Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED
STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR Telephone: (0761) 2970089 Fax: (0761) 2664343/2970119 e-mail [email protected]
Corporate office: Madhya Pradesh Power Transmission Co. Ltd., Block No.2, Shakti Bhawan, Rampur, Jabalpur 482008, CIN-U40109MP2001SGC014880, Email-mdtransco.nic.co.in
No.07-05/SG-9B-II/387 Jabalpur, dated:20.02.2019
To
As per distribution list
Sub: Agenda of 68th meeting of Operation and Coordination Committee of MP. …
The Agenda of 68th meeting of the Operation and Coordination Committee of MP
scheduled on 27th February 2019 at Vijan Mahal, Tilhari, Mandla Road, Jabalpur has been
uploaded on the website of SLDC ‘www.sldcmpindia.com’ and can be downloaded.
(R.A. Sharma) Member Secretary, OCC SLDC, MPPTCL, Jabalpur
mailto:[email protected]
Distribution List 1. The Chief Engineer (Works), MP Power Transmission Co. Limited, Shakti Bhawan, Jabalpur, email-
[email protected]. 2. The Chief Engineer (T&C), MP Power Transmission Co. Limited, Jabalpur. Fax No- 0761-2665593, 2702710 Email-
[email protected] 3. The Chief Engineer (Transmission-East Zone), MP Power Transmission Co. Limited, Shakti Bhawan, Jabalpur. Email-
[email protected]. 4. The Chief Engineer (Transmission-West Zone), MP Power Transmission Co. Limited, Indore. 5. The Chief Engineer (Transmission-Central Zone), MP Power Transmission Co. Limited, Bijlee Nagar, Govindpura,
Bhopal, email- [email protected]. 6. The Chief Engineer (Plg & Des), MP Power Transmission Co. Limited, Jabalpur, Fax No- 0761-2660908 Email-
[email protected] 7. The Chief Engineer (Procurement.), MP Power Transmission Co. Limited, Jabalpur, .Fax No- 0761-2660908 Email –
[email protected] 8. The Chief Engineer(EHT:Const.), MP Power Transmission Co. Limited, Jabalpur. Fax-0761-2661618, E-mail-
[email protected]. 9. The Chief Engineer(EHT:Maint&insp.), MP Power Transmission Co. Limited, Jabalpur. Fax-0761-2665593, E-mail-
[email protected]. 10. The Executive Director (O & M:Gen), MP Power Generating Company Limited, Jabalpur. Fax No- 0761-2664749,
Email- [email protected], Email- [email protected] 11. The Chief Engineer (O&M:Hydel), MP Power Generating Co. Ltd, Jabalpur, Fax No-0761-2664749. 12. The General Manager(PM), MPPMCL, Jabalpur Email – [email protected] [email protected] 13. The Superintending Engineer (GCC), MPPGCL, Jabalpur Email – [email protected] [email protected]. 14. The General Manger (DCC-EZ), DISCOM Control Centre, MP Poorva Kshetra Vidyut Vitaran Co.Limited, Jabalpur,
Fax No- 0761-2668503, Email – [email protected]. 15. The Dy. General Manager (DCC –CZ), DISCOM Control Centre, MP Madhya Kshetra Vidyut Vitaran Co. Limited,
Bhopal, Fax No-0755-2580611,Email- [email protected]. 16. The Executive Engineer (DCC-WZ), DISCOM Control Centre, MP Paschim Kshetra Vidyut Vitaran Co. Limited, Near
Polo Ground, Jail Road, Indore, Fax No- 0731-2421554, Email- [email protected]. 17. The Executive Engineer, Sub Load Despatch Centre, MPPTCL, Indore, Fax No- 0731-2874515, Email –
[email protected]. 18. The Executive Engineer, Sub Load Despatch Centre, MPPTCL, Bhopal, Fax No- 0755-2885220, Email –
[email protected] 19. The General Manger(RO), MPPMCL, In front of Bhojpur Club, E-4, Arera Colony,Bhopal, Fax No-0755-2423046,
[email protected] 20. The Chief Engineer (PM&C), Narmada Hydroelectric Development Corpn. Ltd, NHDC Parisar, Shamla Hills, Bhopal –
462013., Fax No- 0755-4030130,Email – [email protected] [email protected] 21. The Chief Electrical Distribution Engineer, West Central Railway (WCR), General Manager’s Office, Electrical
Department, Jabalpur-482001 (MP), Fax: 0761-2627629, Email- [email protected], [email protected], M-9752415312, Mr.Satyendra Kumar (Dy.CE), Mob.9752415301 (CEDE, WCR).
22. The General Manager, Indira Sagar Power Station, NHDC Office complex, PO : Narmada Nagar, Distt : Khandwa (MP) – 450 119, Fax No- 07323-284080, Email – [email protected]
23. The General Manager, Omkareshwar Power Station, Prashsnik Bhawan, Urja Vihar, Sidhwarkut, Distt : Khandwa (MP) – 450 554, FaxNo-07280-271703, Email- [email protected], [email protected], [email protected].
24. The Director (Projects), BLA Power Limited, At : Niwari, PO: Khorsipan, Tah : Gadarwara, Distt ; Narsinghpur 487 551, Fax No. 07791-243667 / 243669, Email – [email protected]
25. The Sr. Vice President, Jaiprakash Power Ventures Ltd., Village Sirchopi Subpost Office-Agasod, Post Office-Bina- 470113 Distt- Sagar, Fax No. 07580-277200, Email – [email protected] [email protected],
26. The Chief Executive Officer, Kalpataru Satpura Transco Pvt. Ltd., Satpura Colony, Betul Road, Old Itarsi, Distt. Hoshangabad, Email – [email protected]
27. M/s Ujaas Energy Ltd. 701, NRK Business park, Vijay Nagar Sqaure, Indore – 452010, Email id :[email protected] 28. M/s Suzlon Global Services Ltd., 1090, Scheme no. 114, Park-2, Ring Road, Universal Hospital Row,
Email- [email protected], Indore – 452010, [email protected]
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]
ITEM NO. 1 : CONFIRMATION OF MINUTES : Minutes of 67th meeting of Operation & Coordination Committee of MP held on 04th January 2019 at SLDC, MPPTCL, Jabalpur were forwarded to the committee members vide No. 07-05/SG-9B-II/146 Jabalpur dated 18.01.2019. No comments have been received.
[OCC may confirm the minutes]
ITEM NO.2: REVIEW OF SYSTEM OPERATION DURING THE MONTHS DECEMBER 2018 TO JANUARY 2019. 2.1. Frequency Particulars: During DECEMBER 2018 the system frequency was below 49.90 Hz for 12.68% of time against 10.69% of time during JANUARY 2019. The system frequency was above 50.05 Hz for 10.29% of time during DECEMBER 2018 against 19.05 % of time during JANUARY 2019. The system frequency was within the IEGC range of 49.90-50.05 Hz for 77.03 % of the time during December 2018 against 70.26 % of time during JANUARY 2019. The average monthly frequency was 49.97 Hz during month of DECEMBER 2018 and 49.97 Hz during month of JANUARY 2019.
The detailed frequency particulars for the month of December 2018 and JANUARY 2019 are
enclosed at Annexure-2.1. The brief detail of frequency profile is given here under:-
Month Average frequency
Minimum Integrated frequency over an hour
Maximum integrated frequency over an hour
Instantaneous Minimum Frequency
Instantaneous Maximum Frequency
DECEMBER 2018 49.97 Hz 49.79 Hz 50.08 Hz 49.67 Hz 50.25 Hz
JANUARY 2019 49.99 Hz 49.82 Hz 50.1 Hz 49.58 Hz 50.28 Hz
[Committee may like to note]
2.2 Operational Matters
2.2.1 Operational Discipline : System operated in terms of frequency profile for the months DECEMBER
2018 and JANUARY 2019 is as given below for discussion by the committee :
Month % of time Frequency Below 49.90 Hz
% of time Frequency above 50.05 Hz
% of time frequency within the permissible range of 49.90-50.05 Hz.
Average monthly frequency
DECEMBER 2018 12.68% 10.29% 77.03% 49.97 Hz
JANUARY 2019 10.69% 19.05% 70.26% 49.99 Hz
[Committee may like to note]
AGENDA FOR 68TH MEETING OF OPERATION & COORDINATION COMMITTEE OF MP TO BE HELD ON 27th FEBRUARY 2019 AT 10:30 AM AT VIJAN MAHAL, TILHARI, MANDLA
ROAD, JABALPUR.
Agenda of 68th OCCM of MP 1
2.2.2 Voltage Profile: During the months DECEMBER 2018 and JANUARY 2019 the maximum and minimum voltage as recorded at following important 400 KV s/s in MP Grid:-
Sr. No.
Name of 400 KV
Substation
DECEMBER 2018 JANUARY 2019 Max. Voltage Min. Voltage Max. Voltage Min. Voltage
Observed Observed Observed Observed
Voltage KV Date
Voltage KV Date
Voltage KV Date
Voltage KV Date
1 Bhopal 420.5 31.12.18 395 22.12.18 420 27.01.19 398 22.01.19
2 Bina 419.3 31.12.18 392 22.12.18 419 06.01.19 396 04.01.19
3 Gwalior 418 02.12.18 387 22.12.18 415 07.01.19 393 04.01.19
4 Indore 421 13.12.18 399 17.12.18 420 26.01.19 399 22.01.19
5 ISP 423 13.12.18 403 22.12.18 421.2 27.01.19 402 22.01.19
6 Nagda 423 13.12.18 398 22.12.18 421 26.01.19 400 24.01.19
7 Pithampur 421 13.12.18 401 17.12.18 422 21.01.19 399 22.01.19
8 Birsinghpur 426 15.12.18 408 31.12.18 426 15.01.19 407 03.01.19
9 Singhaji 423.4 24.12.18 409 17.12.18 423.1 14.01.19 409 22.01.19
10 Satpura 425 31.12.18 409 05.12.18 424 05.01.19 407 24.01.19
11 Itarsi 424.4 31.12.18 403 17.12.18 424 01.01.19 402 22.01.19
12 Ashta 426 13.12.18 398 04.12.18 425 26.01.19 398 04.01.19 [Committee may please note & discuss]
2.2.3 Status of Capacitor Banks in sub-transmission system: The updated information of the status of capacitor banks in sub-transmission system as on 31th JANUARY 2019 as submitted by DISCOMs is detailed below:
DISC
OM
Capacitor bank installed in good condition (No)
Capacitor Banks healthy but not in service due to control ckt problem
Capacitor bank installed but defective & are repairable (No)
Requirement of repair against each unit (No)
Requirement against non-repairable capacitor banks
Capacitor banks already covered under ADB T-V
Balance capacitor banks to be covered in other schemes
600 KVAR
1200 KVAR
1500 KVAR
600 KVA
R
1200 KVA
R
1500 KVA
R
600 KVAR
1200 KVAR
1500 KVAR
No of 100 KVAR Units
required
600 KVAR
1200 KVAR
600 KVAR
1200 KVAR
600 KVAR
1500 KVAR
EZ 408 142 51 08 05 01 21 07 0 25 - - - - - -
CZ 2 684 822 - - - 1 0 0 3 0 0 0 0 0 0
WZ 637 556 720 0 0 0 14 06 15 166 08 17 - - - 3
Agenda of 68th OCCM of MP 2
Central Discom is requested to `update their format for submission of details of Capacitor Bank as per prescribed format. The ‘Capacitor Banks healthy but not in service due to control ckt problem’ have not been included in the details submitted by Central Discom.
