LSC – EN-MEF-OSS 1
LS1 Status @ Injectors
K. Foraz on behalf of N. Gilbert, S. Mataguez, D. Hay & D. McFarlane
LSC 24th May2013
24/05/2013
LSC – D. Hay 2
ENPSB (1/4)
24/05/2013
The clean up campaign to remove surface & underground cables is now completed.
Installation of the underground cables is estimated to be at ~8% completion.
Cable continuity and Burndy connector tests for the Multipole power converters are ongoing.
On site preparations for the beam dump replacement project are ongoing.
Installation of electrical power sockets. Clean up campaign in the Booster basement (BTM/BTY beam
element storage).
The new PAD access control system is now fully operational. PAD functional tests successfully completed. Biometric access will commence on Monday 27th May. Installation of the D31 MAD is in progress.
Burndy conncetors
New access system
LSC – D. Hay 3
ENPSB (2/4)
24/05/2013
Replacement of the PSB lift AS-45 has started (the lift is no longer operational). The special lifting support device for the removal of the lift
motor and ancillary electrical equipment is under construction (EN-HE T.Foreste).
Works access SAS’s are currently being installed at each floor level.
Material access to the Booster’s radiation controlled areas will be via the tremie in 361 supervised by the transport and RP services. During the works, access to the booster complex will be
redirected via the BHP hall as indicated.
Lifting support installation
Access to PSB
LSC – D. Hay 4
ENPSB (3/4)
24/05/2013
2013
2014
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
2013
2014
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
PSB Hall PSB Tunnel
MAGNET TESTS
TESTS MULTIP. CONV.
General maintenance
General maintenance
Survey
MagnetsCables
Cables
LIFT
RE
PLAC
EMEN
T
MU
LTIP
. CO
NV.
TE-A
BT
Survey
Hardware commissioning and cold check out
CV
SETUP WITH BEAM
VACU
UM
RF
EN-S
TI
BE-B
I & C
O
BE-B
I & C
O
ACCE
SS
COMMISSIONING NEW ACCESS SYSTEM
Beam back from L2 to PSB 30/05/2014Beam back from PSB to PS 20/06/2014
Beam Off : 11/02/2013
CV
Survey Magnets Cable Lift &
crane CV Vacuum RF BI & CO Access EPCPowerin
gTests
Collimation (STI)
KickersSepta
LSC – D. Hay 5
ENPSB (4/4)
24/05/2013
50 52 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50
Forecast
2.8
5.2
6.4
6.6
6.6
7.2
9.4
13.4
17.2
20 23.6
24.2
27.4
28.8
31.6
33.8
36.6
37.6
42 44.8
46.8
51 54.4
58.4
61.6
64.2
65.8
69.2
72 72.6
74.6
74.8
76.6
78.6
79.8
80.4
81.2
81.6
85.2
86.2
88 88 88 88 NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
Actual
2.8
5.2
6.4
6.6
6.6
7.2
9.4
13.4
17.2
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
5
15
25
35
45
55
65
75
85
95
Progress curve - PSB machine - week 21 (21/05/2013)
Prog
ress
(For
ecas
t vs A
ctua
l)
LSC – S. Mataguez 6
ENCPS (1/5)
24/05/2013
PS Tune Strip-line BPM in SS72 has been installed and aligned.
Route Goward shielding improvement program is advance, the Septum 16 External Shielding program is on study how to start 1 month earlier.
Main magnets HV tests are completed How many Main Magnets need to be refurbished?
PS Tune Strip-line
Goward road
S. Mataguez 7
ENCPS (2/5)
24/05/2013
• CV Consolidation program is on-going.– Removal of asbestos:
• HVAC TR 6 & 8 and galleries 1&3 completed (galleries 1&3 are accessible)• HVAC TR 1 & 3 and galleries 5 & 7 in progress (40%)
– Mechanical dismantling of HVAC TR 5 just started (10%)– Civil engineering activity
• HVAC TR 6 & 8 is completed• chimney 6 & 8 just started
• The 10 MHz Coarse Tuning Groups of Two 10 MHz Cavities is completedTest will be done before the water station stopped (31/05)
• PS PSS Safety and Access System Installation: – The access via Door 101 is not possible from 01/04 to 20/06– The access via Door 111 is not possible from 21/05 to 24/06
• General Maintenance of the Kickers system is on-going.
HVAC5 mechanical dismantling
Door 111 is out of service !
