M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
Report to the LCLS Facilities Advisory Committee
•Project Management Status–Cost and Schedule Performance–Funding, Obligations & Costs–Milestones & Critical Path–Procurement Status
•Risks & Mitigations•Summary
Mark Reichanadter
LCLS Deputy Director
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
2
Review DocumentationLCLS Project Review information:
http://www-ssrl.slac.stanford.edu/lcls/fac/2008-november/index.htmlBack-up documentation
Responses to June 2008 FAC RecommendationsSeptember 2008 Monthly ReportCurrent LCLS Risk Registry
Thumb-drives available
Questions? Contact:Helen O’Donnell X3368, [email protected] Mitchell X5377, [email protected]
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
3
LCLS OverviewFocus is on three primary issues
Safety – Construction and installationConstruction nearly complete (Turner 98%)Installation safety management good so far.
Endgame project planningProject 85% Complete, Line Item 88%Performance good so far, ~ on scheduleCost/Schedule contingency adequateAny upscopes need to be defined now.
Transition into Operations/ScienceMature commissioning plans. Ops is next.
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
4
Project StatusLCLS performance is on track with baseline
TPC = $420M (TEC = $352M, OPC = $68M)CD-4 = July 31, 2010TPC >84% Complete, TEC >88% CompleteContingency on TEC = $17.7M
43% on remaining work
Management Reserve on OPC = $8.9M43% on remaining work
LCLS received its full request under a CRTEC first five months FY09 funding + $5MOPC first five months FY09 funding
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
Project Performance
5
1.1 Project Management 20,251 88.7% 22,822
1.2 Injector 20,239 100.0% 20,239
1.3 Linac 27,274 96.5% 28,257
1.4 Undulator 44,994 97.7% 46,065
1.5 X-ray Transport 22,372 79.5% 28,134
1.6 X-ray Endstations 3,407 35.9% 9,482
1.9 Conventional Facilities 121,374 88.0% 137,915
1.X Controls 33,382 80.7% 41,362
1 LCLS Total Base Cost 293,293 87.7% 334,277
352,000
17,723
43.2%
2 LCLS Other Project Cost 38,689 65.4% 59,123
68,000
8,877
43.4%
LCLS Total Project Cost (TPC) 331,982 84.4% 420,000
% CompleteWork
Accomplished
% Contingency on ETC
LCLS Total Other Project Costs (OPC)
Available Mgmt Reserve
% Mgmt Reserve on ETC
Total Budget at Completion
LCLS Baseline Performance - September 2008 (AYK$)
WBS
LCLS Total Estimated Cost (TEC)
Available Contingency
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
6
Project Performance (Sep08)TPC
BCWS $336.4MBCWP $332.0MACWP $330.9MObligations (cum) $337.6M
TEC (Line Item)Est at Complete (EAC) $338.1M
Includes variances and Pending BCRsIncludes upscopes for SXR Integr/Install and Hutch #6
EAC Cost to go contingency 30.7%Remaining Work (ETC) $ 45.3M
~$3M is under contract
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
7
Earned Value Indices
Rebaseline to address FY07 CR approved in Jan08.CPI & SPI performance steady
0.5
0.6
0.7
0.8
0.9
1.0
1.1
1.2
1.3
1.4
1.5
LCLS Cost and Schedule Indices (TEC Only)
BCWP/BCWS (SPI)
BCWP/ACWP (CPI)
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
8
Cost and Schedule Variances
SV due to delays in (Turner) construction and installation-related activitiesRecently improved, expected to continue
LCLS TEC Cost and Schedule Variances
(8,000)
(7,000)
(6,000)
(5,000)
(4,000)
(3,000)
(2,000)
(1,000)
0
1,000
Jan-08
Apr-08
Jul-08
AY
K$
SV
CV
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
9
TEC (Line Item) Performance
0
50000
100000
150000
200000
250000
300000
350000
400000
(AY
$K
)
BCWS
BCWP
ACWP
BA
OBL
~$1.8M carry-forward
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
10
DOE (Level 2) Milestone PerformanceLCLS DOE (Level 2) Milestones Baseline Date Actual VarianceDelivery of Undulator 1st Articles to MMF 3-Jul-06 15-Jun-06 -12 daysSector 20/Alcove Beneficial Occupancy 21-Jul-06 14-Apr-06 -70 daysMMF Qualified & Ready to Measure Prod Undulators 28-Aug-06 28-Aug-06 0 daysStart Injector Commissioning (Drive Laser) 29-Jan-07 15-Dec-06 -22 daysInjector Accelerator Readiness Review (ARR) Comp 31-Jan-07 30-Mar-07 42 daysStart Injector Commissioning(UV Beam to Cathode) 9-Apr-07 5-Apr-07 -2 daysLinac Water/Power Available 11-Jul-07 29-Mar-07 -74 daysLinac (Li20-Li30) Ready for Commissioning 1-Dec-07 1-Dec-07 0 daysStart Installation of Undulator Facility 16-May-08 14-Aug-08 64 daysBTH-UN-FEE-NEH-CUP Beneficial Occupancy 21-Jul-08 14-Aug-08 18 daysLinac (Li20-Li30) Commissioning Complete 30-Jul-08 2-Apr-08 -86 daysSafety Analysis Document (SAD) Approved 29-Aug-08 23-Sep-08 17 daysXT-FEH Beneficial Occupancy 22-Oct-08 17-Nov-08 (P) 18 days (P)XT Start FEE Installation 13-Jan-09 On ScheduleLCLS ARR Complete (BTH thru NEH) 17-Apr-09 EarlyStart Linac-to-Undulator (LTU) Commissioning 20-Apr-09 EarlyXT Start Tunnel Installation 27-May-09 On ScheduleStart Undulator Commissioning (1st Light) 6-Jul-09 On Schedule2-D Detector Shipped to SLAC 30-Jul-09 On ScheduleStart FEE Commissioning with Beam 6-Aug-09 On ScheduleFirst X-Rays into NEH - Initiate Early Ops 10-Sep-09 On ScheduleXE Start Installation in FEH 17-Sep-09 On ScheduleFirst X-Rays into FEH 26-Feb-10 On Schedule
