ILM Bearing
Method of functioning
Prepared: KC Revised: KC Approved: GM
Revision: 01 Date: 29.10.2003Page: 1/5
O:\Marketing\03 HOMEPAGE\mageba-Homepage 2004 (V. II)\6 Unterlagen für Webpage\2 Produkte&Dienstleistungen\3 Brückenlager\2 kartei Lager\03 Downloads\04 Taktschiebelager\02 EN\1 Produkteinformationen\Alte Dokumente\ILM_Bearing_2003_10_Specification.doc
Brackets (for launching)
mageba Incremental Launching Bearing ILM
1) General description
a) Typical cross section
b) Typical top view
During launching sliding plates have to be rigidly supported at the protruding ends to avoid bending of sliding plates
Top plate Bottom plate
ILM Bearing
Method of functioning
Prepared: KC Revised: KC Approved: GM
Revision: 01 Date: 28.10.2003Page: 2/5
O:\Marketing\03 HOMEPAGE\mageba-Homepage 2004 (V. II)\6 Unterlagen für Webpage\2 Produkte&Dienstleistungen\3 Brückenlager\2 kartei Lager\03 Downloads\04 Taktschiebelager\02 EN\1 Produkteinformationen\Alte Dokumente\ILM_Bearing_2003_10_Specification.doc
c) Brackets, to hold the top plate during launching
d) Fixing bolts for transportation and presetting of top plate
Bolts item 28 and plate item 25 to be Removed after finishing of launching
To be cut before operation of bearing
ILM Bearing
Method of functioning
Prepared: KC Revised: KC Approved: GM
Revision: 01 Date: 28.10.2003Page: 3/5
O:\Marketing\03 HOMEPAGE\mageba-Homepage 2004 (V. II)\6 Unterlagen für Webpage\2 Produkte&Dienstleistungen\3 Brückenlager\2 kartei Lager\03 Downloads\04 Taktschiebelager\02 EN\1 Produkteinformationen\Alte Dokumente\ILM_Bearing_2003_10_Specification.doc
Launching direction
Stainless steel sheet (temporarely)
Concrete superstructure
Elastomeric pad
Fixation during launching (temporarely)
H
Pad
Mortar filled through separate channels
Dowels provisionally placed into the recess and bolted to top plate
Bolts
Fixation to be dismount
2) ILM bearing during launching procedure
3) Proposals for fixation after launching procedure
Proposal 1: Connection with dowels
ILM Bearing
Method of functioning
Prepared: KC Revised: KC Approved: GM
Revision: 01 Date: 28.10.2003Page: 4/5
O:\Marketing\03 HOMEPAGE\mageba-Homepage 2004 (V. II)\6 Unterlagen für Webpage\2 Produkte&Dienstleistungen\3 Brückenlager\2 kartei Lager\03 Downloads\04 Taktschiebelager\02 EN\1 Produkteinformationen\Alte Dokumente\ILM_Bearing_2003_10_Specification.doc
Studs
Gap filled with epoxy resin
Fixation to be dismount
Sliding plate welded to top plate
Bolts Studs
Top plate premounted in such a way that it is exactly above the bearing at final position
Fixation to be dismount
Top plate previously mounted to superstructure
Gap filled with epoxy resin
Top plate premounted in such a way that it is above the bearing at final position
Proposal 2: Connection to top plate previously mounted with bolts
Proposal 3: Connection to previously mounted top plate by welding
ILM Bearing
Method of functioning
Prepared: KC Revised: KC Approved: GM
Revision: 01 Date: 28.10.2003Page: 5/5
O:\Marketing\03 HOMEPAGE\mageba-Homepage 2004 (V. II)\6 Unterlagen für Webpage\2 Produkte&Dienstleistungen\3 Brückenlager\2 kartei Lager\03 Downloads\04 Taktschiebelager\02 EN\1 Produkteinformationen\Alte Dokumente\ILM_Bearing_2003_10_Specification.doc
Proposal 4: Connection to previously mounted top plate by using transversal fixation bars
Fixation dismounted
Studs Bolts
Fixation bars
* Distance measured after launching and fixation bars manufactured accordingly