Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
05/05/2018
1
1
Budapest, 08.05.18ERRA Course «Principles of Electricity Markets»
Incentive Regulation of Smart Distribution Systems: from Input-based Demonstration to Output-based Deployment
Luca Lo Schiavo ARERA - Regulatory Authority for Energy, Networks and Environment Infrastructure Regulation, deputy directorMember of CEER DS (distribution system) WG Member of ACER INF (elecricity infrastructure) TF
Staff of the Regulatory Authority have the duty to disclaim in public that only personal opinions are presented when speaking in public at conferences, workshops and seminars.
Ethical code of ARERA,10(2)
Content of this presentation
Luca Lo Schiavo, AEEGSI (Italy) 2ERRA 08.05.18
RES evolution in Italy and effects of “system trans formation”The Italian power system and the impact on distribution networks
Overall approach to innovationInput-based vs output-based incentive mechanisms
Input-based regulatory incentives for demonstration phaseLearning from pilot projects of active distribution grids
Output-based regulatory incentives for deployment p haseThe mechanism for promoting roll-out of smart functionalities
Annex 1: Output-based regulatory incentives for Quality of ServiceAnnex 2: Smart metering (from 1st to 2nd generation)Annex 3: Electro-mobility and recharge infrastructure
05/05/2018
2
KEY FIGURES: energy demand in Italy
Luca Lo Schiavo, ARERA (Italy) 3ERRA 08.05.18
Total demand 2016: 320.000 GWh/yr
Self-consumption:30.000 GWh/yr (estimate)
System peak: 55-59 GW~20 GW min.load night, ~30 GW Sundays, daylight
Household consumption~2.200 kWh/user3.3 kW capacity
0,6 Million prosumers
0%
20%
40%
60%
80%
100%
23%
2%
25%
36%
15% HV
MV
LV(small
business)
LV(households )
KEY FIGURES: electricity infrastructures in Italy
Distributionand metering
Transmission
Number of companies 137 DSOs 1 TSO
Voltage levelsMV (10-20-25 kV)
LV (230-400 V)HV (130-150 kV)
EHV (220-380 kV)
Type of network Radial(with back-feeding in MV)
Meshed
Dimension Total: 37 Million cust. Around 60.000 km(of which 23.000 EHV)
Aggregated RAB 22,700 M€ 11,700 M€
UnbundlingFunctional and legal
De-branding (>100k cust)
Full ownershipunbundling
Luca Lo Schiavo, ARERA (Italy) 4ERRA 08.05.18
05/05/2018
3
KEY FIGURES: electricity distribution companies in It aly
DSONumber of
LV customer
1. E-distribuzione 32.2 million
2. Areti (Roma) 1.6 million
3. Unareti (Milano/Brescia) 1.1 million
4. Ireti (Torino) 0.5 million
5.SET distribuzione (Trento province)
0.3 million
6. – 10.5 DSO «medium size»250.000 - 100.000 cust.
0.8 million (aggreg.)
11. – 42.32 DSO «small size»100.000 – 5.000 cust.
0.7 million (aggreg.)
43. – 137.95 DSOs «micro-size»Less than 5.000 cust.
0.1 million (aggreg.)
Luca Lo Schiavo, ARERA (Italy) 5ERRA 08.05.18
«SYSTEM TRANSFORMATION»: main driving forces
6
The electricity sector is undergoing a radical transformation in a very narrow timeframe:
• strong growth of renewable sources All RES are 44.6% of total installed in 2016 compared with 24% in 2004; All RES produce 37.3% of total production in 2016 compared to 18.4% in 2004;
• strong spread of unpredictable renewable sourcesWind+PV are 24.5% of the total installed in 2016 compared to 1.3% in 2004; Wind+PV produce 13.7% of the total production in 2016 vs 0.6% in 2004
• strong spread of distributed generation (up to 10 MVA) DG is 21% of the total installed in 2015 compared with 4.6% in 2004; DG produce 18.1% of the total produced in 2015 compared with 4.7% in 2004
• radical changes of electricity flowsThe electricity flows in Italy have changed in recent years , due to the high penetration of new RES especially in the south, where the load is lower; transmission investments are relevant (around 1 billion/year)
ERRA 08.05.18 Luca Lo Schiavo, ARERA (Italy)
05/05/2018
4
«SYSTEM TRANSFORMATION»: gross installed capacity
7ERRA 08.05.18 Luca Lo Schiavo, ARERA (Italy)
0
5.000
10.000
15.000
20.000
25.000
30.000
35.000
40.000
45.000
50.000
55.000
1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
MW
Biomass and waste Photovoltaics Wind Geothermal Hydro
22,5% of the total
installed
44,6% of the total
installed
PV: 3,5 GW in 2010 18,4 GW in 2013 19,3 GW in 2016
«SYSTEM TRANSFORMATION»: gross energy production
8ERRA 08.05.18 Luca Lo Schiavo, ARERA (Italy)
05.000
10.00015.00020.00025.00030.00035.00040.00045.00050.00055.00060.00065.00070.00075.00080.00085.00090.00095.000
100.000105.000110.000115.000120.000125.000
1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
GWh Biomass and waste Photovoltaics Wind Geothermal Hydro
19,0% of the total
37,3% of the total
Unpredictable renewablesources (PV and wind): 13,7% of the total
05/05/2018
5
«SYSTEM TRANSFORMATION»: peak load and reserve margin
9ERRA 08.05.18 Luca Lo Schiavo, ARERA (Italy)
19,0% of the total
Unpredictable renewablesources (PV and wind): 13,7% of the total
«SYSTEM TRANSFORMATION»: residual demand (net DG)
Luca Lo Schiavo, ARERA (Italy) 10ERRA 08.05.18
…from 2010…
… to 2015
-11,0 GW
-3,0 GW
Average Sunday in April , residual demand
The phenomenon is really crucial on Sundays and Holidays in Spring and Summer(low load, high PV production if the sun is shining, combined in spring
with still low temperatures and high performance of PV panels)
05/05/2018
6
11ERRA 08.05.18 Luca Lo Schiavo, ARERA (Italy)
«SYSTEM TRANSFORMATION»: changes in hourly profiles
2010 2016
Higher ramps
Curtailment risk
Loadcovered
by wind and PV
Week-days
Week-ends
12ERRA 08.05.18 Luca Lo Schiavo, ARERA (Italy)
«SYSTEM TRANSFORMATION»: changes in energy flows
2004 2015
05/05/2018
7
13ERRA 08.05.18 Luca Lo Schiavo, ARERA (Italy)
«SYSTEM TRANSFORMATION»: cost of State incentives
Mill
ions
Euro
per
year
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
[TW
h]
Electrical energy produced from RES and encouraged
New incentives for renewables
Photovoltaic incentives
Feed in tariff l. n. 244/07
Incentives substituting Green certificates
Green certificates
Cip 6 (only renewables)Energ
y pro
duce
d[T
Wh]
State incentives have beenvery generous especially for
PV
From 2013, new PV units are no
longer incentivized
0500
1.0001.5002.0002.5003.0003.5004.0004.5005.0005.5006.0006.5007.0007.5008.0008.5009.0009.500
10.00010.50011.00011.50012.00012.50013.00013.50014.000
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
[Mili
oni d
i eur
o]
Costs of incentives for electrical energy produced by RES
New incentives for renewables
Photovoltaic incentives
Feed in tariff l. n. 244/07
Incentives substituting Green certificates
Green certificates
Cip 6 (only renewables)
14 di 65
RES Connection: Critical areas
• in white, all the non critical areas;
• in yellow, areas served through primary stations, in standard operating mode, for which Pimm > 0,5 * Pcmin;
• in orange, aeras served through primary stations, in standard operating mode, for which Pimm> Pcmin;
• in red, aeras served through primary stations, in standard operating mode, for which
Pimm – Pcmin > 0,9 * Pn. The red areas are considered critical areas.
