LRTP Consistency Review for STIP Amendments and NEPA Approval

  • Upload
    tomas

  • View
    28

  • Download
    0

Embed Size (px)

DESCRIPTION

LRTP Consistency Review for STIP Amendments and NEPA Approval. Office of Policy Planning, FDOT Office of Project Development, FHWA September 10, 2013. Guidance. Purpose: Sets thresholds for project changes that trigger LRTP amendments at: STIP approval STIP amendment NEPA approval - PowerPoint PPT Presentation

Citation preview

Page 1: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

LRTP Consistency Review LRTP Consistency Review for STIP Amendments for STIP Amendments

and NEPA Approvaland NEPA Approval

Office of Policy Planning, FDOTOffice of Project Development, FHWA

September 10, 2013

Page 2: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

GuidanceGuidance Purpose:

• Sets thresholds for project changes that trigger LRTP amendments at: STIP approval STIP amendment NEPA approval Addition or change to plan

Provide• Analytical framework for consistency review

2

Page 3: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

Coordination/CommunicationCoordination/Communication

District Coordination/Communication

REQUIRED

3

Page 4: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

ConsistencyConsistency Project must be consistent with Adopted LRTP

Cost Feasible Plan.

Variables for Review:• Cost

• Timing

• Project Scope

4

Page 5: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

First STEPFirst STEP Clearly identify project within LRTP:

• Whole

• Segment (corridor)

• New

Identification facilitates communication

LRTP

Project

5

Page 6: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

AnalyzeAnalyze

*LRTP Project Δ (Delta)

Identification Cost Timing

Project Scope

* Base document6

Page 7: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

AnalyzeAnalyze

*LRTP Project Δ (Delta)

Identification

Cost

Timing

Project Scope

7* Base document

Page 8: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

AnalyzeAnalyze

*LRTP Project Δ (Delta)

Identification Cost Timing

Project Scope

* Base document8

Page 9: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

Project cost includes:• Phases after PD&E

Design/PE

ROW

Construction

9

Cost

Cost for Determining LRTP AmendmentCost for Determining LRTP Amendment

Page 10: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

Principle: CostPrinciple: Cost Amendment Needed

• Project cost

> 50% AND > $50 million

Ramifications• Change of scope

• Project

justification

10

Cost: Percent increase over original

Cost Increase(millions)

$100

$90

$80

$70

$60

$40

$30

$20

$10

100%90%80%70%60%40%30%20%10%

Amendment Needed

Page 11: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

AnalyzeAnalyze

*LRTP Project Δ (Delta)

Identification Cost Timing Project Scope

* Base document11

Page 12: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

Principle: TimingPrinciple: Timing Automatic LRTP amendment:

• Project added to LRTP 1st 5 years (TIP/STIP years) causes imbalance resulting in project moved out

Automatic modification:• Project/phases: = or < $5 million

LRTP TIP/STIP

Years

Available Funding

Project Costs

12

Automatic amendment:• Full project deleted from

LRTP CFP

Page 13: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

TimingTiming Projects within LRTP displayed in bands of years

• 5 year increments

LRTP

CFP Needs

1st 5-yr band TIP/STIP years

2nd 5-yr band 3rd 5-yr band Last (10-yr) band Needs/ Illustrative List

13

Page 14: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

Timing (Amendment)Timing (Amendment) Required Amendment when:

• Advancing project > 2 bands (10 years)

• Adding phase from CFP to LRTP 1st 5-year band (TIP/STIP years) causing imbalance

• Adding new project to Cost Feasible Plan

• Adding new phase to LRTP 1st 5-year band (TIP/STIP years) from Needs Plan causing imbalance

14

LRTP Amendment ExamplesCFP Needs

1st 5-yr band TIP/STIP years

2nd 5-yr band 3rd 5-yr band Last (10-yr) band Needs/ Illustrative List

TO FROM TO FROM

TO FROMTO ANY BAND FROM

Page 15: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

AnalyzeAnalyze

*LRTP Project Δ (Delta)

Identification Cost Timing Project Scope

* Base document15

Page 16: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

Principle: ScopePrinciple: Scope Major change in scope: automatic amendment

• Change in project termini (expansion)

• Addition (add bridge, lanes, interchange)

Minor change:• Project termini may have minor variations

= or < 5% of total project length

• Cost analyses may indicate scope change

16

Page 17: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

ReviewReview

Coordination/communication essential & continual

Project description – consistent with LRTP• Establish cost, timing, scope for project (phase) analysis

17

Project Principles

Change in scope

Increase in cost of over 50% AND $50 million

Advancing project > 10 years or (2) five-year bands

Adding new project to CFP

Moving project to first LRTP 1st 5-years (TIP/STIP years), causing imbalance

Automatic Amendments

Page 18: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

When assessing for LRTP Consistency, look at:• Project costs

• Initiation phase

• Project scope

Look to Florida LRTP Amendment Thresholds document for further guidance.

18

TIP/STIP Consistency with LRTPTIP/STIP Consistency with LRTP

Page 19: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

QUESTIONS?QUESTIONS?

19

Page 20: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

NEPA CONSISTENCYNEPA CONSISTENCY

NEPA Approval Granted If:

• Environmental Requirements Satisfied; and

• Amendment to LRTP, STIP or TIP is NOT Needed; and

• Funding Scenarios Are Met20

Planning Consistency

NEPA DOCUMENT CONSISTENCYNEPA DOCUMENT CONSISTENCY

Page 21: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

Final NEPA Document ApprovalFinal NEPA Document Approval

“Open ended project”• Allocation of funds (PDE/Design) for a project with no clear time frame

or commitment for construction.

• Ramifications: Inefficient use of limited transportation funds Potential projects based on outdated planning assumptions and design

Demonstrate progress and commitment towards construction of project

Progress/Commitment Variable

Variable:

21

Page 22: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

Acceptable Project Funding Scenarios for Acceptable Project Funding Scenarios for FHWA NEPA ApprovalFHWA NEPA Approval

Project

PE

ROW

CONSTRUCTION

Project

PE

ROW

CONSTRUCTION

In LRTP CFP Not in LRTP CFP

Note: PE means Design

22

Page 23: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

Project

Segment 1 Segment 2 Segment 3

PE PE PE

ROW ROW ROW

Construction Construction Construction

Project

Segment 1 Segment 2 Segment 3

PE PE PE

ROW ROW ROW

Construction Construction Construction

In LRTP CFP Not in LRTP CFP Note: PE means Design

Acceptable Project Funding Scenarios for Acceptable Project Funding Scenarios for FHWA NEPA ApprovalFHWA NEPA Approval

23

Page 24: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

Project

Segment 1 Segment 2 Segment 3

PE PE PE

ROW ROW ROW

Construction Construction Construction

In LRTP CFP Not in LRTP CFP

Acceptable Project Funding Scenarios for Acceptable Project Funding Scenarios for FHWA NEPA ApprovalFHWA NEPA Approval

Note: PE means Design

24

Page 25: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

Unacceptable Project Funding Scenario for Unacceptable Project Funding Scenario for NEPA ApprovalNEPA Approval

Project

Segment 1 Segment 2 Segment 3

PE PE PE

ROW ROW ROW

Construction Construction Construction

In LRTP CFP Not in LRTP CFP

20 Years

Note: PE means Design

25

Page 26: LRTP Consistency Review  for STIP Amendments  and NEPA Approval

QUESTIONS?QUESTIONS?