[Action: MPPTCL, DISCOMS]
2.2.4 Status of Shunt Capacitor Banks installed at various EHV Transmission Substation: The updated information of the status of installed capacitor banks (in MVAR) in EHV transmission system as on 31.01.2019 as submitted by MPPTCL is given below:-
[Action: MPPTCL]
2.2.5 Status of completion of ongoing Transmission Schemes being executed by MPPTCL: The various ongoing Transmission Schemes completed during the financial year 2017-2018 (up to JANUARY 2019) and plan for completion of various ongoing Transmission Schemes for the Year 2017-2018 is enclosed as Annexure 2.2.5(i) and 2.2.5(ii) respectively.
[Action: MPPTCL]
2.2.6 U/F and df/dt Relay Operation (i) U/F and df/dt Relay Operation: Frequency did not touch 49.20 Hz during DECEMBER 2018 and
JANUARY 2019. There was no df/dt operation during the same period. [Action: MPPTCL]
(ii) Defective u/f, df/dt relays: MPPTCL has informed that all the df/dt and U/F relays are in operation,
where the U/F relays are not available, the numerical relays programmed for under frequency operation. Defective df/dt relay at 220KV Sagar & 220KV S/S Chhatarpur have been replaced & at 132KV S/S Chapda the df/dt protection is provided through df/dt feature of DPR. All U/F stages are in good/ healthy & working condition. [Committee may like to note]
2.3 Power Cuts / Load restrictions/Differential Load Shedding by DISCOMS & group allocation to
33 KV feeders: (i) Details of DISCOM wise Power supply given to various domestic categories during the period
DECEMBER 2018 and JANUARY 2019 is enclosed at Annexure 2.3(i).
[Committee may like to note]
Voltage Class
Capacitor bank installed as on
30.11.18(MVAR)
Capacity Added after Last OCC
Meeting (MVAR)
Capacitor banks already covered under ADB T-V
TOTAL CAPACITY AS ON 31.01.19
(MVAR)
Capacitor Bank Installed but
defective & are not repairable (No &
MVAR) 220 KV 100.00 0.00 - 100.00 All in Service
132 KV 1238.00 0.00 - 1238.00 33 KV 5212.50 67.00 - 5279.50 Total 6550.50 67.00 - 6617.50
Agenda of 68th OCCM of MP 3
(ii) Group Allocation to Newly Commissioned existing EHV substations:- The region wise list of 33 KV
feeders emanating from various newly commissioned/existing EHV substations for which groups have not
been allocated is given in Annexure 2.3 (ii). The DISCOM wise details of pending group allocation to 33 KV
feeders is given below:-
SN DISCOM Region No of 33 KV feeders for which groups to be allocated
01
EAST
Jabalpur 13 02 Sagar 00 03 Rewa 00 04 Total 13 05
WEST Indore 05
06 Ujjain 06 07 Total 11 08
CENTRAL Bhopal 08
09 Gwalior 00 10 Total 08
TOTAL Grand Total 32
Discoms are requested to furnish the details as per list enclosed at Annexure-2.3(ii) in the meeting. In view of the above it is requested that the order copy for which group have been allocated may
please be submitted to P&D, MPPTCL under intimation to SLDC. [ACTION: DISCOMs]
ITEM NO. 3 : OPERATIONAL PLANNNING: 3.1 Generating Units under planned outage and proposed maintenance programme: The annual maintenance /outages of thermal generating units of MPPGCL during February 2019 to March 2019 is NIL as intimated by ED(O&M:Gen.). Hydel Unit outage as intimated by CE (O&M:Hydel), MPPGCL in 67th OCCM is detailed as below:- S.NO. NAME OF HPS & UNIT NO. FROM DATE TO DATE REASON
1. Tons Unit # 1 15.03.2019 02.04.2019 For replacement of C&R panel 2. Tons Unit # 2 03.04.2019 21.04.2019
3. Tons Unit # 3 22.04.2019 12.05.219 The Annual Maintenance schedule for 2019 as submitted by NHDC is as follows:- S.NO. NAME OF HPS & UNIT NO. FROM DATE TO DATE REASON
1. ISP Unit # 1 01.03.2019 15.03.2019 Annual Maintenance 2. ISP Unit # 2 16.03.2019 31.03.2019 Annual Maintenance 3. ISP Unit # 3 01.04.2019 15.04.2019 Annual Maintenance 4. ISP Unit # 4 16.04.2019 30.04.2019 Annual Maintenance 5. ISP Unit # 5 01.05.2019 15.05.2019 Annual Maintenance 6. ISP Unit # 6 16.05.2019 31.05.2019 Annual Maintenance 7. ISP Unit # 7 01.06.2019 15.06.2019 Annual Maintenance
Agenda of 68th OCCM of MP 4
8. ISP Unit # 8 16.06.2019 30.06.2019 Annual Maintenance [Committee May like to note]
3.2 Proposed shutdown programme of Transmission lines / Transformers: The proposed shutdown of transmission elements for the period 01.03.2019 to 30.04.2019 submitted by MPPTCL is enclosed as Annexure-3.2.
[Committee May like to discuss]
3.3 Long Outages of transmission elements and protections: The status submitted by MPPGCL /MPPTCL are given below:-
Sr. No
Line/Transformer/ etc under long Outage
Outage date Reason Response from Utility
1. 16MVA BBL make X’mer at 132KV S/S Berasiya. 10.06.2018
X’mer tripped on Differential & Buchholz
Trip Indications
MPPTCL informed that X’mer replaced by another 20MVA transformer on dt 21-01-2019.
2. UAT-7B, STPS, Sarni 30.06.2018 Differential relay & bucholz relay operated.
Order placed to M/s Shree Abirami Engineering works Chennai, Tamil Nadu on dtd-24.12.2018. Latest status may also be intimated by MPPGCL in the meeting.
3. 500 MVA, 400/220 KV X’mer at STPS. 19.04.2018
X’mer tripped at 21:55 Hrs. due to LA Burst. Emergency shutdown taken for 15 days from
21.04.18 to 05.05.18 for CPRI oil filtering and
RLA testing work.
MPPGCL informed that Owing to adverse report of RLA conducted on ICT during shutdown, proposal for permanent discontinuation of ICT from service has been submitted. In 67th OCCM, Chairman OCC stated that the matter is under dispute, as MPPTCL has shown reluctance for decommissioning of ICT looking to system constrain and proposed to commission GIS at STPS with 500 MVA ICT in service in review meeting of Energy department. Therefore MPPGCL & MPPTCL shall discuss the matter with each other and resolve the matter at the earliest & intimate to SLDC. Latest status may also be intimated by MPPGCL/MPPTCL in the meeting.
4. 50 MVAR (Make GE) Line Reactor at 400KV Sarni-Asta Ckt-I.
31.03.2018
Under outage since 31.03.18 due to concentration of
Acetylene gas. DGA test of transformer oil of
reactor was carried out by M/s CPRI, Bhopal.
MPPGCL informed that NIT has been uploaded on dtd-20.08.2018 & enquiry has been opened on 19.09.2018 and certain queries on techno commercial issues have been sought from M/s GE(T&D) India(OEM). Price bid opened on 05.12.2018 & price clarification & correspondence is going on with firm. Latest status may also be intimated by MPPGCL in the meeting.
Agenda of 68th OCCM of MP 5
Any transmission element/ EHV element under outage, which has not been intimated/included under aforesaid outage list, should be invariably intimated to SLDC. All entities are requested to ensure the same. The utility may submit the latest status.
[Action:MPPGCL/MPPTCL]
ITEM NO. 4 : OPERATIONAL STATISTICS FOR THE MONTH OF DECEMBER 2018 AND JANUARY 2019: The details of actual generation, Schedule from Central Sector, demand etc. are given in the following Annexures: Annex. 4.1 Unit wise actual Generation of MPPGCL thermal Units and station wise Generation of
MPPGCL & NHDC Hydel Units. Annex. 4.2.i Power Supply Position(Energy Balance Sheet). 4.2.ii. Power Supply Position Scenario:-
POWER SUPPLY POSITION FOR THE MONTH : Dec 18 All Fig in MW
Particulars
Max Dem
Met on : 27-
Dec-18 AT :
09-00
Average 01-10 Dec
Average 11-20 Dec
Average 21-30 Dec
Average Monthly
STATE PEAK DEMAND MET 13778 10460 10183 10478 10373 BREAKUP :-
STATE THERMAL (Actual Gen) 3540 3276 3174 2965 3138
STATE THERMAL (RSD) Total MW 0 0 0 0 0
STATE HYDEL 1465 500 524 675 567
IPP (STATE) 312 228 181 308 239
CENTRAL SECTOR (Schedule) 2669 2580 2461 2649 2563
CENTRAL SECTOR (Surrender) 0 87 177 83 115
IPP (INTER STATE) 2099 2264 1937 2008 2070
RAILWAY 226 223 225 204 217
RENEWABLE ENERGY 696 553 689 515 586
OTHERS -54 -132 -114 -96 -114
BANKING / PURCHASE / SALE 2614 1033 1172 1280 1161
DEVIATION 210 -65 -66 -31 -54
DEVIATION (AVERAGE) 210 Between (-823 to 573)
Between (-862 to 548)
Between (-922 to 670)
Between (-922 to 670)
ENERGY SUPPLY STATE (LU) 2523.30
Agenda of 68th OCCM of MP 6
POWER SUPPLY POSITION FOR THE MONTH : Jan 19 All Fig in MW
Particulars Max Dem Met on :
05-Jan-19 AT : 09-00
Average 01-10 Jan
Average 11-20 Jan
Average 21-30 Jan
Average Monthly
STATE PEAK DEMAND MET 14089 10492 10273 9372 10046
BREAKUP :-
STATE THERMAL (Actual Gen) 3491 3074 3230 3027 3110
STATE THERMAL (RSD) Total MW 0 0 0 0 0
STATE HYDEL 1817 596 411 312 440
IPP (STATE) 377 262 305 298 288
CENTRAL SECTOR (Schedule) 3241 2830 2610 2320 2587
CENTRAL SECTOR (Surrender) 0 149 312 544 342
IPP (INTER STATE) 2411 2164 2259 2146 2190
RAILWAY 225 223 231 217 224
RENEWABLE ENERGY 650 480 568 674 574
OTHERS -162 -125 -146 -176 -149
BANKING / PURCHASE / SALE 2081 1034 845 602 827
DEVIATION -41 -46 -41 -48 -45
DEVIATION (AVERAGE) -41 Between (-778 to 594)
Between (-828 to 594)
Between (-1259 to 802)
Between (-1259 to 802)
ENERGY SUPPLY STATE (LU) 2540.88 Annex. 4.3 Hourly Average of Availability and Demand. Annex. 4.4 Hourly average schedule Vs Drawal of DISCOMs.
