Upload
hoangkien
View
219
Download
2
Embed Size (px)
Citation preview
LonghornDamLabyrinthWeir
ConceptualEvaluation
Preparedfor:
Austin Energy
June2013
Preparedby:
FREESEANDNICHOLS,INC.10814JollyvilleRd.,Bldg.4,Ste100
Austin,Texas78759512‐617‐3137
TBPEFirmF‐2144
LonghornDamLabyrinthWeir
ConceptualEvaluationPreparedfor:
Austin Energy
June2013
Preparedby:
FREESEANDNICHOLS,INC.10814JollyvilleRd.,Bldg.4,Ste100
Austin,Texas78759512‐617‐3137
TBPEFirmF‐2144
AU412421
DRAFT
This document is released for the purpose of interim review under the authority of Dustin Mortensen, P.E., Texas No. 100000 on June 21, 2013. It is not to be used for construction, bidding or permit purposes. Freese and Nichols, Inc. Texas Registered Engineering Firm F‐ 2144
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
i
TABLEOFCONTENTS
1.0 PROJECTOVERVIEW..................................................................................................................................1
1.1 Background.................................................................................................................................................1 1.2 Purpose.........................................................................................................................................................1 1.3 RiverFlowRates.......................................................................................................................................1
2.0 GATEDSTRUCTURE....................................................................................................................................4
2.1 OriginalDesign..........................................................................................................................................4 2.2 GateOperation...........................................................................................................................................6 2.3 GatedSpillwayRatingCurve...............................................................................................................9 2.4 HistoricalPerformanceofExistingDam.....................................................................................10 2.5 GateRehabilitationProjectSummary..........................................................................................12
3.0 FIXEDWEIR.................................................................................................................................................14
3.1 FixedWeirOverview...........................................................................................................................14 3.2 LabyrinthWeirExamples..................................................................................................................15 3.3 ProposedLabyrinthConfigurationatLonghornDam..........................................................17 3.4 LabyrinthWeirRatingCurve...........................................................................................................19 3.5 LabyrinthPerformance......................................................................................................................21 3.6 BackwaterAnalysis..............................................................................................................................25
4.0 LABYRINTHWEIRASSESSMENT.......................................................................................................26
4.1 LakeLevels...............................................................................................................................................26 4.2 HikeandBikeTrail...............................................................................................................................26 4.3 CesarChavezStreetatLamarBoulevard....................................................................................26 4.4 ExistingStructuresandthe100‐YearFloodplain...................................................................27 4.5 DebrisandSedimentation.................................................................................................................27
5.0 STAKEHOLDERMEETINGS...................................................................................................................29
5.1 PublicWorks...........................................................................................................................................29 5.2 ParksandRecreation...........................................................................................................................29 5.3 WatershedProtectionDepartment...............................................................................................30 5.4 AustinWaterUtility.............................................................................................................................31 5.5 LowerColoradoRiverAuthority....................................................................................................31 5.6 LakeBrazosDamSiteVisit................................................................................................................31
6.0 ENVIRONMENTALANDPERMITTINGCONSIDERATIONS.....................................................32
6.1 EnvironmentalPermitting................................................................................................................32 6.2 TCEQDamSafety...................................................................................................................................32
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
ii
6.3 StateHistoricPreservationOffice..................................................................................................32
7.0 OPINIONOFPROBABLECONSTRUCTIONANDOPERATIONCOSTS.................................34
7.1 GateRehabilitationProject...............................................................................................................34 7.2 LabyrinthWeirProject.......................................................................................................................34 7.3 LifeCycleCosts.......................................................................................................................................35
8.0 CONCLUSION...............................................................................................................................................36
8.1 Comparison..............................................................................................................................................36 8.2 Conclusion................................................................................................................................................37
TableofFigures
Figure1:LonghornDamExistingSitePlan...................................................................................................5 Figure2:CrossSectionofDamandStillingBasinthroughLiftGate.................................................6 Figure3:Downstreamsideofautomatedbasculegate...........................................................................7 Figure4:Downstreamviewofliftgate3.......................................................................................................8 Figure5:GateoperationoccursonthissidewalksharedwiththeHikeandBikeTrail...........9 Figure6:GatedSpillwayRatingCurve–BestCaseScenario.............................................................10 Figure7:HistoricalNormalLevelswithReleasesfromTwoTurbinesatTomMillerDam.11 Figure8:HistoricalLadyBirdLakeLevelscomparedtoBestCaseGateOperation................12 Figure9:PlanViewofTypicalLabyrinthWeir........................................................................................14 Figure10:LakeBrazosDamshortlyafterconstruction.......................................................................15 Figure11:LakeTownsendLabyrinthWeirunderConstruction(Schnabel,2013).................16 Figure12:ElmendorfDam................................................................................................................................16 Figure13:RenderingofLabyrinthWeiratLonghornDam................................................................17 Figure14:LabyrinthWeiratLonghornDamwithcyclesconnectedtoexistingbridgepiers.......................................................................................................................................................................................18 Figure15:LabyrinthWeiratLonghornDamwithcyclesnotconnected toexistingbridgepiers.............................................................................................................................................................................18 Figure16:RatingCurveforGatedStructureandLabyrinthWeir...................................................19 Figure17:HistoricalLadyBirdLakeLevelsvs.PredictedRatingCurves....................................20 Figure18:FractalLabyrinthWeir.................................................................................................................21 Figure19:HistoricalDamPerformanceandPredictedLabyrinthPerformance......................22 Figure20:ObservedandPredictedLakeLevelsforNovember2004Flood...............................23 Figure21:ObservedandPredictedLakeLevelsforSeptember2010Flood(TropicalStormHermine)...................................................................................................................................................................23 Figure 22: Observed and Predicted Lake Levels during typical LCRA Releases from OneTurbine.......................................................................................................................................................................24 Figure 23: Observed and Predicted Lake Levels during typical LCRA Releases from TwoTurbines....................................................................................................................................................................24
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
iii
TableofTablesTable1:DischargeforVariousStormEvents..............................................................................................2 Table2:HistoricalEventswithDischargeGreater than25,000cfs(USGSGage08158000,ColoradoRvatAustin)...........................................................................................................................................3 Table3:KeyFeaturesofGateRehabilitationConceptualDesign....................................................13 Table4:LakeLevelsatVariousStormEvents..........................................................................................20 Table5:GatedStructureRepair,OperationandMaintenanceItemCosts...................................34 Table6:LabyrinthWeirConstructionandOperationCosts..............................................................35 Table7:LifeCycleCosts.....................................................................................................................................35 Table8:AttributesofAlternatives.................................................................................................................36 Appendices Appendix A ‐ Backwater Figures Appendix B ‐ Flood Prone Areas Identified by Parks and Recreation Appendix C – Labyrinth Weir Opinion of Probable Construction Cost Appendix D ‐ Survey Points Appendix E ‐ Rating Curves Appendix F – Project Schedules
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
ES‐1
EXECUTIVESUMMARY
Longhorn Dam was constructed with a gated spillway in 1960 to create a cooling pond for Holly Power
Plant. Austin Energy has operated and maintained the dam since construction. Now, with the
decommissioning of Holly Power Plant, Longhorn Dam will have no functional relationship to Austin
Energy and power generation. Nevertheless, Austin Energy continues to operate and maintain the dam
and gates. The dam is now in need of numerous repairs and upgrades to improve the reliability of the
dam and spillway gates. A conceptual design to repair the dam, replace the gate operators and make
improvements to the channel and river banks was previously prepared by Freese and Nichols, Inc. (FNI).
Austin Energy prioritized the repairs in the conceptual design and decided that $10 million in repairs
were dam operation and maintenance priorities. Prior to designing the proposed improvements, Austin
Energy requested that FNI evaluate the option to construct a fixed weir at Longhorn Dam in lieu of
repairing the gates and operators. It was anticipated that a fixed weir would reduce the operations and
maintenance requirements of the dam.
This report presents the conceptual evaluation of a labyrinth spillway as a fixed weir and replacement to
the gates at Longhorn Dam. A labyrinth spillway is a passive structure that uses a trapezoidal‐shaped
weir wall geometry (plan view) to increase the weir length in a channel and thus increase discharge. The
labyrinth weir has benefits over the gated structure; these benefits are directly related to the
elimination of the gates. The largest benefit is that the labyrinth does not require personnel to operate
the lift gates during storm events or to verify that the automated bascule gates are functioning properly.
Another benefit is predictable lake levels during storm events. The historical record indicates that lake
levels have risen several feet higher than predicted by river models due to spillway gates not being
timely opened. Operating spillway gates during storm events to maintain the desired lake levels is
challenging and requires frequent gate adjustment. The labyrinth weir will eliminate higher than
anticipated lake levels caused by difficulties in proper gate operation. The labyrinth weir will also
prevent water from being wasted, which has occurred when the gates release more water than planned
causing the lake level to drop below normal pool.
There are drawbacks to the labyrinth weir at Longhorn Dam. During major floods similar to those that
occurred in 1997 and 2002, the labyrinth weir will cause the lake level to be approximately two feet
higher than it would be if the spillway gates were operated properly and timely. Historically the
Longhorn Dam gated system has not approached this level of control. Another drawback of the labyrinth
weir is that debris will not flow over the dam as easily as it does through the gates. The labyrinth weir
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
ES‐2
will likely require debris removal, especially following storm events, although this could be mitigated
with a debris boom upstream.
The opinion of probable construction cost for the labyrinth weir is $15.0 million and the cost to repair
the gated structure is $10 million. Based on a 50‐year design life and 4% interest rate, the present value
of the gated structure is estimated at $20,000,000 and the present value of the labyrinth at
$17,040,000.
Longhorn Dam is a very important asset in need of improvements to properly serve its recreational
purpose. The labyrinth weir is a feasible replacement for the gated spillway. The selection of this
alternative over the gate repairs must consider if the advantages of reduced operational costs and more
predictable lake levels outweigh the disadvantages of higher lake levels during flood events and debris
removal.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
1
1.0 PROJECTOVERVIEW
1.1 BACKGROUND
Longhorn Dam is owned by Austin Energy and creates Lady Bird Lake. The dam was constructed in
conjunction with the Holly Power Plant to create a cooling pond for the plant. Now that the plant has
been de‐commissioned, Austin Energy is in the position of maintaining the dam solely for the purpose of
creating Lady Bird Lake. Austin Energy is charged with operating and maintaining the nine spillway gates
at the dam which are used to regulate the lake level and pass flood flows. The gates have a history of
poor operation and are not reliable. In 2012, Freese and Nichols (FNI) completed a conceptual design to
rehabilitate the dam and make improvements to the gate operation (Freese and Nichols 2012). The
proposed gate improvements would result in a dam that is more reliable and easier to operate.
