22
LT113393

LT113393 - Pepro LLC

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: LT113393 - Pepro LLC

LT­11­3393

Page 2: LT113393 - Pepro LLC

TEST REPORT:LIGHTNING DIRECT EFFECTS TESTSON SHIELDED SHELTER ENCLOSURESReport by: Approved by:

K. E. Crouch M. M Dargi

For

PEPRO, LLC 671 Colbert Ave. Oil City, PA 16301

Purchase Order No. 4097

Tests by: Witnessed by:

K. Crouch Victor Garmong D. Deblois Kelly Lander P. Saldo Terry Ausel

Adam Felmlee Gerardo Ruiz Tom O’Neil (PEPRO)

Test dates: References:

31 January 2011 DB: 361, pp. 5­8 1­3 February 2011

3 March 2011

Lightning Technologies, Inc. 10 Downing Industrial Parkway Pittsfield, MA 01201­3890U.S.A.

Page 3: LT113393 - Pepro LLC

Lightning Technologies, Inc. Test Report LT­11­3393, Rev. (­) 10 Downing Industrial Parkway 3 March 2011                           

Page 4: LT113393 - Pepro LLC

Pittsfield, MA 01201­3890 Page ii of iv

TABLE OF CONTENTS

SECTION NO. PAGE NO.

1.0 INTRODUCTION .................................................................................................. 1

2.0 BACKGROUND .................................................................................................... 1

3.0 SUMMARY ........................................................................................................... 1

4.0 TEST ARTICLES .................................................................................................. 2

5.0 TEST EQUIPMENT .............................................................................................. 5

6.0 TEST REQUIREMENTS ...................................................................................... 6

6.1 Lightning Test Levels ................................................................................. 6 6.2 Shielded             Shelter Enclosure Grounding Means .......................................... 6 6.3 Isolated Test               Generator Current Returns ................................................... 6

7.0 TEST SETUP AND PROCEDURES ..................................................................... 6

8.0 TEST RESULTS ................................................................................................... 8

8.1 High Voltage Tests .................................................................................... 8 8.2 HighCurrent Tests ..................................................................................... 9

9.0 DISCUSSION OF RESULTS ................................................................................ 8

9.1 Walk­in Shelter .......................................................................................... 8 9.1.1 High           Voltage Tests ....................................................................... 8 9.1.2 High Current Tests             ....................................................................... 9

9.2 Mobile Shelter ............................................................................................ 9 9.2.1 High           Voltage Tests ....................................................................... 9 9.2.2 High Current Tests             ....................................................................... 9

9.3 Micro Shelter .............................................................................................. 9 9.3.1 High           Voltage Tests ....................................................................... 9 9.3.2 High Current Tests             ..................................................................... 10

Appendix A – Raw Data Oscillograms .............................................................. A­1 – A­21

Page 5: LT113393 - Pepro LLC

Lightning Technologies, Inc. Test Report LT­11­3393, Rev. (­) 10 Downing Industrial Parkway 3 March 2011                           

Page 6: LT113393 - Pepro LLC

Pittsfield, MA 01201­3890 Page iii of iv

LIST OF TABLES

TABLE NO. PAGE NO.

Table 1 – Radio and Antenna Cable Equipment ............................................................. 4

Table 2 – Calibrated Equipment ...................................................................................... 5

Table 3 – High Voltage Test Results ............................................................................. 10

Table 4 – High Current Test Results ............................................................................. 11

LIST OF FIGURES

FIGURE NO. PAGE NO.

