35
LOREM IPSUM DOLOR SIT ADMIN AMET CONSET LOREM IPSUM DOLORS SIT AMET FOAMED ASPHALT STABILIZED BASE (FASB) – ANOTHER TOOL FOR AIRFIELD PAVEMENT STRUCTURAL REHABILITATION? The Solution for the 2013 Groundside Road (Russ Baker Way) Rehabilitation Project at YVR Presented by: Ken Fyvie, Airfield Pavement Specialist SNC Lavalin Inc – Airport Group

LOREM IPSUM (Russ Baker Way) Rehabilitation …Thursd… · LOREM IPSUM DOLORS SIT AMET FOAMED ASPHALT STABILIZED BASE (FASB) ... • Constructed via Federal Ministry of Transport,

Embed Size (px)

Citation preview

LOREM IPSUM

DOLOR SIT ADMIN

AMET CONSET LOREM IPSUM DOLORS SIT AMET

FOAMED ASPHALT STABILIZED BASE (FASB) – ANOTHER TOOL FOR AIRFIELD PAVEMENT

STRUCTURAL REHABILITATION?

The Solution for the 2013 Groundside Road (Russ Baker Way) Rehabilitation Project at YVR

Presented by: Ken Fyvie, Airfield Pavement Specialist SNC Lavalin Inc – Airport Group

SWIFT is about airfield pavements, not

highway pavements!

Yes it is… But many (all?) of the same challenges apply to airfield pavements as for highway pavements including:

• Insufficient pavement strength for current traffic mix & loading “legacy pavements”

• Geometric constraints

• Operational constraints/duration of work

• Financial constraints

• So….

Presentation Outline

• Project Background & Site Information

• Rehabilitation Options − Options considered

− Selected solution

• Project Execution/Getting’ ‘Er Done − The Foamed Asphalt Stabilized Base (FASB) Process

• Observations & Conclusions − Results

− Advantages / Benefits

Questions?

Russ Baker Way Northbound spring 2013 – alligator/fatigue cracking, rutting, etc.

Project Background & Site Information

Project Background & Site Information

Russ Baker Way Southbound spring 2013 – alligator/fatigue cracking, rutting, etc.

Russ Baker Way Background & Site Conditions

• Russ Baker Way, North and Southbound lanes, Miller Road to Inglis Drive

• Overall roadway: ~1.7 kms, 4 – 6 lanes divided with no-post barriers, grass & raised medians & some curb & gutter

• Constructed via Federal Ministry of Transport, early 1970’s

• Inglis end resurfaced during No. 2 Road Bridge construction

• Richmond-Vancouver commuter route; YVR Terminal(s) access routes; air-freight; fire hall; BCIT campus; bus route

• Fatigue issue concentrated in wheel paths between Miller Road & north of Gilbert, ~1.25 kms

Russ Baker Way Location Context

To YVR Main Terminal Arthur Laing Bridge to Vancouver

No. 2 Road Bridge to Richmond

Dinsmore Bridge to Richmond

Sea Island/YVR

City of Richmond To South Terminal

Russ Baker Way Location – Major Distress Zone

Major distress zone ~ 1.25 kms

Russ Baker Way Background & Site Conditions

Relative strength & condition assessed, March 2010, including: − Benkelman Beam

deflection testing − Visual condition − As-built drawings for

pavement structure − Test pits at road edge

from BCIT campus road widening work

− City of Richmond traffic data, 2006 “arterial road” 53,230 (ADT) north of Gilbert

− City of Richmond traffic data, 2006 “arterial road” 37,300 (ADT) south of Gilbert

− Preliminary pavement rehabilitation options provided in 2010 (by others)

As Built Records (Transport Canada historical)

₋ Asphalt concrete pavement: 90 mm (3.5”)

₋ Crushed granular base: 230 mm (9”)

₋ Select sand sub-base: 450 mm (18”)

₋ Compacted sub-grade: 300 mm (12”)

City of Richmond “Standard” Divided Arterial roadway pavement section:

₋ Asphalt concrete pavement: 150 mm (6”)

₋ Crushed granular base: 230 mm (9”)

₋ Granular sub-base: 500 mm (20”)

₋ Compacted sub-grade: 300 mm (12”)

₋ Design MPSR < 1.00 mm

1. Overlay with 50 mm new hot mix asphalt: reflection cracking, limited term solution.

2. Partial Reconstruction: remove existing asphalt pavement, re-compact granular base & partial base gravel replacement/thickening; 150 mm of new hot mix asphalt: medium term solution. Partial strengthening. Reflection cracking mitigated?