The dam was previously operated and maintained by personnel at the Holly Plant. Because the Holly
Plant has ceased operation and is no longer staffed by Austin Energy personnel, ongoing efforts of gate
operations and maintenance at Longhorn Dam have been complicated. In an effort to minimize or
eliminate the need for gate maintenance and operations, Austin Energy requested that FNI conduct a
feasibility study of a fixed weir at Longhorn Dam as an alternative to the currently planned modifications
to the existing gates and hoists.
1.2 PURPOSE
This study developed a conceptual design of a fixed weir at Longhorn Dam and evaluated the feasibility
of the concept. The purpose was to evaluate lake levels with the labyrinth weir, identify stakeholders
who would be affected and develop budgetary opinions of probable cost. The conceptual design is
preliminary and intended to provide information to help decide how to proceed with improvements to
Longhorn Dam. The purpose of this report is to provide a summary of the concept and highlight
attributes and design considerations.
1.3 RIVERFLOWRATES
Daily flows through Longhorn Dam are largely controlled by Lower Colorado River Authority (LCRA)
releases from the Highland Lakes dams and especially Tom Miller Dam. There are two turbines at Tom
Miller Dam through which LCRA typically releases water. During storm events, flow through Longhorn
Dam comes from releases from Tom Miller Dam flood gates as well as flood flows from area creeks.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
2
LCRA has estimated flow rates at Longhorn Dam due to various storm events (Halff Associates 2003).
Discharge from the turbines as well as the various storm events are shown in Table 1.
Table 1: Discharge for Various Storm Events
Event Discharge
(cfs)
One Turbine 1,750
Two Turbines 3,500
2‐year 14,564
5‐year 24,567
10‐year 29,945
25‐year 50,050
50‐year 90,046
100‐year 90,361
500‐year 366,912
Lake Travis and Mansfield Dam significantly reduce flooding in the City of Austin by storing floodwaters
in the lake and releasing them in a controlled manner. LCRA releases from Mansfield Dam are regulated
by the U.S. Army Corps of Engineers (USACE). The regulations typically require LCRA to limit flows near
Longhorn Dam to 30,000 cfs. Releases of floodwater from Lake Travis may last from a few days to a few
weeks. Historical records show that average daily flow rates due to releases from Mansfield Dam have
exceeded 25,000 cfs for extended periods on a number of occasions. Table 2 shows that there have
been 141 days where the average daily flow rate was above 25,000 cfs since Mansfield Dam was
completed in 1942. These flows occurred in nine different years. The 2010 storm is not included in Table
2 because the average daily flow in 2010 only reached 15,900 cfs according to the USGS.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
3
Table 2: Historical Events with Discharge Greater than 25,000 cfs (USGS Gage 08158000, Colorado Rv at Austin)
Year Total Days
Average Daily Flow Rate
Maximum Average Daily Flow Rate
1957 32 34,072 37,900
1959 4 31,125 35,400
1977 4 30,200 31,500
1987 11 27,291 31,700
1992 49 29,635 35,500
1997 16 27,400 28,500
2002 6 26,166 26,800
2004 4 26,450 27,100
2007 15 25,953 26,700 Flood events that began in December and ended after January 1 are included with the following year.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
4
2.0 GATEDSTRUCTURE
2.1 ORIGINALDESIGN
Longhorn Dam is located on the Colorado River in the City of Austin approximately 1.5 miles east of IH‐
35. The dam is approximately 1,240 feet long and consists of a 506‐foot wide gated spillway with an
earthen embankment on each side of the spillway. The gated spillway supports a four lane bridge for
Pleasant Valley Road and the Hike and Bike Trail. Figure 1 shows a plan view of the dam.
Longhorn Dam was constructed in 1959 to create a cooling water supply for the Holly Power Plant. The
dam also improved the reliability of the water intakes to Seaholm Power Plant and the Thomas C. Green
Water Treatment Plant by replacing a rock weir located upstream of South First Street. The original
design of the dam included plans for a dam without the highway bridge as well as with the highway
bridge. The original study found that a highway bridge could be constructed across the river as part of
the dam for much less than the cost of a separate bridge (Brown & Root 1958). There are no
hydroelectric generating facilities at the dam, although there have been several studies regarding
hydroelectricity at Longhorn Dam, the most recent in 2011 (Toohey 2011).
The dam has seven, 50‐foot wide by 13‐foot tall manually operated lift gates and two, 50‐foot wide by 9‐
foot tall automated bascule gates. The spillway gates discharge into an 85‐foot long concrete bottomed
stilling basin. The stilling basin has an end sill that maintains 7 feet of water behind the gates to dissipate
energy. Figure 2 shows a cross section of the dam and stilling basin.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
6
Figure 2: Cross Section of Dam and Stilling Basin through Lift Gate
2.2 GATEOPERATION
The two bascule gates were designed to operate automatically and maintain the lake near elevation
428.25 ft‐msl without intervention from operating personnel. Unfortunately, the gates are no longer
able to perform this function well (Freese and Nichols 2010). The bascule gate operators are an
outdated mechanical and hydraulic system that requires frequent adjustments. The controls consist of
an elaborate system of valves, cables and pulleys. Adjusting the gate requires trial and error movements
of the cables and valves. The moving parts are worn and difficult to stabilize, causing the gate to require
additional adjusting. When this occurs, personnel must visit the dam several times a day to adjust the
gates. With the Holly Power Plant closing, personnel will be located further from the dam and frequent
visits to the dam will become more difficult with corresponding time delay to the gate operations.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
7
Figure 3: Downstream side of automated bascule gate.
When the river flow exceeds the bascule gates’ capacity, personnel must visit the dam and open the lift
gates. The need to open these gates frequently occurs after normal working hours and with limited
warning. The lift gates have a long history of poor operation, failing to open or close properly. Currently,
the guide wheels on Gate 1 have broken off the side of the gate, and the gate is jammed in the slot,
rendering the gate inoperable. The lift gates tend to open unevenly and rack in the gate guides.
Fortunately, each time a gate has been racked; Austin Energy has been able close the gate before the
lake level dropped significantly. Lifting cable failures are also common, making gate operations
impossible until the cable is repaired. The lift gates are opened with an electric hoist that lifts from one
side of the gate which contributes to the gate operating difficulties.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
8
Figure 4: Downstream view of lift gate 3.
Determining when and how much to open the lift gates requires trial and error. The amount gates are
typically opened is based on the experience the Holly Power Plant personnel have gained over the years.
Once a gate is opened, the lake level is monitored and if it begins to rise or fall more than desired,
additional adjustments are made.
The lift gates are operated with controls located at each pier. In order to access the controls, personnel
must open the door on the pier. The open door blocks the sidewalk, which is also the Hike and Bike Trail.
The roadway is a few feet from the pier doors. A concrete barrier and chain‐link fence have been
installed to protect personnel from motorists.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
9
Figure 5: Gate operation occurs on this sidewalk shared with the Hike and Bike Trail
2.3 GATEDSPILLWAYRATINGCURVE
The spillway was designed to maintain the full capacity of the river channel without materially increasing
the water level upstream over that which would prevail prior to the dam construction. The nine gates
have the discharge capacity to maintain a constant lake level up to approximately 42,000 cfs. At this
point, the tailwater below the dam is approximately equal to the lake level and the lake level is
controlled by the river level more than the spillway gates. The automated bascule gates were designed
to allow the dam to pass more than 7,500 cfs with the lake at the normal pool elevation of 428.25 ft‐msl
without opening a lift gate. Once this flow rate is exceeded, the manual lift gates must be opened to
prevent the lake from rising. The original designers assumed that due to the river control by Tom Miller
Dam and Mansfield Dam there would be adequate time provided to raise the lift gates for any flood
(Brown & Root 1958).
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
10
Figure 6 shows the rating curve assumed for the dam. This rating curve is used to model water surface
elevations through the City due to flood events. The rating curve assumes that the lake level at
Longhorn Dam does not rise until flows exceed the gate capacity. This rating curve is the best case
scenario assuming perfect gate operation and, as discussed in the following section, is unlikely to occur
during storm events.
Figure 6: Gated Spillway Rating Curve – Best Case Scenario
2.4 HISTORICALPERFORMANCEOFEXISTINGDAM
The gated spillway rating curve shown in Figure 6 is based on the best case scenario for gate operation.
The rating curve is presented based on the assumption that all of the gates are fully functional and
opened just enough to anticipate increased flows but not too much to waste water by lowering the lake
level. Operating the gates in this manner is challenging. The original specifications for the automated
bascule gates allowed for the lake to fluctuate within plus or minus 3 inches of normal pool and allowed
the lake to rise six inches before the bascule gates are fully opened (Brown & Root 1959). Figure 7 shows
typical fluctuations of the lake level with LCRA generating through two turbines. The figure shows that
Gate rating curve assumes all gates are functional and opened in a timely manner.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
11
the bascule gate generally causes the lake to fluctuate one foot per day and that the lake is frequently
above 429 ft‐msl. Replacing the bascule gate controls with a modern system will improve this
performance but will still allow the lake to fluctuate approximately six inches.
Figure 7: Historical Normal Levels with Releases from Two Turbines at Tom Miller Dam
The manual lift gates would not typically be opened until the river flows exceed the bascule gate
capacity. As seen in Figure 7, the lift gates would generally not be opened until after the lake reaches
429 ft‐msl and if the flow rates continued to increase. Due to the flash flood nature of the Colorado
River and the limited storage volume in Lady Bird Lake, determining when to open lift gates is
challenging. LCRA shares river flow predictions with Austin Energy and notifies Austin Energy of gate
operations at Tom Miller Dam. This coordination with LCRA helps with the gate operations but there is
still uncertainty to flood timing. The river flow rate can increase in a few hours from a volume easily
handled by the bascule gates to a volume requiring five lift gates to be open. Additionally, lake levels
often rise during non‐working hours, extending the response time for a gate operator. Now that
personnel are no longer stationed at Holly Power Plant 24‐hours a day, the response time may increase
even more.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
12
Historical lake level records from November 13, 2001 through December 13, 2012 were reviewed In
order to determine how the dam has performed in the past. In Figure 8, each dot represents one hour
during the time period mentioned above, and each dot’s position indicates the river flow rate and lake
level elevation during that hour. The figure shows that the lake elevation has frequently exceeded the
elevation predicted by the rating curve for the gates.
Figure 8: Historical Lady Bird Lake Levels compared to Best Case Gate Operation
2.5 GATEREHABILITATIONPROJECTSUMMARY
Longhorn Dam is in need of numerous repairs and upgrades to improve the reliability of the dam and
spillway gates. The existing condition of the dam is documented in a 2010 inspection report (Freese and
Nichols 2010). Following the inspection, FNI prepared a conceptual design to improve gate operations
and reliability and provide enhancements to the downstream channel, river banks and the Hike and Bike
Trail. The opinion of probable construction costs for the conceptual design was $14.2 million (Freese and
Nichols, April 2012). After reviewing the conceptual design, Austin Energy prioritized the repairs and
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
13
determined that $10 million in repairs were dam operation and maintenance priorities. The key repairs
prioritized by Austin Energy are summarized in Table 3 along with the benefits of these features.