Figure 1 – SMRS 650 Voltage and Current Configuration ............................................... 2

Figure 2 – FDRS 6 x 6 Voltage and Current Configuration ............................................. 3

Figure 3 – CLP1­Mini Site Voltage and Current Configuration ........................................ 4

Figure 4 – Typical Applied High Voltage Test Oscillogram, Vpk

=1,300 kV, Chop Time = 8 μs........................................................................................ 12

Figure 5 – Typical Flat Line and Oscillatory Measurement Response, Test No. 3 ........ 12

Figure 6 – Typical High Current Test Oscillogram, Ipk

= 89 kA, Test No. 11 .................. 17

Figure 7 – Walk­in Shelter Positioned in High Voltage Test Area ................................. 13

Figure 8 – Walk­in Shelter Setup Showing Gap between Electrode and Antenna ........ 13

Figure 9 – High Voltage Strike Attachment to Walk­in Shelter ...................................... 14

Figure 10 – Typical High Current Measurement Response, Test No. 11, 88 kA ........... 17

Figure 11 – Typical High Current Measurement Response, Test No. 18, 76 kA ........... 18

Figure 12 – High Current Injection Test Setup for Walk­in Shelter ................................ 18

Figure 13 – Antenna High Current Injection Point (Similar for all Shelter Tests) ........... 19

Figure 14 – Mobile Shelter Positioned in High Voltage Test Area ................................. 14

Page 7: LT113393 - Pepro LLC

Lightning Technologies, Inc. Test Report LT­11­3393, Rev. (­) 10 Downing Industrial Parkway 3 March 2011                           

Page 8: LT113393 - Pepro LLC

Pittsfield, MA 01201­3890 Page iv of iv

LIST OF FIGURES

FIGURE NO. PAGE NO.

Figure 15 – High Voltage Strike Attachment to Mobile Shelter ...................................... 15

Figure 16 – High Voltage Strike Attachment to Isolated Mobile Shelter ........................ 15

Figure 17 – High Current Injection Test Setup for Mobile Shelter ................................. 19

Figure 18 – High Current Injection Test on Mobile Shelter ............................................ 20

Figure 19 – Micro Shelter Positioned in High Voltage Test Area ................................... 16

Figure 20 – High Voltage Strike Attachment to Micro Shelter ....................................... 16

Figure 21 – High Current Injection Test on Micro Shelter, Test No. 14, 70.5 kA ........... 20

Page 9: LT113393 - Pepro LLC

Lightning Technologies, Inc. Test Report LT­11­3393, Rev. (­) 10 Downing Industrial Parkway 3 March 2011                           

Page 10: LT113393 - Pepro LLC

Pittsfield, MA 01201­3890 Page 1 of 20

1.0 INTRODUCTION

Lightning direct effects tests were performed on shelter enclosures (Faraday cage                   design) to demonstrate their ability to tolerate lightning strikes to the shelter without                       damage to the radio equipment. The shelter enclosures tested represented the range of                       enclosure sizes presently deployed. The test results contained in this report relate only to                         the test items/part numbers tested.

Tests were performed by K. Crouch, D. DeBlois and P. Saldo of Lightning                       Technologies, Inc. (LTI) in Pittsfield, MA during the period of 31 January to 3 February                           2011. Testing was conducted in accordance with LTI Test Procedure LT­TP­11­437 (Ref.                     1). Changes were made during the tests and are outlined in this document. The systems                           were operated, monitored and witnessed by Victor Garmong, Adam Felmlee, Gerardo                   Ruiz, Terry Ausel, Kelly Lander and Tom O’Neil of PEPRO, LLC.

2.0 Background

When radio equipment shelters are installed in field locations, lightning strikes                   attach to the radio antennas injecting high voltages and currents into the radio antenna                         tower and the antenna cables.

During a natural lightning strike event, the high voltage attachment portion of the strike                         connects the lightning channel to the shelter. After attachment, the high current portion of                         the strike is injected into the shelter. During the simulated lightning tests, a high voltage test                             generator was used to make the attachment. A high current generator was then connected                         to the attachment point and discharged to deliver a high current discharge.

For those installations where the shelters can be powered from electric utility                     transmission lines, lightning strikes can also attach to the utility lines injecting high voltages                         and/or currents into the radio power supply. The power surge suppressors used in the                         shelters have been designed and certified to the requirements of IEEE C62.42­1991,                     Table 4, Category C3. No tests were applied to the power line suppressors

3.0 SUMMARY

High voltage lightning strike attachment tests were applied to the shelters using a                       1.2 x 50 μs waveform at a 1,300 kV peak level. High current conducted entry tests were                               applied to the shelter using a 25 x 60 μs waveform with levels from 75 to 90 kA.