For low and medium voltage networks, the grid operator identifies:
where:
• area is a province or group of municipalities or a municipal territory or part of it;
• Pcmin is the min load, defined as the load of the area in the quarter of hour of the minimum regional ;
• Pn is the sum of the rated power of all HV/MV transformers installed in the primary stations of the area;
• Pimm is the sum of the Required Injected Power, as requested by appliers for connection.
14ERRA 08.05.18 Luca Lo Schiavo, ARERA (Italy)
05/05/2018
8
15 di 65
Critical areas
�� ������
��
EHV/HVMV
EHV/HVMV
EHV/HVMV
EHV/HVMV
EHV/HVMV
EHV/HVMV
T1 T2
T3
T4 T5
T6
Pcmin
area
Required injected power = 250 kWRequired injected
power = 250 kWRequired injected power = 250 kWRequired Injected
Power (RIP) = 250 kW
�� ����� �
�
��
M1
M2
M3
M4
IMPACT ON DISTRIBUTION NETWORK: DSOs’ VIEWPOINT
Luca Lo Schiavo, ARERA (Italy) 16
Reverse Power Flow Time (RPT) : % of time (hours) during which energy flows from Medium Voltage (distribution) to High Voltage (Transmission)� RPT is an extremely relevant
indicator of distribution criticalities, used by the Italian Energy Regulator
Due to «connect and forget»approach, for the time being we do not have congestions on MV lines: RES have been connected only after proper network reinforcement. This approach may lead in the long run to overcost in network development (in comparison with smart solutions)
ERRA 08.05.18
05/05/2018
9
Content of this presentation
Luca Lo Schiavo, AEEGSI (Italy) 17ERRA 08.05.18
RES evolution in Italy and effects of “system trans formation”The Italian power system and the impact on distribution networks
Overall approach to innovationInput-based vs output-based incentive mechanisms
Input-based regulatory incentives for demonstration phaseLearning from pilot projects of active distribution grids
Output-based regulatory incentives for deployment p haseThe mechanism for promoting roll-out of smart functionalities
Annex 1: Output-based regulatory incentives for Quality of ServiceAnnex 2: Smart metering (from 1st to 2nd generation)
European Regulators’ recommendations for innovation (2 010)
Perform societal cost-benefit assessment
Introduce output regulation: value for money of users
Distinguish grid-related versus market-related activities
Improve consumer awareness for energy use and market opportunities
Learn from best regulatory practices
Ensure stable regulatory framework and long-term return on investments
Decouple profits and volume for grid operators
Incentivise innovative solutions (demonstration pilots)
Adopt open protocols and standards for interoperability
Disseminate the results and lessons learned from the demonstration projects
Luca Lo Schiavo, AEEGSI (Italy) 18
First, keep the system secure
ERRA 08.05.18
Source: CEER Smart Grid Position paper. June 2010 (E10-EQS-38-05)
ROLL OUT
PILOT
05/05/2018
10
Potential impact on system security (voltage dips on T- grid)
Due to reduction of rotating machinesconnected to Transmission grid, there isless Shortcircuit-Power available and therefore voltage dips generated atT-level have larger impact (in this simulation the spatial distributionof DG has been assumed homogeneous)
80% Vnante PV
80% Vnpost PV
Distance
Residual
Voltage
0
1 p.u.
Luca Lo Schiavo, AEEGSI (Italy) 19ERRA 08.05.18
DG frequency tolerance: outcome of retrofit (mandator y by ARERA)
Source: ENTSO-e «Dispersed Generation Impact on Continental Europe Region» position paper, 15 Nov.2014
Luca Lo Schiavo, AEEGSI (Italy) 20
A first EU-wide incident alreadyhappened on 4th Nov. 2006:split of Europeansynchronous area due to a RES-relatedproblem in NorthernGermany: ~2 GW of DG disconnected in Italy due to previousnarrow bands; nowadays, the sameincident would havea far larger effect, without the new tolerance windows
ERRA 08.05.18
05/05/2018
11
Reduced risk in case of deep voltage dip in the grid
With new FRT requirementsWithout new FRT requirements
Luca Lo Schiavo, AEEGSI (Italy) 21ERRA 08.05.18
SMART SYSTEMS =
SMART GRID + SMART USERS
DISTR. NETWORKAUTOMATION
CONNECTION RULES FOR DG
VOLTAGEREGULATION
NETWORKRESILIENCE
smart grids
ELECTRICVEHICLES
RECHARGINGINFRASTRUCTURE E-mobility
ELECTRONICMETERS
smart metering
COMMUNICATIONINFRASTRUCT.
FLEXIBILITYSERVICES
«HAN»: HOMEAREA NETWORK
Demandresponse
IN-HOMEDEVICES
DEMANDAGGREGATION
LARGE SCALEINTERMITT.GEN.
windintegration
STORAGESYSTEMS
storageV-2-G
SERVICES
ARERADECISIONS
292/06393/13
87/16222/17(SM 2g)
ARERADECISION 96/11POSITION 5/15
ARERA DECISIONS 39/10 > 12/11 > 646/15
ARERADECISION
5/10
ARERADECISION
43/1366/13
ARERACONSULTATIONS
354/13 AND 298/16DECISION 300/17
Luca Lo Schiavo, ARERA (Italy) 22ERRA 08.05.18
Focus of pilotdemonstration projects
What «innovation» includes?