Table 3: Key Features of Gate Rehabilitation Conceptual Design
Repair Benefit
Replace bascule gate controls Bascule gate will maintain normal lake level in tighter range than with existing system
Replace lift gate hoists Lift gates will open and close evenly, reducing likelihood of gates becoming stuck or the cables coming loose.
Construct hoist platform on piers Hoist platform will move operations away from the public sidewalk reducing Hike and Bike Trail closures.
Recoat bascule and lift gates Gates will be protected from corrosion for many years.
Provide second set of stop logs Duration of construction will be reduced.
Provide remote monitoring. Allow remote observation of the dam to verify performance and security.
Replace electrical system Provides second power feed to operate gates in case of power failure. Replaces obsolete electrical parts.
The conceptual design for the gate improvements replaced the controls for the automated bascule gate
with modern electronic controls. The new controls would be expected to reduce the daily fluctuations in
lake level to approximately six inches. The conceptual design for the lift gates replaced the lift gate
hoists that contribute to the gate racking and becoming stuck. The lift gates would remain manually
operated, requiring personnel to respond to floods and determine when to open the lift gates. While
not included in the conceptual design, the manual controls could be located at a remote location, which
would eliminate the travel time needed to reach the dam and open the gates. It would not, however,
reduce the amount of time required to recognize that the gates should be opened.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
14
3.0 FIXEDWEIR
3.1 FIXEDWEIROVERVIEW
A fixed weir is an overflow structure with no moving parts. It can consist of a concrete wall, a rounded
spillway, or a high spot in a channel. Since there are no moving parts, it is “fixed” in position, as opposed
to a gated structure. Fixed weirs have several advantages to gated structures. They do not require
operation during storm events eliminating human and mechanical error and their maintenance
requirements are typically less.
The chief advantage of gated structures is discharge capacity. Discharge from a dam is related to flow
area. Gated structures increase flow area by opening gates, thus increasing the area below the gate to
pass flow. Gated structures can maintain a nearly constant lake level for a wide range of discharges.
Because fixed weirs do not have moving parts, the only way to increase the flow area at a given weir,
and thus the discharge, is for the lake to rise. For a given channel width, a gated structure will typically
have a higher discharge capacity than a straight fixed weir.
Labyrinth weirs have been developed in order to obtain the benefits of fixed weirs without sacrificing
the discharge capacity of gated structures. Labyrinth weirs are linear weirs that appear folded in plan‐
view to increase the crest length for a given width. A plan view of a typical labyrinth weir section is
shown in Figure 9. A labyrinth weir is able to pass large discharges at relatively low heads compared to
traditional weirs of equal width. Each triangle shape of the labyrinth weir is called a cycle.
Figure 9: Plan View of Typical Labyrinth Weir
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
15
3.2 LABYRINTHWEIREXAMPLES
As a result of their hydraulic performance and geometric versatility, labyrinth weirs have been placed in
streams, canals, rivers, ponds and reservoirs as headwater control structures, energy dissipaters, flow
aerators, and spillways. Labyrinth weirs are well suited for spillway rehabilitation where aging
infrastructure, dam safety concerns, freeboard limitations, and a revised and larger probable maximum
flow have required increased spillway capacity. Labyrinth weirs have been constructed since as early as
the 1950s. Many of them were constructed at existing dams as a replacement to gated spillways. FNI
designed Lake Brazos Dam labyrinth weir, shown in Figure 10 as a replacement to a gated spillway on
the Brazos River near Waco, Texas. The innovative labyrinth weir design combined reuse of the existing
dam site with an unconventional spillway configuration and yielded substantial reduction in
construction cost and time. Following construction, the project received numerous awards for its
innovative design approach and successful construction (Vasquez et al. 2007).
Figure 10: Lake Brazos Dam shortly after construction
Lake Townsend Dam impounds the primary water supply for the City of Greensboro, North Carolina
(Figure 11). A 300‐foot wide labyrinth weir was chosen to replace the existing, deteriorating concrete
gated spillway to provide additional spillway capacity and a low maintenance structure for the City
(Schnabel 2013). This project was also an award‐winning rehabilitation project.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
16
Figure 11: Lake Townsend Labyrinth Weir under Construction (Schnabel, 2013)
The San Antonio River Authority constructed a labyrinth weir on Elmendorf Lake in 1995 to replace a
gated structure built in 1973. The 12‐foot tall weir is 350 feet wide and has 1,700 linear feet of weir
(Figure 12).
Figure 12: Elmendorf Dam
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
17
3.3 PROPOSEDLABYRINTHCONFIGURATIONATLONGHORNDAM
A labyrinth weir could be constructed at Longhorn Dam on the existing stilling basin. A rendering of the
labyrinth weir is shown in Figure 13. The labyrinth weir consists of approximately 17 cycles and 2,200
linear feet of wall. Two different configurations have been developed, each with advantages. The first
configuration is shown in Figure 14. The cycles are connected to the existing bridge piers. The second
configuration is shown in Figure 15. The cycles do not connect with the existing bridge piers. The
configuration that connects to the piers may simplify construction by making it easier to dewater the
work areas. The other configuration has approximately 100 more feet of weir length and avoids
modifying each pier to connect with the labyrinth weir. The benefits of each configuration should be
evaluated if design of the labyrinth weir continues. A 10‐foot wide by 10‐foot tall slide gate has been
included in both configurations. The slide gate is not needed to pass flood flows but can be used to
lower the lake for hydrilla control or other reasons.
The current labyrinth concept removes all nine gates and provides a sluice gate to lower the lake for
maintenance. Another option would be to replace eight of the gates and leave one of the existing gates
to lower the lake for maintenance. The remaining gate would require repairs to improve reliability. If all
nine gates are removed, the gate piers which currently support the mechanical equipment would be
available for other uses, such as widening the Hike and Bike Trail.
Figure 13: Rendering of Labyrinth Weir at Longhorn Dam
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
18
Figure 14: Labyrinth Weir at Longhorn Dam with cycles connected to existing bridge piers
Figure 15: Labyrinth Weir at Longhorn Dam with cycles not connected to existing bridge piers
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
19
3.4 LABYRINTHWEIRRATINGCURVE
The labyrinth weir was sized to maintain the existing rating curve as much as possible. The crest of the
labyrinth weir was set at elevation 427.6 ft‐msl, approximately 8 inches below the current normal pool
level of 428.25 ft‐msl. This crest level was set so that the lake would be 428.25 ft‐msl when two turbines
are discharging at Tom Miller Dam. The labyrinth rating curve is shown in Figure 16 along with the best
case scenario gate rating curve. Table 4 shows flow rates, lake levels and the difference between the
gated spillway lake elevations and the labyrinth weir lake elevations for the various storm events. Lake
elevations for events up to and slightly beyond the 25‐year event would be somewhat higher with the
labyrinth weir than with the gated spillway. The lake levels for the gated and labyrinth spillways would
be nearly equal approximately midway between the 25‐year and 50‐year storm events. Thereafter, the
reservoir elevations would be the same for both the gated spillway and the labyrinth. The rating curves
shown in the following figures for the existing structure assume that all gates are functional and opened
in a timely manner to manage flows. The labyrinth rating curve assumes that it is free from debris which
would reduce the weir efficiency and cause increased lake levels.
Figure 16: Rating Curve for Gated Structure and Labyrinth Weir
Gate rating curve assumes all gates are functional and opened in a timely manner. Labyrinth rating curve assumes the weir is free from debris and sediment.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
20
Table 4: Lake Levels at Various Storm Events
Event Discharge
(cfs)
Gated Spillway
Headwater
(ft‐msl)
Labyrinth Weir
Headwater (ft‐msl)
Increased Headwater Due to Labyrinth
Weir
(ft)
2‐year 14,564 428.3 429.3 1.0
5‐year 24,567 428.3 430.0 1.7
10‐year 29,945 428.3 430.3 2.0
25‐year 50,050 430.7 431.7 1.0
50‐year 90,046 439.2 439.2 0.0
100‐year 90,361 439.2 439.2 0.0
Figure 17 shows the historical lake level compared to the labyrinth weir rating curve. The figure shows
that the lake level has frequently exceeded the elevation predicted by the labyrinth spillway rating
curve. While the true flood performance of the existing structure must include inefficiencies in gate
operation due to maintenance and operational limitations, the labyrinth spillway would be expected to
more closely follow the predicted rating curve because the labyrinth passively responds during flood
events.
Figure 17: Historical Lady Bird Lake Levels vs. Predicted Rating Curves
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
21
There are design modifications that could be made to the labyrinth to mitigate the head rise. The crest
could be lowered even more, but that would also lower the normal pool level. The angle of the labyrinth
cycles could be reduced, which would increase the length of each cycle and the overall weir length. A
third option would be a fractal labyrinth weir. A fractal labyrinth weir would consist of constructing a
small labyrinth alignment out of steel plate to act as the overflow crest along the top of the large
labyrinth walls (Figure 18). The fractal labyrinth could be constructed on the entire large labyrinth or
only on a few of the cycles. Fractal labyrinths have not been implemented in major civil projects, but a
similar concept has been laboratory tested with promising results for lower heads (Erpicum, et al. 2011).
The fractal labyrinth could potentially reduce the labyrinth head rise up to the 25‐year event. A
significant modeling effort would be required to evaluate the impact of the fractal labyrinth. The steel
plate could potentially be subject to more damage than the concrete labyrinth, increasing maintenance
obligations.
Figure 18: Fractal Labyrinth Weir
3.5 LABYRINTHPERFORMANCE
In order to evaluate the historical performance of the gated structure and the predicted performance of
the labyrinth weir, FNI prepared visual comparisons of the expected labyrinth performance when it is
subjected to available historical flows. The first visual comparison incorporates more than ten years of
historical data. Figure 19 shows a simulation of what the lake levels would have been with the proposed
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
22
labyrinth weir, given the historical flows at the dam. The figure also shows the actual lake levels during
this time. Note that given these historical flow rates, the labyrinth would have reduced a number of
peak lake levels and eliminated events where the lake fell below normal pool.
Figure 19: Historical Dam Performance and Predicted Labyrinth Performance
An examination of the data shown in Figure 19 for significant flood events and typical operation is
shown in Figure 20 through Figure 23. Figure 20 shows that the highest lake level during the November
2004 flood would have been reduced by 2.8 feet with the labyrinth in place. The figure also shows that
between November 26 and December 2, the lake level with the labyrinth would have been
approximately 1.5 feet higher than what actually occurred with the gated spillway. The performance of
the labyrinth was also compared to the Tropical Storm Hermine flood of September 2010 and the
labyrinth would have reduced the peak lake elevation for that storm event as well (Figure 21).
