Upload
satishgoel
View
24
Download
1
Tags:
Embed Size (px)
DESCRIPTION
A small report of LUHRI hydro power project
Citation preview
LUHRI H.E.PROJECT (3X155=465MW) HIMACHAL PRADESH
1. INTRODUCTION Luhri Hydroelectric Project located in Shimla district of Himachal Pradesh
envisages utilization of waters of the river Satluj for power generation on a run
of the river type development, harnessing a head of about 127 m.
The project with a proposed installation of 465MW (3x155MW) would afford
an annual energy generation of 2037.15 MU in a 90% dependable year. The
tariff from the project at present day cost would be Rs 1.66.
The diversion site is located at Latitude 30 15' North, Longitude 77 15' East.
The dam site is about 80 km from Shimla, the state capital.The nearest rail
head and airport are located at Shimla.
2. SCOPE OF WORKS The Luhri H.E.Project envisages construction of
A 60m high(above river bed) straight gravity type concrete dam
across river Satluj to divert 596 cumecs of discharge;
Four numbers desilting chambers of length 580m(L) and size
14m(W) x25m (H) to remove silt particles of size 0.25mm and
above;
A 15.50 km long and 10.50m diameter head race tunnel terminating
in a surge shaft;
A 147 m high 37 m diameter open to sky surge shaft;
Three no's 220m long, 5.55m diameter pressure shaft;
an underground powerhouse having an installation of 3 Francis
driven generating unites of 155MW each operating under a net
head of 108m.
100m long and 10.50 m diameter tail race tunnel to carry the power
house releases back to the river;
It is proposed to evacuate the power generated at Luhri Project by
Looping in Looping out of 400 kV Jhakari-Hissar D/C line with
TRIPPLE SNOWBIRD conductor at Luhri. As per recommendations
made by PGCIL in their report on master plan for evacuation of power
from various projects located in Satluj basin, this line is proposed to
be LILOed at Rampur.
The Salient features of the project are given at Annex-I and a layout map at Plate I.
3. HYDROLOGY
The catchment area of river Satluj at the proposed dam site is about 52403
sq. km. The water availability for the project has been considered on the basis
of 10-daily discharge series at Suni and Rampur. The long term series at
Luhri dam site has been developed on proportionate catchment area basis
from these two sites. The computed series has been utilized for Power
Potential Studies. The design flood has been assessed as 6579 cumecs.
4. POWER POTENTIAL STUDIES
The computed inflow series for 31 years viz 1972 to 2003 has been
considered in the assessment of a power benefits from the project. As per
GOI notification for tariff the year 1997-98 corresponds to 90% dependable
year. An installation of 465 MW comprising 3-generation units of 155 MW has
been proposed. The energy availability from the project in a dependable and
an average year has been summarized below:
Particulars Dependable year
Annual Energy Generation
Annual Energy Generation (GWh) 2037.15
Annual Load Factor (%) 64%
Generation during Lean Flow Season (Dec.-Feb.)
Energy Output (GWh) 208.64
Load Factor (%) 24.15
The design energy for tariff at 95% availability in a 90% dependable year has
been worked out at 2037.15 GWh.
A pondage of 67.80 mcm has been provided in the diversion dam which
would enable the station to operate as peaking station.
5. POWER EVACUATION ASPECTS
It is proposed to evacuate the power generated at Luhri Project by Looping in
Looping out of 400 kV Jhakari-Hissar D/C line with TRIPPLE SNOWBIRD
conductor at Luhri. As per recommendations made by PGCIL in their report
on master plan for evacuation of power from various projects located in
Satluj basin, this line is proposed to be LILOed at Rampur.
6. ENVIRONMENTAL ASPECTS The project is located in middle area of upper Satluj valley. Most of the land
falls under the category of forest land. Based on assessment of
environmental impacts, management plans have to be formulated for
Catchment Area Treatment, compensatory afforestation and other
environmental issues. These issues would be addressed during the
investigation for DPR.
7. ESTIMATE OF THE COST The project is estimated to cost Rs. 1930.84 crores including IDC at January
2004 price levels. The preliminary cost estimate of the project has been
prepared as per guidelines of CEA/CWC. The break down of the cost
estimates is given below:
Civil works : Rs. 1139.67 Crores
Electro Mechanical works : Rs. 461.73 Crores
Sub total (Generation) : Rs. 1601.40 Crores
Transmission works : Rs. 10.86 Crores
Total (Hard Cost) : Rs. 1612.26 Crores
Interest During Construction : Rs. 318.58 Crores
Grand Total : Rs. 1930.84 Crores
8. FINANCIAL ASPECTS
As indicated above, the Luhri Hydro-electric project with an estimated cost of
Rs. 1930.84 crores (including IDC of Rs. 318.58 crores) and design energy of
2037.15 GWh in a 90% dependable year is proposed to be completed in a
period of 6 years. The tariff has been worked out considering a debt-equity
ratio of 70:30, 16% return on equity, annual interest rate on loan at 10% and
12% of energy as Free power to Home State available after losses. The tariff
for first year and levellised tariff works out Rs. 2.10 /kWh & Rs. 1.66 /kWh
respectively.
9. CONCLUSIONS Luhri hydroelectric project involves simple civil works and could be completed
in 6 years. The project would afford design energy of 2037.15 GWh in a 90%
dependable year. The cost per MW installed works out Rs. 3.92 crores. The
Preliminary Feasibility Report indicates that the scheme merits consideration
for taking up for Survey & Investigation and preparation of DPR.
LUHRI HEP(465 MW)
I
SALIENT FEATURES OF THE PROJECT LOCATION State Himachal Pradesh District Shimla River Satluj Vicinity Diversion dam site near Village Nathan & Power House site near Village Chaba about 80 km from
Shimla (HP). Geographical co-ordinates 7715- 7730 3015-3125 SOI Toposheets 52E/7 HYDROLOGY Catchment area at diversion site. 52403 Sq km Average runoff in 90 % dependable year 9548 MM Average runoff in 50 % mean year 121131 MM DIVERSION DAM Type Concrete Gravity Full reservoir level El 770.00 m. Maximum pond level El 773.00 m. M D D L El 728.00 m River Bed Level at Dam site El. 709.80m.
LUHRI HEP(465 MW)
II
SEDIMENTATION CHAMBERS No. of sedimentation chambers 5 Width 16m. Depth 35.5m. Length 705 m. Particle size to be arrested +0.25 mm. Design discharge 586.00 cumecs. Flow through velocity 0.3 m/s HEAD RACE TUNNEL Type Horse shoe, concrete lined Diameter 11 m finished. Length 15500 m. Design discharge 586 cumecs. SURGE SHAFT No. One Type Restricted Orifice ( Underground ) Diameter 52.00 m
LUHRI HEP(465 MW)
III
Orifice Dia. 5.54 m PRESSURE SHAFTS No. 3 Type Circular steel lined (Underground) Diameter 6.35 m ( Finished ) Length 220.00 m each Steel Liner Type ASTM 537 Thickness Varies from 15 to 35 mm POWER HOUSE / TRANSFORMER HALL CAVITY Type Underground Installed capacity 465 MW(3 x 155 MW) Size of machine hall 123m (L) X 21m (W) x 51m(H) Size of transformer hall 78m (L) X 16m (W) x 25m(H) Gross head 128.00m Net head at 586 cumecs tunnel 88.00 m discharge
LUHRI HEP(465 MW)
IV
ELECTRO- MECHANICAL EQUIPMENT TURBINES No. and type 3 nos., Francis turbines Design head 88.00 m Design discharge 195.33 cumecs TAIL RACE TUNNEL Size & Type 11.00 m dia. Horse shoe shape Length 150 m POWER GENERATION Installed capacity 465 MW Annual generation -90% dependable year 1825.13 GWH -50% dependable year 2060.50 GWH COST ESTIMATE ( Rs in crores) Civil Works 1235.70 E-M Works 461.73 Transmission 10.86 Total base cost of Project (January 2004 price level) Rs.1708.29 Crores
LUHRI HEP(465 MW)
V
FINANCIAL ASPECTS Cost per MW of installed capacity Rs. 3.49 Crores Sale rate per unit (at bus bar) 90 % dependable year
First year Rs. 2.41 per unit Tenth year Rs. 1.80 per unit Levellised tariff for 35 years Rs 1.89 per unit
( 12 % discount rate)
LUHRI HEP (465 MW)
I.1
CHAPTER-I
SUMMARY
1.1 GENERAL PROJECT FEATURES
1.1.1 GENERAL
Luhri Hydroelectric Project located in Shimla district of Himachal
Pradesh, is a run-of- the river type development proposed to harness
the hydel potential of river Satluj between Luhri and Chaba villages.