[Committee may like to note] ITEM NO. 5 : SYSTEM DISTURBANCE IN MP DURING OF DECEMBER 2018 AND JANUARY 2019: The Grid Disturbances and Grid Incidents in MP during these months are given in Annexure 5.
[Committee May like to discuss] ITEM NO. 6.0 : IMPORTANT OPERATIONAL ISSUES:- 6.1 STATUS OF COMPLETION OF ONGOING SCHEMES FOR COMMISSIONING OF REACTORS / TRANSMISSION ELEMENTS:- The present status regarding schedule and commissioning of reactors / transmission elements is as below:-
Agenda of 68th OCCM of MP 7
S.No. 400 KV S/s Size MVAR
Implementing Agency
Expected Date of Commissioning as intimated in last OCC
1. Line Reactor on 400 kV Sapura–ISP line at STPS
50 MVAR MPPGCL
In 66th OCC MPPGCL informed that the price bid has to be opened and the reactor will be commissioned by June 2019. Latest status may please be submitted by MPPGCL in the meeting.
2. Bus Reactor at SSTPS 125 MVAR MPPGCL
Work will be carried out under PSDF as intimated by MPPGCL in 62nd OCC in 66th OCC MPPGCL informed the committee that the drawing has been approved and reactor is expected to be commissioned by March 2019. Latest status may please be submitted by MPPGCL in the meeting.
The latest status may be submitted in the meeting.
[Action: MPPGCL/NHDC] 6.2 GENERATOR DATA SHEET OF SINGHAJI TPS UNIT # 1, 2, 3 & 4:- As per claus – 11, 12, 13 of Manual on Transmission Planning Criteria Of CEA the generator data is required for modeling
the generators for simulation studies. It is also to mention that due to integration of RE Generators in the grid
& its variable generation for which the precise simulation studies have to be done for proper grid management.
Further vide e-mail dtd- 12.12.2018 & 21.12.2018 Singhat TPS was requested to submit the generator data of
Singhaji TPS Unit #1,2,3&4. The requested data was submitted by MPPGCL.
In view of the above, it is to mention that the details submitted earlier was not complete and missing
details which is required to be re-submitted as conveyed vide e-mail dtd-12.02.2019 is as follows:-
1. For Stage-1 Singhaji (2x600 MW)
a. Complete Generator Technical datasheet which includes various curves like Capability, OCC, SCC etc b. PSS Tuning report of Unit-1,2
c. Turbine Governor model details with inertia of Turbine and governor system(transfer function block
diagram)
d. Turbine governor commissioning reports
e. PSS and AVR Model details (transfer function block diagram)
f. GT technical datasheet (name plate)
2. For Stage-2 Singhaji (2x660 MW) unit-3
a. Turbine Governor model details with inertia of Turbine and governor system(transfer function block
diagram).
b. Turbine governor commissioning reports
c. AVR and PSS parameters-to be downloaded from AVR and submitted.
Agenda of 68th OCCM of MP 8
Further it is to mention that with the commissioning of Unit-4 at Singhaji the details related to unit-4
shall also be submitted. Hence seeing to the security of the grid the modeling of generators for precise
simulation studies has to be done, therefore Singhaji TPS, MPPGCL is requested to comply with CEA
regulations and kindly furnish the required details for modeling of generators for simulatuion studies at the
earliest to this office for further submission to WRLDC.
[Action: MPPGCL]
6.3 AVAILING SHUT DOWN ON NON-ISTS ELEMENTS (ELEMENTS FOR WHICH ONLY APPROVAL OF MP-SLDC IS REQUIRED) AND OUTAGE MODULE THEREOF:- The parallel run of the ABT, OA & MIS system is in progress and the outage module has already been initiated
(link:- http://223.31.122.117:8080/EltrixPortal/login.jsp). Further it is to inform that the User ID and Password
for all the circles/generating stations/EHT-M/EHT-C along with user manual of the outage module has already
been provided vide this office e-mail dtd-14.01.2019. Also vide this office letter no. No No.07-05/174-
B/Kalki/131 dtd-15.01.2019 all the concerned entities/authorities were requested to communicate the User
ID/Password & issue necessary directives to the respective authorities to initiate the use of web based outage
module.
In view of the above all the concerned entities are again requested to submit/process the outage,
tripping, generator outage, generator start/stop, new element charging request through web based outage
module in addition to the existing practice. It is also to mention that from 01.04.2019 it will be mandatory to
process the outage request through outage module only, hence all the entities shall approach for approval of
shut down through outage module. In case of any queries/addition of element/etc the entities can write to us
on e-mail:- [email protected], [email protected] and can coordinate with Shri. Manish Tamrakar, Mob.
No. 7999535347 & Shri.G.Rakesh – 9606796709. It is also to mention that WRLDC has developed a
separate portal for WR-OCCM approval of outage of ISTS elements which shall be discussed separately.
[Action: MPPTCL/MPPGCL/DISCOM’S/NHDC/KALPTARU/JP BINA/BLA]
6.4 WEB BASED OCC OUTAGES SOFTWARE FOR REPLACING THE EXISTING GOOGLE SHEET:- WRLDC has prepared Web Based Application Software for planned outage coordination that would replace the existing coordination through Google Sheet. The Software comprising
following features and process:-
a) The proposed outages for upcoming OCC uploaded in web based portal before 5th of every month.
b) Compiled OCC outage could be viewed and commented before the OCC meeting.
c) Outage after approval in OCC, will be used for further processing.
d) The readiness of D-3 days will be filled in Web portal by concerned utilities through their login
credentials.
e) Non-OCC outages will be updated and same is presented to WRPC for approval, before being
considered for approval.
f) Anyone could comment and give their feedback before D-3 days.
g) The necessary utility concurrence may be availed before processing any outage.
Agenda of 68th OCCM of MP 9
h) The outage considered for approval could be viewed on D-2 days.
i) The outage approved by WRLDC on D-2 days could be viewed on web portal.
j) The final approved outage after NLDC concurrence is available on D-1 days in individual login
credential.
k) The re-schedule of outages is also done as per the approved guideline.
l) Everyone could view the outage approval status online.
The utilities are requested to adhere with guidelines framed regarding OCC outage procedure.
[Action: MPPTCL/MPPGCL/NHDC/JP BINA/BLA]
6.5 REVIEW OF AUFLS SETTINGS:- Review of AUFLS Scheme was being deliberated from 2nd NPC meeting. The decision of 8th NPC in respect to AUFLS scheme is mentioned hereunder: -
AUFLS Existing frequency (Hz) Proposed frequency (Hz) Quantum of load shedding (MW)
Stage-I 49.2 49.4
Same as per existing quantum Stage-II 49.0 49.2
Stage-III 48.8 49.0
Stage-IV 48.6 48.8
It is decided that AUFLS scheme with four stages and raising the frequency by 0.2 Hz viz 49.4, 49.2,
49.0 & 48.8 Hz. The quantum of AUFLS would be reworked by NPC Secretariat based on the discussions held
in this regard. It is therefore beneficiaries are requested to change their AUFLS settings as per decision of 8th
NPC at the earliest under intimation to WRPC Secretariat. With regard to State wise quantum of load
shedding, status quo may be maintained till decision is taken by NPC subsequently.
[Action: MPPTCL /DISCOM’S]
6.6 CREATION OF GIS BASED ENERGY MAP OF INDIA BY NITI AAYOG:- Director, CEA, New Delhi letter No. 07/02/ceA/pfam/Niti Aayog/2018 dtd. 09.02.2018 (copy enclosed), addressed to
CMDs/MDs/Chairperson of Discoms / Power Utilities, has requested to provide data pertaining to power
utilities in attached format (Annexure-6.6) for development of Geospatial Energy Map of India. Accordingly, it
has been requested to provide soft copy of these data to email Id- [email protected]. In the above
context, it is to mention that Niti Aayog is developing a user friendly GIS based Energy Map of India which
would provide true locations of energy resources in India including Power Plant, coal, and oil reserves,
transmission lines, refineries etc. The CEA is nodal agency to collect all data pertaining to the power sector of
India by collecting it from different utilities of power factor. In view of above, it is requested that consolidated
information pertaining to your Company in prescribed format may please be made available in soft copy to
CEA, New Delhi under intimation to this office. The above data may be emailed to mail Id -
[email protected]. He details has been submitted by P&D MPPTCL and NHDC. The other entities are
requested to submit the required details in prescribed format at the earliest. The Committee may discuss the matter
[Action: MPPTCL/MPPGCL/DISCOMS/NHDC/JPBINA/BLA/All State Entities]
Agenda of 68th OCCM of MP 10
6.7 UPDATED 33KV NETWORK DIAGRAMS AS ON 31.01.2019 AND DETAILS OF 33KV NETWORK PLANNED FOR NEXT 10 YEARS:- It has been directed by the Board of Directors of Transco in 93rd meeting that 4 year plan of upcoming transmission system of MPPTCL be
reviewed through independent agency after taking into consideration the capacity addition during the period of
last 5 years i.e. from 2013-2018. Accordingly RFP specification No.TR-67/2018 has been published on
03.10.2018 and final order has been placed to M/s ERDA Vadodara on 25.01.2019 for review of 5 years
transmission plan (2017-22) of MPPTCL and carrying out detailed studies for identification of new transmission
works for subsequent 5 years (2022-27). In context to above, it is to mention that the 33kV feeder wise details regarding existing 33kV network and the
plans for the next 10 years (up to 2027) shall be required for the aforesaid study by the consultant. The details
regarding existing 33kV network i.e. number and capacity of 33/11kV transformer installed in 33/11kV
substation, length of each 33kV line section with name of conductor used. 33kV HT consumers connected with
their contract demand, solar/wind/other renewable power plants connected with their capacity for each 33kV
feeder should be marked on map as per geographical location. The 33kV network planned for future should be
indicated with dotted lines and the details be provided in Annexure-6.7.i, ii & iii. The letters to each Discom
regarding submission of information have already been sent by CE(P&D), MPPTCL, however the desired
information is still awaited.
