LS1 Days
Report from Vacuum, Surfacesand Coatings (VSC) group
Technology Department (TE)
José Miguel JIMENEZ
J.M. Jimenez, 12 June’12 TE-VSC
TE-VSC 2
Main topics
• LS1 coordination
• TE-VSC Plan Items• Implications for TE-VSC• Impacts to other Groups
• TE-VSC Group contributions
• Resource status
• Closing remarks
J.M. Jimenez, 12 June’12
LS1 CoordinationTE-VSC Structure (June’12)
Vacuum, Surfaces and Coatings
José Miguel JIMENEZGroup Leader
Paolo CHIGGIATODeputy Group Leader
Injectors & Vacuum Measurement Section
[IVM]
Section LeaderPaolo CHIGGIATO
Engineers & PhysicistsG. VANDONI
J.A. FERREIRAR. KERSEVAN
Technical EngineersJ. HANSEN
B. JENNINGERS. MEUNIERI. WEVERS
TechniciansA. BRUTON
J. CAVEC. COLLOMB PATTON
P. DEMARESTA. HARRISONJ. KORTESMAA
P. LANCONA. MICHET
A. MONGELLUZZOA. SINTUREL
N. THAUS
LHC Beam VacuumSection
[LBV]
Section LeaderVincent BAGLIN
Engineers & PhysicistsG. BREGLIOZZI
G. LANZA
Technical EngineersG. CATTENOZB. HENRIST
E. PAGEG. SCHNEIDER
TechniciansD. CALEGARIJ. FINELLE
J. GALLAGHERA. MARRAFFA
A. VIDALN. ZELKO
Engineering & Insulation Vacuum
Section[EIV]
Section LeaderPaul CRUIKSHANK
Engineers & PhysicistsM. GALLILEEC. GARION
N. KOSCP E TE-VSC-EIV-2011-277
Technical EngineersP. LEPEULEW. MAAN
TechniciansJ. CHAURE
P. COLYH. KOS
L. MOURIERE. PAJU
H. RAMBEAU
Interlocks, Controls & Monitoring Section
[ICM]
Section LeaderPaulo GOMES
Engineers & PhysicistsG. PIGNY
Technical EngineersF. ANTONIOTTIS. BLANCHARD
H. VESTERGARD
TechniciansD. ANDEREGGF. BELLORINIG. GIRARDOT
B. RIO
Surfaces, Chemistry & Coatings
[SCC]
Section LeaderMauro TABORELLI
Engineers & PhysicistsL. ANTUNES FERREIRA
S. CALATRONIP. COSTA PINTO
S. ILIEA. SUBLET
Technical EngineersC. CHARVET
M. MALABAILAH. NEUPERT
W. VOLLENBERG
TechniciansJ. CAROSONE
D. LETANT-DELRIEUXS. FOREL
P. GARRITTYL. LEGGIERO
B. TEISSANDIERM. THIEBERT
CP C TE-VSC-SCC-2011-278CP C Surface treatments
[Sep'12]CP C Surface treatments
[Sep'12]
TE-VSC 4
LS1 CoordinationName of Contact Persons in TE-VSC
Vacuum, Surfaces and Coatings (VSC)Technology Department (TE)
José Miguel JIMENEZ (GL)[16 0763]Paolo CHIGGIATO (DGL) [16 3689]
Injectors & Associated
Experimental Areas
All activities related to
maintenance, consolidations and upgrades
José ANTONIO FERREIRA[16 9183]
Paolo CHIGGIATO (SL)
[16 3689]
LHCBeam and Insulation Vacuum
Beam Vacuum
Consolidation and upgrade of beam vacuum systems and support to
equipment owners
Vincent BAGLIN (SL)
[16 4287]
Giuseppe BREGLIOZZI
[16 2517]
Insulation Vacuum
Warm-ups, leak detections & pump downs
Paul CRUIKSHANK
(SL)[16 0756]
(Fellow)[16 XXYY]
Insulation Vacuum
Consolidations following 3-4,
PIMs and Splices train
Cédric GARION[16 5257]
(Staff position)[16 XXYY]
Experimental Areas
Consolidation and upgrade of
experimental beampipes
Mark GALILLEE[16 9509]
Cédric GARION[16 5257]
Surfaces, Chemistry &
Coatings Supports
All activities of support to
surface treatments, coatings and
chemistry analysis
Mauro TABORELLI (SL)
[16 3890]
CoatingsSergio
CALATRONI[16 3613]
ChemistryBenoit
TESSANDIER[7 8822 ]
Surfaces treatments
Marina MALABAILA
[16 4814]
Vacuum Controls
Industrial Controls and
Supervision tools
Paulo GOMES (SL)