The project envisages construction of a 60m high (above river bed)
concrete gravity dam on the river Satluj near village Nathan for
diversion of a design discharge of 586 cumecs, through four intakes
and underground desilting arrangement into a 15.50 km long, 11.00m
finished diameter head race tunnel on the right bank of Satluj river. The
tunnel terminates in a 52 m diameter open to sky surge tank. The
water from surge tank shall be further conveyed through three no's,
each 6.35 m diameter, 220 long steel penstock to three generating
units in an underground power house at Chaba. A gross head of 128 m
is available at the power station, which shall be utilized to generate 465
MW (3x155MW) of power.
1.2 MAIN COMPONENTS OF THE PROJECT 1.2.1 River diversion works
For the construction of the dam and appurtenant works, the river
diversion is proposed to be done through a diversion tunnel, located on
the left bank of river, capable of carrying non-monsoon flood of 1267
cumecs. Partly constructed works of the concrete dam on the left bank
and in the river portion shall be allowed to be over topped during
monsoon period.
LUHRI HEP (465 MW)
I.2
Coffer dams shall be constructed up-stream and down-stream of the
dam axis near the inlet & outlet portals of the diversion tunnel every
year after the monsoons.
1.2.2 Diversion dam It is proposed to construct a straight gravity type concrete dam, 60 high
(above river bed) near Nathan Village to divert 586 cumecs of
discharge.
The full reservoir level and the minimum draw-down level will be at El
770 m and 728 m respectively. The diurnal pondage afforded by the
dam would be 12.45 MM3 . The water spread of the reservoir does not
involve any rehabilitation problem, as the area submerged is barren
land without any habitation.
1.2.3 Intake Structure The intake structure comprising five intakes, proposed on the right
bank of river shall be designed to handle a discharge of 733 cumecs.
1.2.4 Desilting arrangement
An underground desilting arrangement has been proposed on the right
bank of river to exclude silt particles down to 0.25 mm size from the
water before it enters the head race tunnel. The arrangement
comprises five parallel compartments each consisting of chambers
705 m long, 35.50 m high (including 7.50 m hopper portion) and 16 m
wide.
LUHRI HEP (465 MW)
I.3
1.2.5. Head race tunnel
The head race tunnel, from the junction point at link tunnels from
desilting chambers to the main surge tank, is 15.50 km. long and 11 m
diameter horse shoe in section. The tunnel diameter is based on
techno-economic studies for a discharge of 586 cumecs with a flow
velocity of 5.81 m/sec.
1.2.6 Main surge tank
The main surge tank, located at the intake of the penstock at 15.50 km
from the 0 RD of head race tunnel, will be 52 m dia and 147.00 m high
with a restricted orifice and two horizontal expansion galleries 10 m D-
shaped and 150 m long each. A 6.50 m D-shaped adit is proposed at
El 670.00 m to approach the bottom of the surge tank to facilitate
construction. The upper expansion gallery shall be approached for
construction through a 6.50 m D-shaped adit.
1.2.7 Pressure shaft tunnels
Three penstock tunnels, each 220 m long and 6.35 m dia would take
off from the surge tank at an angle of approximately 90 to the
horizontal. These would be lined with high tensile steel corresponding
to ASTM-A-537 varying in thickness from 15mm near the penstock
intake to 35mm at the power house end. Each penstock will feed one
of the three generating units. A spherical valve has been provided in
each penstock branch to enable closing of penstock penstock
whenever required.
LUHRI HEP (465 MW)
I.4
1.2.8 Power house An underground power house of internal dimensions 123 m x 21 m and
51 m high would be located about 130m below the natural surface
level. The power house will have an arched roof with concrete lining
and shall house three generating units, each of 165 MW capacity. The
transformer and underground switch yard (78 m x 16 m x 25 m) are
located downstream of the power house cavern. Shotcrete and rock
bolting at suitable spacing will be provided in these caverns.
Two utility tunnels taking off from the tail race tunnel shall be provided
to approach the bottom portion of the power house and shall facilitates
the excavation of the machine hall, transformer gallery and tail race
surge chamber. To approach the top of the machine hall as also the
top of transformer gallery and tail race surge chamber, an adit is
proposed to be constructed with its portal at EL. 668 m. This adit
shall be used for construction of arch portion and other works from the
top.
1.2.9 Tail race tunnel
The tail race tunnel with 11 m horse shoe section, 150 m long will be
provided to carry the discharge from four draft tube tunnels emanating
from the power house.
1.3 STUDIES UNDERTAKEN
1.3.1 Various alternatives
Four potential diversion sites have been identified, namely Luhri-I,
Luhri-II and Dam site-III & IV. Generally good conditions exist for dam
construction at Nathan dam site, which may be considered as a good
site for a concrete gravity dam. The rock mass is composed of strong
LUHRI HEP (465 MW)
I.5
to very long quartz phyllite, with relatively poorly developed cleavage.
Continuous, horizontal structures are apparent on the south side of the
river, with essentially massive quartzite interrupted by widely spaced
planes, which are assumed to be tight cleavage planes. In addition,
near vertical joint surfaces were observed to cross the river valley
obliquely. These usually display a steep dip in the upstream direction
and produce a blocky structure in the valley slopes. The rock may be
suitable for use in the production of aggregates for concrete purposes.
1.3.2 Hydrological Studies (a) Hydrology: - Collection of Hydro meteorological data
i) Discharge data of Satluj river at Rampur ii) Discharge data of Satluj at Suni iii) Discharge data of Satluj at Kasol
(b) Water availability studies
i) Computation of 90% availability and 50% availability discharges.
ii) Flow duration curve iii) Power generation in a 90 % and 50 % dependable years
(c) Flood studies
i) Flood frequency analysis for Monsoon flood ii) Flood frequency analysis for Non-monsoon flood.
1.3.3 Initial Environmental studies
i) Digitisation of maps (toposheets) with permission of SOI. ii) Satellite imageries as required from NRSA.
LUHRI HEP (465 MW)
I.6
iii) Processing of satellite data for the area of interest by the
consultant. The procedure adopted for processing will be: - a) Multi-spectral LISS(23.5m resolution) and Single Band PAN(
5.8 m resolution) data. b) Land use classification for the area will be carried out after
geo-referencing the satellite data. c) Land use classification consisting of the following
1. Vegetation crown, Cover (Tree canopy) 2. Built up areas? Rocky outcrop etc. 3. Agricultural land (Land on which Agriculture is being
practised currently). 4. Vegetation density classification (Low, medium, high). 5. Water bodies 6. Barren land 7. Any of the peculiar land use category, as per local
scenario. 8. Land use pattern. 9. Vegetal cover/density 10. Approximate population density.
1.4 COST AND FINANCIAL ASPECTS
The estimate of costs has been prepared in detail to arrive at the total cost of the project. The estimates are based on the prices prevailing in January-2004. The detailed estimate of cost of civil works is based on the conceptual layout plan and preliminary designs of different components of the works. The layout of different works have been taken after considering various alternatives and economical layout have been adopted. For carrying out preliminary design, detailed analysis of rates of different items of works have been prepared as per Guidelines of CWC (Guidelines for preparation of project estimate for river valley projects- March 1997). The rates for hydraulic gates, hoists and cranes etc. are
LUHRI HEP (465 MW)
I.7
based on the prevalent market rates for such works. Apart from main civil works, the provisions under various other sub-heads are also based on the Guidelines of CWC. Cost of generating plant and equipment is based on current budgetary prices of plants for similar equipment for other projects Provisions for other items like establishment, audit and accounts etc. are as per norms of CEA. The total cost of the project at January 2004 price level excluding escalation, IDC and Financing Charges works out as under:
Civil Works
1235.70
Crore
Electrical Works
461.73
Crore
Transmission
10.86
Crore
Total
1708.29
Crore
The cost per MW of installed capacity works out to Rs. 3.49 Crore (at January 2004 price level). Thus, the cost per MW for this project is quite low, making the project very attractive.
1.5 RECOMMENDATION
Detailed survey's as per CWC guidelines are to be done before
detailed project report to firm up the various components.
LUHRI HEP (465 MW)
I.8
Detailed geological investigations I,e,drill holes at dam site to confirm
the depth to bed rock, drift at various adits and other geological
investigations as per CWC guide lines.
LUHRI HEP
1
CHAPTER II
BACKGROUND INFORMATION
2.1 GENERAL INFORMATION ABOUT THE RIVER/BASIN/SUB-BASIN
River Satluj rises near Rakas-Tal lake which is fed by lake Mansarover at
about 4570m above mean sea level between Rakas-Tal and Shipkilla,
near the Indian border, the Satluj river takes a North-Westerly course for
a length of about 320 Km in the Tibetan province of Nari-Khorsam. The
Satluj is joined by several tributaries in Nari-khorsam such as Changchu,
Drama Yankti, Chonak, Manglan, Transuo, Summa, Trap etc.