05/05/2018
12
Output-based vs Input-based incentives: a frame
OUTPUT-BASED
• e.g. Quality of Supply (from 2000)
• Key outcome indicators (e.g.SAIDI, SAIFI+MAIFI, …)
• Metrics ought to be: clear and fair, trackable and auditable
• Output valuation is needed (based on estimates of avoided externalities – e.g. VOLL)
• May be used as stable regulation, however needs periodic tuning (typically every regulatory period)
INPUT-BASED
• esp. suited: Innovation (up to 2015)
• Benefit/Cost ratio used to select pilot projects
• Demonstration projects are evaluated ex-ante
• Input-based ncentive is not based on value for the customer/system
• Intended to be a transitional regulation: when metrics are developed, evolution towards output-based incentives is preferable for roll-out deployment
Luca Lo Schiavo, AEEGSI (Italy) 23ERRA 08.05.18
The Italian Regulator’s approach to demonstration pilot s
• Demonstration pilot: real operations in real grid (no lab)
• Regulatory attention to both effectiveness (performance) and efficiency (cost): pilots are paid by all customers….
• Transparency of the rules: procedures, evaluation methods and criteria, etc., known ex-ante
• Knowledge development with the involvement and the support of the best expertise (RSE and University like Politecnico MI)
• Continuous monitoring in the medium and long term: cost benefit analysis for the whole life-time of the new components
• Output disclosure: because demonstration pilots are paid by all customers > results must be public (no patents)
• Replicability and dissemination of the best-practices
Luca Lo Schiavo, AEEGSI (Italy) 24ERRA 08.05.18
05/05/2018
13
Content of this presentation
Luca Lo Schiavo, AEEGSI (Italy) 25ERRA 08.05.18
RES evolution in Italy and effects of “system trans formation”The Italian power system and the impact on distribution networks
Overall approach to innovationInput-based vs output-based incentive mechanisms
Input-based regulatory incentives for demonstration phaseLearning from pilot projects of active distribution grids
Output-based regulatory incentives for deployment p haseThe mechanism for promoting roll-out of smart functionalities
Annex 1: Output-based regulatory incentives for Quality of ServiceAnnex 2: Smart metering (from 1st to 2nd generation)
Requirements for smart grid demonstration pilot projec ts
• Focus on MV networks: 75% of DG rated power
• Active grids only: at least reverse power-flow for 1% of timefrom MV to HV
• Real time control system at MV level: the selected MV network has to be controlled (voltage limits / anti-islanding)
• Open grid: non-proprietary communication protocols required, in order to minimize interface costs for network users
• Selection process with both quantitative benefit/cost ratio and qualitative score – time consuming process
• Awarded with extra-WACC (+2%) for 12 years (“input-based”)
• Dissemination: report to the Regulatory Authority every six months for selected projects, published on Regulator’s website
Luca Lo Schiavo, AEEGSI (Italy) 26ERRA 08.05.18
05/05/2018
14
KPI approach for smart grid pilot projects evaluati on
Synthetic indicator IP used to assess ex-ante the expected performance of the demonstration projects
C
AjP
IP
m
ij
smart ∑=
⋅=
8760EIEI
P prepostsmart
−=
IP: priority index
Aj: project benefits [point score]
C: project costs [€]
P-smart: increase in DG-produced electricity / hour [MW]
EI-post: DG-produced electricity that can be injected in the network after the project in safe conditions [GWh]
EI-pre: DG-produced electricity that can be injected in the network before the project without reverse flow [GWh]
Aj: score for size, innovation, feasibility, replicability
Quantitative cost and mainbenefitindicator
Further benefits qualitative scoring
Luca Lo Schiavo, AEEGSI (Italy) 27ERRA 08.05.18
P-smart concept: hosting capacity in safe conditions
MV
HV
MVMV
LVLV
REVERSE POWER-FLOW
TIME: 1% of year Vcontrol
Psmart is the increase in DG-production (PDG) that can be connected to the grid in safe conditions (voltage, currents, frequency) thanks to smart investments on the grid
Passive network: NO flow from MV to HV
Smart network – latency 10-20 s remote voltage regulation
Smart network – latency 200 msremote intertrip (no islanding)*
Smart network – latency 200 ms: + storage (regulatory issues)
Min. Load
PDG
PDG= 0
Psm
art
* Very critical in Italydue to fast reclosure (400ms) for network automation
Luca Lo Schiavo, AEEGSI (Italy) 28ERRA 08.05.18
05/05/2018
15
«in safe conditions for voltage, currents and frequency»
• Power modulation: modulating active power
Related to Current (thermal) limits > latency: minutesCostly solution due to loss of revenue for generators (not implemented)
• Voltage regulation: modulating reactive power
Related to Slow Voltage Variations > latency: some tens of secondsVery low-cost solution for voltage network constraints
• Intertrip: combined dialogue between DSO and DG in order to avoid inslanding in case of network fault and secure the system
Related to both Frequency perturbation and fast Voltage Dips > latency hundreds of millisec (from 2012 a local solution has been implemented)
• Keep alive: in case ICT layer is not available, DG rolls back in old setting in order to avoid risks (check every 1 second)
Luca Lo Schiavo, AEEGSI (Italy) 29ERRA 08.05.18
Smart distribution system functionalities (tested i n pilots)
Luca Lo Schiavo, AEEGSI (Italy) 30ERRA 08.05.18
1. TSO-DSO integrationMeasurement collection, DG production forecasting and data transmission towards TSO systems - better observability
5. Fast MV fault IsolationDetection on isolation of MV fault sections without the tripping of the breaker at the line departure(requires extra-performant tlc )
6. Electricity storageUsage of electrochemical storage as a mean for improving QoSand managing RES intermittency – further evaluation needed
2. Voltage ControlParticipation of MV Distributed Generation to Voltage regulation on MV feeders – higher hosting capacity
3. Active power modulationParticipation of MV distributed generation to ancillary services market (not yet disciplined for units below 10 MVA)