Portable radios transmitted and received a signal (tone) to and from the shelterduring the tests. The radios operated between and after all tests. The continued operationof the radios met the survivability requirements of this test program. ________Ref. 1 Lightning Technologies, Inc. Test Procedure LT­TP­11­437, Lightning Direct Strike Tests on

Page 11: LT113393 - Pepro LLC

Shielded Shelter Enclosures, Rev. ­, K. E. Crouch, 31 January 2011

Page 12: LT113393 - Pepro LLC

Lightning Technologies, Inc. Test Report LT­11­3393, Rev. (­) 10 Downing Industrial Parkway 3 March 2011                           

Page 13: LT113393 - Pepro LLC

Pittsfield, MA 01201­3890 Page 2 of 20

Energy delivered to a 50 Ω resistor at the location where the antenna cable entered                           the radio did not exceed 10 μJ. Antenna cable shield currents monitored at the radio                           entrance did not exceed 40 A peak and 25 μs durations. Voltage measurements made                         between an internal equipment rack and the shelter wall ground point did not exceed 50 V                             and 25 μs durations during high voltage tests. Measurements made during the high current                         tests did not exceed 5 volts and 80 μs durations. Measurements made on the ac power                             line exhibited voltage clamp levels typical of suppressors installed on 240 volt power lines.                         These measurements were all very similar and did not yield any unexpected levels.

4.0 TEST ARTICLES

The test items supplied by and operated by PEPRO, LLC personnel included a                       Mobile Shelter (SMRS 650), a Walk­in Shelter (FDRS 6 x 6) and a Micro Shelter (CLP1­                             Mini Site). Pictures and descriptions of the test items are given in Figures 1 through 3 and                               Table 1. Limits on the size of the high voltage and high current test areas prevented testing                               the enclosures with the antenna towers fully raised. The following pictures show the test                         articles as configured for both high voltage and high current tests.

Figure 1 – Mobile Shelter (SMRS 650)

Page 14: LT113393 - Pepro LLC

Lightning Technologies, Inc. Test Report LT­11­3393, Rev. (­) 10 Downing Industrial Parkway 3 March 2011                           

Page 15: LT113393 - Pepro LLC

Pittsfield, MA 01201­3890 Page 3 of 20

Top View

Figure 2 – Walk­in Shelter (FDRS 6 x 6)

Side View

Page 16: LT113393 - Pepro LLC

Lightning Technologies, Inc. Test Report LT­11­3393, Rev. (­) 10 Downing Industrial Parkway 3 March 2011                           

Page 17: LT113393 - Pepro LLC

Pittsfield, MA 01201­3890 Page 4 of 20

Top View

Figure 3 – Micro Shelter (CLP1­Mini Site)

Table 1 – Radio and Antenna Cable EquipmentManufacturer Equipment Model No. Serial No. Shelter Channel

Motorola Quantar

680CYB0021 SMRS 650 8TAC92 T5365A

301CZF0007 CLP1­Mini Site 8TAC93

T5367A 360CCM0033 FDRS 6x6 8TAC94

Side View

Page 18: LT113393 - Pepro LLC

Lightning Technologies, Inc. Test Report LT­11­3393, Rev. (­) 10 Downing Industrial Parkway 3 March 2011                           

Page 19: LT113393 - Pepro LLC

Pittsfield, MA 01201­3890 Page 5 of 20

5.0 Test Equipment

Table 2 provides a list of calibrated equipment used during these tests. All                       measurement equipment furnished by Lightning Technologies, Inc. is calibrated by a                   commercial calibration agency in accordance with the requirements of the second edition                     of ISO/IEC 17025:2005, General Requirements for the Competence of Testing and                   Calibration Laboratories, and/or ANSI/NCSL Z540­1­1994, Calibration Laboratories and             Measuring and Test Equipment­General Requirements, using standards traceable to the                 National Institute of Standards and Technology.