Immediately after entering the Indian territory near Shipkilla, the river
takes a south-westerly direction on its way to Bhakra gorge about 320 Km
away after crossing, which it emerges into the plains of the Punjab. The
Satluj crosses the Great Himalayas at a point where the range bifurcates.
At Rampur, it crosses the Dahuladhar range then traverses through a
series of successive Shivalik ranges and the Naina Devi range, where the
Bhakra dam is situated, is the last of the series. Between Suni and
Dehar, the river takes a somewhat north-westerly direction. After Dehar,
the river turns in a south -westerly direction to reach the foot of Naina
Devi range. The Naina Devi range deflects the river again in a north-
westerly direction when it flows parallel to the range for about 32km
before cutting through it at Bhakra gorge.
The principal tributaries of the Satluj below Shipkilla are the Spiti,
Kashang, Baspa, Bhaba, Nogli, Kurpan, Nauti, Sholding, Sorang, Bharari,
Ali and Ghambar khad.
Numerous glaciers large and small, drain into the Satluj at various points
LUHRI HEP
2
on its course. East of Mansarover and feeding its principal source are the
glaciers of the Ganglug Gaungni, the southern glaciers of the Gauglung
Gangni, glaciers of Kailash flow into the Satluj through the lake of Rakas
Tal, The Northern glaciers of peak Kamer also contribute to the streams.
The glaciers of peak Riwa phargul that stands in the Satluj catchment
also flow into it. There are many Himalayan glaciers draining
into its tributaries. The Baspa and many more from the direction of the
Bara-Lacha pass from the watersheds of the Chenab and Beas.
The fall of Satluj from its source to the plains of India is very uniform. The
height of the bed is about 4570m near Rakas-Tal, 2530m near Shipkilla,
915m at Rampur, 416 m at Bilaspur and 350m at the Bhakra Dam site.
The total catchment area of the Satluj above the Bhakra dam site is about
56875 Sq.km (21960 Sq.miles) and above the Nathpa diversion site is
about 49820 Sq.km (19235 Sq.miles) from Bhakra to Nathpa, 148 Km on
a straight line and 193Km by river, the drainage area is comparatively
narrow with an average width of about 35km. This part of catchment has
an area 7055 Sq.km and above Nathpa the catchment is considerably
wider than below it. The river Satluj drains an area of about 50880 Sq.km
(196745 Sq.miles) at Rampur discharge site.
A gross fall of 2180m is available in the river bed from Shipkilla to Bhakra
in an length of about 320 Km and about 990m from Shipkilla to the
Shongtong Barrage site. The valley is narrow in the portion from Shipkilla
to Pooh and from Thopan to Rampur. In the portion between Pooh to
Thopan and Rampur to Bhakra the valley is comparatively wider. It is
widest in the portion immediately upstream of Bhakra. The bed slope of
river is flat from Shipkilla to Jangi dam site for a distance of about 43 km,
which is of the order of 1 in 175. It becomes steep between Jangi Dam
site and Rampur, the slope being 1 in 87 and is again flatter from
Rampur to Kol Dam site with a slope of 1 in 300. It is the flattest in the
LUHRI HEP
3
Bhakra reservoir area, the portion down stream of the Kol Dam, where
the bed slope is 1 in 500.
2.2 POWER SCENARIO
2.2.1 Sources of energy
India is endowed with a vast hydropower potential. As per the latest
assessment carried out by the CEA, exploitable hydro potential in India
has been estimated at about 84000 MW at 60% load factor, which can
yield an annual power generation of over 440 TWh of electricity and with
additional seasonal energy, the total energy potential is about 600 TWh a
year. Only
14.5% of this potential is under operation and 7.2% of the potential is
under execution. Thus the bulk of the potential amounting to 77.9% is yet
to be developed.
About 73% of India's total installed capacity is thermal-based (Table 3.2).
However expansion of this energy source is encountering difficulties
because of the burden it places on the infrastructure for supply (mines)
and transportation (railways) of coal. Considering that the capacity of
Indian Railways to carry coal effectively is limited and additional tracks
are required, and the coal is of low quality and costly to transport over
long distances, it appears logical to develop thermal projects in specific
areas, e.g. coal-based projects in Bihar, Orissa, Eastern Uttar Pradesh
and surrounding areas, and gas-based power near the port belts of
Gujarat and Maharashtra, and place total emphasis on hydropower in
States such as Himachal Pradesh, Punjab, Haryana, Western Uttar
Pradesh and far-East India - the Himalayan belt.
LUHRI HEP
4
Table 2.2
Share of Hydropower in India's Installed Capacity
Year
Total installed Capacity (MW)
Hydropower
Capacity (MW)
Share of
Hydropower (%)
1962-63
5801
2936
50.6
1969-70
14102
6135
43.5
1979-80
28448
11384
40.0
1989-90
63636
18308
28.8
1991-92
69070
19189
27.8
1993-94
76718
20366
26.6
In the Northern Region, hydropower is the most suitable source of power
since both thermal/nuclear or other fuel-based source of energy involve
carriage of raw material over long distances making the cost of
development uneconomical. There are no thermal-based power projects
in Himachal Pradesh.
2.2.2 Hydropower potential of Himachal Pradesh
Himachal Pradesh along with the States of Jammu & Kashmir and Punjab
form part of the Great Indus Basin. This basin comprises six major rivers,
viz., Indus, Jhelum, Chenab, Ravi, Beas, and the Satluj, and drains a total
area of 1.16 x 106 km2, out of which 0.17 x 106 km2 lies in India. A total of
about 190 hydropower schemes have been identified in the Great Indus
Basin having a firm hydropower potential of 11993 MW at 60% load
factor.
According to the CEA in its publication "Hydro Electric Power Potential of
India", December 1988, in various States and river basins in the country,
the total potential in Himachal Pradesh is 12480 MW at 60% load factor,
with an installed capacity of 20800 MW.
The Satluj basin in Himachal Pradesh has a hydropower potential of 9444
LUHRI HEP
5
MW, which represents approximately 33% of the likely installed capacity
in Himachal Pradesh. Seven schemes in the Satluj are already in
operation with total installed capacity of 3090 MW. The remaining 6354
MW potential is yet to be developed. Two major projects in the basin
namely 1500 MW Nathpa-Jhakri, a joint enterprise between the Central
Government and the Government of Himachal Pradesh, and the 300 MW
Baspa II Project, a privately-financed development sponsored by the
State Government, has recently been commissioned.
Besides Nathpa-Jhakri and Baspa II, the following projects in the Satluj
basin have been identified and form part of the river unexploited potential.
Kol Dam
800 MW
Rampur
400 MW
Karcham-Wangtoo
1000 MW
Shongtong-Karcham
400 MW
Thopan-Powari
480 MW
Jangi-Thopan
480 MW
Ghanvi-II
10 MW
The proposed Luhri Hydroelectric Project has a capacity of 480 MW and
is located on the Satluj River, upstream of Thopan-Powari Project.
In addition to the Satluj, other rivers which are part of the Great Indus
Basin and pass through the State of Himachal Pradesh, also contribute to
the power potential of the State. The most important are: Beas River,
4586 MW; Ravi River, 2379 MW, Chenab River, 3832 MW.
LUHRI HEP
6
Himachal Pradesh thus has considerable hydropower potential. In the
long run, it is more economical for development than thermal power, as it
utilises perennial natural resource which otherwise goes to waste. For the
prosperity of the state and benefit of the country the hydro-power
development in Himachal Pradesh needs a renewed thrust. The
hydroelectric potential of Himachal Pradesh, however, is not likely to be
consumed in the State, and therefore will be available for meeting the
requirements in other parts of the country, and particularly in the Northern
Region.
2.2.3 Thermal power potential of Himachal Pradesh
Himachal Pradesh being located in the far North end of the country and
considerably away from the coalfields, does not have any prospect of
having thermal projects. The same consideration applies to other northern
states.
2.2.4 Power Scenario in India
The installed capacity in India increased from 1362 MW in 1947 to 64,729
MW in 1990 at the end of the 7th Plan. During that period energy jumped
from 4 to 264 TWh. However, despite that appreciable growth, power
demand has almost throughout outstripped the supply.
At the end of the 7th Plan, the shortfall in energy availability on an " all
India " basis was 6.8%. The corresponding shortfall in peak availability
vis-a-vis demand was about 7.6%. In the Northern Region, the shortage
with regard to peak availability was 19%. In July 1991, the peaking
shortage for the country as a whole increased to 16.7% from 7.6% in
March 1990, while the energy shortage rose to 7.9% from 6.8%.
