1 Customer Name: Living Brick Ltd Project Name Chavasse Building - Lydia Ann Street Progress Report Date: 02/02/19 Contract No: 12 Scheduled Project Handover date: 22/03/19 Progress Meeting Venue: Crossfield Site Offices Lydia Ann Programmed Duration: 69 weeks Current week no: 62 Are Works Either Ahead of Programme On Target In Delay Site Manager: John Farrell SM Dave Guy PM BRIEF PROJECT OVERVIEW: To erect a 6 storey residential block consisting of 47 No Units, 20 x studios, 18 x 1 bed and 9x 2 bed apartments. With 11 No car parking spaces, associated facilities and two ground floor commercial units. Progress Report

Lydia Ann Street - Client Progress Report 06.04 · External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Lydia Ann Street - Client Progress Report 06.04 · External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

1

Customer Name: Living Brick Ltd

Project Name Chavasse Building -

Lydia Ann Street

Progress Report Date: 02/02/19

Contract No: 12 Scheduled Project

Handover date:

22/03/19

Progress Meeting

Venue:

Crossfield Site Offices –

Lydia Ann

Programmed Duration: 69 weeks

Current week no: 62

Are Works Either Ahead of Programme On Target In Delay

Site Manager: John Farrell SM

Dave Guy PM

BRIEF PROJECT OVERVIEW:

To erect a 6 storey residential block consisting of 47 No Units, 20 x studios, 18 x 1 bed and 9x 2

bed apartments. With 11 No car parking spaces, associated facilities and two ground floor

commercial units.

Progress Report

Page 2: Lydia Ann Street - Client Progress Report 06.04 · External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

2

Chavasse Building – Lydia Ann Street

Contractors Report

Report for Weeks: 54-62 Report for period ending: 2nd Feb 2019

1.0 Executive Summary

The project is currently in week 62. This report takes account of progress for weeks 54-62.

Weeks 54-62

Mac Roofing coping to top deck.

Mac Roofing 5th floor quadcore cladding 40% complete.

Window pressings.

M&E 1st fix 85% complete.

M&E 1st fix works in progress to communal areas.

Joinery 1st fix works in progress.

Super structure brick work complete.

External mastic to moving joints 45% complete

Sub mains and distribution 80% complete.

1st floor apartments tape and joint in progress.

2nd floor closing up of apartments & tape and joint in progress.

Brick clean ongoing to all elevations.

Mist coat paint

Page 3: Lydia Ann Street - Client Progress Report 06.04 · External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

3

1.1 On Site Progress Weeks 54-62 Mac Roofing commenced parapet coping works to 5th floor top deck currently 70% complete. Rear elevation complete in line with scaffold dismantle. Lower level parapet timber is now in place ready for finishing detail. Mac Roofing commenced installation of quadcore to 5th floor in preparation for powder coated rainscreen cladding 40% complete. External window/doors now complete from floors 1 – 5 LDG are now installing powder coated window reveal pressing to rear elevation 80% complete. These windows are now ready for Juliet balcony’s to be installed starting Monday 4th Feb. Mechanical and electrical first fix installation on the 1st-4th floor 100% complete. Electrical first fix to all communal areas in progress and stat service riser cupboards with incoming mains.

Joinery 1st fix now in progress 100% complete 1st – 4th floor to Apt entrance and internal rooms along with all timber pattress. External and internal brick and blockwork is now 100% complete excluding hoist apartment. External mastic works is in progress to all movement joints 45% complete. Tape and jointing to the 1st floor apartments is now 100% complete and now in progress on the 2nd floor. Mist coat spray application 60% complete to 1st floor apartments. External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

1st floor:- Apts 1st & 2nd fix100% 2nd floor:- Apts 1st fix 100% ,2nd fix 60% 3rd floor:- Apts 1st fix 100% , 2nd fix 25% 4th floor:- Apts 1st fix 90%. 5th floor:- in progress with sacrificial ceiling

Page 4: Lydia Ann Street - Client Progress Report 06.04 · External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

4

1.2 Off Site Progress Planning & Building Control trackers under review and updated as conditions

discharged. Matter ongoing.

Mains electrical connection date confirmed as Wednesday 13th February.

A strategy is ongoing to condense the current programme in order to recover any lost time due to inclement weather & design challenges.

Building Control have ongoing visits as closing of apartments continues.

278 works design issued to LCC awaiting approval.

Water main inspection booked in to follow electrical connection.

1.3 Procurement Orders placed to date:-

Bora Construction – Groundworks Leach – Structural Steel Metaldeck and Concrete – Raised Floor Solutions Windows and Doors – Lancashire Double Glazing Passenger Lift – Knowsley Lift Services Utilities – Matrix Networks M&E—CP Hood Brickwork - Cara Intumescent paint – Zeras Scaffold – Kirk SfS/Dryliners – Preston Dryliners Roofing--MAC Roofing Tarmac:- Multi Pave NW Ltd Joinery:- Taurus Windposts:- The Steel Workshop Kitchens:- Ocean Kitchens Glass Balustrade – RJ Edwards Juliet Balcony – The Steel Workshop Roller Shutter – National Roller Shutters UK Mastic works – Nationwide sealants Painting & decorating – Prodec

1.4 On Site Progress for

coming weeks

Quadcore and rainscreen cladding to 5th floor .

5th floor terrace built up roof works

Juliet balcony installation

Scaffold dismantlement

Passenger lift installation

Kitchen installation

2nd fix joinery work

Sanitaryware installation

Tiling

Painting

1.5 Matters likely to affect

programme

1.6 Estimated Completion

Date

22/3/19

1.7 Have Crossfield

Construction carried out any

additional works other than

contract works this Month?

Accelerated labor on site

Extended working hours

Weekend work

Page 5: Lydia Ann Street - Client Progress Report 06.04 · External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

5

1.8 Health & Safety Issues

None to date. All operatives inducted all works as per method statements & risk

assessments.

1no. fire drill taken place and site was evacuated successfully.

Page 6: Lydia Ann Street - Client Progress Report 06.04 · External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

5

Progress Photos

Page 7: Lydia Ann Street - Client Progress Report 06.04 · External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

6

Page 8: Lydia Ann Street - Client Progress Report 06.04 · External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

7

Page 9: Lydia Ann Street - Client Progress Report 06.04 · External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

8

Page 10: Lydia Ann Street - Client Progress Report 06.04 · External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

9

Page 11: Lydia Ann Street - Client Progress Report 06.04 · External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

1

0

Page 12: Lydia Ann Street - Client Progress Report 06.04 · External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

1

1

Page 13: Lydia Ann Street - Client Progress Report 06.04 · External brick clean in progress to all elevations in line with progressive scaffold dismantle. PDL partitions progress as follows

1

2

Details of Next Scheduled Meeting

KD/PW

Issued By:

Dave Guy - Project Manager John Farrell – Site Manager