Table 2 – Calibrated EquipmentManufacturer Equipment Model No. Serial No.

Calibration

Date Due Date

High Voltage Tests

Tektronix Oscilloscope

DP04034 C021222 26 Mar 10 26 Mar 11

TDS3034B

C010791 22 Dec 10 22 Dec 11

B027504 21 Jan 11 21 Jan 12

Haefely Voltage Divider CR2400­350

05101161.12.1­ 12.2 05101161.20.1

22 June 06 22 June 11

Pearson Current Probe 4160

080861 13 Jul 10 13 Jul 11

080862 4 Aug 10 4 Aug 11

80134 20 May 10 20 May 11

High Current Tests

Tektronix Oscilloscope

B033378 20 Oct 10 20 Oct 11 TDS3032B

B015906 6 Aug 10 6 Aug 11

TDS3034B

B027504 21 Jan 11 21 Jan 12

C010791 22 Dec 10 22 Dec 11

Pearson

Page 20: LT113393 - Pepro LLC

Attenuator A10 099671 15 Jul 10 15 Jul 11

Current Probe

1423 099639 18 Nov 10 18 Nov 11

4160

80134 20 May 10 20 May 11

80861 13 Jul 10 13 Jul 11

T&M Research

Current Viewing

F­1000­4 0410­28 14 Oct 10 14 Oct 11

Resistor

W­2­01­4S 8303­10 14 Oct 10 14 Oct 11

Page 21: LT113393 - Pepro LLC

Lightning Technologies, Inc. Test Report LT­11­3393, Rev. (­) 10 Downing Industrial Parkway 3 March 2011                           

Page 22: LT113393 - Pepro LLC

Pittsfield, MA 01201­3890 Page 6 of 20

6.0 TEST REQUIREMENTS

6.1 Lightning Test Levels

The high voltage transients were applied with a 1.2 x 50 μs waveform in the positivepolarity at 1,300 kV. This was sufficient to arc across a nominal 3 meter gap.

The high current test waveform and current level was applied with a nominal 25 x 60                             μs waveform, in the positive polarity at current levels of 68 kA to 89 kA. Current waveforms                               and amplitudes varied as a function of test article impedance (inductance and resistance).                       These current levels were the maximum currents that the generator could supply to the test                           article impedances.

6.2 Shielded Shelter Enclosure Grounding Means

Encasement of rebar in concrete is used as a grounding electrode when fabricated                       in accordance with the NFPA 70: NEC2005, Article 250, Paragraph 250.52, Grounding                     Electrodes (A) Electrodes Permitted for Grounding, (3) Concrete­Encased Electrode.

Concrete pads were installed on the SSE units for all tests. The concrete pads were                           included for informational purposes. Failure of the pads did not constitute a failure of the                           shelter.

6.3 Isolated Test Generator Current Returns

The voltage between a shelter and the earth depends on the resistivity of the soil                           and the grounding materials buried in the soil. On mountaintops where the shelter may be                           installed, the soil may be very rocky which results in a very high soil resistivity. In some of                                 these sites, the lightning surge arcs through the soil as it exits from the shelter. To verify that                                 Faraday Cage designs can protect the radio equipment in these situations, tests were                       conducted with the shelter isolated which allowed the strikes to arc to the ground plane.

There are many considerations that must be taken into account in designing                     grounding for a facility. The tests described herein used isolation as a worst­case situation                         but that does not mean that ungrounded structures are advocated.

7.0 TEST SETUP AND PROCEDURES

The shelters were subjected to simulated lightning tests to determine the ability of                       the shelter to prevent damage to electrical and/or electronic radio equipment contained in                       the shelter. High voltage attachment tests were applied to the shelters and high current                         tests were injected into the antenna attachment point of the shelter.