For the 8th Plan(1992-97), the Central Electricity Authority (CEA) had
LUHRI HEP
7
estimated a need based capacity addition of 48000 MW,which was scaled
down to 30 558 MW taking into account the availability of resources. At
the end of 1997-98 India had an energy shortage of 8.1% and a peaking
shortage of 11.3%. Even with the planned capacity addition of more than
30,000 MW, the shortages in the terminal year of the 8th Plan, i.e. 1997,
would continue to be at the same level. As a matter of fact the situation is
likely to be worse as slippages are anticipated in the planned capacity
addition.
2.2.5 Demand and Supply in Himachal Pradesh State
Himachal Pradesh, being mostly a hilly terrain State and located in the far
North end of the country, considerably away from the coal fields, has little
prospect of having thermal projects. Having considerable hydropower
potential, which is generally found to be more economical for
development than thermal power, power generation in the future for
Himachal Pradesh has to be essentially from hydro-power sources.
As per the 15th Electric Power Survey of India, carried out by the Central
Electricity Authority (CEA), the energy requirement of Himachal Pradesh
for 1990-91 was 1487 GWh. This demand was projected to increase to
2536 GWh in 1994-95. Similarly, the peak load requirement for 1990-91
was 325 MW, which was expected to increase to 541 MW in 1994-95.
Table 2.3 shows the supply of energy and power as well as future
demand during the period 1990-91 to 1994-95 as projected by Central
Electricity Authority (CEA) in the 14th Electric Power Survey of India.
Table 2.3
POWER SUPPLY AND DEMAND FOR HIMACHAL PRADESH
Item
1990-91
1991-92
1992-93
1993-94
1994-95
Installed Capacity
274
274
296
301
301
Peak Availability
340
347
379
458
475
LUHRI HEP
8
Peak Load
325
366
415
477
541
Surplus/Deficit
15 4.6
- 19 - 5.2
- 36 - 8.7
- 19 - 4.0
- 66
- 12.3
Energy Availability
2013
2047
2147
2521
2711
Energy Requirement
1487
1688
1925
2224
2536
Surplus/Deficit
526 35.4
359 21.3
222 11.5
297 13.4
175 6.9
The future demand scenario for the period 1995-2010 as projected by the
CEA in the 15th Electric Survey Report with respect to Himachal Pradesh
is as depicted in Table 2.4.
Table 2.4 Energy and Peak Load Demand for Himachal Pradesh Period 1995 to 2010
Period
Energy Demand (GWh)
Peak
Demand (MW)
1995-96
2879
609
1996-97
3254
683
1997-98
3662
763
1998-99
4103
848
1999-2000
4576
939
2004-05
7378
1457
2009-10
10606
2020
It can be observed that energy requirements are likely to increase during
the period 1991-2010 from 1487 GWh in 1990-91 to 10606 GWh in 2009-
2010, and the peak load demand would do increase from 325 MW to
2020 MW during the same span.
LUHRI HEP
9
2.2.6 Demand and Supply in the Northern Region
The hydropower potential of Himachal Pradesh, is obviously surplus to its
own requirement. However, it will be usefully made available to meet the
power and energy requirements in other parts of the country, and very
particularly, the Northern grid. This is the case of major projects such as
Bhakra and Beas, which supply power to the Northern grid. Another
example is the 540 MW Chamera Project, situated in the north-western
part of the State, which started operating in 1994 and supplies New Delhi
through a 510km long transmission line. For planning purposes it is
therefore necessary to study the energy and power requirements of the
Northern region as a whole, since the region will be the recipient of any
hydropower project likely to be developed in Himachal Pradesh in the
future.
On the basis of the addition of capacity during the 8th Plan period, the
CEA has estimated the requirements of the Northern Region as shown in
Table 2.5.
Table 2.5
Power Demand and Supply for the Northern Region in the Period
1990-95
Item
Unit
1990-91
1991-92
1992-93
1993-94
1994-95
Installed Capacity
MW
19203
20581
22195
24274
26681
LUHRI HEP
10
Peak Availability MW 11408 11291 12777 14008 15271 Peak Load
MW
14908
16259
17721
19240
20814
Surplus/Deficit
MW %
- 3500 - 23.5
- 4338 - 26.7
- 4944 - 27.9
- 5232 - 27.2
- 5543 - 26.6
Energy Availability
GWh
80803
82755
88165
95959
106143
Energy Requirement
GWh
79338
86553
93396
102416
110841
Surplus/Deficit
GWh
%
1465 1.8
- 3798 - 4.4
- 6231 - 6.6
- 6457 - 6.3
- 4698 - 4.2
Table 2.6 lists the future energy and load requirements for the Northern Region.
Table 2.6 Energy and Peak Load Demand for the Northern Region Period 1995-2010
Period
Energy (GWh)
Peak Load
(MW)
1995-96
119887
22466
1996-97
129587
24234
1997-98
139976
26124
1998-99
151086
28143
1999-2000
162954
30295
2005-06
248332
45634
2009-10
318715
58117
From Tables 2.5 and 2.6, it can be seen that the peak demand over a period of 20 years is likely to double from 14908 MW in 1990-91 to as much as 58117 MW in 2009-2010.
2.2.7 Satluj river hydropower potential
The Government of India and the State of Himachal Pradesh have
identified the Satluj river as one of the main sources of hydroelectric
power, and have initiated several hydro-electric projects along the reach
of the river and its tributaries under their jurisdiction. These projects, in
LUHRI HEP
11
varying stages of planning, construction, completion and operation,
include:
- Bhakra-Nangal, 1164 MW, operating
- Kol, 800 MW, concept stage
- Rampur-Behna, 400 MW, concept stage
- Nathpa-Jhakri, 1500 MW, under operation
- Karcham-Wangtoo, 1000 MW, investigation stage
- Shongtong-Karcham, 402 MW, investigation stage
- Thopan-Powari, 480 MW, concept stage
- Jangi-Thopan, 480 MW, concept stage
- Pooh-Spillo 300 MW, concept stage
- Khab-Pooh 300 MW, concept stage
These projects are all run-of-the-river, with the exception of Bhakra-
Nangal. Additional hydro projects, planned and operating have been
identified on tributaries of the Satluj, such as Sanjay Vidyut Pariyojana -
Bhaba (120 MW, operating), Nogli (3 MW, operating), Ghanvi (22.5,
operating), Baspa II (300 MW, Operating) and Baspa I (concept stage).
Some of the potential projects listed here may not be built in near future,
but it is reasonable to assume that the preliminary studies have indicated
these projects to be technically feasible, there will be a strong motivation
to build them as the demand for power grows and limited fuel resources
tend to exhaust.
Further developments, in addition to those listed here, may be seriously
considered at some time on both the Satluj and its tributaries. A program
to develop small hydro projects on streams flowing through villages is
also in place.
2.3 NEED OF THE PROJECT
From the growth of peak demand and anticipated installed generating
LUHRI HEP
12
capacity on the basis of schemes proposed for benefits under
construction/consideration during eighths and ninth five year plan, it is
observed that there is a dire need to provide additional capacity to the
Northern grid to meet the increasing demand of the grid. Thus new
scheme have to be taken up immediately and implemented to drive timely
benefits.
The most important source of power development in the Northern region
is Hydro resources located in Himachal Pradesh, Uttar Pradesh and
Jammu and Kashmir. Luhri Hydroelectric Project is very attractive
scheme from the view of deriving benefits in the beginning of tenth five-
year plan.
, LUHRI HEP
III - 1
CHAPTER - III PROJECT AREA
3.1 INTRODUCTION
The Government of India and the State of Himachal Pradesh have
identified the Satluj river as one of the main promising future sources of
hydroelectric power. Development of Satluj waters was started in a big
way first by Bhakra-Nangal Project. Government have now initiated
several hydroelectric projects along the reach of the Satluj and its
tributaries. The Luhri Hydroelectric Project is envisaged as a run-of-the-
river development on the Satluj river, in the reach between Luhri and
Chaba villages in Shimla District of Himachal Pradesh just downstream of
confluence of Behna khad with Satluj river nearLuhri.
3.2 LOCATION AND ACCESS
Himachal Pradesh is located in the western portion of the Great
Himalayan Mountain Range of northern India, bounded by the State of
Jammu-Kashmir to the North, Tibet to the East, and the plains of northern
India to the South and West. The Satluj river is one of the major rivers
draining this region. It rises in the Tibetan Plateau, passes via steep
valleys and gorges through the Himalayan Mountains and foothills and
meets the Arabian sea across the plains of Northern India.
The project site area is about 80 km from Shimla, the State capital, and is
an upstream development to the proposed Kol dam Electric Project ( 800
MW) on the Satluj river.
3.3 CLIMATE
The study region is falls between climatic zones I and III of northern India.