The performance of the labyrinth was also compared to the historical performance when LCRA is
generating power at Tom Miller Dam. Figure 22 and Figure 23 show the dam performance for one and
two turbine turbines releasing at Tom Miller Dam. There has historically been a 6 to 15 inch fluctuation
in lake levels between generation releases and no generation releases. The fluctuation with the
labyrinth will be similar.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
23
Figure 20: Observed and Predicted Lake Levels for November 2004 Flood
Figure 21: Observed and Predicted Lake Levels for September 2010 Flood (Tropical Storm Hermine)
Peak lake level would not have occurred with labyrinth in place.
Higher lake level would have occurred with labyrinth in place.
Peak lake level would not have occurred with labyrinth in place.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
24
Figure 22: Observed and Predicted Lake Levels during typical LCRA Releases from One Turbine
Figure 23: Observed and Predicted Lake Levels during typical LCRA Releases from Two Turbines
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
25
3.6 BACKWATERANALYSIS
Section 3.4 showed that the labyrinth weir increases the lake level at Longhorn Dam by up to 2 feet
compared to the best case gate operation. Section 3.5 showed that the labyrinth weir will reduce peak
lake levels during storm events by eliminating the need to operate gates. Section 3.5 also showed that
once there has been enough time to properly adjust the gates, the gated structure will maintain lower
lake levels than the labyrinth weir. These analyses were based on the lake level at Longhorn Dam. In
order to determine what impact the elevated lake levels at the dam may have upstream, the City’s HEC‐
RAS effective models were used. These models assume that the lake level remains constant at Longhorn
Dam until approximately 40,000 cfs. As mentioned previously, this is not typically the case.
Flows for the 2‐year event to the 100‐year event were modeled, along with steady flow rates of 25,000
and 30,000 cfs representing the large historical floods shown in Table 2 that had extended periods of
relatively steady high flows. Results of the modeling are shown in Appendix A. Observations from the
backwater analysis will be discussed in later sections.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
26
4.0 LABYRINTHWEIRASSESSMENT
4.1 LAKELEVELS
The labyrinth weir will result in less fluctuation in lake levels than the gated structure has had
historically. As seen in Figure 8 the lake has dropped below normal pool many times due to improper
gate operation. This represents lost water that LCRA must release to refill Lady Bird Lake. The labyrinth
weir will reduce peak lake levels during storm events but will cause a longer duration of higher lake
levels.
4.2 HIKEANDBIKETRAIL
The Hike and Bike Trail and the new Boardwalk are located on Lady Bird Lake. Austin Energy surveyed
many locations along the river to obtain elevations for the Hike and Bike Trail. The survey points are
included in Appendix D. The City’s Public Works Department provided a copy of the Boardwalk drawings
which included the elevations of the Boardwalk. The backwater analysis showed that with best case gate
operations the Boardwalk will be above the 25‐year storm event lake level and submerged by the 50‐
year event. A small section of the Boardwalk will be submerged by the 25‐year storm event with the
labyrinth weir. Results from the backwater analysis are shown in Appendix A.
For the labyrinth weir, low spots on the existing Hike and Bike Trail will be inundated during the 5‐year
event, while under best case gate operation conditions these low spots would be inundated during the
10‐year event. Due to the uncertainty with current gate operation, the Hike and Bike Trail may be
inundated earlier than the 10‐year event.
4.3 CESARCHAVEZSTREETATLAMARBOULEVARD
There is a low spot on West Cesar Chavez Street beneath the Lamar Boulevard Bridge. This area has
historically flooded and caused Cesar Chavez to be closed. FNI searched for records indicating when and
for how long the roadway has been closed but did not find any data. Discussions with the City of Austin
Watershed Department (Watershed) indicated that the flooding may be due to the lake backing water
into the culvert in this location. Reportedly, Watershed now blocks the culvert during large floods to
prevent lake water from flowing from the lake into the street and then pumps local drainage from the
roadway.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
27
The backwater analysis showed that Cesar Chavez may flood beginning in the 5‐year event with the
labyrinth weir and in the 10‐year event with the gated structure. The analysis with the steady flow rates
representing extended floodwater releases from Mansfield Dam indicated that Cesar Chavez would not
flood with the existing structure as long as the gates are operated correctly but may flood with the
labyrinth. There may be engineering methods available to prevent the flooding of Cesar Chavez, such as
the installation of a backflow preventer and sump pump in the culvert. The backwater analysis also
indicated that constrictions in the river between South First Street and South Lamar Boulevard increase
the water level. These constrictions include the bridge piers and possibly remnants of an old rock dam
and sediment that accumulated behind the rock dam. Removal of the rock dam remnants and sediment
may reduce the likelihood of flooding at West Cesar Chavez Street and Lamar Boulevard.
4.4 EXISTINGSTRUCTURESANDTHE100‐YEARFLOODPLAIN
The labyrinth weir and gated structure will perform similarly for the 50‐year and 100‐year storm events.
The labyrinth will not increase the lake levels at these events. Watershed provided finished floor
elevations of structures along the river. The lowest structure is Joe’s Crab Shack on Riverside Drive. The
backwater analysis indicated that Joe’s Crab Shack would not be inundated by either the gated structure
or the labyrinth weir at the 25‐year event but would be inundated during the 50‐year event with either
structure.
4.5 DEBRISANDSEDIMENTATION
While some debris washes over labyrinth weirs, large debris such as trees can become caught in the
cycles. Debris buildup can reduce the labyrinth weir discharge capacity. Debris will need to be cleaned
from the labyrinth weir. A debris boom could be installed upstream of the dam to collect debris and
prevent it from accumulating on the labyrinth weir. An access road could be provided downstream of
the labyrinth to facilitate debris removal from the downstream side. The renderings shown in Figure 13
through Figure 15 show a debris boom upstream of the dam. Figure 13 also includes an access road on
the downstream side.
Watershed Field Operations Division currently cleans debris from the lake and removes more than 200
tons of trash from the lake annually. There are already several debris booms in the lake that capture
debris upstream and reduce the amount reaching Longhorn Dam. While removing debris from the
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
28
debris boom or from the labyrinth would increase the lake cleaning effort, it would also have the
environmental benefit of removing the trash from the lake and not allowing it to pass downstream.
Sedimentation can reduce labyrinth weir discharge if significant sediment accumulates in the cycles.
Lady Bird Lake has not experienced significant sedimentation. No issues with sediment accumulation are
anticipated but the possibility of sedimentation should be evaluated.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
29
5.0 STAKEHOLDERMEETINGS
Lady Bird Lake is a valuable asset to the downtown area. Hence, there are many parties who have an
interest in the lake. Austin Energy and FNI held meetings with many of the stakeholders to identify
concerns regarding the labyrinth weir.
5.1 PUBLICWORKS
A meeting was held with Pirouz Moin, Supervising Engineer, Infrastructure Management Group of the
Public Works Department on March 22, 2013 to discuss the labyrinth weir’s impact on the Pleasant
Valley Bridge. The two labyrinth configurations were presented. Mr. Moin preferred the option that did
not connect the weir to the existing piers. He highlighted the need to consider differential movement
between the existing structure and the labyrinth weir. Changes in water surface elevation during storm
events for both structures were discussed. Mr. Moin did not see any major issues with the labyrinth
related to his group. At the time of the meeting, the backwater analysis had not been performed and
the potential flooding at Cesar Chavez Street and Lamar Boulevard had not been identified and was not
discussed in the meeting.
Mr. Moin also asked about the impact the changed water levels may have on the Boardwalk that is
currently under construction. He put us in touch with David Taylor, Boardwalk Project Manager, who
provided copies of the Boardwalk drawings. Mr. Walker asked if the mechanical equipment would still
be needed at the dam if the labyrinth weir were built. During planning on the Boardwalk, public works
looked into using the dam to widen the Hike and Bike Trail. He expressed interest in using the dam for
the Hike and Bike Trail if it would not interfere with the dam mechanical equipment.
5.2 PARKSANDRECREATION
A meeting was held with Charles Vaclavik and Ricardo Solis, division managers of the Parks and
Recreation Department (PARD) along with several other PARD personnel on March 29, 2013. The
labyrinth weir concept was presented and discussed. The historical performance of the existing dam
was discussed including the quick lake rise during a flood due to timing of gate operations. Similarly, the
performance of the labyrinth weir was discussed including the reduction in peak water surface elevation
and longer duration of elevated lake levels for certain events. The potential for a lower normal pool if a
labyrinth weir was built was also discussed. PARD indicated that vendors on the lake may be impacted
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
30
by a lowered normal pool level. The vendors have floating docks and the level change may affect the
dock access.
PARD was concerned about the impact to the Hike and Bike Trail during construction at the dam. FNI
explained that modifications to the gates will require significant work from the bridge while the
labyrinth construction would likely have less impact since most of the labyrinth construction will take
place below the bridge. We also discussed that if the labyrinth is constructed and the existing gate hoist
equipment is removed, there is a possibility that the piers could be used to improve the Hike and Bike
Trail over the dam in the future.
Following the meeting, PARD identified a few areas along the Hike and Bike Trail that have flooded in
the past. These areas were at Auditorium Shores between the Stevie Ray Vaughn Statue and the Pavilion
on the south side of the river and the entire trail from Waller Creek to Festival Beach on the north side
of the river as well as the peninsula at Holly Power Plant. Maps of the flood prone areas provided by
PARD are included in Appendix B. The backwater analysis in Appendix A shows the storm events that
impact these areas.
5.3 WATERSHEDPROTECTIONDEPARTMENT
Several meetings were held with Watershed to discuss the labyrinth weir. Kevin Shunk, (Floodplain
Management, Flood Early Warning System), provided finished floor elevations for several structures
along the river. Once the backwater modeling was complete, FNI met with Mr. Shunk and Eduardo
Acosta to discuss the results. The drainage criteria manual requires stormwater runoff peak flow rates
for the two, ten, twenty‐five and one‐hundred year frequency storms to not cause increased inundation
of any building or roadway surface. There was discussion that the drainage criteria manual was
developed mainly for uncontrolled streams. Permitting the labyrinth weir will require some discussion
within Watershed to determine how to apply the drainage criteria manual for the project. The baseline
water surface in the model is based on the best case scenario gate operations. Since the best case
scenario is not representative of the historical operations, a different baseline may be needed for this
project. Mr. Shunk indicated that Watershed’s Field Operations Division cleans the lake. No coordination
has taken place with this division to discuss the potential debris on the labyrinth.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
31
5.4 AUSTINWATERUTILITY
FNI evaluated Austin Water Utility (AWU) as a stakeholder to the project. AWU has water and
wastewater lines that cross beneath the lake as well as manholes located on the shore. Since the
difference in water surface elevations is only two feet at small events and there is no difference for the
50‐year and larger events and the lake has historically exceeded the predicted lake levels with the
labyrinth weir, no impact to the Utility is anticipated. Further consultation in the future may be required.
5.5 LOWERCOLORADORIVERAUTHORITY
A meeting was held with LCRA regarding the labyrinth on April 8, 2013. FNI and Austin Energy
introduced the concept of a labyrinth weir for Longhorn Dam. LCRA was enthusiastic about the project.