LSC – S. Mataguez 8
ENCPS (3/5)
24/05/2013
• Forecast– Sector PR90 will be venting in order to remove PR.BWS85 for re-
calibration and to remove the tuner of the 80MHz cavity
– Removal of SMH16 & SMH42
– Dismantling of cranes PR06 & PR20
– Start of the refurbishment of the piping of the chilled water circuit (no chilled water in PS, L2, L3)
LSC – S. Mataguez 9
EN
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
2013
2014
PS Surface
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
S1
2013
2014
Oct1(SS01-SS13)
102121
Oct2(SS14-SS26)S2 122
SYOct3
(SS27-SS39)S3 SY104
Oct4(SS40-SS51)S4 117
SYOct5
(SS52-SS64)S5 Oct6(SS65-SS76)S6 111 S7 Oct7
(SS77-SS90)112 Oct8
(SS91-SS100)S8 TT2 Line101 CRG7G5G3G1
CPS (4/5)
24/05/2013
Magnet
Civil engineering
Access CVVentil
CV water
Septa (SE)
Kickers
Collimation (STI)
Vacuum Cable EL
(pow.)Lift & crane
Powering
TestsRF Contro
lEPCFire
detection
Survey
Beam instrumenta
tion
RF
CE
CE
CE
R.Goward
Lift B269
Maintenance Sealing
Powering tests
EPC
Magnet tests
Magnet tests
MU14 MU55\57 MU75
SS15 Liberate
CE
PS PSS complex new access system commissioning
Sept.16
HVAC
HVAC
HVAC
HVAC
HVAC
HVAC
HVAC
HVAC
HVAC
HVAC
HVAC
HVAC
HVAC
CV water
SMH16
SEH23Dummy
SMH42
SMH57
STP
STP
Vacuum bake-outs
STP
STP
STP
EL
RF
RF
RF
RF
RF
RF RF
RF
10/07
01/05
Physics
PS Setup with BeamPS Operations Cold Check-out
Control
DSO tests
Ready for extraction 10/07/14
LSC – D. Hay 10
EN
50 52 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50
Forecast
2.8
5.2
6.4
6.6
6.6
7.2
9.4
13.4
17.2
20 23.6
24.2
27.4
28.8
31.6
33.8
36.6
37.6
42 44.8
46.8
51 54.4
58.4
61.6
64.2
65.8
69.2
72 72.6
74.6
74.8
76.6
78.6
79.8
80.4
81.2
81.6
85.2
86.2
88 88 88 88 NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
Actual
2.8
5.2
6.4
6.6
6.6
7.2
9.4
13.4
17.2
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
5
15
25
35
45
55
65
75
85
95
Progress curve - PSB machine - week 21 (21/05/2013)
Prog
ress
(For
ecas
t vs A
ctua
l)CPS (5/5)
24/05/2013
LSC – D. McFarlane 11
ENSPS (1/3)
24/05/2013
• Preparation works for the Civil engineering works in TT10 have begun.– Vacuum chambers have been removed from the work area– Magnets are in the process of being removed
• EL cable campaigns are slightly ahead of schedule.– EL are currently working in BA1 (surface, shaft and 1-), BA3 and BA5– EL will be starting at BA4 next week (1 month ahead of schedule)
• The remaining 17 magnets that need to be changed (identified during the magnet tests in March) are now scheduled to be change during the 1st 2 weeks of June.
• The vertical realignment of sextant 6 is progressing well. (on schedule)
• CV will be replacing the main isolating– (starting in June) as a result the main SPS ring main will be drained from the
17th June until the 30th August. While the ring main is drained there will be no water in the fire hydrants. In order for the fire brigade to still have access to fire water at each point in the event of an emergency they are in the process of installing large water reservoirs at each point.
Water reservoir in BA1
TT10 line –dismantled
Cabling campaign in SPS
LSC – D. Hay 13
ENSPS (3/3)
24/05/2013
50 52 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50
Forecast
0 0 0 0 0 1.875
3.125
6.5
10.8125
13.8125
18.0625
23.875
25.625
27.6875
32.875
35.5625
37.3125
40.9375
43.625
48.5
49.625
52.625
53.1875
54.6875
58.375
62.0625
63.875
65.6875
66.875
69.9375
70.5
72.3125
76.3125
76.875
79 80.1875
81.375
86.375
90.75
93.875
94.0625
94.25
94.4375
96.5
97.3125
97.5
99.375
100
100
100
100
100
Actual
0 0 0 0 0 1.875
3.125
6.4375
10.125
12.1875
15.8125
20.6875
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
NaN
5
15
25
35
45
55
65
75
85
95
Progress curve - machine SPS - 24/05/2013
Prog
ress
(For
ecas
t vs A
ctua
l)
LSC – N. Gilbert 14
ENAD (1/2)
24/05/2013
• Buffer zone equipped with access system. TREC system installation is progress
• Vacuum:– maintenance is progressing well– Girder line 7000: : 3D layout finalized. Vacuum team now takes over for the
manufacturing of the connection elements
• Electrical activities are progressing well
• BNH06 removal - delays in coil manufacturing – 1st coil manufactured by the end of this month
• Renewal stoch. cooling power supply : commissioning could not be
completed (foreseen by the end of this month)
• Concern : cooling water is needed for the bake-outs, but a solution looks possible (discussion with EN/CV on 23/05) ! Discussions to be continued with EN/CV.
AD buffer zone
Power supply of stoch. cooling
LSC – N. Gilbert 16
ENLEIR (1/2)
24/05/2013
• Buffer zone at the Linac is progressing well. (will be shared with LEIR)
• Reshuffling shielding blocks for new access point was
completed 2 weeks ago. • Scheduling and organizing of future bake-out (sectors 1, 2
and 5) in progress– Concerns with the chilled water availability