Zone I, the Tropical Monsoon climate, extends from the Indian Ocean
, LUHRI HEP
III - 2
north as far as Wangtoo, with its effects modified by elevation and
topography. The tropical monsoon climate involves an
annual rainfall in excess of 1000 mm, occurring mostly in the months of
June to October. The study region, however, experiences lmoderate
rainfall as the mountains between the plains and the study region capture
most of the precipitation.
Climatic Zone III, the Arid Mountain Climate, affecting the Tibetan and
western China Plateau, is characteristically cold and dry in winter, and hot
and dry in summer. This is highly modified by the topography of the study
region. From November to May, the region experiences a generally north-
easterly flow of cold continental air moving out from across the Tibetan
Plateau. The effect of this flow is somewhat modified by the mountains
but it can result in high winds. Winter precipitation occurs as a result of
westerly disturbances. From June to September, the region experiences
the south-westerly monsoon from the Indian Ocean, though, once again
the region's location in the heart of the Himalayas modifies the effect, and
precipitation is small.
3.4 GEOLOGY
The project area lies in Mehbar and Maldi gneisses comprised of kyanite
and psamatic gneisses with bands of schist and quartzite. These are
intruded by basic and acidic rocks. All the rocks are well foliated. The
general trend is N-S with moderate dips toward East. These are
transacted by a number of joints of which the foliation and strike joints are
the most predominant followed in frequency by steeply dipping transverse
joints. The rock formations within the project area going upstream from
the tailrace consist of the Wangtoo, Rampur and Jutogh gneisses and
granites. The Wangtoo rocks are overlaid by the Rampur followed by the
Jutogh, the three series having thrusted contacts.
Rocks are generally covered by glacial deposits, rock debris, alluvial
terraces and fans. The soils of the Satluj valley are relatively poor sandy
, LUHRI HEP
III - 3
loam, and exposed bedrock, rocks and gravel abound. In the valley
bottom there is virtually no soil, but between elevations 1200 and 3500 m,
the soils support some forest cover and are cultivable to a certain extent.
3.5 SEISMICITY
The project area lies in an active seismic region, zone IV of the Seismic
Zoning Map of India. Available data on seismicity within a radius of 150
kms of the project shows that earthquakes having a magnitude greater
than 5 on the Richter scale occur at frequent intervals. Important seismic
events which have taken place in the past 150 years and caused
significant damage include the 1905 Kangra quake (magnitude 8+), the
1908 Kullu quake (magnitude 6.0), the 1945 and 1947 Chamba quakes
(magnitude 6.5 & 6.6), the 1975 Kinnaur quake (magnitude 6.8) and the
1991 Uttarkashi quake (magnitude 6.6).
3.6 SOCIO-ECONOMIC CHARACTERISTICS
The Shimla region has deep roots in Indian mythology, legends and
literature. The Shimla region was formerly a part of the princely state of
Kumarsain / Suni. The State of Himachal Pradesh came into existence in
1960 and Shimla became a district. Contact with the outside world
accelerated when National Highway 22 was built by the Border Roads
Organization, following the 1962 Sino-Indian war. One immediate
consequence of the road construction was that interior of Shimla became
integrated into the cash economy of Himachal Pradesh. The State has
continued to play a role in introducing techniques and policies that have
enhanced production despite the poor soils of the area.
LUHRI HEP
CHAPTER-IV
GEOLOGY
4.1 INTRODUCTION
The Central Electricity Authority (CEA), with a view to fill the gap
between supply and demand in the field of power have embarked on
an exercise to assess balance hydroelectric potential in the country
and rank the schemes thus identified in various parts of the country in
different river basins. As a part of the exercise, 162 schemes with
probable installed capacity of 50,600 MW and located in various river
basins spread over 16 states have to be taken up for preparation of
Pre Feasibility Reports (PFRs) in the first phase. The schemes found
feasible are proposed to be taken up for further development in X and
XI Five Year Plans. The proposed Luhri Hydroelectric Project is one
such scheme identified in Satluj basin in shimla District of Himachal
Pradesh State. Luhri Hydroelectric Project is a run of the river scheme
that envisages the construction of a diversion dam/weir across the river
Satluj near village Luhri (31 21' 40" N: 77 26 25" 'E'; 53 E/7), about
13 km long conductor system and power house on the left bank of
Satluj, 1 Km upstream of village Pandoa (3117'10"N: 7719'10"E, 53
E/7). The proposed power house would have installed capacity of 425
MW.
4.2 REGIONAL GEOLOGY
The area forms a part of the Lesser Himalaya and presents a
diversified relief with high rugged hills of carbonate rocks, deep valleys,
LUHRI HEP
steep escarpments and cliff faces. There is a great variation in altitude ,
from 640 m near Tattapani to 3100 m at Shali peak. The satluj forms
the main drainage system of the area that flows from the NNE to SSW
direction, from north of Jhunajan to Chamba where it takes almost an
east-west trend.. The main tributaries of the river are Nauti, Pandoa
and Sowera Khads, meeting the Sutlej at Chaba, Paildoa and Bagthal,
respectively. A number of small nalas feed these khads giving rise to a
dendritic type of drainage pattern. An oval shaped lake, about 300m
long and 220m broad is located in the east of village Kariali. It has
probably been formed by damming of the northwest flowing nalas by a
landslide mass from the adjoining hills. During the monsoons the lake
gets filled with water which slowly flows underneath and emerges as
springs at Drawl, Graon and then flows in an open channel before
merging with the Sutlej river.
The rocks exposed in the area under reference belong to the Kullu,
Shali and Basantpur Groups. Thelithostratigraphic succession in the
area modified after Sharma and Ahluwalia(1977) is given below:
Basic sills and dykes (intrusives) Shimla Group Basantpur Formation : Grey, dark grey shale, slate,
carbonaceous shale, lenticular
bands of limenstone, quartzite.
-----------------------------------Thrust----------------------------------------------------------------
Bandla Formation Grey siltstone, quartzite and shale.
LUHRI HEP
Pamali Formation Thin bedded limenstone, dolomite,
quartzite towards the top.
Shali Makri Formation Purple, greenish grey slate, splintery,
shale, quartzite and limenstone.
Tattapani Formation Grey and pink massive dolomite and
phylitised shales.
Sorgharwari Formation Pink and grey limestone, Khatpul
Formation Massive dolomite.
Khaira Formation Pink and white quartzite,
Ropri Formation : Not exposed in the area.
-----------------------------------------Thrust---------------------------------------
Khokan Formation Quartzite, quartz chlorite and quartz
biotite schists,
slates phyllites and schists,
garnetiferous schists.
Kullu
Group Garh- Manjrot Streaky mylonitic gneiss, banded and
augen gneisses.
The crystallines and metamorphites of the Kullu Group physically
overlying the Basantpur Formation belonging to Shimla Group along
the thrust (Jutogh Thrust) have been mapped from Naraini Ghati in the
LUHRI HEP
south to Kanda in the north. Between Thach and Naraini Ghati the
Kullu Group rocks at the contract, is represented by dark grey slate,
phyllite and schist followed by coarse grained steaky gneiss dark grey,
green chloride and Biotite-schist coarse grained streaky gneiss
predominates at the contract between Thathal and Kanda.
Except the lower most Formation Ropri, all the other Formations of
Shali Group are developed in the area. Khaira Formation consists of
pink and white quartzite and a small outcrop of this rock, about 50m
long 2.30m wide occurs in the southwest of Kariali. Pink and grey
quartzite of the Khaira Formation is conformably succeeded by grey
blue, massive, tough and compact dolomite. This shows a
characterisitic rugged weathering and encloses impersistent bands of
chert near Darabla, along the road section, about 30 cm thick band of
jet black shale occurs within the dolomite for about 50m along the
strike. The Khatpul dolomite is gradationally overlain by light pink to
light purple, well bedded and laminated lime stone with purple shale
partings. The pink and purple limestone invariably grades into each
other, along, as well as across the strike. Pink limestone, however
remains the dominant and consistent of all the Formations. Lime Stone
breccia, formed by the solution action is met with near Bagh. Calcite
veins are sporadically found in these limestones. A few malachite
stains are encountered in the pink limestone near Karioli. The based
part of the limestone is shaly and cherty. The limestone is traced from
Jhanjan in the northeast to Padian in the southwest over a distance of
about 15 km. with average which of about 500 m. Sorgharwari
Formation passes graddationally into massive dolomite of the
Tattapani Formation. The dolomite contains chert bands ranging in
width from 2-8 cms. The dolomite is grey, grayish blue and pale pink
and contains impersistant grey and black slate partings and phyllitised
LUHRI HEP
shales. In the area the Formation is traced from north of Mungna in
southwest to Jamrog in the northeast over a distance of about 17 kms
with an average width of about 500m. Conforably overlying the
Tattapani Formation is the Makri Formation which constitutes grey,
greenish grey and purple shale and slate. As grey splintery shale, grey
quartzite, grey limestone, cherty splintery shale, grey quartzite, grey
limestone, cherty dolomite and grey quartzite form the components of
this Formation. These are traced from Mungnna in the southwest to
Kanda in the northwest over a distance of about 18 kms with width
varying from 10m to about 1 km. Parnali Formation overlies the Makri
formation. It consists predominantly of grey dolomite, which is highly
cherty and contains lenticular sporadic bands of white and grey
quartzite and thin bedded bluish limestone. This is traced from north of
Sakra in southwest to Rehri in the northeast over a strike length of
about 25 kms with an average width of about 800m. The rocks don't
extend beyond Rehri due to a fault. The youngest Formation of the
Shali Group is the Bandla Formation which comprises grey siltstone
quartzite, shale and sandstone. In the entire area, the rocks are
encountered between LOI and Garrech for a strike length of about 3
kms with an average width of about 500m. A small lens of these rocks
has also been noticed in the northwest of Sai Ser. The absence of this
Formation in the rest of the area is attributed to a fault.