LCRA is required to maintain minimum flow rates at downstream river gages. The bascules gates can be
unpredictable and complicate LCRA’s river operations. When the bascule gates cause the lake to drop
below normal pool, LCRA must release additional water to fill the lake before the bascule gates release
the flow. As a passive structure, the labyrinth weir will be more predictable than the bascule gates and
will not allow the lake to drop below normal pool.
5.6 LAKEBRAZOSDAMSITEVISIT
Representatives from Austin Energy met with Ricky Garrett, City of Waco Director of Utility Services on
April 17, 2013 to discuss their experience with the labyrinth weir at Lake Brazos Dam. Mr. Garrett
discussed the history of Lake Brazos Dam and the reasons for converting the gated spillway to a
labyrinth weir. The gates were unreliable and frequently failed rendering the lake non‐existent for
extended periods. The City of Waco has been happy with the labyrinth weir performance. Debris collects
on the weir and has been removed five times in six years. The dam was scheduled to be cleaned in May
2013. Following the visit with Mr. Garrett, the group visited Lake Brazos Dam to observe the weir and
debris.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
32
6.0 ENVIRONMENTALANDPERMITTINGCONSIDERATIONS
6.1 ENVIRONMENTALPERMITTING
An environmental site assessment was performed as part of the conceptual design for the gate repair.
The assessment searched for items that could impact the project or require additional permitting. No
sites such as former underground storage tanks and other facilities that may have contaminated the soil
were found that have the potential to have caused conditions of environmental contamination within
the project limits. No mapped historical or cultural places were found within the project limits, therefore
no impacts are expected to historical or cultural places due to the project construction. No critical
environmental features or threatened or endangered species were located in the project area. No
impacts to the project are anticipated based on the environmental study. It is anticipated that the
proposed labyrinth modifications can take place under U.S. Army Corp of Engineers Section 404
Nationwide Permit which allows maintenance to existing dams.
The City of Austin tree protection ordinance will apply to this project. Trees larger than 8 inches in
diameter are protected and may not be removed unless the Watershed Protection and Development
Review Department (WPDRD) has issued a permit for the removal. There are a few protected trees in
the project area. Coordination with WPDRD will occur as part of final design. WPDRD may require
mitigation, including the planting of replacement trees, as a condition of application approval.
The project is located on City parkland. Coordination with PARD will occur to coordinate easements for
work areas, material storage sites and access roads.
6.2 TCEQDAMSAFETY
The Dam Safety Program of the Texas Commission on Environmental Quality (TCEQ) monitors and
regulates dams in the State of Texas. Texas Administrative Code requires that dam owners submit final
construction plans and specifications to TCEQ for review and approval before commencing construction
or repairs to an existing dam. The final design will be subject to TCEQ approval and will be in accordance
with TCEQ criteria.
6.3 STATEHISTORICPRESERVATIONOFFICE
The Antiquities Code of Texas was passed in 1969 and requires that the Texas Historical Commission
staff review any action that has the potential to disturb historic and archeological sites on public land.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
33
Actions that need review under the Antiquities Code of Texas include any construction program that
takes place on land owned or controlled by a state agency or a state political subdivision, such as a city
or a county. Projects that require review include:
Reservoirs constructed by river authorities and water districts;
Construction of recreational parks or the expansion of existing facilitates by city governments;
Energy exploration by private companies on public land; and
Construction by a city or county government that exceeds 5 acres or 5,000 cubic yards,
whichever comes first. If the activity occurs inside a designated historic district or affects a
recorded archeological site, it needs to be reviewed, regardless of project size.
Rehabilitation or demolition of a building owned by a state agency or university that is listed or
eligible to be listed in the National Register of Historic Places (NRHP).
The State Historic Preservation Office (SHPO) was consulted in the conceptual design for the gate repair
project. The dam is not listed as a State Archeological Landmark (SAL) or in NRHP. However, the dam
may be eligible for listing in the National Register of Historic Places (NRHP). If the project does not
require a permit from the Corp of Engineers, a review by SHPO will not be required. However, a need for
a Corp of Engineers permit is anticipated, therefore an evaluation of NRHP eligibility would need to be
performed and a thorough evaluation of the project would need to be made by SHPO during final
design. The project will likely require a permit from the Texas Historical Commission.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
34
7.0 OPINIONOFPROBABLECONSTRUCTIONANDOPERATIONCOSTS
7.1 GATEREHABILITATIONPROJECT
The gated structure has served the City for over 50 years and is in need of repairs. As discussed in
Section 2.5, after reviewing the gate rehabilitation conceptual design, Austin Energy prioritized the
repairs and determined that $10 million in repairs were dam operation and maintenance priorities.
Once the dam has been repaired, there will be ongoing operation and maintenance (O&M) costs. Austin
Energy reports that the gates have historically been recoated every ten years. This frequency is unusual
as 25 to 30 years is more typical for spillway gates. A 15‐year frequency for gate coatings was selected
for further cost analysis. The remote monitoring and control system for the gates will also need to be
updated every 15 years. Operation of the gates will require that trained personnel be available 24 hours
a day to operate the lift gates in storm events and verify proper operation of the automated bascule
gates regularly. Austin Energy estimated the need for six trained personnel assigned halftime to the dam
and provided labor costs for these personnel. The estimated costs to repair, operate and maintain the
gated structure are shown in Table 5.
Table 5: Gated Structure Repair, Operation and Maintenance Item Costs
Item Frequency Cost
Engineering Design One Time $600,000
Rehabilitation Construction One Time $10,000,000
Gate Coatings 15‐years $1,500,000
Control System Upgrades 15‐years $100,000
O&M Labor Costs Annual $360,000
O&M Expense Costs Annual $125,000
7.2 LABYRINTHWEIRPROJECT
Design of the labyrinth weir will require the use of computer and physical models to further evaluate the
labyrinth performance and refine the labyrinth discharge rating curve. The study will also verify the
gated structure rating curve. These studies will increase the duration of the design over the gate
rehabilitation project. The opinion of probable construction cost for the labyrinth weir is $15.0 million;
details of the probable cost are included in Appendix D. The cost includes a service road to access the
downstream side of the labyrinth and to drive behind the entire width of the labyrinth. This road can be
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
35
used to facilitate debris removal. As an alternate, this access road could be eliminated and debris
removed with a crane on Pleasant Valley Bridge but would impact traffic. The elimination of the access
road would reduce the probable construction by approximately $1 million. Schedules for the two
alternatives are included in Appendix F. The labyrinth weir will have small annual operational cost. The
slide gate should be exercised annually to verify that it functions. Debris will need to be removed on an
as‐needed basis. The estimated costs to construct and operate the labyrinth weir are shown in Table 6.
Table 6: Labyrinth Weir Construction and Operation Costs
Item Frequency Cost
Engineering Design One Time $1,500,000
Initial Cost One Time $ 15,000,000
Debris Cleaning Annual $20,000
Exercise Gate and Miscellaneous Observation Annual $5,000
7.3 LIFECYCLECOSTS
The present value and the equivalent annual worth of the gated structure and the labyrinth weir were
calculated for a 50‐year life cycle and 4% interest rate and are shown in Table 7. Based on the assumed
operation and maintenance costs, the labyrinth weir is less expensive than the gated structure.
Table 7: Life Cycle Costs
Gated Structure Labyrinth Weir
Present Value $20,000,000 $17,040,000 Equivalent Annual Worth $930,600 $793,100
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
36
8.0 CONCLUSION
8.1 COMPARISON
Longhorn Dam is in need of improvements. Both the gate rehabilitation and the labyrinth weir provide
many benefits over the existing condition. Table 8 summarizes the attributes for each of the two
configurations of Longhorn Dam as discussed in this preliminary investigation.
Table 8: Attributes of Alternatives
Factors Alternative
Gate Improvements Labyrinth Weir
Initial Engineering and Construction Cost
$10,600,000 $16,500,000
50‐year Present Value $20,000,000 $17,040,000
Flood Operation Requires personnel at any time of day to operate gates
No operation required
Debris Removal None Approximately once per year
Peak Lake Levels Lake rises quickly during storm events due to delay in gate operation
Instant and passive flood response significantly reduces peak lake levels for storm events
Lake levels during extended flood events
After period of gate adjustment, lake level at dam can be near normal pool
The lake level will remain elevated during extended flood events or flood releases from upstream dams
Lake level reliability Lake level is a function of inflow and gate opening configuration, which leads to significant variation
Lake level is only a function of inflow leading to consistent and predictable lake levels
Wasted Water Gates can allow lake to drop below normal pool
Lake will not drop below normal pool
Maintenance Requires regular maintenance and adjustment
Minimal
Hike and Bike Trail
Removes most operational requirements from the public sidewalk reducing Hike and Bike Trail closures
May allow the piers to be used to support the Hike and Bike Trail
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
37
8.2 CONCLUSION
This report presented a conceptual design for a labyrinth weir at Longhorn Dam, evaluated the hydraulic
feasibility and identified stakeholders to the project. The analysis found that the labyrinth weir would
improve the operational requirements of Longhorn Dam by eliminating the need for gate operations.
Peak lake elevations during flood events would likely be reduced by eliminating the gate operations. The
lake level would remain elevated during high river flows. Additional analysis and evaluations will be
required to determine if a labyrinth weir is appropriate at Longhorn Dam. Items to consider when
evaluating the labyrinth weir have been discussed previously and include:
Environmental permitting including historic considerations,
Management of river trash and debris,
Reduced ability to lower the level of Lady Bird Lake for upstream maintenance or hydrilla
control,
Impact of increased lake level on Hike and Bike Trail,
Impact of increased lake level on West Cesar Chavez Street
The information presented in this report should be considered conceptual in nature. The replacement of
an existing gated spillway with a labyrinth weir is an involved project requiring detailed analysis and
design.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
38
REFERENCES
Brown & Root, Inc., (August 1958). Report on Low‐water Dam: Prepared for City of Austin, Texas.
Brown & Root, Inc., (February 9, 1959). Low Water Dam Contract Drawings.
Brown & Root, Inc., (1959). Low Water Dam Colorado River contract No. 80, Legal Notice, Specification,
Proposal, Contract & Bond Form.
Toohey, Marty. (May 25, 2011). “Company proposes hydropower plant at Longhorn Dam”, Austin
American‐Statesman, accessed May 29, 2013, http://www.statesman.com/news/news/local/company‐
proposes‐hydropower‐plant‐at‐longhorn‐da‐1/nRbLr/
Schnabel (2013). Lake Townsend Dam ‐ Dams and Levees Portfolio. www.schnabel‐eng.com. Accessed
March 4, 2013.
Vasquez, V., Boyd, M., Wolfhope, J., and Garret, R. (2007). “A labyrinth rises in the heart of Texas.”
Proceedings of the 28th Annual USSD Conference. 813‐826.
Halff Associates, Inc., (October 2003). “Flood Damage Evaluation Project: Information Paper: Lower
Colorado River Basin Study ‐ Phase I Problems, Needs and Opportunities,” Report and Appendices A and
B, prepared for Lower Colorado River Authority and U.S. Army Corps of Engineers.