4. Anti – IslandingDetection of possible islanding condition on MV Network – no longer needed after local solution implemented in 2012
05/05/2018
16
Dissemination activity of pilot projects
Luca Lo Schiavo, AEEGSI (Italy) 31ERRA 08.05.18
Acknowledgements (Annex 1 to cons.paper 255/2015/R/ee l)
L’Autorità esprime profondo apprezzamento per il lavoro svolto e l’impegno profuso da tutte le persone coinvolte dalla sperimentazione. Nell’impossibilità di ringraziare individualmente, si desidera in particolare segnalare
• il personale delle imprese di distribuzione che ha seguito i progetti pilota tenendo i contatti con l’Autorità (Fiori e Francucci di A.S.SE.M., Pisciotta e Tallei di ASSM, Fasciolo, Lucchini, Martinazzi e Pluda di A2A Reti Elettriche, Carta, Liotta e Zendri di ACEA Distribuzione, Loperfidoe Paulucci di ASM Terni, Bianchin e Perron di DEVAL, Alagna, Consiglio, Di Lembo, Di Napoli, Lombardi, Massimiano e Petroni di ENEL Distribuzione),
• i professori e ricercatori universitari che hanno fornito contributi tecnici e scientifici sia in fase di valutazione che di disseminazione (La Scala del Politecnico di Bari, Borghetti dell’Università di Bologna, Pilo dell’Università di Cagliari, Delfino dell’Università di Genova, Pelacchi dell’Università di Pisa, Turri e Fellin dell’Università di Padova, Ippolito dell’Università di Palermo, Capone, Delfanti, Falabretti, Merlo, Olivieri del Politecnico di Milano),
• nonché altri esperti (Timò del CEI, Sica di FederUtility, De Nigris e Celi di RSE, Carlini e Giannuzzi di Terna, e Denti, Graditi, Noia e Pigini coinvolti come esperti nella fase di predisposizione dei progetti)
• e tutte le altre persone, anche delle imprese fornitrici di apparati e servizi, che sono state a vario titolo coinvolte nella realizzazione dei progetti e di cui non è possibile indicare qui i nomi
Allegato 1, documento di consultazione 255/2015/R/eel, 29 maggio 2015
Luca Lo Schiavo, AEEGSI (Italy) 32ERRA 08.05.18
05/05/2018
17
Content of this presentation
Luca Lo Schiavo, AEEGSI (Italy) 33ERRA 08.05.18
RES evolution in Italy and effects of “system trans formation”The Italian power system and the impact on distribution networks
Overall approach to innovationInput-based vs output-based incentive mechanisms
Input-based regulatory incentives for demonstration phaseLearning from pilot projects of active distribution grids
Output-based regulatory incentives for deployment p haseThe mechanism for promoting roll-out of smart functionalities
Annex 1: Output-based regulatory incentives for Quality of ServiceAnnex 2: Smart metering (from 1st to 2nd generation)
PROJECT ASSESSMENT: lessons learned from abroad…
“Many technical and economic features of the Smart Grid, Distributed Generation and Demand Response providediffuse benefits to the customers that are hard to put a value on.
[US] regulators must engage in lenghty proceedings to set methods of measuring the value and then utilities must administer them under the critical eye of regulators…”
P. Fox-Penner, Smart Power, 2010
In ARERA strategic vision, output-based, selective incentive regulation is the key progress towards «smart regulation»
Luca Lo Schiavo, ARERA (Italy) 34ERRA 08.05.18
05/05/2018
18
INNOVATION: from pilot projects to output-based incent ives
CEER Guide-lines (2010)
Smart grid Pilot projects (launched 2011)input-based regulation
Dissemi-nation events (2013-14),public disclosure on website
Lesson learnt (public consultation 255/2015)
Output-based regulation (2016-19) for 2 smart functionalities: Observabilityand Voltage smart regulationon MV networks
Luca Lo Schiavo, ARERA 35
ARERA-AGCOMcollaboration on
M2M issues(2014>)
!
ERRA 08.05.18
Initial thoughts for output-based incentives (paper 255/2015)
Luca Lo Schiavo, AEEGSI (Italy) 36ERRA 08.05.18
Learning from pilots
Bal.Marketrules notready yet
DSO revenues stillRAB-based
Detailed analysis of smart functionalities
Valuable results for some functionalities
Without specific balancing market rulesfor DG, network users are not interested
but first results may be achieved by DSOseven without involving network users
New TOTEX approach envisagedfor eliminating perverse incentives
Output-based regulatory incentivesfor a few smart functionalities
High RES penetration
Selectivity of smart investments: priorityin areas with higher level of RES
Still to be defined: financial supportfor «early bird» network users
05/05/2018
19
Example of «complexity levels»: voltage control (255/2 015)
Luca Lo Schiavo, AEEGSI (Italy) 37ERRA 08.05.18
Caso Base Programma P3 Programma P3 + IRE
Linea Limite termico [MW]
Limite tensione [MW]
Limite termico [MW]
Limite tensione [MW]
Aumento rispetto caso
base (%)
Limite tensione [MW]
Limite termico [MW]
Aumento rispetto
caso base (%)
Carpinone 7.402 - 7.402 - 0% - - 0%
Sessano 7.647 - 7.647 - 0% - - 0%
Colle Breccione 11.594 - 11.594 - 0% - - 0%
Pesche - 7.258 8.658 8.658 19% 8.658 8.658 19%
Pescolanciano - 7.624 8.233 8.233 8% 8.233 8.233 8%
Fontecurelli - 3.296 - 4.406 34% 4.623 4.623 40%
Polverone - 4.519 - 5.365 19% 5.431 5.431 20%
Pescorvara 4.386 - 4.386 - 0% - - 0%
S. Domenico - 4.164 - 5.023 21% 5.512 5.512 32%
Santa Maria - 5.049 - 5.232 4% 5.532 5.532 10%
TOTALE [MW] - 31.91 - 36.917 16% 37.989 - 19%
«Caso Base»: withoutany smart functionality
«Programma P3»: first level of complexity (no communication with DG)
«Programma P3+IRE»:highest level of complexity(with communication with DG)
A relevant benefit can be extracted evenat less complex levels
NEW INCENTIVES FOR DSOs: output-based, selectivity
1. Observability of DG(and TSO-DSO data exchange)
2. Improved voltage control on MV networks
Benefits Less reserve due to better forecast; less control action due to better knowledge of system conditions � 5% reduction of fast resources, with a 50 M€/year saving
Higher hosting capacity (HC): deferred distribution investments
� based on experimental data, 16% HC increase, with a saving for each PS equal to 50 M€/year
Benefit/cost ratio
Under conservative assumptions: 3.3