The Shimla Group extends from the Giri to the Satluj and Baghar at the
base of Chunar Mountain Range leaving out the Halog-Chali ridge.
Isolated outliers are seen in the Bharari Khad, Batawara and Kindu
where they directly overlie the Shali Group. The shimla Group again
reappears in the NW part of Himachal, covering Thanoli, Kehluadn the
Ravi over the Shali structural belt and beneath the crystalline thrust
sheet. Its extension beyond the Ravi into the Kashmir Himalaya is
LUHRI HEP
confirmed where it is variously referred as the "Agglomeratic Slate and
Ramban Formation. Beyond the "Syntaxial bend" it passes into the
Hazara Group. In the SE part of the Himachal, Shimla Group rocks
reappear unconformably over the Deioban and beneath the Janusar
thrust sheet of the Nigali Dhar-Korgai synclines of the Blaini-Infra Krol,
Krol-Tal sequence. It continues in that position towards Garhwal
Himalaya before being finally tectoniclly overlapped by the Janusar
thrust sheet. It also crops out in the window zones of Parahat and
Bidhalana in the southern Garhwal Himalaya.
The Shimla Group is divisible into four formations on the basis of certain
characteristic lithological association and order or superposition :
______________________________________________________________________
Formation Members Lithology Thicknes in meters (approx.)
______________________________________________________________________
Upper Conglomerate, arkosic sandstone Proto-quartzite, grey and purple, shale 1600
Sanjauli Lower Greywacke sandstone (medium to coarse-
Grained), greywacke siltstone, shale and
Siltstone alteration, orthoquartzite.
Chhaosa Shale and siltstone alteration greywacke,
siltstone and orthoquartzite. 1300
Kunihar Shale and silt stone alterations with limestone
interbeds (earlier referred to as Kakarhatti 450
limestone)
Basantpur D Thick bedded to platy greyish blue lime-
Stone with interbedded shale (local facies)
LUHRI HEP
C Massive to bedded limestone -
Dolomite (local facies _
B Shale, siltstone with interbeds of lenticular
Limestone; shale is sporadically carbonaceous
Impresistent band of quartzite and dolomite.
A Greyish white quartzite and conglomerate
(sporadic )
Out of the four formations of Shimla Group, the present area contains
only the rocks belonging to Basantpur Formation. The Basantpur
Formation overlies the various formations of the Shali Group and
includes grey, dark grey shales and slates. Highly carbonaceous shale
bearing pyrite, is generally developed near the contract with the Kullu
Group. The carbonaceous rocks are well exposed in places like north
of Garech, west of Thathal, west of Dakolu, South of LOI and North of
Rehri. The rocks, at place, contain thin lenticular bands of platy
limestone. A number of such lenticular bands of limestone have
developed over a wide area around Naldehra. Small outcrops of grey
platy limestone having a resemblance with that of the Basantpur
Formation occur within the rocks of the Shali Group in the south of
Naklog Ghati, southeast of Senu (in Makri Formation) and west of LOI
(in Paruali Formation). The Contact between the Shali Group and the
Basantpur Formation is a tectonic one. The rocks have been traced
from Chaba to Baldiha and from Dalog Pass to Kanda.
Several sills and dykes of doleritic and dioritic composition cut across
the various Formations of the Shali Group along the weak planes.
Such intrusives of various shapes and sizes have been recorded in the
LUHRI HEP
Sorgharwari Formation around Kariali, east of Kothi, southeast of
Bathora; in the Tattapani Formation in the north Markalu;in Parnali
Formation in the east of Uparia Kayalu and in the Bandla Formation
north of Khaibal. The intrusives do not show any contact effects with
the wall rock, probably indicating the low temperature conditions of the
intrusion.
The Shimla Group is generally free from volcanic element. However,
locally dolerite-diabase dykes are seen intruding into the Shimla Group
and are particularly seen in the Basantpur Formation. Such dykes are
seen in Basantpur - Seoni area.
The Kullu Group fully frames the Larji-Rampur Window Zone, and is in
turn, partly framed by the Salkhala on the western side and by the
Vaikrita on the eastern side. In the southeastern part it lies on the
subthrust side of the Jutogh Thrust Sheet. Further west and northwest
it rests over the Shalli Structural Belt along Suketi Thrust as a long,
linear and narrow nappe. Beyond the Ravi in the Jammu-Kashmir the
thrust links up with the Punjab Thrust. The Kullu Group is one of the
three principal crystalline nappes of Himachal Pradesh.
The Kullu Group comprises the following sequence of formations.
Khokaan Formation Quartzite, quartz chlorite and quartz biotite schists, slates
phyllites and schists, garnetiferous schists.
Garh - Manjrot Streaky mylonitic gneiss, banded and augen geniesses.
Formation
LUHRI HEP
Khamarada Formation Carbonaceous to graphitic schists and phyllite locally
garnetiferous; lenticular greyish blue and cream coloured
platy limestone and calc-schists.
--------------------------------------------Thrust------------------------------------------------------
The Kullu Group constitutes the southern frontal crystalline thrust sheet
tectonically transgressing over the Lesser Himalayan Tectogen. One
characteristic features of the Kullu Thrust sheet is the development of
a highly sheared mylonite gneiss (Manjrot - Garh Gneiss) tectonically
intermixed with the carbonaceous phyllite and limestone along the sole
of the t hrust sheet particularly in the sector from Baragaon in SE to the
Rani in NW and also around the Larji-Rampur Window Zone. This
thrust represents a major and the most pronounced tectonic
discontinuity in the Himachal Pradesh and can bde equivalent to the
Main Central Thrust of the Himalaya (Srikantia, 1988).
Garh- Majrot Formation connsist of quartzose, banded and streak
gneisses, pale greyish green in colour, showing alternate beds of
schist and quartzite and even carbonaceous phyllite. The gneiss is
highly streak and strongly foliated and mylontised augens of feldspar.
Coarse grained of blue quartz stand out prominently. In Baragaon in
the Satluj Valley the Garh- Manjrot gneiss appears prominent along the
Kullu Thrust Sheet. In Himachal Pradesh the Garh - Manjrot Gneiss is
fairly persistent along the strike and occupied a definite tectono-
stratigraphy position.
Khokhan Formation comprise mainly of quartzite, quartz schist, quartz
chlorite and quartz biotite schist, slates, phyllites and garnetiferous
schists. Locally amphibolites appear associated with the
LUHRI HEP
metasediments. The Formations is tectonically succeeded by the
Jutogh Thrust sheet on Satluj valley.
4.3 STRUCTURE AND TECTONICS
The Kullu Group consisting of carbonaceous schist, chlorite schist and
augen gneiss physically overlies the rocks of the Basantpur Formation
along a thrust (Jutogh thrust). The contact between the Shali Group
and the Basantpur Formation is tectonic and shows evidence of
movement. The regional strike of the rocks formations is NW -SE with
dips varying from 200 to 700 on either side. The area reveals a
regional anticlinal structure with its axis running in NW -SE direction.
A number of open and overturned type of folds developed in the Shali,
have increased the outcrop width of the deposit on the eastern limb.
Cross folding in the area has resulted in the formation of a
complicated outcrop pattern. Dolomite of Parnali Formation is folded
into a syncline with a N60E-S60E trending axis. This may be
complementary to the main anticline. In the northeastern part of the
area the contact between the Basantpur Formation and Shali Group is
faulted and the along this fault the Parnali and the Bandla Formation
have been eliminated. In the Nauti Khad area (southwestern part) also
the Basantpur Formation has been brought to rest over the Parnali
dolomite along a fault. A few oblique faults are also noticed in the area.
