B, Uchgaon, Tq. Karveer, Dist. Kolhapur

APPROVED

1st consent to operate for

modernization and renewal of

existing unit and their

amalgamation

31.05.2022 It was decided to grant 1st consent to operate for modernization and renewal of existing unit and their amalgamation by imposing following conditions: 1. Industry shall extend the existing BG of Rs. 10 lakh obtained

towards O&M of pollution control system. 2. Industry shall achieve the standard for parameter BOD- 30 mg/lit

instead of consented standard 100 mg/lit within 03 months. It was decided to return the BG of Rs. 5 lakh obtained towards compliance of consent to establish as industry has complied the same.

4th CAC meeting of 2017-18 (CtoR cases Booklet No. 4) dated 23.08.2017 Page 35 of 35

Application Unique Number

Industry Name & Address

Decision on grant of consent

Consent granted upto

Remarks/Discussion

Consent shall be issued after submission of requisite consent fee.

87 Metro Hitech Co-op textile Park Ltd., T-7, kagal hatkanagale 5 start MIDC, Kagal, Kolhapur

APPROVED

1st consent to operate

31.01.2019 Committee noted that industry has obtained clarification from environment Department, GoM vide letter dated 06.07.2017 regarding applicability of environmental clearance. In the letter, it is stated that “ As per EIA Notification 2006, amended on 09.12.2016, EC is not required for construction of industrial shed but such buildings shall ensure compliance of the environmental conditions mentioned in the said notification”. In the view of above, It was decided to grant 1st consent to operate for integrated textile Park on total plot area 3,15,000 Sq. mtrs and total BUA is 1,05,821.55 Sq. mtrs. by imposing following conditions: 1. Industry shall submit the BG of Rs. 10 lakh towards O&M of

common pollution control system facilities provided by the textile park

Consent shall be issued after verification of applicability of EC under area development and after submission of requisite consent fee.

88 MPCB-0000025005

Patanjali Food & Herbal Park, Nagpur Private Ltd., Sector, 12A/16, MIHAN, Hingna, Nagpur

APPROVED

Consent to establish for

food and food processing

activity

Commissioning of the unit or 5

years whichever is

earlier

It was decided to grant Consent to establish for food and food processing activity by imposing following conditions:-

1. Industry shall submit the BG of Rs. 10 lakh towards compliance of consent to establish conditions.

2. Industry shall recycle/reuse 100% treated effluent in process, cooling tower etc. by providing RO and MEE so as to achieve ZLD.

3. Industry shall amend the EC obtained by MIHAN for effluent generating industry.

4. 1st Consent to operate will be considered only after obtaining amendment in EC for effluent generating activity.

Consent shall be issued after submission of requisite consent fee.

The meeting ended with vote of thanks