It is therefore requested that the desired details as mentioned above may be made available to CE-Planning &
Design, MPPTCL, Shakti Bhavan, Rampur, Jabalpur by each Discom along with the diagrams of 33kV network
emanating from EHV substations updated as on 31.01.2019 in respect of all the circles under East, West and
Central Discom positively by 31st March-2019. The data shall be made available to CE-Planning & Design,
MPPTCL, in prescribed format and the same may be mailed on CE(P&D) address e-mail :-
[email protected]. [Action: DISCOM’S]
6.8 MAPPING OF FEEDERS:- As earlier, it has been requested to initiate the process of mapping of AUFLS feeders in SCADA system, however no any progress in this regard noticed so far. In 8th NPC, it has
been decided that WRPC would submit the details / progress of feeder mapping to NPC Secretariat on regular
basis (quarterly).
In view of above, it is requested quarterly details/ progress of mapping of feeders may kindly be
furnished so that same may be communicated to WRPC for onward communication.
[Action: MPPTCL/DISCOM’S] 6.9 PROTECTION AUDIT OF HYDEL POWER STATIONS OF MPPGCL:- The MPPGCL vide letter No. 07-10/601-PSDF, dtd 21/02/2018 has conveyed that protection audit of switchyard associated
with 10 hydro power plants of MPPGCL is required to be carried out by WRPC. Further, it was decided that
work or protection audit of all switchyard carried by a team constituted by WRPC accordingly nominations
were invited from utilities for protection audit team. Vide this office email dtd 11.07.2018 the name of officers
from MPPTCL, NHDC and MPPGCL was conveyed to WRPC. MPPGCL is insisting for early completion of
Agenda of 68th OCCM of MP 11
mailto:[email protected]
aforesaid protection audit, considering provisions of MOM of TESG meeting of PSDF regarding the
observations for PSDF grant on MPPGCL proposal in 37th meeting held on 19.01.2018.
As a sequel to above, SE (Protection), WRPC is intimated that looking to difficulties at WRPC level to
constitute a committee for aforesaid work, it has been directed that committee may be constituted MP- SLDC.
However, detailed programme for Protection Audit to be carried out be intimated to WRPC, so that WRPC may
depute one member from WRPC their end. MPPGCL is therefore requested to furnish detailed programme for
conducting Protection Audit along with data required in this regard as requested by WRPC earlier, so that
proposed Protection Audit could be carried out.
It is mentioned that the matter has been discussed in In 67th OCCM. The representative from CE(Hydel), MPPGCL has ensured that the required details of protection audit will be submitted within a week
time, however requisite details of Hydel Power Station of MPPGCL have not been provided till date. Thus, the
Protection Audit Activities still could not initiate further. The matter may please be expedited and needed
information be provided to SLDC without further delay. [Action: MPPGCL]
6.10 LOAD DROPPING SCHEME AT 400KV & 220 KV SUBSTATIONS TO HANDLE EMERGENCY CONDITION: - This issue have been discussed during various OCC meetings and the representative of T&C has promised that updated load dropping scheme installed at various substations will
be provided , however the requisite details has not be provided to SLDC so far. This data is urgently required
for real time system operation monitoring and to take remedial action to handle contingency condition In view of the above CE(T&C), MPPTCL is requested provide the desired details at the earliest.
[Action: MPPTCL]
6.11 INSPECTION OF RELAYS OF AUTOMATIC UNDER FREQUENCY LOAD SHEDDING AND CERTIFICATION THEREOF: - It is desired that for safe & secure operation of integrated system, the under frequency relay should be connected in the system in healthy condition.
Accordingly, WRPC is pressing hard to provide the self-certified status of healthiness of relays of Automatic
Under Frequency Load Shedding (AUFLS) and periodic checking of the same. Vide this office various
correspondence. The CE (T&C) and also SE(T&Cs) were requested to provide status of healthiness of relays
of Automatic Under Frequency Load Shedding on priority basis to SLDC, so that same may be communicated
to WRPC. Inspite of repeated request vide various correspondence, moreover the matter had been raised in
OCC meeting of MP in time to time, however the desired information are still awaited from utilities. It is therefore desired that the above matter may be treated as urgent and status of healthiness of
Automatic Under Frequency Relays may be provided to SLDC and also the under frequency may be tested
periodically. In this context it is also mentioned that time to time WRPC official as well as SLDC official shall
visit the sub-stations to ascertain the healthiness of under frequency relay.
Committee may please discuss the matter.
[Action: MPPTCL(T&C/P&D), Discoms]
Agenda of 68th OCCM of MP 12
6.12 PROVISION OF SYNCHRONIZATION FACILITY AT EHV SUB-STATIONS OF MPPTCL AND AT ALL POWER HOUSE: - As per Grid Code, the synchronization facility should be available at all the Power Stations, 400 KV Sub-stations, 220 KV Sub-stations and 132 KV sub-stations in the path of black
start. In 60TH OCC meeting MPPTCL representative informed the committee that order for 69 no.
synchronization trolleys has been placed and 1 no. synchronization trolley has been delivered for checking
and testing purpose at 220KV S/S Barwaha. In subsequent meetings this issue has been discussed. However,
no any fruitful progress has been observed so far. In the above context it is indicated that at Manikheda HPS
and Rajghat HPS synchronization facility is not available. It is felt that every Hydel Power station should be
equipped with synchronization facilities invariably for system reliability and Crises Management. Also at
Manikheda HPS & Rajghat HPS single bus system exists, hence MPPGCL is requested to explore the
possibility for commissioning of Double Main Transfer Bus system. Thus, MPPGCL is requested to provide
synchronization facility at Manikheda HPS and Rajghat HPS and MPPGCL may kindly provide status of
making synchronization facility in aforesaid HPS. The MPPTCL may kindly provide the status of installation and commissioning of synchronization trolleys at different substations. Further, is also requested to indicate, whether
synchronization facility could be provided at Karera & Pichhore substation on priority basis. The
matter has been discussed with officers of T&C wing, it is conveyed that they are making arrangement
for installation of synchronizing trolley at Pichhore S/s at the earliest. T&C may please update the position.
The matter was discussed in the meeting. [Action: MPPTCL]
6.13 DELAY IN SUBMISSION OF DOCUMENTS FOR FIRST TIME CHARGING OF ELEMENTS:- As per procedure laid down by NLDC for integration of new EHV elements into the grid and issuance of certification thereof vide letter dtd-26.05.2014, wherein it is indicated that all transmission
licensees intending to commission any transmission element belonging to them and which is a part of a
interstate transmission system shall submit FTC document for approval of RLDC. Further WRLDC vide e-mail
dtd-02.01.2019 intimated the launch of FTC Software along with the user manual. In view of the above it is to inform that, after registration the separate user id & password of MPPTCL
& MPPGCL provided by WRLDC was forwarded to respective entities so that they can upload FTC documents
through this new FTC portal (link-http://ftc.wrldc.in:8080/ftc_wrldc/). Hence all the respective entities are
requested to apply for integration of any transmission element belonging to them and which is a part of a
interstate transmission system through this FTC portal within the specified time limit (i.e., 10 days prior to
anticipated date of first time charging). It is requested that licensee / utilities shall strictly adhere with time
schedule for documentation of first time charging of new transmission elements of all interstate line and all
EHV elements 400kv and above. It may also be ensured that FTC formalities should have completed before
availing outage for integration of element. The authority submitted FTC document should ensure compliance
of protection/ metering/Telemetry issue in coordination with T&C official. It is also desired that all necessary
data should have made available to all adjacent s/s for relay coordination well before targeted date. The
authority submitted FTC document should ensure all formalities have been completed otherwise it would be
Agenda of 68th OCCM of MP 13
http://ftc.wrldc.in:8080/FTC_WRLDC/
difficult to obtain clearance from WRLDC. In general, non-attachment of requisite papers/ SLD/ document of
standing committee approval or approval of competent authority for intrastate elements /approval of Electrical
inspector /noncompliance of relay coordination of adjacent s/s / providing information incorrectly caused delay
in obtaining FTC approval. Therefore, it is desired that FTC document completed in all respect may be
provided in stipulated time schedule so that FTC formalities could be completed within targeted date of
charging.
[Action: MPPTCL/MPPGCL/ISP/OSP/JP BINA/BLA/All State Entities]
6.14 TEN DAILY RESERVOIR OPERATION TABLE OF MPPGCL HPS: - In the meeting held in Regional Office of MPPMCL at Bhopal on 24.09.2016 to discuss availability from Sardar Sarovar Project, ISP
& OPS and State Hydel Plants for Rabi season, MPPGCL had agreed to obtain ten daily reservoir operation
table from WRD and NVDA for their operation of their hydro generators. In last 54th, 55th & 56th OCCM, request
has been made to MPPGCL for furnishing the same to SLDC within a week.
It is requested that MPPGCL shall submit the Ten Daily Reservoir Table of hydel power stations in
coordination with NVDA and WRD for optimum utilization of available water in the reservoirs during the
summer season.
[Action: MPPGCL]
6.15 REGULATE VOLTAGE DURING PEAK / OFF-PEAK HOURS:- It was apprised to the committee that Switchable Shunt Reactors are being taken in service during high voltage conditions. However,
in view of inadequate shunt reactive compensation, the generating units are advised to contribute in voltage
regulation by operating their units in under-excited mode (absorb Reactive Power) within the capability curve.
The MW, MVAR and Voltage of generating units was time to time. In various OCC meeting of MP, attention has been drawn regarding MVAR generation by Power Station
when bus voltage were deviate from nominal. It is observed that MVAR injection/absorption of generators are
not as per the system requirement. Such operation is not desirable and it is therefore desired that AVR setting
and the GT taps may be reviewed / adjusted so as to enable the unit to contribute in voltage regulation within
the capability curve. The directives in this regard may please be adhered to regulate the voltage during peak
hours as well as off peak hours.
Generators are requested to provide MVAR support as per the system requirement and absorb MVAR
when voltages are high to the extent as per their capability curve.
[Action: MPPTCL/MPPGCL/NHDC/KALPTARU/JP BINA/BLA]
ITEM NO. 7: BLACK-START MOCK DRILL OF HYDEL POWER STATIONS : Black Start mock drill of Hydel stations of MPPGCL:- During 2018-2019 the black start mock drill
successfully carried out at Hydel power station as mentioned below:-
S.NO. NAME OF HPS DATE OF MOCK DRILL
1 Pench & Bargi HPS Joint Mock Drill 11.04.2018
2. Gandhi Sagar HPS 06.07.2018
Agenda of 68th OCCM of MP 14
3. Rajghat HPS 29.08.2018
4. Manikheda HPS 18.12.2018
The Black Start Mock Drill at Birsinghpur HPS was conducted on 20.12.2018 but the mock drill
was suspended due to abnormal sound observed from generator side during mock drill.
All the concerned generators are requested to propose a tentative date of Black Start Mock Drill in
ensuing month.