[16 3982]
Hardware and Cables
Gregory PIGNY[16 9526]
J.M. Jimenez, 12 June’12
TE-VSC 5
TE-VSC Plan itemsImplications for TE-VSC (1/2)• 161 Plan Items entered (2012-06-09 @ 21:54)
– 17 need ECRs #Items %• P0 14 8.7• P1 61 37.9• P2 40 24.8• P3 42 26.1• P4 4 2.5
P0+P1+P2 represent 71%of the requests
LHC represents 50% of the requests
• Status in plan.cern.ch– 91 involve only TE-VSC– 70 require support from other
groups
J.M. Jimenez, 12 June’12
Count of StatusAccelerator Priority Total
AD P2 2P3 3
AD Total 5HIE-ISOLDE P3 5
HIE-ISOLDE Total 5LEIR P2 2
LEIR Total 2LHC P0 10
P1 42P2 17P3 15
LHC Total 84LINAC P1 4
P2 2P3 5
LINAC Total 11PS P1 5
P2 5P3 4P4 1
PS Total 15PSB P2 4
P3 1P4 1
PSB Total 6SPS P0 4
P1 10P2 8P3 9P4 2
SPS Total 33Grand Total 161
Count of StatusPriority Accelerator Total
P0 LHC 10SPS 4
P0 Total 14P1 LHC 42
LINAC 4PS 5SPS 10
P1 Total 61P2 AD 2
LEIR 2LHC 17LINAC 2PS 5PSB 4SPS 8
P2 Total 40P3 AD 3
HIE-ISOLDE 5LHC 15LINAC 5PS 4PSB 1SPS 9
P3 Total 42P4 PS 1
PSB 1SPS 2
P4 Total 4Grand Total 161
TE-VSC 6
TE-VSC Plan itemsImplications for TE-VSC (2/2)• Manpower
– 50 FTEs required (TE-VSC) #FTE %• P0 8.7 17.9• P1 22.2 45.5• P2 8.0 16.5• P3 9.1 18.8• P4 0.6 1.3
P0+P1+P2 represent 80% of theTE-VSC Manpower
LHC represent 40% of the TE-VSC Manpower
J.M. Jimenez, 12 June’12
Sum of FTEAccelerator Priority Total
AD P2 1.8P3 0.2
AD Total 1.9HIE-ISOLDE P3 0.0
HIE-ISOLDE Total 0.0LEIR P2 0.2
LEIR Total 0.2LHC P0 8.3
P1 19.3P2 4.4P3 6.6
LHC Total 38.6LINAC P1 0.4
P2 0.2P3 0.3
LINAC Total 0.9PS P1 0.8
P2 0.4P3 1.1P4 0.3
PS Total 2.6PSB P2 0.3
P3 0.0P4 0.3
PSB Total 0.5SPS P0 0.4
P1 1.7P2 0.8P3 1.0P4 0.1
SPS Total 4.0Grand Total 48.7
Sum of FTEPriority Accelerator Total
P0 LHC 8.3SPS 0.4
P0 Total 8.7P1 LHC 19.3
LINAC 0.4PS 0.8SPS 1.7
P1 Total 22.2P2 AD 1.8
LEIR 0.2LHC 4.4LINAC 0.2PS 0.4PSB 0.3SPS 0.8
P2 Total 8.0P3 AD 0.2
HIE-ISOLDE 0.0LHC 6.6LINAC 0.3PS 1.1PSB 0.0SPS 1.0
P3 Total 9.1P4 PS 0.3
PSB 0.3SPS 0.1
P4 Total 0.6Grand Total 48.7
TE-VSC 7
TE-VSC Plan itemsImpact to other groups• 161 Plan Items entered (2012-06-09 @ 21:54)
– 70 need support from other groups #Items %• P0 Total 4 5.7• P1 Total 31 44.3• P2 Total 17 24.3• P3 Total 16 22.9• P4 Total 2 2.9
– 10 Groups are asked to support TE-VSC #Items %
• EN-EL 40 42.6• BE-ABP 13 13.8• EN-MME 13 13.8• EN-HE 12 12.8• TE-MSC 4 4.3• DGS-RP 4 4.3• EN-MEF 3 3.2• TE-CRG 2 2.1• EN-CV 2 2.1• BE-BI 1 1.1
• Status in plan.cern.ch– 3 “Yes” completed– 5 “pending”– 62 “Not filled”
J.M. Jimenez, 12 June’12
Count of StatusAccelerator Priority Total
AD P2 1P3 1
AD Total 2HIE-ISOLDE P3 3
HIE-ISOLDE Total 3LHC P0 2
P1 21P2 7P3 4
LHC Total 34LINAC P1 2
P2 1P3 2
LINAC Total 5PS P1 3
P2 3P3 2
PS Total 8PSB P2 2
PSB Total 2SPS P0 2
P1 5P2 3P3 4P4 2
SPS Total 16Grand Total 70
Count of StatusPriority Accelerator Total
P0 LHC 2SPS 2
P0 Total 4P1 LHC 21
LINAC 2PS 3SPS 5
P1 Total 31P2 AD 1
LHC 7LINAC 1
PS 3PSB 2SPS 3
P2 Total 17P3 AD 1
HIE-ISOLDE 3LHC 4
LINAC 2PS 2SPS 4
P3 Total 16P4 SPS 2
P4 Total 2Grand Total 70
TE-VSC 8
TE-VSC Plan itemsImpact to other groups: EN-EL case
• 20% (614 cables) correspondto the needs for newprojects
• 16% correspond to P3 34% if cumulated