Under conservative assumptions: 2.5
Output Rated power [MW] of DG connected to each MV/HV Primary Substation accurately observable
Transformation capacity [MVA]of each HV/MV Primary Station with improved voltage control
Yearly incentives
20 Eur/MW x PRES x months / 12(OSS-1: 20 sec. measurement)
250 Eur/MVA x SHV/MV
(REGV-1: not yet local control)
Luca Lo Schiavo, ARERA (Italy) 38
output-based incentives for smart functionalities are granted only in area with RPT > 1%
ERRA 08.05.18
05/05/2018
20
39
«Output-based» incentive regulation mechanisms: summ ary
OUTPUT DISTRIBUTION TRANSMISSIONSAIDI (cust. minutes lost)
Rewards/penalties (unplannedfrom 2000; planned from 2017)
-
ENS (energy notsupplied)
Rewards/penalties (2008)Mitigation (reduction rewards)
SAIFI+MAIFI (long and short interruptions)
Rewards/penalties (from 2008) -
GS* multiple interruptions
Customer Compensation (MV only) (2004)
Contribute to customercompensations
GS* very long interrupt. Customer compensation and penalties (2007, ren. 2016/17)
Contribute to customercompensations and penalties
GS* commercial quality 11 guaranteed standards (6 in 2000, then enlarged)
-
Smart grid Rewards only, 2 innovation outputs(observab.MV, hosting capacity)
Target capacityin critical T-grid sections
Additional capacity (in the limit of target capacity, CBA approach)
* GS: guaranteed standards
IMPORTANT STEPS AHEAD IN «SMART REGULATION»…
1. Output-based Regulation is the key step towards«smart regulation» as it combines efficiency and effectiveness
Luca Lo Schiavo, ARERA (Italy) 40
2. Selective priorities are needed to ensurevalue-for-money deployment of smart infrastructures
3. Cost/benefit analysis provides ground for system-wide incentives that transfer part of positive externalities to DSOs
4. Learning process is the way to build robust regulation, due to the uncertainty and risks of new technology applications
5. Flexibility is still a target that requires new balancingmarket rules, standardisation and advanced TLC services
ERRA 08.05.18
05/05/2018
21
FULLY IN LINE WITH ACER/CEER “BRIDGE TO 2025” VISION
Regulatory framework must adapt to the new challenges:
• Enable DSOs to take on the role of a neutral market facilitator and avoid DSO foreclose competition
• Accompany the development of new flexibility markets (on both sides: demand as well as distributed generation)
• Review distribution network tariff structure in order to develop focused incentives for smarter networks
• Clearly define DSOs’ and TSOs’ respective roles, establishing coordination requirements (system security)
• Enable customer awareness on his/her own energy footprint through smart metering data on consumption
Towards a future-proof power system…
Luca Lo Schiavo, ARERA (Italy) 41ERRA 08.05.18
INNOVATION: the relevance of independent regulation
Luca Lo Schiavo, AEEGSI (Italy) 42
Regulation should … endeavor to find approaches that
facilitate technological change, experimentation,
and the possibility of disruptive business models that
defy the classic approaches of incumbents.
As the technology evolves, the following issues merit
further evaluation and study. How smart is smart enough?
It merits investigation whether there are less expensive
alternatives that could provide nearly equal benefits.
OECD, DAF/COMP(2010)10, p.185
ERRA 08.05.18
05/05/2018
22
Thank you for your attention [email protected]
www.arera.itPlease visit:
Suggested reading on the Italian case (smart grid)CHANGING THE REGULATION FOR REGULATING THE CHANGEInnovation-driven regulatory developments in ItalyICER Distinguished regulatory scholar Award 2012http://www.iern.net/portal/page/portal/IERN_HOME/ICER_HOME/ABOUT_ICER/Distinguished_Scholar_Award_2012
Luca Lo Schiavo, ARERA (Italy) 43ERRA 08.05.18
Suggested reading on the Italian case (smart metering)SMART METERING: AN EVOLUTIONARY PERSPECTIVEGuidelines and lessons learnt from the Italian regulatory experienceHighly Acknowledged Paper ERRA regulatory research Award 2017http://erranet.org/knowledge-base/erra-regulatory-research-award/#winner2017
Annex 1Output-based regulatory incentives
for Quality of Service
Luca Lo Schiavo, ARERA (Italy) 44ERRA 08.05.18
05/05/2018
23
FUNDAMENTALS
• QoS is a worthy good
• The regulator wants to provide regulated companies with economic signals in order to deliver the optimal level of QoS
• It’s up to the regulated company to define the most effective actions (e.g. investments, resource organization, automation, etc) to minimise the total cost
Luca Lo Schiavo, ARERA (Italy) 45ERRA 08.05.18
Incentive regulation in practice is considerably more complicated than incentive regulation in theory.
Paul Joskow“Incentive Regulation in Theory and Practice:
Electricity Distribution and Transmission Networks”, CEEPR Paper 05-014, Sept. 2005
QoS INCENTIVE REGULATION IN PRACTICE
• Most EU regulators adopt an output-basedincentive regulation scheme fo QoS (esp. Continuity of Supply, both for distributionand transmission)
• CEER regularly publishes a Benchmarking of QoS Report (first comparison of incentive schemes for QoS in the 3rd CEER Report)
• Basic elements of most incentive schemes:
Luca Lo Schiavo, ARERA (Italy) 46ERRA 08.05.18
1. QoS metrics (clear and fair, trackable and auditable)
2. QoS baseline and improvement valuation (WtP, WtA)
3. Toolkit for managing uncertainty (acceptable risk)
05/05/2018
24
• Rewards and penalties are basedon net indicators
THE REGULATORY EXPERIENCE IN ITALY: 1. METRICS
Luca Lo Schiavo, ARERA (Italy) 47ERRA 08.05.18
• Internationally-used QoS indicators (SAIDI, SAIFI, MAIFI)
• Separately per kind of outage (unnotified vs notified)
• Separately per «district» (each internally homogeneous)
• Separately per voltage level and causeSAIDI-net
SAIFI-net
• Rewards and penalties are basedon net indicators
• Regulatory guidancefor recording QoSevents (incl. SCADA)
• Audits in field(sanctions)
THE REGULATORY EXPERIENCE IN ITALY : 2a. BASELINE
Luca Lo Schiavo, ARERA (Italy) 48ERRA 08.05.18
INCENTIVE REGULATION ADJUSTMENT FROM 1ST TO 2ND REGULATORY PERIOD
Referencestandards
0
10
20