[Action : MPPGCL/NHDC]
ITEM NO. 08: AVAILABILITY BASED TARIFF (ABT) RELATED ISSUES: 8.1 TESTING & CALLIBRATION OF METERS AND NON-RECEIPT OF TIMELY JMR DATA:
1. SLDC has already requested CE(T&C) office in previous OCCMs to issue instructions to site officials for
testing / calibration of meters installed at the Sub-Stations as per Regulations 10 and 18 of Central
Electricity Authority (Installation and operation of meter) Regulation 2010. CE(T&C) office is requested to
apprise the status of testing / calibration of interface meters to committee.
2. CE(T&C) office was repeatedly requested in previous OCCMs to issue instructions to all circle offices for furnishing the JMR data in standard format enclosed herewith as Annexure-8.1 to SLDC on email id- [email protected] before 7th of every month. However, JMR data of all TNCs are still not being received by SLDC up to 15th of every month in required format. CE(T&C) office is again repeated requested to issue instructions to all circle offices for furnishing the JMR data in standard format by 7th of every month at email [email protected].
[Action : CE(T&C) MPPTCL] 8.2 NON RECEIPT OF ABT METER DATA OF RAILWAY TSS THROUGH AMR SYSTEM:
SLDC has already requested in 67th OCCM that ABT meter data of following TSS of Railways is not being received through AMR system:
1. Railway TSS Bordhai.
2. Railway TSS Umreth.
3. Railway TSS Mansakra.
4. Railway TSS Khirkiya.
Railway representative has assured to coordinate with M/s Secure Meters Ltd. and SLDC for resolving
the problems related with data downloading of meter data through AMR System installed at SLDC. However,
meter data of above TSS points is still not being received by SLDC. Railways is requested to take immediate
steps for providing data to SLDC nthrough AMR.
[Action : Railway]
8.3 AMR FACILITY FOR THE ABT METERS INSTALLED AT MPPGCL :
Agenda of 68th OCCM of MP 15
In compliance to state commission directives for computation of weekly transmission losses and Deviation
charges, SLDC has requested the MPPGCL for providing the AMR facility on the meters installed at the
interface points for data downloading through AMR System installed at SLDC. Accordingly MPPGCL has
provided AMR facility on 107 Nos ABT meters installed at the interface points as intimated by CE(Thermal),
O/o ED(O&M:Gen), MPPGCL vide letter No. 426 dated 01.03.2016. The status of Febraury 2018 of ABT meter
data (42 Nos) not received through AMR system of SLDC has been emailed to GCC, MPPGCL on 18rd
Febraury-2018. MPPGCL is requested to take up the matter with M/s Secure Meters Ltd. to resolve the
problems related with non-readability of meters integrated successfully and provide AMC of AMR facility
installed at Power Houses to M/s Secure Meters Ltd so that complete data of meters is received at SLDC.
MPPGCL is requested to apprise the status of AMC.
MPPGCL is requested to furnish the meter master of ABT meters installed at interface points of Hydel
power station as standy meters and provide AMR facility on standby and check meters.
MPPGCL is requested to instruct officials of SSTPS PH-I & II for furnishing the JMR data of Secure meters
where AMR is provided and whose data is downloaded by SLDC. Futher, the 15 minutes blockwise data
recorded in the meter no. XD435287 installed at GT of SSTPS PH-II unit-III do not match with midnight data i.e
monthly injection data, SLDC vide letter No.07-05/SG-11/SEM/347 on date 14.02.2019 has aleady requested
to take up the matter with M/s Secure Meters Ltd. for resolving the problem. MPPGCL may apprise status to
the Committee.
In case of Sanjay Gandhi Thermal Power Station of MPPGCL, the injection recorded by the ABT meters
installed at the outgoing feeders generally do not match with the generation recorded at Generator end.
MPPGCL is requested to advise the site officials for monthly checking / verification of feeder wise data with
Generator and Station Xmer wise data. [Action : MPPGCL ] 8.4 NON RECEIPT OF ABT METER DATA OF ISP & OSP HPS THROUGH AMR SYSTEM:
SLDC has already requested in 67th OCCM that the ABT meter data of ISP & OSP HPS is not being received through AMR system. ISP & OSP were requested to coordinate with M/s Secure Meters Ltd. & SLDC
for resolving the problems related with downloading of meter data through AMR. OSP has integrated meters
with AMR system except meter Sr. Nos. XC560147, XC560148, XC560150, XC560152, XC560154. ISP has
replaced the SIM but details not furnished to SLDC for integrating with AMR system. ISP & OSP are requested
to expite the integrating with AMR system and apprise the status to Committee.
[Action : ISP & OSP HPS]
8.5 NON RECEIPT OF MONTHLY INJECTION DATA (JMR) OF NEWLY COMMISSIONED WIND & SOLAR POWER PROJECT FOR ISSUANCE OF MONTHLY STATE ENERGY ACCOUNT :
The concerned SE(O&M)’s do not furnish the monthly injection data of following newly commissioned
Wind & Solar Power Project connected at 33KV level. However, SLDC is incorporating the injection data
recorded in ABT meter in SEA, but, verification of data could not be done.
Agenda of 68th OCCM of MP 16
i) 15MW Solar Power Project of M/s Simcom Pvt. Ltd. having (Simcom(1MW), Eastman(4MW) , Made
Easy(10MW) connected through 33KV Ctk-I at 220KV Ganjbasoda. – SE(O&M) Vidisha.
ii) 15MW Wind Power Project of M/s Tirupati Dhar Renewable Power Pvt. Ltd. connected at 33KV Jaitpura
Dhar. – SE(O&M) Dhar.
iii) 15MW Wind Power Project of M/s Dhar Wind Power Projects Pvt. Ltd. connected at 33KV
Dashera Maidan – SE(O&M) Dhar.
DDCs, Bhopal and Indore is requested to take up the matter with their CE(Comml), office for issuance of
directives to concerned SE(O&M)’s to furnish the injection data by 3rd or 4th of every month.
Further, SLDC has repeatedly raised the issue in OCCM’s that monthly generation data of Wind
and Solar Projects is not being received from SE(O&M) Dewas till 7th of every month. DDC, Indore is
requested to take up the matter with their CE(Comml), office for issuance of directives to SE(O&M),
Dewas to furnish the JMR generation data by 3rd or 4th of every month.
The injection data of the following wind & solar generators connected at 132KV level and above is not
furnished by the concerned EE(T), MPPTCL. SLDC consider the data received through AMR or through MRI
by site official in monthy SEA, but verification of data could not be done.
i) 42MW Wind Power Project of M/s Suzlon Gujrat Wind Park Ltd. connected at 220KV Badnagar
substation through 132KV Ckt.
ii) 21MW Wind Power Project of M/s Sarjan Realities Ltd. connected at 220KV Badnagar substation
through 132KV Ckt.
CE(T&C) office is requested to issue necessary instructions to concerned filed offices for furnishing the
injection data to SLDC by 3rd or 4th of every month.
[Action : DISCOMS & MPPTCL] 8.6 TIME DRIFT IN ABT METER INSTALLED AT THE POOLING STATIONS OF WIND AND SOLAR GENERATING STATIONS AND SLIDING WINDOW PROBLEM:- SLDC has already requested in previous OCCMs that the ABT meters installed at the following Pooling Stations of Wind & Solar
Power Project has time drift and thus not recording the correct data. SLDC has requested to Generators with
copy to concerned licensee vide letter no. 3142 dated 29/10/2018 for time synchronization of the ABT meters
with GPS so that correct DSM account of these Wind and Solar Projects is issued by SLDC.
Sr.No. FEEDER NAME LOCATION NAME Location VOLTAGE LEVEL
Meter No
1 33 KV UJAAS 1 BERCHHA 132KV S/S BERCHHA Grid S/s End 33 XB571652 2 33 KV UJAS -2 ICHHAWAR 132KV S/S ICHHAWAR Grid S/s End 33 MPC59975
Agenda of 68th OCCM of MP 17
3 GLOBUS STEEL & POWER 132KV S/s SITAMOU Generator End 33 XC562469 4 33KV BHADRESH_SUSNER 132KV S/S SUSNER Grid S/s End 33 XB593639 5 UJAAS-1 AGAR 132KV S/S AGAR Grid S/s End 33 MPC59595 6 UJAAS-2 AGAR 132KV S/S AGAR Grid S/s End 33 MPC59596
SLDC has already requested in previous OCCMs that the ABT meters installed at the following Solar
Generating Stations are recording the 15 minutes block wise data on slinding window principal thus blockwise
data do not match with midnight data. The concerned officials are requested to ensure that ABT meters
installed at interface points shall record load survey data in 15 minutes time block. Further concerned EE(T)’s
are requested to advice RE Generators for immediate replacement of these ABT meters.
i. 12MW Avenger solar pvt Ltd. connected at 132KV S/s Suwasara.
ii. 2.55MW M/s Porwal Auto Component connected at 132KV S/s Makdon.
DCC, Indore & Bhopal is requested to take-up the issue with concerned officials for time synchronization
and replacement of ABT meters.
[Action : West & Central Discoms]
ITEM NO. 9: SCADA and E&T RELATED ISSUES: 9.1 ARRANGENEMENT OF TELEMETRY OF IMPORTANT 220KV SUB STATIONS & 132KV S/S HAVING INJECTION FROM RENEWABLES/CAPTIVE POWER PLANTS OR HAVING INTERDISCOM FEEDERS /TRACTION FEEDERS-
The telemetry of new 400KV S/s, 220KV S/s, important 132KV S/s having injection from renewable generating Stations, Captive Power Plant & Railway Traction feeders is to be provided before charging of the sub stations. However, telemetry of Eleven Sub Stations i.e. 132 KV Raghogarh, 132 KV Isagarh, 132 KV Pratappura, 132 KV Udaipura, 132 KV Ghatabillod, 132 KV Nowgaon, 132 KV Prithvipur, 132 KV Lalbarra, 132 KV Mandsaur, 132 KV Dongrital, 132 KV Chandrawatiganj is to be provided to SLDC.
The 220KV Gudgaon & 220KV Jaora is also scheduled to be charged shortly and telemetry
is to be provided before its charging. MPPTCL may please provide the plan for arranging telemetry of these sub stations.
In last OCCM, MPPTCL informed that procurement of RTUs for 132 KV Raghogarh, 132 KV
Isagarh, 132 KV Pratappura, 132 KV Udaipura is under progress. However the integration of telemetry of above S/s is still pending & no progress in the matter has been observed. MPPTCL is requested to provide present status as well as expedite the commissioning of telemetry of these sub stations.
In addition to the above telemetry of Birsingpur HPS and Zinna HPS is also not available and same needs to be provided by MPPGCL. In last OCCM, MPPGCL informed that order for procurement of 7 RTUs will be placed by end of Jan-19 & MPPGCL was requested to finalise the data channel plan in coordination with SLDC and MPPTCL and initiate procurement of PLCC cabinet /outdoor equipments/ VFT modems so that the data channel shall be available before commissioning of RTU. MPPGCL is requested to provide the current status in the matter.