Erpicum, S. and Laugier, F.D.R. and Pirotton, M. and Boillat, J.L. and Reverchon, B. and Schleiss, A.J.
(2011). Development of a new concept of Piano Key Weir spillway to increase low head hydraulic
efficiency: Fractal PKW, Labyrinth and Piano Key Weirs: PKW 2011, CRC Press/Balkema.
Freese and Nichols, Inc. (April 19, 2012). Longhorn Dam Modernization Conceptual Design Report,
Austin, Texas.
Freese and Nichols, Inc. (December 6, 2010). Longhorn Dam Comprehensive Facility Review, Austin,
Texas.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
Appendix A Backwater Figures
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
§̈¦35
Lady Bird Lake
UV1
!
Longhorn Dam
Tunnel ThroughEmbankment
Joe's CrabShack
AuditoriumShores
Top of Manhole & Gutterat Cesar Chavez & Lamar
Shoal CreekPeninsula
Texas RowingCenter
Trail Near WallerCreek Boathouse
Trail and Boat Rampat Holiday Inn
FestivalBeach
HollyPeninsula
Low Point on TrailNear Lakeshore Blvd
Trail Near AustinAmerican-Statesman
Boardwalk
Trail and Boat Ramp atStephen F. Austin High
W 15th St
E 7th St
E 8th St
W Oltorf St
W Martin Luther King Jr Blvd
S Lamar Blvd
Cong
ress A
ve
E 6th St
Braz
os St
Hether St
E 9th St
E 12th St
E 3rd St
E 12th St
Barton Springs Rd
W Riverside Dr
Atlan
ta St E Martin Luther King Jr Blvd
W 8th StW 7th St
E 2nd St
Treadwell St
W Cesar Chavez St
Winsted
Ln
Parke
r Ln
E Live Oak St
Cong
ress A
ve
Enfield Rd
Webberville Rd
E Riverside Dr
Blueb
onne
t Ln
Nava
sota
St
Color
ado S
tNas h Hernandez Sr Rd
W 12th St
E Annie St
W Live Oak St
N Plea
sant
Valle
y Rd
Rio G
rande
St
San A
ntonio
St
E 5th St
Lava
ca St
Chestnut AveE 15th StN Pleasant Valley Rd
Pede
rnales
St
Guad
alupe
St
Robe
rt T M
artine
z Jr S
t
Woodland Ave
Haskell St
WLy
nnSt
S Pleas
ant V
alley
Rd
W Annie St
Robert E Lee Rd
W 6th St
S Lakeshore Blvd
West
Ave
Holly St
Rosewood Ave
Kinne
y Ave
W Mary St
E 11th St
Coma
l St
S 5th
St
S Con
gress
Ave
E 2nd St
S 1st
St
W 5th St
N Lama
r Blvd
S Lam
arBl
vd
Northwestern Ave
Comal St
Chico
n St
Chicon St
Path: H:\WR_DESIGN\FIGURES\AU412421_Fig1.mxdDate Saved: 5/30/2013 1:54:55 PM
FN
PR
OJ
EC
T N
O.
DA
TE
CR
EA
TE
D
DA
TU
M &
CO
OR
DIN
AT
E S
YS
TE
M
FIL
E N
AM
E
PR
EP
AR
ED
BY
LVA
13
17
9
SS
J
AU
41
24
21
_F
ig1
.mx
d
Da
te:
5/3
0/2
01
3
µ
FREESE
AND N
ICHOL
S, INC
.108
14 JO
LLYVIL
LE RO
ADBU
ILDING
4, SU
ITE 10
0AU
STIN,
TX 78
759PH
ONE: 5
12.61
7.3100
FIGURE
1
NA
D8
3 S
tate
Pla
ne
(fe
et)
Te
xa
s C
en
tra
l
RoundRock
LibertyHill
UV1325
UV21UV4
UV1
UV29
UV360
UV427
UV71
UV191UV95
UV71
UV343 UV111
UV275
UV195
UV12
UV304
£¤183
£¤290
£¤79
§̈¦35
Travis
BastropHays
Caldwell
Burnet Williamson
Travis County, Texas
Base Map: 2012 NAIP 1-Meter Orthoimagery
NA
D8
3 S
tate
Pla
ne
(fe
et)
Te
xa
s S
ou
th C
en
tra
l
5/3
0/2
01
3
AUST
IN EN
ERGY
Hike
and B
ike Su
rvey
Point
sLo
ngho
rn Da
m Mo
derni
zation
ProjectLocation
1,500 0 1,500750
Feet
! Survey Points
Boardwalk Survey Area
A1
A2
420
425
430
435
440
445
450
455
460
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
ELEV
ATION (FT‐M
SL)
DISTANCE UPSTREAM FROM LONGHORN DAM (MI.)
EXISTING DAM
PROPOSED LABYRINTH
POINTS ALONG NORTH TRAIL
POINTS ALONG SOUTH TRAIL
INTERSTATE
35
S. CONGRESS AVE.
S. 1ST ST.
UNION PACIFIC RR
S. LAMAR BLVD
CONFLUEN
CE W/
BARTO
N CREEK
MOPACEX
PY
RED
BUD TRAIL
LONGHORN DAM
TOM M
ILLER DAM
2‐YEAR STORMWATER SURFACE PROFILES
Note: Water surface profile for existing dam assumes instant operation of gates in response to flood flows according to the "best case " rating curve.
A3
420
425
430
435
440
445
450
455
460
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
ELEV
ATION (FT‐M
SL)
DISTANCE UPSTREAM FROM LONGHORN DAM (MI.)
EXISTING DAM
PROPOSED LABYRINTH
POINTS ALONG NORTH TRAIL
POINTS ALONG SOUTH TRAIL
INTERSTATE
35
S. CONGRESS AVE.
S. 1ST ST.
UNION PACIFIC RR
S. LAMAR BLVD
CONFLUEN
CE W/
BARTO
N CREEK
MOPACEX
PY
RED
BUD TRAIL
LONGHORN DAM
TOM M
ILLER DAM
5‐YEAR STORMWATER SURFACE PROFILES
Note: Water surface profile for existing dam assumes instant operation of gates in response to flood flows according to the "best case " rating curve.
A4
420
425
430
435
440
445
450
455
460
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
ELEV
ATION (FT‐M
SL)
DISTANCE UPSTREAM FROM LONGHORN DAM (MI.)
EXISTING DAM
PROPOSED LABYRINTH
POINTS ALONG NORTH TRAIL
POINTS ALONG SOUTH TRAIL
INTERSTATE
35
S. CONGRESS AVE.
S. 1ST ST.
UNION PACIFIC RR
S. LAMAR BLVD
CONFLUEN
CE W/
BARTO
N CREEK
MOPACEX
PY
RED
BUD TRAIL
LONGHORN DAM
TOM M
ILLER DAM
10‐YEAR STORMWATER SURFACE PROFILES
Note: Water surface profile for existing dam assumes instant operation of gates in response to flood flows according to the "best case " rating curve.
A5
420
425
430
435
440
445
450
455
460
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
ELEV
ATION (FT‐M
SL)
DISTANCE UPSTREAM FROM LONGHORN DAM (MI.)
EXISTING DAM
PROPOSED LABYRINTH
POINTS ALONG NORTH TRAIL
POINTS ALONG SOUTH TRAIL
INTERSTATE
35
S. CONGRESS AVE.
S. 1ST ST.
UNION PACIFIC RR
S. LAMAR BLVD
CONFLUEN
CE W/
BARTO
N CREEK
MOPACEX
PY
RED
BUD TRAIL
LONGHORN DAM
TOM M
ILLER DAM
25‐YEAR STORMWATER SURFACE PROFILES
Note: Water surface profile for existing dam assumes instant operation of gates in response to flood flows according to the "best case " rating curve.
A6
420
425
430
435
440
445
450
455
460
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
ELEV
ATION (FT‐M
SL)
DISTANCE UPSTREAM FROM LONGHORN DAM (MI.)
EXISTING DAM
PROPOSED LABYRINTH
POINTS ALONG NORTH TRAIL
POINTS ALONG SOUTH TRAIL
INTERSTATE
35
S. CONGRESS AVE.
S. 1ST ST.
UNION PACIFIC RR
S. LAMAR BLVD
CONFLUEN
CE W/
BARTO
N CREEK
MOPACEX
PY
RED
BUD TRAIL
LONGHORN DAM
TOM M
ILLER DAM
50‐YEAR STORMWATER SURFACE PROFILES
Note: Water surface profile for existing dam assumes instant operation of gates in response to flood flows according to the "best case " rating curve.
A7
420
425
430
435
440
445
450
455
460
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
ELEV
ATION (FT‐M
SL)
DISTANCE UPSTREAM FROM LONGHORN DAM (MI.)
EXISTING DAM
PROPOSED LABYRINTH
POINTS ALONG NORTH TRAIL
POINTS ALONG SOUTH TRAIL
INTERSTATE
35
S. CONGRESS AVE.
S. 1ST ST.
UNION PACIFIC RR
S. LAMAR BLVD
CONFLUEN
CE W/
BARTO
N CREEK
MOPACEX
PY
RED
BUD TRAIL
LONGHORN DAM
TOM M
ILLER DAM
STEADY 25,000 CFSWATER SURFACE PROFILES
Note: Steady flow conditions may develop during extended flood releases from Lake Travis at Mansfield Dam.
A8
420
425
430
435
440
445
450
455
460
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
ELEV
ATION (FT‐M
SL)
DISTANCE UPSTREAM FROM LONGHORN DAM (MI.)