3. Full Depth Reclamation: Pulverize & reinstate with 230 mm +/- additional granular base and 150 mm new HMA (~ 380 mm increase in pavement elevation/impact of adjacent pavement/curb & gutter, etc.). Strengthened. Reflection cracking mitigated.

Preliminary Rehabilitation Options (2010)

Next Steps (2013) – Detailed

Design/Construction

28 shallow test holes - confirm layer thicknesses, assess granular qualities; complete topo survey

Next Steps (2013) – Detailed

Design/Construction

1. Establish 2-3 alternative rehabilitation options considering expected pavement performance, traffic, geometric and cost constraints

2. Provide cost estimates for options

3. Pro’s & con’s of options

4. Provide recommendations

5. Include optional pay items & pricing in tender as applicable

Next Steps (2013) – Detailed

Design/Construction

SNC-Lavalin - Rehabilitation Option(s)

1. Cold-mill & inlay 65 mm – limited functional life, no increase in strength, reflection cracking, return of fatigue cracking

2. Remove 90 mm asphalt & 60 mm granular base & dispose, replace with 150 mm HMA – disruptive, existing material wasted

3. Divide roadway into 3 segments; vary treatments based on deflections, distress severity & extent

4. Deep repair Miller and Gilbert intersection segments (1 & 3): remove asphalt & granular to 150 mm, replace with new HMA

5. Full depth reclamation to 325 mm (no additives) remove 125 mm base, grade & re-compact base, place 150 mm new HMA

6. Full depth reclamation to 325 mm, remove 125 mm base& re-use; grade & re-compact , FASB to 200 mm, place 125 mm of new HMA (-19 mm, high stability)

Selected Rehabilitation Option

1. Divide roadway into 3 segments; vary treatments (3 segments, 3 treatments) based on deflections, traffic, distress severity & extent

2. Segments 1 & 3: deep repair Miller and Gilbert intersection segments (remove asphalt & granular to 150 mm, replace with new HMA)

3. Cold-mill & inlay non-thru lanes & shoulders (65 mm)

4. Segment 2: Pulverize to 325 mm, remove 125 mm of pulverized granular & re-use; grade & re-compact, (option for FSAB) place 150 mm/125 mm of new HMA

5. Detailed contractor Traffic Management Plan required

Tenders Results

Full Depth Reclamation (FDR) without FASB

Full Depth Reclamation (FDR) with FASB

$ 0.00 + 15 %

~ 15% additional cost considers net savings associated with 25 mm reduction in HMA thickness YVR Engineering chose to use FASB technology due to expected improvement in long-term pavement performance: more robust; less waste. Wanted to assess process and performance for potential use on other groundside roads and selected airfield pavements FDR/FASB grading and removal/replacement 06:00-20:00; asphalt paving 20:00-06:00. Option to work 7 days per week.

Key Dates/Construction Progress

Key Milestones Date

Award (Columbia Bitulithic Ltd./Lafarge) July 4, 2013

Construction Start (detours/traffic prep) July 25, 2013

Pulverizing starts (southbound) July 31, 2013

FASB Southbound & HMA Paving August 9-20 (2 days curing)

FASB Northbound & HMA Paving August 21-September 3 (2 days curing)

Intersection deep repair/mill & inlay August 27-September 3

Paint Markings/Signals September 5-25

Substantial Performance October 3, 2013

Total Performance (including added work)

October 11, 2013 (includes south terminal loading areas (2), Agar Drive & new bike path paving)