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
11
ScheduleCritical Path (CP) to CD-4
Undulator/FEE C.O. – install – FEL commission – Photons in FEH = ~108 working days
Soft X-ray Mirror System = 109 daysXE TUN/FEH PPS Shielding & Supports = 111 daysPop-Up Camera System = 113 days AMO readiness is tight for early science but not CD-4
Space Renovation B.O. = ~83 daysRenovation of existing space has low technical risk
Evaluating options to enhance the science program
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
12
Procurement StatusProcurement and technical teams co-located
1 Manager, 1 Buyer (technical components)1 Contract Administrator (A/E, CM/GC contracts)1 Construction Buyer (Davis-Bacon contracts)
Administer field changes and submittals
1 P/T Consultant (price and change negotiations)Weekly technical/procurement staff meetings
Advance procurements monitored via APP’s
LCLS <$10M procurement remain.~$4.5M Space Renovation. ~$3-4M FEH Hutches.
LUSI procurements will use same processes.SSO approval still required for >$500K.
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
13
Project Risks & Mitigating ActionsSafety – Construction and Installation
Fully staffed in ES&H, construction safety and oversight (UTR’s)Increased inspections, SLAC-enforced procedures, daily tool box meetingsHands-on safety management by LCLS, SLAC & DOERecent performance improved, watch for complacency
Cost / Contingency Analysis (End Game) Nov08 – Bottoms-up ETC on remaining workMonthly Estimate at Complete (EAC) analysis
Construction claim set asideLooking at scope buy-backs to optimize science program
CR – Does not appear to adversely impact on LCLS
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
14
TEC Remaining Work
PM1% 0%
LN0%
UN0%
XTOD2%
XES2%
CF5%
CT2%
88% Work Complete
LCLS TEC Remaining Work (AYM$)
End Game PlanningRemaining costs still dominated by CF
Hutches, Space RenovationPotential Claims
Photon SystemsOther Project Costs
Re-estimate remaining costsUpdate schedule logicResource ratesContingency estimatesUpscopes to enhance science
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
15
Project Risks & Mitigating ActionsTransition from project to a science/user facility
Reorganize LCLS DirectorateAccelerator System Division
Transition from PPA Directorate to LCLS Experimental Facilities Division
Manage photon operations, User administration, outreachNew Directorate – need to staff up.
Strategic Projects DivisionLCLS/LUSI projects (focus is project delivery)
Engineering and Physics DivisionCentralize technical staff for customer support (XFD, SPD, ASD)Common standards and configuration controlStarted to document LCLS “lessons learned’
Business Office Centralize business systems for ops and project managementScope-driven WBS for LCLS (to be SLAC-wide)
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
LCLS Directorate OrganizationLCLS Directorate
Define and deliver the transformational potential of Ultrafast photon science through efficient
and effective operation of the Linac Coherent Light Source as a BES User facility
Business Office
Deliver the enabling Infrastructure necessary for efficient operation
of LCLS
Accelerator Systems Division
Deliver the LCLS quality beam in a sustainable and efficient manner that meets the
needs of the user program
Engineering Physics Division
Deliver the approach, resources, and standards, to optimize the configuration of LCLS in a reliable,
available, and maintainable manner
Experimental Facilities Division
Deliver the instrument systems and user administration activities necessary for efficient
performance of a user based research program
Strategic Projects Division
Deliver the planning and implementation of next generation upgrades and major
modifications of LCLS
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
17
SummaryOverall, LCLS making steady progress
Construction (Turner) phase near completionCost and schedule performance good so farContingencies adequate to address project risks
Bottoms-up ETC for remaining work, add in any final upscopesRegular EAC and contingency calculations to manage endgame
Challenges ahead:Safety management of (Turner) construction and installation activitiesOptimize LCLS science with endgame of TEC and OPCTransition of LCLS into science and operations.
M. Reichanadter
LCLS Project Management [email protected]
11-13 November 2008 FAC Meeting
Slac National Accelerator Laboratory
18