The telemetry of these identified Sub Stations is urgently required for monitoring of grid.
Hence the progress in the matter as well as further schedule of commissioning of telemetry may please be provided by MPPTCL & MPPGCL.
Agenda of 68th OCCM of MP 18
[Action: - CE (T&C)/CE (Procurement), MPPTCL, ED(O&M :Gen), MPPGCL]
9.2 UPGRADATION OF EXISTING RTUS & DISCREPANCY IN TELEMETRERED VALUES RECEIVED FROM DIFFERENT EHV S/S & POWER STATIONS & The present status of telemetry discrepancy including upgradation requirement is enclosed herewith as Annexure-9.2. The list of major telemetry discrepancies is as given below :-
(a) MPPGCL Generating Substations :-
1. Satpura TPS :- Sr.No.
Description Unit Pending since
MPPGCL response in meeting dtd.30.10.18
MPPGCL response in 67th OCC
1. Gen-7 GT MVAR More than 1 year
- MPPGCL informed that the unit is to be dismantled, so procurement of transducer is not possible. SLDC requested MPPGCL to utilize the spare transducers, if any, for replacement.
2. 400 KV Astha 1 & 2
Line Reactor
Commissioning
MPPGCL informed that signals of reactor are configured in database of Satpura SCADA system but values are not being conveyed to SLDC. NIT has been issued for configuration of point & it shall be completed within one month.
MPPGCL informed that engineer of service provider will visit the site & it will be configured at the earliest.
2. Singhaji Phase II TPS :-
3. SGTPS :-
Sr.No Description Unit Pending since MPPGCL response in 67th OCC 1. Gen-3 MW/MVAR Commissioning SLDC informed that telemetered values of
Gen-3,4 & Station transformer is not available since its commissioning & no action in the matter has been taken by MPPGCL despite constant pursuance by SLDC. SLDC informed MPPGCL that commercial operation of Generator-4 shall not be permitted until telemetry of Gen-3, 4, Station Transformer & RGMO/FGMO signal status is provided by MPPGCL.
2. Gen-4 MW/MVAR Commissioning 3. Station
Transformer MW/MVAR (Data not stable)
Commissioning
Sr.No.
Description Unit Pending since
MPPGCL response in meeting dtd.30.10.18
MPPGCL response in 67th OCC
1. 400 KV STN TRANSFORMER 5A
MW More than 6 months
MPPGCL informed that order has been placed for purchasing transducers & shall be restored within one month. In
MPPGCL informed that the work is under progress & it shall be completed at
Agenda of 68th OCCM of MP 19
4. Amarkantak TPS:-
5. Gandhi Sagar HPS :-
response SLDC informed that transducers may be arranged from the HPS where new RTUs are installed or from T&C where several RTUS having these type of transducers are replaced with new RTUS.
the earliest.
2. STN TR 1 (220 KV)
CB More than one year
MPPGCL informed that cabling work of breaker upto RTU panel is required to be done & shall be done within one month.
MPPGCL informed that no work has been done in response to which SLDC requested MPPGCL to expedite the work.
3. 220/33 KV Transformer
CB/MW/MVAR
More than one year
MPPGCL informed that it shall be provided within one month.
MPPGCL informed that all the discrepancies will be rectified after procurement of transducers.
4. 400 KV Bus 1 Freq More than ten months
MPPGCL informed that corrective action including testing of transducer/arrangement of new transducer shall be completed within a month.
5. 220 KV Bus 2 Voltage More than ten months
MPPGCL informed that procurement of transducer is under process & it shall be commissioned by March-19. SLDC informed that recently RTU of Rajghat & Devlond has been replaced, so transducers can be arranged from Rajghat & Devlond till procurement of new transducers.
6. 400 KV Katni-1 CB-Faulty - - -
Sr.No Description Unit Status
1. 220 KV Panagar-1 CB Faulty
2. 220 KV Bus Coupler CB Faulty
3. 220/132 KV Xmer CB Faulty
Sr.No.
Description Unit Pending since
MPPGCL response in meeting dtd.30.10.18
MPPGCL response in 67th OCC
1. Gen-4 CB More than 10 months
MPPGCL informed that it shall be rectified within 15-20 days. Further SLDC informed that it is gathered from Gandhisagar HPS that when CMR is kept ON it leads to tripping of Unit. MPPGCL informed that they will check the wiring.
MPPGCL informed that these discrepancies shall be rectified after upgradation of RTUs.
2. 33 KV Rajasthan(Kuakheda) feeder
MW/MVAR
Commissioning
SLDC informed that the telemetry of this feeder is of utmost importance as it is an inter-regional feeder. MPPGCL informed that they will arrange for the telemetry of this feeder on priority.
Agenda of 68th OCCM of MP 20
6. Rajghat HPS :-
Discrepancies of Station Transformers:-
S.No. Name of TPS Station Xmer Field Value SCADA Value 1
SGTPS Station Xmer 1 6 MW 3 MW
2 Station Xmer 2 5.4 MW 3 MW 3 Station Xmer 5 A 3 MW 150 MW 4 Satpura TPS Station Xmer 3 2 MW 0 MW MPPGCL vide letter dtd.31.12.18 stated that “Upgradation of existing RTUs in TPS is not
required & suitable measures have been taken to remove discrepancies as & when required”. In last OCC, SLDC informed that large no. of discrepancies pertaining to MPPGCL generating stations are persisting since long time & thus MPPGCL was requested to arrange & expedite rectification of discrepancies /upgradation of RTUs in MPPGCL TPS. MPPGCL is requested to provide current status in the matter.
(b) Transmission/ other Generating Substations :- Sl
No. Name of Substation Name of feeders/transformers
01 400 ISP
1.Telemetry of 125 MVAR Bus Reactor not available. 2.Telemetered values of 400 KV Nagda MVAR is 10 times of actual value. 3. Telemetered values of 400 KV Indore-1 MW.
02 400 KV Kirnapur Wrong MW/MVAR value of 132 KV Dongargarh
03 220 KV Seoni 1. Wrong value of 220 KV Seoni-PG-2 2. Wrong value of 220 KV Bus II Voltage 3. Wrong CB status of 160 MVA Xmer II
(Secondary side) 4. 132 KV Bus Voltage & Frequency
(In last two OCC meeting, it was decided that telemetry of 220KV Seoni shall be shifted to Dongfeng RTU to rectify the above issues. However, action for shiting /rectification in existing RTU is still pending)
04 400 KV Bhopal 1.315 MVA Xmer-IV Main & Tie CB This discrepancy is pending since last one year & no
Sr.No.
Description Unit Pending since
MPPGCL response in meeting dtd.30.10.18
MPPGCL response in 67th OCC
1. Gen-1 CB Commissioning of new RTU
MPPGCL informed that it shall be rectified at the earliest.
Agenda of 68th OCCM of MP 21
corrective actions have been taken by MPPTCL.
05 400 KV Astha 1. CB status of 220 KV Mugaliyachhap This discrepancy is pending since last one year & no corrective actions have been taken by MPPTCL. 2. Wrong CB status of 400/220 KV Xmer-1 (Sec
Side) 06 220 KV Rajgarh Biaora (i) 220 KV TBC CB status
(ii) 220 KV Voltage & Frequency 07 400 KV Indore 400 KV ISP-II line reactor CB wrong status
08 400 KV Chhegaon Wrong CB status of :- i. 132 KV IC I & II ii. 220/132 KV Xmer II (Sec side)
09 400 KV Julwaniya All 132 KV CB status showing open
10 400 KV Katni Wrong CB status of 400 KV Damoh-1
11 220 KV Kotar Wrong CB status of 220 KV Satna 1, 132 KV Rampur Baghelan, 132 KV RTS
12 220 KV Chichli CB status of 132 KV Udaipura 1
13 220 KV Mandideep CB status of 220/132 KV Xmer II & III
14 220 KV Nimrani Telemetry of 33 KV Maral
15 220 KV Indore East CB status of 220 KV Dewas
16 220 KV Nepanagar CB status of 160 MVA Xmer-3, 132 KV Bahadarpur-1 & 2, 20 MVA Xmer-3
17 220 KV Dewas CB status of 220 KV Bus Coupler & 220 KV Indore East
18 220 KV Kotar Faulty CB of 220 KV Satna-1
19 220 KV Satna 1.Wrong MW value of 220 KV Satna-PG-4
20 220 KV Maihar Wrong CB status of 220 KV Satna-PG
21 220 KV Chichli Wrong CB status of 132 KV Udaipura-1
22 220 KV Bina Wrong CB status of 220 KV Ganjbasoda
In last two OCCM, ISP informed that the case for purchasing new RTUs has been initiated by
ISP & it will be completed by 4-5 months in response to which ISP was requested to expedite the progress. The present status along with schedule for rectification of telemetry may please be provided by ISP.
In last OCC, MPPTCL informed that there is some problem in RTU at 400 KV Kirnapur.
MPPTCL (T&C) is pursuing the matter with BHEL but no significant response/action has been taken by BHEL. MPPTCL is requested to provide the current status in the matter.
Agenda of 68th OCCM of MP 22
It has been observed that in substations telemetered through DFE RTUs, the transformer voltage output is used for telemetry of bus voltage. This results in wrong bus voltage in case of transformer outage. MPPTCL is requested to arrange for separate MFM for telemetry of bus voltage.
Further, It has also been observed that some times the bay no. of the charged element is changed without intimation of change in the physical address of RTU elements to SLDC. This results in the wrong telemetered values to SLDC. Recently at 220 KV Nepanagar S/s, telemetry of 132 KV Pipalpani feeder was charged though existing bay of 132 KV Bahadurpur feeder without intimation to SLDC thus resulting in wrong telemetered values of both the feeders. MPPTCL is thus requested to ensure prior intimation of any change in bay or physical address of RTU elements to SLDC.
CERC has recently implemented new DSM regulation w.e.f. 1st January, 2019 and in
this regulation change of sign of deviation by the entity is made mandatory after every six time blocks or else additional charges shall be levied for each violation. Thus the accurate computation of MP as well as Discoms’ demand is essential to avoid additional charges on daily DSM charges. Any discrepancy in real time data of Generation Station /Sub stations may lead to financial burden on Discoms’ in terms of additional DSM charges. MPPTCL, MPPGCL & NHDC are thus requested to ensure the continuity of real time data to SLDC SCADA all the time and fault if any, in the telemetry system should be attended promptly. [ACTION: T&C, MPPTCL , O&M: GEN, MPPGCL, NHDC]
9.3 EXTENSION OF RGMO/FGMO SIGNAL TO SLDC/WRLDC :-The RGMO signal of Pench HPS has integrated in SLDC SCADA system & extension of RGMO/FGMO signal of following generating units is still pending:-
S.No. Name of Generating Station
Unit.No. MPPGCL response in last OCC
1 Satpura TPS 6,7,8,9 MPPGCL informed that they will explore the possibility of providing FGMO signal status & will inform SLDC within one week. However no response in the matter has been observed.