30
40
50
60
70
80
90
0 1 2 3 4 5 6 7 8 9
CU
ST
OM
ER
MIN
IUT
ES
LO
ST
(n
et o
f in
terr
uptio
nsno
tattr
ibut
able
todi
strib
utio
nco
mpa
nies
)
TARGETS ACTUAL LEVELS
1998/99 1999/00 2000/01 2001/02 2002/03 2003/04 2004/05 2005/06 2006/07
1° REGULATORY PERIOD
2° REGULATORY PERIOD
REFERENCE STANDARDS
Referencestandards
0
10
20
30
40
50
60
70
80
90
0 1 2 3 4 5 6 7 8 9
CU
ST
OM
ER
MIN
IUT
ES
LO
ST
(n
et o
f in
terr
uptio
nsno
tattr
ibut
able
todi
strib
utio
nco
mpa
nies
)
TARGETS ACTUAL LEVELS
1998/99 1999/00 2000/01 2001/02 2002/03 2003/04 2004/05 2005/06 2006/07
1° REGULATORY PERIOD
2° REGULATORY PERIOD
REFERENCE STANDARDS
Example: URBAN AREAS
Referencestandards
Referencestandards
0
10
20
30
40
50
60
70
80
90
0 1 2 3 4 5 6 7 8 9
CU
ST
OM
ER
MIN
IUT
ES
LO
ST
(n
et o
f in
terr
uptio
nsno
tattr
ibut
able
todi
strib
utio
nco
mpa
nies
)
TARGETS ACTUAL LEVELS
1998/99 1999/00 2000/01 2001/02 2002/03 2003/04 2004/05 2005/06 2006/07
1° REGULATORY PERIOD
2° REGULATORY PERIOD
REFERENCE STANDARDS
Referencestandards
0
10
20
30
40
50
60
70
80
90
0 1 2 3 4 5 6 7 8 9
CU
ST
OM
ER
MIN
IUT
ES
LO
ST
(n
et o
f in
terr
uptio
nsno
tattr
ibut
able
todi
strib
utio
nco
mpa
nies
)
TARGETS ACTUAL LEVELS
1998/99 1999/00 2000/01 2001/02 2002/03 2003/04 2004/05 2005/06 2006/07
1° REGULATORY PERIOD
2° REGULATORY PERIOD
REFERENCE STANDARDS
Example: URBAN AREAS
ReferencestandardsReferencestandards
),],([ avgENSttt PVATfQ −=±
Tt: targets (ex-ante, per district)
At: actual levels(ex-post, per district)
VENS: avg value of 1 hour interrupt. avoided for 1 kW(based on market survey - WTP)
Pavg: avg power of each district[kWavg]
Incentives for quality (year t)
At
Tt
05/05/2018
25
Ex-ante setting of standards, ex-post control of actual levels
Luca Lo Schiavo, AEEGSI (Italy) 49
Ex-ante for 4 years targets are set (baseline)
−= %2;1max
12
1
j
k
j LivPart
LivObαk: territ. density
)1(1,, jtjtj TT α−×= −
t0 1 2 3 4 … … … 12
Stdj,t [SAIDInet]
LivPart
LivObk
Tj,4
0TLivPart =
MaxQMin tj ≤≤ ,0%5 ,,, =⇒<− tjtjtj QAT
+×−= ∑
∈ 8760)( ,,,,
, ,domtjdomndomtjndom
Districtsj
tjtEncEncATQ tj
Ex-post actual levels are compared with relevant targets and reward/penalties applied
Aj,t
Qt [€]
Tj,t
-Min
+Max
[SAIDInet]
Unitary incentive/penalty [€/kWh-not-served]ex-ante based on WTP/WTA customer survey
FSR Cybersecurity 04.05.18
THE REGULATORY EXPERIENCE IN ITALY : 2b. VALUATION
Luca Lo Schiavo, ARERA (Italy) 50ERRA 08.05.18
DOMESTIC CUSTOMERS
Parameter Cdom
BUSINESS CUSTOMERS
Parameter Cndom
(BEST DISTRICTS) Below national ref.
7.2 €/kWh-ENS 14.4 €/kWh-ENS
(MEDIAN) From 1x to 3x nat.ref.
10.8 €/kWh-ENS 21.6 €/kWh-ENS
(WORST DISTRICTS) Above 3x national ref.
14.4 €/kWh-ENS 28.8 €/kWh-ENS
national reference (SAIDI-net): urban 25 min/cust/year, rural 60 min/cust/year
Values based on a Willingness-to-Pay (WtP) survey, commissioned by AEEG. For further details: • Bertazzi, Fumagalli, Lo Schiavo, The use of customer outage cost surveys in policy decision-making:
the italian experience in regulating quality of electricity supply, CIRED (2005) paper n. 300• CEER, Guidelines of Good Practice on Estimation of Costs due to Electricity Interruptions and Voltage
Disturbances, Ref. C10-EQS-41-03, December 2010.
VOLL: UNIT VALUE OF AVOIDED ENERGY NOT SUPPLIED (ENS)
05/05/2018
26
THE REGULATORY EXPERIENCE IN ITALY : a practical cas e
Luca Lo Schiavo, ARERA (Italy) 51ERRA 08.05.18
THE REGULATORY EXPERIENCE IN ITALY : RESULTS
Luca Lo Schiavo, ARERA (Italy) 52ERRA 08.05.18
• Huge improvement in QoSover 4 reg.periods
• Limited impact on tariff(less than 3 €/cust/year)
• Resilience issues in last years (out of DSO control)
• «Convergence» effectto recover existing gaps
among districts of the sameterritorial density
05/05/2018
27
Annex 2Smart metering (from 1st to 2nd generation)
Luca Lo Schiavo, ARERA (Italy) 53ERRA 08.05.18
ELECTRICITY SMART METERING: a synopsis for Italy
54
Italy has been the first Country with full roll-out of smartmetering:
• More than 35 million customers with smart meters
• More than 100 distribution companies operating their ownsmart metering systems (even the smallest ones)
• More than 400 million readings per year remotely operated
• More than 10 million operations per year for remote customer management
• More than 28 million customers with Time-of-Use tariff(households: 2 price-bands; small business: 3 bands)
• More than 15 years of experience in smart metering
Luca Lo Schiavo, AEEGSI (Italy)ERRA 08.05.18
05/05/2018
28
ELECTRICITY SMART METERING: European developmentson
BenchmarkingReport on
Smart metering
Eur. CommissionRecommendation
148/2012
EuropeanDirective
2009/72/CE
2009 2012
EuropeanDirective
2012/27/UE
2014
«WinterPackage»
2016
The pioneering Italian case for smart metering (launched in 2001 on initiative of three distributors, among which Enel)
has been a benchmark for Europe
55Luca Lo Schiavo, AEEGSI (Italy)ERRA 08.05.18
ELECTRICITY SMART METERING: Italy was a pionieer
56
Italy: Decree MiSE 60/2015
Periodical verification forlow-voltage electricity meters: 15 years (“MID meters”)
Investments for smart metering
Italy: 97 euro/point
France*: 135 euro/point
G. Britain**: 161 euro/point
Finland: 210 euro/point
Netherlands**: 220 euro/point
Sweden: 288 euro/point
Spain: not available
Source: Eur.Commission, SWD(2014) 189 final* roll-out on going ** roll-out on going, joint gas/electricity
Luca Lo Schiavo, AEEGSI (Italy)ERRA 08.05.18
05/05/2018
29
ELECTRICITY SMART METERING IN ITALY: benefits
57
1G METERING TARIFF (Euro/point, current values 2004-2016)
Luca Lo Schiavo (AEEGSI)Eurelectric 28.09.17
References to tariff decisions:Del. 5/04; Del. 275/06
Del. 348/07; Del. 199/11Del. 654/15
BENEFITS 1G
• Time-of-use energy pricing (mandatory)
• Monthly readings
• Almost no estimatedbills
• Easy switch (spot reading)
• Minimum “vital” service
• better service(prompt reconnection)
• energy balance in LV networks
Time-of-Use price (LV customers in Universal Supply Regime)
Luca Lo Schiavo, AEEGSI (Italy) 58
• In the free market customers can be supplied with «flat» prices(no ToU mandatory requirement for energy prices).