EXISTING DAM
PROPOSED LABYRINTH
POINTS ALONG NORTH TRAIL
POINTS ALONG SOUTH TRAIL
INTERSTATE
35
S. CONGRESS AVE.
S. 1ST ST.
UNION PACIFIC RR
S. LAMAR BLVD
CONFLUEN
CE W/
BARTO
N CREEK
MOPACEX
PY
RED
BUD TRAIL
LONGHORN DAM
TOM M
ILLER DAM
STEADY 30,000 CFSWATER SURFACE PROFILES
Note: Steady flow conditions may develop during extended flood releases from Lake Travis at Mansfield Dam.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
Appendix B Flood Prone Areas Identified by Parks and Recreation
Kealing
SouthAustin
Parker
OldBakeryTreaty
Oak Square
ButlerPark
Lott
Metz
BoggyCreek
BlunnCreek
PeaseHaskellHouse
Lamar Beachat Town Lake
Roy G. GuerreroColorado
River Park
Gillis
Edward RendonSr. Park at
Festival Beach
Zilker
ParqueZaragoza
E 16TH ST
E CESAR CHAVEZ ST
COLO
RADO
ST
RIVER ST
S 1ST
ST
E OLTORF ST
W 5TH ST
W MONROE ST
RABB RD
PARA
MOUNT
AVE
NEW
TON
ST
E 7TH ST
E 17TH ST
E 12TH ST
BOUL
DIN A
VE HOLLY ST
W 9TH ST
W 12TH ST
ROSEWOOD AVE
HILL
SIDE
AVE
E 2ND ST
E 11TH ST
JULIET ST
W 10TH STW 6TH ST
E 3RD ST
W 6TH ST
CLAWSO
N RDW 7TH ST
FORD ST
N IH
35 SV
RD NB
W 5TH ST
W 10TH ST E 18TH ST
E 13TH ST
E 5TH STE 5TH ST
E 8TH ST
E 4TH ST
N IH
35 SV
RD SB
LUPINE LN
E 10 TH ST
W OLTORF ST
BAYL
OR ST
LONG BO W LN
W 17TH ST
COMAL ST
E MONROE STE ANNIE ST
W 2ND ST
S 6TH
ST
BARTON SPRINGS RD
W 15TH ST
S 7TH
STE 6TH ST
S LAMAR BLVD
E 14TH ST
GARN
ER AV
E
E 10TH STE 11 TH ST
W 16TH ST
KENW
OOD
AVE
E 9TH ST
W 9TH ST
S 2N
D ST
S 6TH ST
GUAD
ALUP
E ST
E 8TH ST
STAC
Y LN
SAN
SABA
ST
FOLT
S AV
E
TRAILS IDE DR
WILSO
N ST
KINN
EY AV
E
KINN
EY RD
LAVA
CA ST
E 9TH ST
HETHER ST
ASHBY AVE
E 20TH ST
NEW YORK
AVE
SH 165
E 20TH ST
S 3R
D ST
E 8TH ST
GARD
EN VI
LL
A LN
E 3RD ST E 2ND ST
S 2ND ST
ANTH
ONY S
T
W 11TH ST
E 7TH ST
TRIN
ITY
ST
E 8TH STE 6TH ST
LEONA STE 13TH
STW 10TH ST
E 4TH ST
SALINA STEV
A STBRODIE ST
W 9TH STW 8TH ST
S CON
GRES
S AVE
CONG
RESS
AVE
S 5TH
ST
W MARY ST
W 3RD ST
WATERLOO TRL
S 4TH
ST
SABI
NE ST
S PLE
ASAN
T VAL
LEY R
D
TINN
IN FO
RD RD
E 3RD STHASKELL ST
DOL PHIN
D R
COLU M BUS DR
E 6TH ST
EUCL
ID AV
E
JESS
IE ST
PARKER
LN
RED RIV
ER ST
CORB
IN LN
BU
RTON DR
TOOMEY RD
S LAKESHORE BLVD
N MOPAC EX
PY NB
E RIVERSI DE DR
E LIVE OAK ST
WALL
ER ST
E RIVERS IDE
DRN
LAMA
R BL
VD
S 3RD
ST
DEL CU
RTO
RD B ONH A M
TE R
LO
CKE
LNSTRATFORD DR
S IH
35 SB
N IH
35 SB
N IH
35 SB
LOU NEFF RD
AustinRowing
DockTexasRowingCenter
Town LakeRowingCenter
Town LakeRowingCenter
TownLake RowingCenter
0 600 1,200
Feet ±
This product is for informational purposesand may not have been prepared for orbe suitable for legal, engineering, or
surveying purposes. It does not representan on-the-ground survey and represents onlythe approximate relative location of propertyboundaries. This product has been produced
by the Parks and Recreation Departmentfor the sole purpose of geographic reference.
No warranty is made by the City of Austinregarding specific accuracy or completeness.
LegendLBL Trail Flood Areas
Yes
No
!y Water Access Area
Creek Centerlines
City of Austin Parks
Lady Bird Lake TrailProblem Flood Areas (Plus Red Bud Isle-not shown)
05 April 2013 MS
JohnsonCreek
ButlerShores atTown Lake
BartonCreek
ZilkerNature
Preserve
Veterans
Eilers(DeepEddy)
UmlaufSculptureGarden
Treaty OakSquare
ButlerPark
AuditoriumShores atTown Lake
AustinHigh Tennis
Center
LamarBeach at
Town Lake
Zilker
WestAustin
ShoalBeach at
Town Lake
S LA
MA
R BL
VD
SB
W 5TH ST W 5TH ST
RESERVE RD
W 9TH HALF ST
PRES
SLER
ST
N M
OPA
C EX
PY SB
FOSTER AVE
BAY
LOR
ST
W 10TH ST
W 6TH STW
5TH ST
BAY
LOR
ST
BLAN
CO S
T
W 9TH ST
BARTON SPRINGS RD
JESS
IE S
T
ATLA
NTA
ST
W 9TH ST
N MO
PAC E
XPY N
B
ANDREW
ZILKER RD
HIG
HLA
ND A
VE
W RIVERSIDE DR
WIN
FLO
DR
W 3RD ST
ROSE ST
W 11TH ST
S MOPAC EXPY NB
W 4TH ST
VALE ST
PAU
L ST
S MOPAC EXPY
SVRD SB
FRANCIS AVEW 8TH ST
W 8TH ST
W 10TH ST
POW
ELL
ST
WES
T LY
NN ST
N L
AM
AR
BLV
D
WA
LSH
ST
VANCE LN
HA
RTH
AN S
T
W 2ND ST
BR O WN
LEE
CIR
BARTON B LV
D
STER
ZING
ST
W 7TH ST
S MOPAC EXPY SVRD NB
S LA
MA
R B
LVD
LEE
BART
ON
DR
ZILKER
CLUBHOUSE RD
N LA
MA
R BL
VD
W CESAR CHAVEZ ST
PRES
SLER
ST
ROBE
RT E
LEE RD TOOMEY RD
NA
TURE
CENT
ER DR
STE
PHE
N
F AUSTIN DR
S MOPAC EXPY SB
S LA
MA
R BL
VD
NB
VETERA
N
S DR
BARTON SPRINGS RD
WILLIAM BARTON DR
OA
KLA
ND
AVE
COLUMBUS DR
BARTON
SPRINGS
RD
STRATFORD DR
CESA
R C
HAV
EZ TO
MO
PAC
NB RAM
P
LOU NEFF RD
LOU NEFF RD
428
430
432
434
428
430
432
434
434
432
428434
432
430
432
430
428
430
432
428
428
428
434
434
434
430
430
430
430
428
428
432
432
432
AustinRowingDock
TexasRowingCenter
0 250 500
Feet
Legend
ELEVATION
428
430
432
434
LBL Trail Flood Areas
Yes
No
!y Water Access Area
City of Austin Parks
±Lady Bird Lake Trail Problem Flood Areas-West End
05 April 2013 MS
This product is for informational purposesand may not have been prepared for orbe suitable for legal, engineering, or
surveying purposes. It does not representan on-the-ground survey and represents onlythe approximate relative location of propertyboundaries. This product has been produced
by the Parks and Recreation Departmentfor the sole purpose of geographic reference.No warranty is made by the City of Austin
regarding specific accuracy or completeness.
Red BudIsle
LAKE CLIFF
CTL
AK
E A
USTIN
BLVD
REDBUD TRL
LAKE C
LIFF
TRL
434
432
432430
43 4
428
428
434
432
428430
432
434
430
430
434
43042
8
434
432
430
428
430
Redbud Isle Inset
0 150 300 450 600Feet
SirSwantePalm
MaryDawson
ButlerShores atTown Lake
DoughertyArts Center
WallerCreek
NicholasDawson
EastBouldinCreek
ButlerPark
AuditoriumShores atTown Lake
NorwoodTract at
Town Lake
Sanchez
BlunnCreek
WestBouldinCreek
WallerBeach at
Town Lake
Shoal Beachat Town
Lake
Edward RendonSr. Park at
Festival Beach
N IH
35
SVR
D S
B
BARTON SPRINGS RD
N IH
35
NB
NASH HERNANDEZ SR RD
N IH
35 SV
RD
NB
E CESAR CHAVEZ ST
BOU
LDIN
AVE
ALT
A V
ISTA
AVE
ALAMEDA
DR
TRIN
ITY
ST
W ELIZABETH ST
CO
NG
RES
S AV
E
HILLSI
DE
AVE
RED
RIV
ER ST
ACADEMY DR
POST OAK ST
N IH
35 SVR
D SB
N IH
35 SVR
D N
B
S IH
35
SVR
D N
B
LE GRANDE AVE
JEWELL ST
NELLIE ST
W JAMES ST
W JAMES ST
W GIBSON ST
EVA
DR
S 5T
H S
T
S 2N
D ST
DAW
SON
RD
BRA
ZOS
ST
EAST
AVE
RA
INEY
ST
S 3R
D ST
BRU
SHY
STSA
N M
AR
CO
S ST
S L
AM
AR BL
VD
SB
SABI
NE
ST
BRA
ZOS
ST
DAVIS ST
SPENCE ST
RIVER ST
W ELIZABETH ST
RED
RIV
ER ST
DRISKILL ST
W CESAR CHAVEZ STE 2ND ST E 2ND
ST
E 3RD ST
ME
LISS
A LN
EVA
ST
E 4TH ST
LAMBIE ST
DAW
SON
RD
THE
CIRCLE
WILLOW ST
EBONY ST
W 2ND ST
HAYWOOD
AVE
E 2ND ST
RAV
INE
DR
RETAMA ST
HASKELL ST
S IH 35 SB
S 1S
T ST
S IH 35 N
B
LAMBIE ST
S IH
35
SVR
D SB
E 3RD ST
DANIEL DR
SUNNY LN
RA
INEY
ST
W RIVERSIDE
DR
LE
E BA
RTO
N DR
S C
ON
GR
ESS
AVE
N IH
35 SB
E RIVERSIDE DR
W RIVERSIDE
DR
W RIVERSIDE DR
N IH
35 SV
RD
NB
WA
LLER
ST
N IH
35
SVR
D S
B
S 3R
D ST
S 3R
D S
T
EAST
AVE
EAST
AV
E
EDGECLIFF
TER
BIC
KLE
R RD
NEWNIN
G AVE
434 432
428
432
430
432
434432
432434
432
432
430
434
428
430
434
434
432
430
434
434
Town LakeRowingCenter
Town Lake Rowing Center
Town LakeRowingCenter
0 250 500
Feet
Legend
ELEVATION
428
430
432
434
LBL Trail Flood Areas
Yes
No
!y Water Access Area
City of Austin Parks
±Lady Bird Lake Trail Problem Flood Areas-Central
05 April 2013 MS
This product is for informational purposesand may not have been prepared for orbe suitable for legal, engineering, or
surveying purposes. It does not representan on-the-ground survey and represents onlythe approximate relative location of propertyboundaries. This product has been produced
by the Parks and Recreation Departmentfor the sole purpose of geographic reference.No warranty is made by the City of Austin
regarding specific accuracy or completeness.
