Loraine Independent School District. Campus Improvements Construction Update January 21 , 2012. PROJECT STATUS. PLANS. PLANS. SCHEDULE. SCHEDULE STATUS. Underground Plumbing And Electrical Rough-in Is Complete In All Areas - PowerPoint PPT Presentation
Citation preview
Loraine IndependentSchool District
• Campus Improvements• Construction Update
• January 21, 2012
PROJECT STATUS
Budgeted Amount
Cost Savings
GMP Total
Amount Billed
Through December
% Comp
Owner's Contingency
Contractor Contingency
$10,800,000 $83,599 $10,716,401 $1,899,230 17% $106,287 $214,328
PLANS
PLANS
SCHEDULE
Underground Plumbing And Electrical Rough-in Is Complete In All Areas
Concrete Slabs Have Been Poured In All Areas That Are Ready At This Time.
Masonry is 90% Complete In Locker Room Areas And Has Begun At The Gymnasium.
Steel Erection Is In Progress at the Gymnasium, Locker Room And JH/HS Classroom Areas
Bus Barn Concrete Has Been Poured
SCHEDULE STATUS
Masonry at Gymnasium
Gymnasium Steel Structure
Masonry and Steel at Gym
Steel at JH/HS Classroom Wing
Masonry Will Continue Over The Next Month Steel Erection Will Continue In All Areas Exterior Drywall Framing And Sheathing Will Begin MEP Wall And Ceiling Rough-In Will Follow CMU And
Drywall Framing The Bus Barn Structure Will Deliver By Mid February
LOOKING AHEAD