Steps for FASB / Repaving Process

1. Foamed Asphalt Stabilized Base mix design (by contractor/3rd party testing lab)

2. Asphalt concrete pavement/granular base reclamation (pulverization), 125 mm removal, re-grading & compaction

3. Foamed Asphalt Stabilized Base (FASB) processing, compaction, fine grading & curing

4. Place new HMA (coarser mix, high stability; surface lift paved in echelon with hot joints)

Property Minimum

Dry Stability, @ 25°C, kN 9.0

Retained Stability @ 25°C, % (24 hrs) 50

Dry Indirect Tensile Strength, kPa 300

Wet Indirect Tensile Strength, kPa 150

Tensile Strength Ratio, % 50

Bitumen Content, % 2.5

Cement Content, % 1.0

Field Compaction, % max. modified proctor dry density

98

FASB Mix Requirements (200 mm)

In accordance with Wirtgen Cold Recycling Manual, 2nd Edition (2004) and Project Specifications

Gettin’ ‘Er Done – the FASB Process

Wirtgen WR2500S Reclaimer (pulverizing)

Wirtgen WR2500S Reclaimer and water tanker truck (pulverizing)

Gettin’ ‘Er Done – the FASB Process

Pulverized, re-graded and re-compacted granular base before FASB treatment

(southbound lanes)

Pulverized, re-graded granular base before FASB treatment

(southbound lanes)

Cement powder applied to granular surface, before foaming treatment

Gettin’ ‘Er Done – the FASB Process

Wirtgen WR2500S reclaimer led by asphalt cement nurse truck, followed by

water tanker truck

FSAB bitumen addition metering system

Gettin’ ‘Er Done – the FASB Process

Cement distributer with metering system

Gettin’ ‘Er Done – the FASB Process

The FASB Process, schematic courtesy of Wirtgen

The FASB Process, schematic courtesy of Wirtgen

Gettin’ ‘Er Done – Bitumen Foaming Process

Post Construction Observations & Conclusions

• QC by Contractor, QA by YVR/Consultant

• FASB test properties met specifications, including all compaction tests (≥ 98 % MMPDD) & TSR’s > 50%

• Stability of FASB mix: all tests > 24 kN (to 35 kN) > 9.0 kN specified

• HMA test properties met specifications, including compaction tests (> 97%)

• Benkelman Beam test comparison by lane, before (2010) versus after (2013) – achieved target deflection of < 1.00 mm MPSR (highest MPSR was 0.86 mm, lowest 0.72 mm)

Advantages & Benefits Achieved

Traffic disruptions reduced by avoiding major layer strengthening/thickening/excavation

Existing pavement materials recycled or re-used

MPSR was lowered by up to 38 %

Major reduction in relative strength variability of rehabilitated pavement

Replacement HMA thickness reduced by 25 mm (~ 17 %)

Trucking of unused material was nearly eliminated (excess used on site), RAP will be re-used by supplier in new HMA

Advantages & Benefits Achieved

Major reduction in need for new aggregate & asphalt (“green”)

Major reduction in truck hauling

Reflection cracking from underlying, cracked asphalt layer eliminated

Longitudinal profile, cross-section & ride quality dramatically improved; surface drainage improved

Project completed within budget & schedule

Contractor’s Traffic Management was excellent & disruption very limited; work completed before seasonal traffic increase

Before and After – A Team

Effort!

Russ Baker Way, Northbound from Cessna Drive (before)

Russ Baker Way, Northbound from North of Cessna Drive (after)

A Viable Airfield Pavement Rehabilitation Solution!

Discussion & Questions…???

Thanks for your time and attention!

WE CARE embodies SNC-Lavalin’s key corporate values and

beliefs. It is the cornerstone of everything we do as a company.

Health and safety, employees, the environment, communities

and quality: these values all influence the decisions we make

every day. And importantly, they guide us in how we serve our

clients and therefore affect how we are perceived by our external

partners. WE CARE is integral to the way we perform on a daily

basis. It is both a responsibility and a source of satisfaction and

pride by providing such important standards to all we do.

WE CARE about the health and safety of our employees, of those who work under our care, and

of the people our projects serve.

WE CARE about our employees, their personal growth, career development and general well-

being.

WE CARE about the communities where we live and work and their sustainable development, and we commit to

fulfilling our responsibilities as a global citizen.

WE CARE about the environment and about conducting our business in an environmentally responsible manner.

WE CARE about the quality of our work.