4.4 SEISMOTECTONICS AND SEISMICITY Seismotectonically, the area is located on eastern margin of Shinmla
Tectonic Block of Narula (1991). It is bound by Sundernagar Fault in
west and Kaurik Fault in east. The project area is located in Main
Himalayan Belt where the tectonic packages are Tethyan and Lesser
LUHRI HEP
Himalayan cover sequences affected by Himalayan Orogeny, low and
high grade complexes tectonically reworked during Himalayan
Orogeny and pre to syntectonic granitods and basic volcanics. The
Foothill Belt constitutes foredeep sediments affected by the terminal
phase of the Himalayan Orogeny (Narula et al.). The northernmost
tectonic element is the dextral Karakoram Fault (KF) which is
subparallel to Indus Suture Zone (ISZ) occurring to the south. Within
the Main Himalayan Belt, the high grade complex is bound in south by
Main Central Thrust (MCT) which is considered most conspicuous
structural element of the Himalayas. Further South, within lesser
Himalayas, the other important tectonic element is Vaikrita Thrust (VT).
The Lesser Himalayan Belt is separated from the Frontal Belt by Main
Boundary Thrust (MBT). The sourthern limit of Frontal Belt is marked
by Main Frontal thrust (MFT). A part from the tectonic planes sub-
parallel to Himalayan trend, a number of transverse features have
been observed. These include Sunder Nagar Fault, Kaurik Fault and
Raura Fault. In the Higher Himalayas, Kaurik Fault Zone is considered
to have triggered the Kinnaur Earthquake of 19th January,1975. The
present area also have Salkhala and Jutogh Thrust which are present
near Karchhaim. Neotectonic activity has been observed along
Karakoram Fault, ISZ, MBT, MFT and Kaurik Fault. Seismically, this
area has subdued seismicity but the areas immediately NE of it, the
clustering of seismic events is observed in the Zone known as Kinnaur
Seismic Zone having N-S alignment. It is traversed by a number of half
graben faults defining Kaurik Fault system. The seismic events in
general in this Zone are shallow focus (0-40 km) but a few events with
intermediate and deeper depths have been observed. To the west of
the area lies Kangra Seismic Block, which is considered very active
seismic zone and has experienced 20 earthquakes with magnitude
more than 5. As per Seismic Zoning map of India (1S:1893-1984), the
LUHRI HEP
area lies in seismic Zone-IV and a number of regional thrusts and
faults are located in the vicinity of the project. Therefore, it is
suggested that appropriate seismic coefficient may be incorporated in
the design of the appurtenant structures of the project.
4.5 GEOTECHNICAL APPRAISAL The proposed Luhri Hydroelectric Project a run of river scheme
proposed in Satluj Basin in Shimla and Kullu districts of Himachal
Pradesh envisages construction of a diversion dam across the river
Satluj near Luhri, a water conductor system comprising 13 km long
head race tunnel to conduct water to proposed powerhouse of the
river Satluj near Pandoa village. The area exposes the rocks belonging
to different formations of Shali, Shimla and Kullu Groups of Proterozoic
age. The contacts between the rocks of different groups are either
faulted or thrusted.
At the site of proposed diversion the river Satluj flows towards NW
through a narrow valley. The area exposes quartzite, banded streaky
gneisses with interbands of schist and quartzite and carbonaceous
phyllite belonging to Garh Formation of Kullu Group. The gneiss is
highly streaky, strongly foliated and mylotinised. Augens of felspars
and coarse grains of the quartz can be observed. The foliation trends
vary from NE-SW to NW-SE. It is suggested that the final location and
type of diversion structure be decided after assessing the thickn ess of
overburden in the river bed and on the abutment and availability of site
for locating proper intake structure for headrace tunnel.
The proposed 13 km long headrace tunnel is aligned in NE-SW
direction on the left bank of the river Satluj. It is likely to encounter the
LUHRI HEP
rocks belonging to Khokan and Garh Formations of Kullu Group and
Sorgharwari, Tattapani, Khaira and Makri Formations of Shali Group
and those of Basantpur Formation of Shimla Group that includes
Shale, Slate, carbonaceous shale with limestone and quartzites. Both
the contacts of this formation are thrusted. The rocks of Shali Group
comprise sedimentary sequence including quartzite,
limestone/dolomites and shales. These rocks are expected to provide
good to fair tunnelling media in general. The HRT is expected to cross
two thrusts along its route. Difficult tunnelling conditions could be
expected in Zones around these thrusts. The conditions may become
poorer if these zones are charged with water. It is suggested that
adequate rock cover over the structure be ensured where it crosses
the surface drainages. It is also suggested that excessive cover over
the structure may also be avoided since hot springs present in this
area and adjacent areas indicate presence of geothermal field that
could result in relatively high temperatures during tunnelling.
The proposed powerhouse with 425 MW installed capacity is
envisaged on the left bank of Satluj near the village Pandoa. The area
exposes pink and grey limestone belonging to Sorgharwari Formation
of Shali Group. It is suggested that the site selected for the structure
may have sound bedrock at reasonable depth and adequate space
free from natural hazards like landslides and enough working space
and suitable locations for other appurtenant structures. The site is
located in Zone IV in Shimla Block of Narula (1991) as per Map of
India Showing Seismic Zones. It is suggested suitable seismic
coefficient be incorporated in the designs of appurtenant structures of
the project.
LUHRI HEP
The geotechnical appraisal is based on regional geological set up and
is without field visit to the project site.
REFERENCES:- Narula, P.L., (1991), Seismotectonic Evaluation of NW Himalayas,
Unpubl. Progr. Rep. Geol.. Surv. Ind..
Narula P.L.Acharayya, S.K. and Banarjee, J(2000). Seismotectonic
Atlas of India and is environs. Pub. Geol. Surv. Ind.
Sharma O.P. and Ahluwalia, A.D. (1977) Report on limestone
investigation, Shimla district, Himachal Pradesh. Unpubl. Progr. Rep.
Geol. Surv. Ind. (1978-77)
Sirkantia, S.V. and Bhargava, O.N. (1988) Geology of Himachal
Pradesh Geol. Soc. Ind. Bangalore, P.406.
LUHRI HEP
V-- 1
CHAPTER-V
HYDROLOGY
5.1 INTRODUCTON
Satluj river is one of the principal river of Himachal Pradesh and it divides
the District Kinnaur into two parts. In its passage through Distt. Kinnaur,
the Satluj river crosses three more or less parallel mountain ranges viz. the
Zaskar Mountain, the Great Himalayas and the Dhauladhar Ranges.
Between three mountain ranges lie the subsidiary valleys of varying
dimensions from the narrow glens and ravines of Tidong and Kirang
streams to the sizeable valleys of Spiti & Baspa river. The significant
tributaries streams and rivers that flow into the Satluj river from south or
along its left bank are successively the Tidong, Hogis, Gyamthing, Baspa,
Duling, Sholding, Manglad etc. Likewise those entering from the north or its
right bank are the Spiti River, Ropa, Kirang, Kashang, Pangi, Choling,
Bhaba, Sorang, Kut and Ganwi Khud. In between there are many seasonal
streams that meet the Satluj river and its tributaries. At Khab it receives the
Spiti river where the bed of the stream is still about 2590 meter above the
mean sea level.
Satluj river rises from Rakas Tal fed by Mansarover lake in Nari Khorsam
province of Tibet and after flowing in West direction for a distance of about
300 Km., it enters India near Shipkilla in District Kinnaur. The Satluj
descends from about 2590 meter at Khab to 936 meters at Rampur
Town, in Distt. Shimla, the main supply station to Distt. Kinnaur. The Satluj
flows in this whole reach between narrow cliffs and therefore there is no
open ground worth describing all along its banks, thus excluding the
possibility of making any storage Dam. The water of the river is more or
less discoloured. Cultivated fields in terraces are generally at considerable
heights from its bank and are thus immune from the turbidity of the
water, which is largest in summer months. Within the limits of the District
LUHRI HEP
V-- 2
Kinnaur the river is not navigable owing to the rapidity of flow and presence
of boulders. After it leaves the boundary of the District Kinnaur near village
Chaura it enters Shimla District.
5.2 CATCHMENT CHARACTERSTICS
The geographical limits of the Satluj basin upto Bhakra Dam lie between
latitude 3015' N to 3125' and longitude 7715' to 7730' It covers its area
in Nari Khorsam province of Tibet (China) and in Himachal Pradesh State
of India. The catchment area at upstream of Rampur is about 50880 Sq.,
Km out of which about 36900 Sq.Km falls in Tibet and 13980 Sq. Km in
India. Catchment area upto Luhri dam site is 52403 Sq.Km.
The basin represents some remarkable physical features. Below it
stretches the loftiest mountain ranges of world radiating from the Pamir
knof. The most southerly of these is the Himalayan Range, which is loftiest
and longest range in the world.