• Replacement of electrical“reglettes” are counted ascables
J.M. Jimenez, 12 June’12
Accelerator Cable QtyLINAC 61
PSB 200PS 345
SPS 788LHC BV 1053LHC IV 27
L4 108AD 164
HIE-ISOLDE 3423088
Sum of Cables QtyPriority Accelerator Total
P0 LHC BV 577SPS 144
P0 Total 721P1 LHC BV 189
LINAC 56PS 279
PSB 110SPS 196
P1 Total 830P2 AD 132
HIE-ISOLDE 342L4 108
LHC BV 14LHC IV 19
PS 33PSB 43SPS 370
P2 Total 1061P3 AD 32
LHC BV 273LHC IV 8LINAC 5
PS 33PSB 47SPS 78
P3 Total 476Grand Total 3088
Sum of Cables QtyAccelerator Priority Total
AD P2 132P3 32
AD Total 164HIE-ISOLDE P2 342
HIE-ISOLDE Total 342L4 P2 108
L4 Total 108LHC BV P0 577
P1 189P2 14P3 273
LHC BV Total 1053LHC IV P2 19
P3 8LHC IV Total 27
LINAC P1 56P3 5
LINAC Total 61PS P1 279
P2 33P3 33
PS Total 345PSB P1 110
P2 43P3 47
PSB Total 200SPS P0 144
P1 196P2 370P3 78
SPS Total 788Grand Total 3088
Summary by Accelerators
Summary by Accelerators
TE-VSC 9
TE-VSC Group contributions
• 145 Group contributions received (2012-06-09 @ 21:54)
– Ratio by priorities could not be extracted from the tool (important)
– 8 Groups are requesting TE-VSC Support #Items % FTE
• TE-ABT 36 25 3.5• BE-RF 34 23 4.1• BE-BI 28 19 3.2• EN-STI 26 18 2.8• BE-ABP 10 7 1.5• BE-CO 5 3 0.2• TE-MSC 5 3 0.6• TE-CRG 1 1 0.2
• Status in plan.cern.ch– 13 “Not filled” checking with requesters– 32 “pending” more detailed needed to complete the filling– 100 “Yes” completed
• Resources involved– Manpower: 16 FTEs (excluding support at the surface: vacuum acceptance tests)– Material budget required: 0.5 MCHF (outside the current agreements)
J.M. Jimenez, 12 June’12
Accelerator TotalAD 0.4
CTF3 0.0LEIR 0.2LHC 6.0
LINAC 4.8PS 0.8
PSB 0.6SPS 2.6
SURF 0.5Grand Total 16.0
Sum of FTEs
TE-VSC 10
TE-VSC Resource statusManpower availabilities: CERN Staffs & Fellows• 59 VSC Staff deployed in all accelerators from Jan’13 to end March’14
– 15 in the Injectors– 30 in the LHC– 14 for the Surface treatments & Coatings support
Then Injector’s Staff partly redeployed in the LHC activities as from Feb’14
Engineers Technical Technicians& Physicists Engineers– IVM: 2 1 8– LBV 3 4 6– EIV 4 2 6– ICM 2 3 4– SCC 2 2 10
• 5 Fellows– 1 in the Injectors– 4 in the LHC2013 2014– Controls 1 1– LHC BV 2 2– LHC Exp. Areas 1 1– LHC IV 1 1
J.M. Jimenez, 12 June’12
TE-VSC 11
ValuesISFSUPJAS Priority Sum of 2012 Sum of 2013 Sum of 2014
FELL P2 120 120FELL Total 120 120
FSU P0 35P1 68 979 490P2 180 150P3 180 120
FSU Total 68 1,374 760IS P0 15 172 213
P1 456 1,329 797P2 340 519 259P3 53
IS Total 811 2,073 1,269Mat P0 855 1,525
P1 2,972 2,302 488P2 1,877 1,325 530P3 1,466 1,977 750
Mat Total 7,170 7,128 1,768PJAS P0 75 60
P1 151 598 290PJAS Total 151 673 350
Staff P1P3
Staff TotalGrand Total 8,200 11,368 4,267
TE-VSC Resource statusManpower availabilities: IS & Collaborations• 57 External Support is based on:
– 23 AL40-30 mainly for LHC activities: mechanics, venting/pump-downsand bake-out installations
2013 2014• LHC BV 11 11• LHC IV 10 10• Injectors 2 2
– 18 FSUs for all activities: mechanics, controls, surface treatments, logistics andbake-out installations
2013 2014• LHC BV 4 4• LHC PIMs/Exp 2 2• Controls 8 4.5• Surface treat. 3.5+2? 3.5+2?