• Consumptions are however read separately for timebands evenfor free market customers (DSO is the metering operator).
Universal Supply Regime: Household & Small business customersthat do not choose their own supplier
USR energy prices regulated by AEEG are differentiated per time-bands on mandatorybasis:
• Household: 2 bandspeak vs. (mid-level+off-peak)
• Small business: 3 bands
M T W T F S S
peak
off-peak
mid-level
7.008.00
19.00
23.00
0.00
24.00
ERRA 08.05.18
05/05/2018
30
SMART METERING: did the “1 st generation” work?
59Luca Lo Schiavo (AEEGSI) 59
WHAT WE GOT OUT OF 1G … …AND WHY
High availability96% of remote readings properly
accomplished (end-to-end)
Very good reliabilityNo relevant cases for meter substitution
due to faults
Limited cases of interference
between PLC and inverters
PV inverters EM emissions reduce data
acquisition (prosumers counting <2%)
1 channel only, not available for
real-time data messages
Communication channel (via PLC band A)
dedicated exclusively to validated data
Very limited use for voltage dataBuffer for interruption events too shortVoltage measurement not compliant with EN 50160
No interoperability with 3rd party
In-Home Devices
No message encryption (launched in 2001),
non disclosed protocol (cyber-sec. reasons)
Slow reconfiguration process Overall firmware download: ≈9 months
ERRA 08.05.18
SMART METERING: “future-proof” design criteria (416/2015)
Ensure electro-magnetic immunity from disturbances
Allow for multi-channel communication (PLC and radio)
Ensure advanced cyber-security measures (eg. data encryption)
Improve integration between smart metering and smart grid roll-out
Minimise constraints of backward compatibility for next generation
Minimize occasions for system reconfiguration (firmware download)
Ensure hardware independency for any function
Keep separate communication resources for remote reading and for energy efficiency
Ensure interoperability with third party in-home devices
Ensure interchangeability with metering systems of other DSOs
Luca Lo Schiavo, AEEGSI (Italy) 60ERRA 08.05.18
05/05/2018
31
SMART METERING: system architecture from “1G” to “2G”
61
PLC (band A)
MV/LVtrasf.
Smart meters
Public TLC
Data Concentrator
AMMsystem(DSO)
web
Retail suppliers
Customisation (for suppliers)
New concept: distinctionbetween
• Chain 1: from meter to retailer (validated data), similar to 1G, empowered
• Chain 2: from meter to customer (directly, realtime data but non validated): new
Third partyin-home devices
“Chain 2”:instantaneous data from meterto customer
PLC (band C)
Remotereading andcustomer management
Reconfiguring the system(download)
Telemonitoring(upload)
Upgrade LTE
+backup RF
Luca Lo Schiavo (ARERA)ERRA 08.05.18
CHAIN 1: meter reading for billing, from 1 st to 2nd generation
Luca Lo Schiavo (AEEGSI) 62
1st
GENERATIONCapacity 1G Meter
reading1G reading content
Default.supplbilling
Households Any(typic 3kW)
Monthly 3 timebands 2 prices(mandatory)
Small business
Up to 55kW Monthly 3 timebands 3 prices(mandatory)
Medium business
Above 55 kW Monthly 96 quarter-hours per day
N/A (only free market)
2nd
GENERATION)Capacity 2G Meter
reading2G reading content
Default.supplbilling
All customers Any Daily 96 quarter-hours per day
N/A (only free market)
1G: fixed time bands, preloaded in the meter � need for massive reconfiguration
2G: time bands directly customizable by suppliers � no need for massive reconfig.