The Himalayas that run first South-East-wards from the Pamir knof and
later in an easterly direction constitute a massive mountain wall extending
over 2500 Km with varying width of 250 to 300 Km.
Topographical and climatically the catchment have been divided into four
categories as below: -
i) Tibetan Plateau
River Satluj rises in Tibetan plateau in the region of the Mansarover Lake
situated at an elevation of 4510 Km above mean sea level. The river
passes through the Tibetan province of Nari Khorsam. The best-known
portion of Nari khorsam and the plateau situated between Zaksar and
LUHRI HEP
V-- 3
Ladakh ranges. This plateau has been formed by the successive deposits
of boulders, gravel, clay and mud in the trough between two ranges. The
deposits lie in parallel and nearly horizontal beds. River Satluj has been
able to cut a channel about 915m deep through the plateau with the water
received from glaciers. The vertical banks stand un-eroded, as there is no
local rainfall. River Satluj in Nari Khorsam region is joined by several
tributaries. The beds of which lie about 305m or more below surface of the
plain and their over changing cliffs similar to those of Satluj have been
spared from destruction by rain. The flat portion of the plateau now
remains standing between profound gorges. There is absolutely no
vegetation in this region when the snowmelts deep channels are formed on
the surface. The river Satluj enters India near Shipkilla after traversing a
length of about 320 Kms in the Tibetan province of Nari khorsam.
ii) Spiti Valley Spiti river is the biggest tributary of the river Satluj and joins river Satluj at
Khab, 14km upstream of Pooh. The characteristics of this catchment area
drained by river Spiti is between 3048 m and 4570m. In this area there is
absolutely no vegetation. The melting snow forms deep flow channels.
iii) Namgia to (Wangtu) This catchment is bounded by moderately high hills 1900m to 3048m and
has little rainfall but heavy snow. The snow line in this region is at 3048m.
The flows in the river are mainly due to snow melting which follow more or
less a regular pattern. Due to the absence of rain, arid\condition prevails
and good forests seen below Reckong Peo do not exist in higher altitude.
The well-formed pine forests near Karcham Wangtu give way to Chilgoza
plantations at the higher elevation. The area has steep slopes with little
earth cover and experiences very little rain.
LUHRI HEP
V-- 4
When snow falls, water enters into the rock crevices where its freezing
during winter cracks and crushes the rocks. The subsequent loads of snow
accelerate this phenomenon. When the snow melts, the disintegrated
debris slide with the water into the river. This cycle repeats year after year.
IV ) Wangtu to Suni The annual rainfall of the catchment is about 1000mm.The area is forested
with scattered to dense patches of trees. There is agricultural development
in several locations mainly along the river and on flatter slopes.
V) Suni to Kol Dam and up to Bhakra Dam This area is in the lower elevations of the Shivaliks range with rise to about
elevation 2100 m. The average slope of the river between Rampur to
Bhakra is about 1 in 300 .The rainfall is heavy and silt loads are high.
Forest cover is sparse and vegetation has been denuded by over- grazing.
5.3 THE RIVER PROFILE
River Satluj rises near Rakas-Tal lake which is fed by lake Mansarover at
about 4570m above mean sea level between Rakas-Tal and Shipkilla, near
the Indian border, the Satluj river takes a North-Westerly course for a length
of about 320 Km in the Tibetan province of Nari-Khorsam. The Satluj is
joined by several tributaries in Nari-khorsam such as Changchu, Drama
Yankti, Chonak, Manglan, Transuo, Summa, and Trap etc. Immediately
after entering the Indian territory near Shipkilla the river takes a south-
westerly direction on its way to Bhakra gorge about 320 Km away after
crossing which it emerges onto the plains of the Punjab. The Satluj crosses
the Great Himalayas at a point where the range bifurcates. At Rampur, it
crosses the Dahuladhar range then traverses through a series of
successive Shivalik ranges and the Naina Devi range, where the Bhakra
LUHRI HEP
V-- 5
dam is situated, is the last of the series. Between Suni and Dehar, the river
takes a somewhat north-westerly direction. After Dehar, the river turns in a
south- westerly direction to reach the foot of Naina Devi range. The Naina
Devi range deflects the river again in a north-westerly direction when it
flows parallel to the range for about 32km before cutting through it at
Bhakra gorge.
The principal tributaries of the Satluj below Shipkilla are the Spiti, Kashang,
Baspa, Bhaba, Nogli, Kurpan, Nauti, Sholding, Sorang, Bharari, Ali and
Ghambar khad.
Numerous glaciers large and small drain into the Satluj at various points on
its course. East of Mansarover and feeding its principal source are the
glaciers of the Ganglug Gaungni, the southern glaciers of the Gauglung
Gangni, glaciers of Kailash flow into the Satluj through the lake of Rakas
Tal, The Northern glaciers of peak Kamer also contribute to the streams.
The glaciers of peak Riwa phargul which stands in the Satluj catchment
also flow into it. There are many Himalayan glaciers draining into its
tributaries. The Baspa and many more from the direction of the Bara-Lacha
pass from the watersheds of the Chenab and Beas.
The fall of Satluj from its source to the plains of India is very uniform. The
height of the bed is about 4570m near Rakas-Tal, 2530m near Shipkilla,
915m at Rampur, 416 m at Bilaspur and 350m at the Bhakra Dam site.
The total catchment area of the Satluj above the Bhakra dam site is about
56875 Sq.km (21960 Sq.miles) and above the Luhri diversion site is about
52403 Sq.km (19235 Sq.miles). The river Satluj drains an area of about
50880 Sq.km (196745 Sq.miles) at Rampur discharge site.
A gross fall of 2180m is available in the river bed from Shipkilla to Bhakra in
LUHRI HEP
V-- 6
an length of about 320 Km. The valley is narrow in the portion from
Shipkilla to Pooh and from Thopan to Rampur. In the portion between Pooh
to Thopan and Rampur to Bhakra the valley is comparatively wider. It is
widest in the portion immediately upstream of Bhakra.
The bed slope of river is flat from Shipkilla to Jangi dam site for a distance
of about 43 km, which is of the order of 1 in 175. It becomes steep
between Jangi Dam site and Rampur, the slope being 1 in 87 and is again
flatter from Rampur to Kol Dam site with a slope of 1 in 300. It is the flattest
in the Bhakra reservoir area, the portion down stream of the Kol Dam,
where the bed slope is 1 in 500.
5.4 HYDROMETEOROLOGICAL ASPECTS 5.4.1 General
The climatic conditions of the Satluj River basin are strongly influenced by
orthographic effects. Elevation 1525 m is the approximate boundary
between areas receiving the majority of precipitation in the form of rain and
those receiving mostly snow.
The catchment in Tibet receives practically no rainfall and precipitation is
mostly in the form of snow. No meteorological data for this catchment is
available for the present study. No precipitation observation is available for
Spiti Valley for this study. Observations at six precipitation station i.e.
Purbani, Kalpa, Sangla, Nichar and Rampur are being carried out in the
catchment in Distt. Kinnaur.
These observations, rainfall since long and snowfall introduced only
recently, are being conducted in a conventional manner. There is no self-
recording rain gauge/snow gauge station in the catchment up to Shongtong
LUHRI HEP
V-- 7
Barrage. There are in all twenty rain gauge stations in the catchment up
to Bhakra Dam site at which long term records are available.
5.4.2 Precipitation
The project catchment receives precipitation due to the South-West
monsoon as well as due to the western disturbances that pass over the
north-west part of the country during winter. On the basis of information
gathered from the different sources, it may be said that South-West
monsoon generally lasts from June to September but may occasionally
extend up to early October. Precipitation during this period which falls as
rain is generally not heavy but at times may contribute significantly towards
flood runoff. The winter precipitation falls either as rain or snow depending
upon altitude and other meteorological conditions and may be very heavy
on occasions but may not contribute directly to river discharge significantly
and mostly goes to feed the snow glacier bound areas of the catchment.
The number and distribution of rain/snow gauges is too small and
scattered to give any quantitative information regarding rain or snow that
occur over different parts of the year over the catchment.
5.4.3 Record of Precipitation
There are at present twenty rain gauge stations in the catchment of Satluj
River upstream of Bhakra, at which long term records are available. The
relevant details of these stations are given in the following table.
LUHRI HEP
V-- 8
TABLE
DETAILS OF RAINGAUGE STATIONS
Sr.No. Name of Station Year of Altitude Average Rainfall
Commencement (m) (mm)
1 Bilaspur (Sadar) 1954 580.25 1103.80
2 Bilaspur (Obs) 1957 587.03 1226
3 Ghumarwin 1958 637 1215.40
4 Arki 1951 1219.20 1228.00