2 SGTPS 1,2,3,4 MPPGCL informed in last two OCC meetings that it is under tendering process & shall be completed within 3-4 months. However no progress in the matter has been observed even after lapse of 4 month period.
3 BARGI HPS 1,2 MPPGCL informed that equipments from BHEL have been received & commissioning shall be done during AOH of Units in 2019.
4 Singhaji TPS Phase II 3,4 MPPGCL informed that as discussed with M/s L&T, RGMO/FGMO is not required. SLDC requested MPPGCL to confirm the same in written so that the matter may be placed before WRPC. The matter has been constantly pursued by SLDC vide letter dtd. 14.02.19, 17.10.18 & 21.08.18. However no response in the matter has been provided by MPPGCL.
Agenda of 68th OCCM of MP 23
MPPGCL is thus requested to kindly arrange for integration of telemetry of RGMO/FGMO in RTU installed at power stations on topmost priority.
[ACTION: O&M: GEN, MPPGCL, NHDC]
9.4(A) NON AVAILABILITY/ UNRELIABLE TELEMETRY OF HYDEL POWER STATIONS :-The telemetry of Hydel Power Stations is very unreliable & frequent long outage with abnormal delay in restoration of same is observed. The RTU availability of MPPGCL HPS is as detailed here under :-
Name of HPS Present
Status Availability
Oct-18 Nov-18 Dec-18 Jan-18
Pench Intermittent 60 75 72 78 Bansagar-III Intermittent 72 70 74 74 Madikheda Intermittent 65 76 71 66 Rajghat Intermittent 71 60 62 77 Gandhisagar Intermittent 72 78 71 52 Bargi Intermittent 71 76 79 72 Tons Intermittent 68 62 65 75 Birsingpur HPS Telemetry not provided to SLDC. Zinna HPS It is to mention that as per CERC communication regulation 2017, availability of telemetry is required to be
ensured more than 99.9% but as indicated above the telemetry availability of Hydel Power Stations is very low.
The telemetry of GandhiSagar HPS is out since 19-01-19 & has not yet been restored despite
constant pursuance by SLDC. Gandhisagar HPS intimated that audio signal level meter is not available & person conversant with communication & telemetry is not available in substation.
In addition to above, the telemetry of Madikheda HPS was out for 10 days from 07-01-19 to 17-01-
19. The restoration of telemetry was delayed because of non-availability of spare PLCC Modem & level meter at Madikheda HPS.
SLDC has constantly pursued the matter in last various OCC meetings regarding arrangement of
RTU/PLCC spares, measuring instruments & adequate trained manpower at MPPGCL stations. However
MPPGCL has not taken any actions regarding this matter.
MPPGCL is thus again requested to take following measures to ensure round the clock availability of real
time data to SLDC:-
1. Arrangement of essential spares at power stations and one set of all spares at centralized location
with intimation to all power stations
2. Arrangement of training to persons looking after telemetry work.
3. Arrangement of measuring instruments like level meters wherever not available.
4. Ensuring availability of RTU configuration at all power stations.
[Action :- ED(O&M:Gen),MPPGCL]
Agenda of 68th OCCM of MP 24
9.4 (B) NON AVAILABILITY/ UNRELIABLE VOICE COMMUNICATION BETWEEN SLDC TO THERMAL/ HYDEL POWER STATIONS :-
It is to inform that as per CERC communication regulation 2017, availability of communication channel is required to be ensured more than 99.9%. However, despite constant pursuance, presently most of the PLCC voice communication of various power stations to SLDC is out since long time and detailed of non-availability as here under: -
Sr.No Name of
HPS/TPS
2 wire PLCC channel
MPPGCL response in meeting dtd.30.10.18
Remark
1.
Bansagar- IV
PLCC voice communication is not established
Mr.Vinay, AE, Tons HPS informed that he will visit Bansagar-IV for restoration of voice communication of Bansagar-IV at the earliest.
Restoration of PLCC channel is still pending.
2.
Madikheda
PLCC voice channel is not working since last 2 years.
Restoration of PLCC channel is still pending. In last OCCM, MPPTCL was requested to arrange for extension of voice channel utilizing Mahalgaon wideband node in coordination with Rajghat HPS.
3
Rajghat
PLCC voice channel is not working since last 2 years
SLDC suggested to extend voice facility upto Rajghat HPS while making the subscriber of 220 KV Bina in coordination with AE Bina. Therefore to commissioned above link voice channel between Rajghat HPS to 220 KV Bina shall require to be established and connect to this channel in PDH equipment at220 KV Bina to extend the voice facility of Rajghat HPS upto SLDC/Backup SLDC.
Voice facility from 220 KV Bina to SLDC Jabalpur has been established, However the voice facility from Rajghat to 220 KV Bina is still pending.
4
Gandhisagar
PLCC voice channel is not working since last 6 month
Restoration of PLCC channel is still pending.
5
Birsinghpur HPS /TPS
PLCC voice channel is not working since long time due to faulty PLCC exchange at Birsinghpur.
AE Birsinghpur informed that presently voice communication between SLDC to thermal power house is proper & the commissioning of EPAX at site is under progress. AE Birsinghpur assured that the voice channel of Birsinghpur HPS shall be restored within one month.
Restoration of voice channel is still pending.
.
Satpura TPS
PLCC voice channel is not working since last 1 years.
AE Satpura informed that faulty card shall be repaired at the earliest. Further, SLDC informed that the OPGW has already been laid between 400 KV Ashta and Satpura TPS and suggested that alternate path can be established using this path by installing end optical
Repair/replacement of Exchange & Card of PLCC equipment at Satpura TPS side is still pending.
Agenda of 68th OCCM of MP 25
equipment.
The matter regarding Non Availability/ Unreliable voice communication Between SLDC to Thermal/
Hydel Power Stations was discussed in last various OCC meeting & special meeting on 30.10.18. However there is no progress in the matter & status provided by MPPGCL in meeting dtd.30.10.18 remains the same.
In last OCCM SLDC pursued the matter regarding extending 2 wire voice facility upto Singhaji 1 & 2
TPS , Madikheda HPS, Rajghat HPS, ISP & OSP HPS from nearest wide band node. Only 2 wire voice facility extension completed for ISP HPS. MPPGCL & NHDC are requested to arrange completion of 2 wire voice facility upto their Power stations.
[ Action :- ED(O&M:Gen),MPPGCL Action :- GM, NHDC]
9.5 NON AVAILABLITY & WRONG TIME STAMPING OF SOE AT SLDC SCADA :-
The proper receipt of Sequence of events (SOE) in SLDC SCADA system from field RTUs is an important feature required for analysis of grid incidents. However, on some instances, it has been observed that the SOE was not received in SCADA system and accordingly, the matter was taken up with field for verification for proper configuration /connections of SOE data in RTUs. After long pursuance, the matter was investigated and it was found that the settings “inf code 2” & “inf code 4” were not correct in Dongfeng make RTUs. These settings have now verified and changed in some of the RTUs and SOE with correct time stamping from RTUS where settings were modified is now receipt in SLDC SCADA/EMS system. However, the verification of the same in most of the RTUs is still pending. The matter regarding verification of SOE in all Dongfeng make RTUS was also discussed in last three OCCM meetings and it was confirmed to arrange the same by end of August 2018. However no significant progress in the matter has been observed. Out of 155 RTUs, SOE verification of 87 RTUs has been completed & the list of RTUs where SOE verification is pending is enclosed herewith as Annexure-9.5. MPPTCL is requested to provide schedule of SOE verification and arrange SOE verification of balance RTUs on top most priority.
9.6 UTILIZATION OF W.B NODE AT BIRSINGHPUR TPS:- In last various OCC, SLDC informed that the W.B node at Birsinghpur TPS has already been
commissioned in 2016. However, despite constant pursuance utilization of node is still pending since last two years due to pending work of laying of cable form W.B node location to PLCC room, Exchange room and RTU. It was informed by SLDC that complete scheme to extend wideband facility upto RTU was prepared by SLDC and forwarded to SGTPS around two years back. The matter is pursued by SLDC constantly. However, required converter and laying of fiber optic cable is still pending. In last OCCM, MPPGCL informed that the procurement of optical cable & modem is still under tendering process. 9.7 LONG OUTAGE OF RTUS, PROBLEM IN DATA AND VOICE CHANNELS & INTERMITTENT TELEMETRY DUE TO NOISE IN COMMUNICATION CHANNEL :- The long outage of telemetry & substations having intermittent telemetry due to heavy noise in communication channel is discussed in detail:-
Sl No. Name of Sub Station Out from /Remark
Agenda of 68th OCCM of MP 26
01 Gandhisagar HPS Out since last one month
02 132 KV Pichhore S/s Out since last one month
03 220 KV Nagra Out since more then one month
03 Satpura TPS Very intermittent
04 132 KV Waidhan S/s Very intermittent
05 Tons HPS Very intermittent
06 Bargi HPS Very intermittent
07 220 KV Rewa Very intermittent
08 Bansagar III HPS Very intermittent
09 220 KV Anuppur Very intermittent
101 132 KV Morwa Very intermittent
11 132 KV Chhindwara Very intermittent
12 220 KV Shahdol Very intermittent
MPERC vide Letter dated 09-08-2017 has directed to submit reason for long outage for RTU & also directed to ensure proper functioning of RTUs. MPPTCL, MPPGCL are requested to sort out rectification of above RTU/data channel on top most priority & arrange for alignment of PLCC Channel & identify/replace the outdoor equipments which injects the noise in the channel/system. [Action :- MPPGCL, MPPTCL] 9.8 TELEMETRY OF RAILWAY TSS SUB STATIONS:-
The telemetry of existing 38 Nos railway Traction Sub Stations & upcoming 25 new railway TSS is required to be provided by railway for monitoring of drawal by each TSS and also monitoring of demand of railway in MP.
In last two OCC Meetings, the railway representative informed that currently the telemetry of
Railway TSS is being extended to Railway Zonal office & further it will be integrated with SLDC. SLDC has constantly requested Railways in last various OCC Meetings to arrange a meeting with SLDC before initiating the integration of telemetry with SLDC .However no such meeting has been arranged by Railways so far. Further Railways has not yet submitted the architecture of telemetry scheme, details of equipments & protocol to be used. Railway is requested to provide present status of telemetry commissioning and arrange a meeting with the implementing agency in coordination with SLDC on topmost priority.
Agenda of 68th OCCM of MP 27
9.9 INFORMATION REQUIRED FOR PMU ANALYTICS UNDER URTDSM PROJECT:- Under the “Unified Real Time Dynamic State Measurement” URTDSM Project, the analytics applications has been installed at SLDC MP for which the relay setting details are required for its configuration from all the sub-stations where PMU’s are installed and its adjacent sub-stations (list of S/s enclosed as Annexure-9.9.1). The format for submitting the required details is enclosed as Annexure-9.9.2.