ERRA 08.05.18
05/05/2018
32
SMART METERING: data collected, from 1 st to 2nd generation
Metering data 1G 2G
Active energy withdrawn 3 values per month [Wh]* every 15 min [Wh]
Active energy injected 3 values per month [Wh]* every 15 min [Wh]
Reactive energy withdrawn 3 values per month [Wh]* every 15 min [VARh]
Reactive energy injected not available every 15 min [VARh]
Active power withdrawn peak in 15 min [W](max value in the month)
peak in 15 min [W](max value in the day)
Active power injected not available peak in 15 min [W](max value in the day)
Instantaneuos power 2 sec [W] (last value on display)
up to 1 sec [W] (available via chain 2 in realtime)
Max/min voltage some measure availablebut non EN50160-compliant
per week [V](EN50160-compliant)
Interruption event
(voltage below 5% of Un)
(in practice not used
because of too short buffer)
on event occurrence: start, end, duration [min.ss]
63(*) Only for 1% of LV customers (those with rated capacity >55kW): 1 value every 15 min
SMART METERING: 2nd generation concept (decision 87/2016)
Luca Lo Schiavo (AEEGSI) 64
«Chain 1»
• Purpose: billing and network managem’ t
• Validated data, SLA
• Daily collection
• Operated by DSO
• Back-up channel
«Chain 2»
• Purposes: customerawareness and valueoffering for suppliers
• Real-time, notvalidated data
• Continuous flow
• Interoperable with 3rd party IHDs
• No back-up channel
ERRA 08.05.18
Under development
05/05/2018
33
CHAIN 2 (new with 2G): interoperable In-Home Device
Luca Lo Schiavo (ARERA) 65
• IHDs developed by third parties (integrated with home ecosystem)
• Standard communication protocol(independent of manufacturers)
• Developed by CEI (standardisationbody) with industry consensus: July-2017 (CEI TS 13-82/85)
• Start with physical layer PLC in CENELEC “band C”
• Monitoring phase under course,very good performance (end-to-end)
• Release 2.1: cooperation with Agcomon further options for chain 2 -consultation paper ARERA n.245/18
wireline/contact
wireline/wireless
Generic
Frequent- 1 retry
Rare - 4 retry
Avg 98,79% 98,23%
95 percentile 97,28% 100 %
99 percentile 50,64% 0 %% success in daily samples
ERRA 08.05.18
CHAIN 2 (new with 2G): real-time communication
• “frequent asynch data”: level of used power capacity changes very rapidly; limitation of contractual power can lead to disconnection
• Requirements: sampling up to every 1 second “frequent asynchdata” are not to be stored (strong privacy issues)
L.Lo Schiavo, A.Pitì (AEEGSI, IT)
1
2
3
3.3
PUSH PUSH PUSH PUSH PUSH PUSH
PUSH ALERT
P [kW]
T [sec]
011001…101
PUSH
66ERRA 08.05.18
05/05/2018
34
SUMMARY: from 1st to 2nd generation of smart meterin g
1G field experience including trials on IHDs
Functional requirements (decision 87/16) after public consultation(416/15)
Rules for cost allowance based on sharing matrix(decision 646/2016)
Roll-out approval: Regulator’s decision after public consultation of distribution company’s roll out plan(decision 222/2017)
Analysis of technical evolution for a more advanced version (“2.1”)of smart meter in cooperation with telecom Regulator (AGCOM)(consultation 245/2018)
Luca Lo Schiavo, AEEGSI 67ERRA 08.05.18
TRASPOR-TATION
Vertical regulation vs cross-sector innovation
68
ENERGY
TELECOM
ENERGY
Luca Lo Schiavo, AEEGSIERRA 08.05.18
05/05/2018
35
COOPERATION AMONG SECTORIAL NRAs: energy and TLC
AEEGSI contribute to AGCOM survey on M2M services
In particular, AEEGSI underlined the relevance of latency and proposed the following classification:
A.monitoring: remote data collection and configuration, without delay requirements
B.control: data collection and implementation commands with low delay requirements (1s)
C. protection: data collection and immediate reaction in difficult circumstances where speed is essential for safety or security reasons (<1s)
Smart meters(traditional)
Smart meters(advanced)
Smart grids(most
functionalities)
Smart grids(faster
functionalities)
69
The AEEGSI contribution to AGCOM survey has been published: www.autorita.energia.it/allegati/inglese/457-14eng.pdf (in English)
Luca Lo Schiavo, AEEGSIERRA 08.05.18
SMART GRID and SMART METERING: a synthesis
Luca Lo Schiavo, AEEGSI (Italy) 70
Smart grid Smart metering
BenefitsRES integrationSystem security
Cost efficiencyRetail competition
Latency issuesDown to 100 ms
(fast fault selection)Close to 1 s
(non validated data)
Size(number of points, IT)
0,6 M prosumers0,4 M MV/LV substations
35 M customers
Asset managementTLC layer relatively
independentTLC layer intimately
embedded
Cooperationenergy/TLC NRAs
Access to passive infrastructure (OF)
Technology neutralityvs best performance
ERRA 08.05.18
05/05/2018
36
Annex 3Electro-mobility and recharge infrastructure
Luca Lo Schiavo, ARERA (Italy) 71ERRA 08.05.18
EV recharge (1/2) (acknowledgement: ABB)
72
+
+
Parking- Parking garage- Residential- Office
Commercial- Daily shopping- Lunch- Medium distance trip
Highway- Long distance trip
Typical time spent 2-10 hours 30-90 min 10-20 min.
Power level < 20 kW ~50 kW 50-300 kW
Typical Performance
2010-2017 Small EV(~30 kWh)
Full charge Full charge To ~80% in 20 min.(Max. 50 kW)
>2018 Long range EV(>80 kWh)
50-100% charge 50-100% charge To 80% in 15 min.(150 - 300 kW)
Luca Lo Schiavo (ARERA)ERRA 08.05.18
05/05/2018
37
EV recharge (2/2) (acknowledgement: ABB)
73
2x4x
8x
First priority for operators: more outlets, more locations
Luca Lo Schiavo (ARERA)ERRA 08.05.18
EV recharge (in public places): main relationships
74
Charging station
Smartmeter
Distribution gridElectric vehicles(EVs)
CHARGING POINT OPERATOR (CPO)
ELECTRICITYSUPPLIER
EV DRIVERS
ELECTRICITYDISTRIBUTION COMPANY
1a
2
3
Displays (can be set to zero at eachtransaction)
4
CONTRACTUAL RELATIONSHIPS
1a. EV Driver – CPO (directly)
2. CPO – Elect.Supplier
3. Elect.Supplier – DSO
4. DSO – CPO (only for connection)
Chargingpoint
Chargingpoint
Chargingpoint
Other usesof electricity
• Interoperability issues are the focus of SGEMS (Sub Group for Electro-Mobility Services) within the Sustainable Transport Forum
Point of delivery
MOBILITY SERVICE PROVIDERS (MSP)
1b
1b
1b. EV Driver – CPO (intermediated by MSP)
Luca Lo Schiavo (ARERA)ERRA 08.05.18
05/05/2018
38
EV recharge at home: removing old «progressive» tariff
75
Yearly expenditure for network tariff [€]
0
50
100
150
200
250
300
0 900 1.800 2.700 3.600 4.500 5.400
Household consumption (P=3 kW)
D2-2015
D3-2015
TD
Resident(2015)
Non resident(2015)
New tariff(2017)
• In Italy a non-linear, progressive tariff for household was introduced in ’70s for energy efficiency
• The progressive tariff proved to be a barrier for electro-efficient new technologies
• ARERA launched a reform for a new cost-reflective tariff for household
• New network tariff has been fully introduced from 1.1.17
• New tariff is largely capacity based (see CEER guidelines, Ref. C16-DS-27-03, 23 January 2017)
Luca Lo Schiavo (ARERA)ERRA 08.05.18
EV recharge prices: an European example
76
€/kWh is a too simple approach:
price of EV charge is due to many factors, not only energy but also number of transactions, speed of charge, time-of-use - Further, price will
be influenced by demand aggregation (role of MSPs as wholesale buyer)
…prices charged by the operators of recharging points accessible to the public are reasonable, easily and clearly comparable, transparent and non-discriminatory
AFID, 4(10)
Luca Lo Schiavo (ARERA)ERRA 08.05.18