– 12 Collaboration: vacuum consolidation related to PIMs and Controls
2013 2014• LHC BV 6 (PL) 6 (PL)
1+1? (ES) 1+1? (ES)• Controls 5 (PL) 5 (PL)
– 4 USAS 2013 2014• Portugal 2 1• Spain 2 2
J.M. Jimenez, 12 June’12
Summary by IS/FSU/PJAS
ValuesAccel. Sum of 2012 Sum of 2013 Sum of 2014AD 695 510 265LHC BV 3,223 5,503 1,696LHC IV 1,393 2,522 1,263LINAC 325 363 160PS 638 402 155PSB 258 235 204SPS 1,670 1,834 524Grand Total 8,200 11,368 4,267
TE-VSC 12
ValuesAccel. Priority Sum of 2012 Sum of 2013 Sum of 2014
AD P2 695 435 265P3 75
AD Total 695 510 265LHC BV P0 518 1,528 266
P1 1,556 2,196 786P2 260 100 24P3 888 1,679 620
LHC BV Total 3,223 5,503 1,696LHC IV P0 12 77 6
P1 717 1,541 860P2 532 839 397P3 132 66
LHC IV Total 1,393 2,522 1,263LINAC P1 293 353 150
P3 32 10 10LINAC Total 325 363 160
PS P1 410 167P2 83 140 65P3 145 95 90
PS Total 638 402 155PSB P2 115 95 54
P3 143 140 150PSB Total 258 235 204
SPS P0 340 202P1 671 952 270P2 533 535 254P3 126 145
SPS Total 1,670 1,834 524Grand Total 8,200 11,368 4,267
TE-VSC Resource statusMaterial
J.M. Jimenez, 12 June’12
Summary by AcceleratorsValuesPriority Accel. Sum of 2012 Sum of 2013 Sum of 2014
P0 LHC BV 518 1,528 266LHC IV 12 77 6SPS 340 202
P0 Total 870 1,807 273P1 LHC BV 1,556 2,196 786
LHC IV 717 1,541 860LINAC 293 353 150PS 410 167SPS 671 952 270
P1 Total 3,647 5,208 2,065P2 AD 695 435 265
LHC BV 260 100 24LHC IV 532 839 397PS 83 140 65PSB 115 95 54SPS 533 535 254
P2 Total 2,217 2,143 1,059P3 AD 75
LHC BV 888 1,679 620LHC IV 132 66LINAC 32 10 10PS 145 95 90PSB 143 140 150SPS 126 145
P3 Total 1,466 2,210 870Grand Total 8,200 11,368 4,267
Summary by priorities
Material cost 23.8 MCHF (procurements…) LHC represent 66% P3 represent 19%
TE-VSC 13
Closing remarks (1/3)
• The ideal sequence would be:– For the arcs
• Pre-installation of mobile pumps (sub-sectors with leaks)• Venting to speed up the warming-up• Leak detections• Follow-up of the trains for PIMs & relief valves installation• “independent” schedule for RF ball & rupture disk installations
– For the LSS• Venting and removal of equipment belonging to other groups• TE-VSC consolidations• Installation of equipment (coming back or new)• Pump downs and bake-out installations• Bake-out and NEG activations• Removal of vacuum bake-out and cleaning
J.M. Jimenez, 12 June’12
TE-VSC 14
Closing remarks (2/3)Optimisation of TE-VSC activities…
J.M. Jimenez, 12 June’12
Venting LHC IV
Removing equipment
TE-VSC consolidatio
nsEquipment
backPump down & bake-out
inst.Bake-out & NEC activ.
TE-VSC 15
Closing remarks (3/3)
• TE-VSC was aware of all most relevant activities– Contacts taken since months with Groups so no big surprises
seen in Plan.cern.ch 121 people (59 Staffs + 5 Fellows + 57 External Support) are
required to execute all activities
• Schedule issues in LSS5, 6, 7 and 8– Need a careful preparation with Katy– Material (mobile pumps, bake-out) & co-activities to be analyzed
• Budget issues for P3 activities– TE-VSC to revise the impact of LS1 day decisions– Feedback to EN-EL on impact to the communicated DICs
• Decrease of the number of cables requested
J.M. Jimenez, 12 June’12