The matter has been constantly being pursued by SLDC from last 4 OCC Meetings, however still the required information is pending to be provided by MPPTCL. The required data has been received from SGTPS, MPPGCL. MPPTCL is requested to furnish the data at the earliest.
[Action :- MPPTCL] 9.10 ENSURING AVAILABILITY OF AIR CONDITIONER AT WIDE BAND NODES:- The availability of air conditioner is essentially required in wide band communication rooms. Accordingly, SLDC is taking up the matter continuously for ensuring proper functioning of air conditioners in wideband communication rooms. However, it is reported that one no.air conditioner at 220KV Ratlam is faulty, power supply for air conditioner at 220 KV Indore(SZ) is not available, non-availability of air conditioner at 220 KV Bhopal & 220 KV Betul. MPPTCL & MPPGCL are requested to ensure availability & running condition of Air Conditioner at following wide band nodes already commissioned :-
MPPTCL Substations MPPGCL Substations 220 KV S/s Satna 220 KV S/s Katni 400 KV S/s Bhopal 400 KV S/s Bina 220 KV S/s Jabalpur 220 KV S/s Itarsi 400 KV S/s Indore 220 KV Chhindwara 220 KV Ratlam 220 KV Shivpuri 220 KV Indore (SZ) 220 KV Shujalpur 220 KV Neemuch 220 KV Gwalior 220 KV Bina 400 KV Pithampur 220 KV Barwaha 220 KV Seoni 220 KV Damoh 400 KV Nagda 400 KV Chhegaon 220 KV Bhopal 220 KV Rajgarh 220 KV Malanpur 220 KV Pithampur Indore chambal Indore SubLDC
Birsinghpur TPH Gandhi Sagar HPS Pench HPS
Agenda of 68th OCCM of MP 28
132 KV Pichhore 220 KV Betul
[Action :- MPPTCL, MPPGCL] ITEM NO 10 : DATE AND VENUE OF NEXT OCC MEETING :
As discussed in 66th OCCM & confirmed by entities the schedule & host of upcoming Operation and Coordination Committee meeting of MP is detailed as below:-
S.NO. OCC MEETING
OF MP HOSTING ENTITY
TENTATIVE DATE
1. 69TH MP-OCCM NHDC 26.04.2019 2. 70TH MP-OCCM MPPGCL 28.06.2019 3. 71ST MP-OCCM DISCOM(WZ) 22.08.2019
In view of the above hosting entity of 69th OCCM may confirm the same in the meeting. The venue of the 69th OCC meeting will be intimated later.
[Action :- All the concerned entities]
***********
Agenda of 68th OCCM of MP 29
S. No. Particulars
1
1.1 Maximum Frequency 50.08 HzBetween 06.00 hrs & 07.00 Hrs on 16.12.18
50.1 HzBetween 13.00 hrs & 14.00 Hrs on 14.01.19
1.2 Minimum Frequency 49.79 HzBetween 07.00 hrs & 08.00 Hrs on 21.12.18
49.82 HzBetween 16.00 hrs & 17.00 Hrs on 21.01.19
1.3 Average Frequency 49.97 Hz 49.99 Hz
2
2.1 Maximum Frequency 50.25 HzAT 06.01.40 HRS ON 02.12.18
50.28 Hz AT 02.01:20 HRS ON 22.01.19
2.2 Minimum Frequency 49.67 HzAT 09.17:30 HRS ON 16.12.18
49.58 Hz AT 07.32:20. HRS ON 04.01.19
3 Percentage of time when frequency was :-
%age of time when frequency was Dec-18 Jan-19
3.1 Below 48.5 Hz 0.00 0
3.2 Between 48.50 Hz and 48.8 Hz 0.00 0
3.3 Between 48.80 Hz and 49.2 Hz 0.00 0
3.4 Between 49.20 Hz and 49.5 Hz 0.00 0
3.5 Between 49.50 Hz and 49.7 Hz 0.00 0
3.6 Between 49.70 Hz and 49.9 Hz 12.68 10.69
3.7 Between 49.9 Hz and 50.05 Hz 77.03 70.26
3.8 Between 50.05 Hz AND 51.5 Hz 10.29 19.05
3.9 Above 51.5 Hz 0.00 0.00
4 No. of times frquency touched 48.80 Hz 0 0
4.1 No. of times frquency touched 48.60 Hz 0 0
4.2 No. of times frquency touched 51.0 Hz 0 0
FREQUENCY PARTICULARS
INTEGRATED OVER AN-HOUR
INSTANTANEOUS FREQUENCY
Dec-18 Jan-19
Agenda of 68th OCCM of MP 30
I S.
No. NAME OF THE TRANSMISSION LINE / (FINANCED BY)
TYPE OF CIR CUITS
ROUTE LENGTH CIRCUIT
KMS.
MONTH OF COMPLETION
DATE OF COMMI-SSIONING
A. 400 KV TRANSMISSION LINES
NIL 0 0
B. 220 KV TRANSMISSION LINES
1LILO of both ckt of Badod-Kota/Modak 220kV line at 220Kv S/s Suwasara (ADB-III Saving)
DCDS 4.382 17.528 June'2018 28.06.2018
2220Kv DCDS Morena(400KV S/s CWRTL Adani Group) - Sabalgarh DCDS line with lilo of one ckt of line at Morena 220Kv s/s (ADB-III Saving)
DCDS 69.64 139.28 Aug'2018 19.08.2018
3220kV DCDS Khandwa(400 PGCIL) - Chhanera line(2x39.217) ADB-III (S)
DCDS 39.217 78.434 Oct'2018 30.10.2018
4LILO of both Ckt of Indore-II (jaitpura) - Ujjain 220kV line at Indore (PGCIL) 765 kV S/S (4x6.026) (UBI)
DCDS 6.03 24.104 Dec'2018charged on 10.12.2018
5220kV DCDS line from Julwaniya 400kV S/s in Sendhwa 220kV S/s (2x35.341) (GEC)
DCDS 35.34 70.682 Dec'2018
charged on 10.12.2018 (Ckt-I) & 25.12.2018 (2nd
ckt)
C. 132 KV TRANSMISSION LINES
1132Kv DCDS 2 phase 4wire line from 220Kv s/s Ashoknagar for PS to 132kV RTS Ashoknagar (2x4.726)
DCDS 4.726 9.452 April'2018 11.04.2018
2
132kV DCSS line from 132kV Balwada - water pumping station No.2 of NVDA at village Mukhtyara (1x2.421) (Contribution Supervision Work)
DCSS 2.421 2.421 May'2018 05.05.2018
3132 kv DCDS Line Chichli - Udaypura (On 220Kv Tower) (ADB-III)
DCDS 46.860 93.720 June'2018 04.06.2018
4LILO of one ckt of Vidisha - Gairatganj line at 132kV Raisen(2x18.221) (ADB-III Saving)
DCDS 18.266 36.532 June'2018 06.06.2018
5LILO of both ckt. Of 132 kV Balaghat - Bhanegaon line at Balaghat/Kirnapur 400kV S/s.(2x0.774 + 4x1.216) (ADB-III)
DCDS 1.990 6.412 June'2018 13.06.2018
6132kV MACT (Bhopal) - Mugaliachhap line (4x20.2 + 2x10.536)
DCDS 30.736 101.872 June'201814.06.2018 (ckt-I) 22.06.2018 (ckt-II)
7132 kv DCSS Dewas-Agrod line (1x20.76) (ADB-III)
DCSS 21.600 21.600 June'2018 27.06.2018
82nd ckt of 132kV Maihar - Amarpatan 132kV line (GEC)
2nd ckt 26.000 26.000 June'2018 28.06.2018
9132kv DCSS Mugaliyachhap - Bilkishganj line (1x17.274) (ADB-III Saving)
DCSS 17.200 35.800 June'2018 28.06.2018
10132Kv DCSS line from 400Kv s/s Katni - RTS Patwara (1x19.417) (CCW)
DCSS 19.414 19.414 June'2018 29.06.2018
11132kv Mugaliya Chaap - Sehore DCSS line (1x19.914 +2x1.140) (JICA)
DCSS 21.054 22.194 July'2018 20.07.2018
12132 kv DCSS Dewas-Barotha line (1x17.428) (JICA)
DCSS 17.428 17.428 July'2018 25.07.2018
13LILO of one ckt of 132kv Neemuch - Mandsore line at Budha 132KV Sub-station (2x21.503) (ADB-saving)
DCDS 43.006 43.006 July'2018 17.07.2018
14LILO of both ckt of 132kv Gandhisagar - Suwasara/Garoth line at Suwasara 220KV S/s (4x1.423) (ADB-saving)
DCDS 1.423 5.692 July'2018 30.06.2018
15132kv DCDS Rajgarh - Khujner/Sindaota line (2x26.499+ 2x1.457) (ADB-saving)
DCDS 27.956 29.413 July'20181x26.499
30.07.2018
16132kv DCSS line Chhindwara-Saori line (1x31.23) (ADB-saving)
DCSS 31.23 31.23 July'2018 31.07.2018
ANNEXURE-2.2.5.i
M.P POWER TRANSMISSION COMPANY LIMITED
TRANSMISSION WORKS COMPLETED DURING 2018-19 (UP TO 31.01.2019)EHV TRANSMISSION LINES
Agenda of 68th OCCM of MP 31
17132Kv DCSS 2 phase 2wire line from 132Kv s/s Shahpura(JBP) for 5MVA PS to RTS Bhitoni (1x5.968) (Contrib)
DCSS 5.968 5.968 July'2018 06.07.2018
18132Kv DCSS line PS III &IV for NVDA at Simrol (1x8.031) (Contrib only supervision)
DCSS 8.031 8.031 July'2018 19.07.2018%
19132Kv DCSS 2 phase 2wire line from 220Kv s/s Maihar for PS to TSS Bhadanpur(1x13.06) (CCW)
DCSS 13.06 13.06 Oct'2018charged on 25.10.2018
20132 kv DCSS Badnagar - Chhayan Line (1x31) ADB-III
DCSS 20.969 20.969 Nov'2018
Part line 20.969 CktKm charged on
05.11.2018 by tapping
arrangement
21LILO of 132Kv Bhopal(220kV) - Bairagarh line at 132kV S/s Badwai (IT Park) (2x0.513) (CCW)
DCDS 1.026 1.026 Nov'2018charged on 30.11.2018
22132Kv DCDS line from 132Kv s/s Morwa for Power supply of 21.6MVA in phase manner on 132kV for RTS Singroli (1x1.809) (CCW)
DCDS 1.052 1.052 Nov'2018
1.052 CktKm charged upto
dead end tower 30.11