BlunnCreek Park
LonghornShores atTown Lake
Manuel andRobert
Donley Park
InternationalShores atTown Lake
Lakeshore atTown Lake
NorwoodTract at
Town Lake
Metz
Holly Shoresat Town Lake
Peace Pointat Town Lake
WallerBeach at
Town Lake
Central MaintenanceComplex atTown Lake
Roy G. GuerreroColorado
River Park
Edward RendonSr. Park at
Festival Beach
E CESAR CHAVEZ ST
AN
THO
NY
ST
WOODLAND AVE
RIVERVIEW ST
E 2ND ST
N IH
35 SVR
D N
B
SAN
SABA
ST
S IH
35 SV
RD
NB
CANTERBURY ST
LUPINE LN
S IH
35 SV
RD
SBGARDEN ST
TAYLOR
GAINES ST
HOLLY ST
CO
MA
L ST
EAST
AVE
BELL
AIRE
DR
REAGAN
TER
E RIVERSIDE DR
SAN
SABA
ST
LOM
A DR WATERLOO
CITY LN
N PL
EASA
NT
VALL
EY R
D
E RI VERSIDE
DR
JULI
US
ST
PED
ERN
ALE
S ST
SHORE DISTRICT DR
SALI
NA
ST
LYN
N ST
LYN
N S
T
LLA
NO
ST
MIL
DR
ED S
T
N PL
EASA
NT
VALL
EY R
D
LOM
A DR
CLA
RA
STLYN
N ST
SUNNY VALE ST
GARDEN ST
TINN
IN F
ORD
RD
HOLLY ST
RIVERVIEW ST
HASKELL ST
HASKELL ST
ELMONT DR
LAD
Y BI
RD L
N
VIO
LET
CRO
WN
LNTO
W
N
LAK
E CIR
BETT
Y JO
DR
TOW
N CR
EEK
DR
JESSE E SEGOVIA ST
N IH
35 NB
UPLA
ND
DR
ROYA
L CREST DR
S PL
EASA
NT VA
LLEY
RD
PARK
ER L
N
S LAKESHORE BLVDS IH
35 SB
N IH
35 SB
E RIVERSIDE
DR
WA
LLER
ST
ELMHURST DR
E RIVERSIDE
DR
NASH HERNANDEZ SR RD
E RIVERSID E
DR
E RIVERSID
E
DR
4 3 2
430
428
434
430
434
432
432
434
434
432
434
434
434
430
428
434
432
432
428
430
432
430
430
430
428
428
428
432
432
428
430432
432
0 250 500
Feet
Legend
ELEVATION
428
430
432
434
LBL Trail Flood Areas
Yes
No
!y Water Access Area
City of Austin Parks
±Lady Bird Lake Trail Problem Flood Areas-East End
05 April 2013 MS
This product is for informational purposesand may not have been prepared for orbe suitable for legal, engineering, or
surveying purposes. It does not representan on-the-ground survey and represents onlythe approximate relative location of propertyboundaries. This product has been produced
by the Parks and Recreation Departmentfor the sole purpose of geographic reference.No warranty is made by the City of Austin
regarding specific accuracy or completeness.
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
Appendix C Labyrinth Weir Opinion of Probable Construction Cost
ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL
1 Mobilization 1 LS 1,058,000$ 1,058,000$
2 Temp. Erosion and Sediment Control 1 LS 75,000$ 75,000$
3 Site Preparation and Restoration 1 LS 100,000$ 100,000$
4 Lift Gate/Hoist Removal 1 LS 250,000$ 250,000$
5 Care Of water 1 LS 1,200,000$ 1,200,000$
6 Flood Insurance 1 LS 60,000$ 60,000$
7 Labyrinth Weir Spillway Slab (3 foot thick) 4,000 CY 400$ 1,600,000$
8 Labyrinth Weir (3 foot thick walls) 6,000 CY 850$ 5,100,000$
9 Concrete Apex Piers 600 CY 800$ 480,000$
10 Concrete Training Walls/ Pier Modifications 1 LS 75,000$ 75,000$
11 Debris Boom 550 LF 600$ 330,000$
12 Access Ramp 1 LS 400,000$ 400,000$
13 Access Drive Behind Labyrinth 1300 CY 400$ 520,000$
13 Additional Foundation Slab Behind Bascule Gates 980 CY 400$ 392,000$
14 Outlet Gate 1 LS 250,000$ 250,000$
15 Handrail 1 LS 41,000$ 41,000$
14 Embankment Drain Pipe 1 LS 50,000$ 50,000$
SUBTOTAL: 11,890,000$
PROJECT SUBTOTAL: 11,890,000$
CONTINGENCY: ~26% 3,110,000$
15,000,000$
IT IS NOT TO BE USED FOR CONSTRUCTION OR BIDDING PURPOSES.
THIS DOCUMENT IS RELEASED FOR PURPOSE OF INTERIM REVIEW.
AustinEnergy
OPINION OF PROBABLE CONSTRUCTION COST
PreliminaryOpinionofProbableConstructionCostLonghornDam
LonghornDamLabyrinthWeir
Prepared by Freese and Nichols, Inc.6/21/2013
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
Appendix D Survey Points
Austin Energy SURVEYING 2526 Kramer Ln Bldg. E Austin TX 78758-4007 1-512-505-7183 Wednesday, May 15, 2013 2:45:08 PM PROJECT: \\Kramer3\Survey\Surveying\HIKE&BIKE TRAIL SHOOTS 5-14-2013.pro -------------------------------------------------------------------------------- Point Coordinates Listing - WEST POSITIVE LAT LONG IN DECIMAL DEGREE FORMAT PT# LATITUDE LONGITUDE Elev Name ------------------------------------------------------------------------------- 1 30.252534291 97.740769389 430.63 GD 2 30.252667285 97.740596028 428.63 TOPWATER 3 30.252216609 97.740828702 434.11 PARKING LOT 4 30.252769559 97.741119026 437.87 PATIO 5 30.261354281 97.747342391 431.11 TRAIL 6 30.261364772 97.747339430 429.00 TOPWATER 7 30.261274656 97.747141271 430.86 TRAIL 8 30.262441033 97.749103028 431.47 TRAIL 9 30.262676478 97.749549873 430.61 TRAIL 10 30.262737220 97.749583191 430.23 TOPROCK 11 30.262746759 97.749582574 428.71 TOPWATER 12 30.262805644 97.749931085 430.65 TRAILTOP 13 30.262883541 97.750183914 430.19 TRAIL 14 30.262994515 97.750532940 430.63 TRAIL 15 30.263253915 97.751156217 432.44 TRAIL 16 30.263388586 97.751820995 434.65 TRAIL 17 30.263778547 97.752469411 432.37 TRAIL 18 30.263832294 97.752422993 428.86 TOPWATER 19 30.263978532 97.753395432 435.88 TRAIL 20 30.264268106 97.755176605 436.29 TRAIL 21 30.265191153 97.757224116 428.71 TOPWATER 22 30.266002982 97.755469881 447.70 STEPS-100FLOOD 23 30.266212010 97.755775002 433.00 TRAIL 24 30.266348489 97.756175346 432.54 TRAIL 26 30.266446816 97.756252431 431.94 MANHOLE 27 30.266451488 97.756247316 431.06 FLOWLINE 28 30.266310672 97.756163568 429.01 WATER EDGE 29 30.266452189 97.755365044 441.68 COA BRASS CAP 30 30.265990854 97.755067104 435.76 TRAIL 31 30.265009205 97.752369384 428.78 TOPWATER 32 30.264198293 97.750286293 432.78 TRAIL 33 30.264289096 97.750597795 432.50 TRAIL 34 30.270332016 97.765928609 428.77 TRAIL 35 30.270305007 97.765911136 429.64 TRAIL 36 30.270341835 97.765982296 430.79 TRAIL 37 30.270260260 97.765996991 428.93 TOPWATER 38 30.272001870 97.768865476 430.88 TRAIL 39 30.271554570 97.767987206 431.38 TRAIL 40 30.271083922 97.767333331 431.99 TRAIL 41 30.269136697 97.762640714 433.20 TRAIL 42 30.260833457 97.742371933 432.23 TRAIL 43 30.260672182 97.742453922 429.92 DOCK
44 30.260512663 97.741830687 435.52 BLDG FLOOR 45 30.260557416 97.741557783 451.58 DECK 46 30.253304936 97.738495525 431.14 TRAIL 47 30.255007269 97.739862665 431.49 TRAIL 48 30.252494773 97.737448214 430.43 TOPBOATRAMP 49 30.252464421 97.737472039 429.35 BOATRAMP 50 30.252447892 97.737485463 428.63 TOPWATER 51 30.252524840 97.737555622 430.49 TRAIL 52 30.252414325 97.737393241 431.15 TRAIL 53 30.250931518 97.734717255 431.08 TRAIL 54 30.250581705 97.733561912 432.27 TRAIL 55 30.250312580 97.732835691 430.62 TRAIL 56 30.249942989 97.732045777 432.00 TRAIL 57 30.249101055 97.730054305 431.80 TRAIL 58 30.248749013 97.728838213 430.29 TRAIL 59 30.248369389 97.727815986 430.06 BOATRAMP 60 30.248340644 97.727829351 428.67 TOPWATER 61 30.250622235 97.715423291 432.15 TRAIL 62 30.250625595 97.716035598 432.28 TRAIL 63 30.250575816 97.716127662 428.67 TOPWATER 64 30.244738580 97.716507037 432.35 TRAIL 65 30.244514469 97.716485861 434.48 TRAIL 66 30.244076989 97.716514240 431.84 TRAIL 67 30.244101151 97.716525271 428.72 TOPWATER 68 30.245343107 97.722504528 433.36 TRAIL 69 30.246063247 97.722195471 441.19 TRAIL 70 30.246430586 97.720699998 432.35 TRAIL 71 30.246465291 97.720676732 431.81 TRAIL 72 30.257720801 97.743123847 432.55 TRAIL
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
Appendix E Rating Curves
LABYRINTH WEIR DESIGN No Approach Velocity
PROJECT: Longhorn Dam TIME: 14:51:55PROJECT NO. 1 DATE: 31-May-13
FLOOD CRITERIA: PMF BY: DGM
USER INPUT
Max. Res Zr 454.0 ft ThicknessCrest el. Zc 427.6 ft Wall Tw 3 ftFloor el. Zf 403.0 ft Slab Ts 3 ftSpillway width Ws 50.0 ft Cutoff DepthApex Width 2a 2 ft Sheet Pile Ds 0 ftNo. of cycles n 2 Conc Wall Dc 4 ftMagnification L/W 4.95
LABYRINTH DIMENSIONS (Per Cycle)CHECK ON RATIOS Wall Height P 24.56341767 ft
Ld/B = 1.60 USE FEWER CYCLES Width W 25.00 ft
Ho/P = 1.08 WARNING! H/P > 0.7! Length L 123.75 ft
L/W RATIO IS OK Wall Length B 59.88 ft
Note: Ld/B must be <= 0.35 Depth D 58.95 ft
Ho/P must be <= 0.9 Head max H 26.44 ft must be >= 6 deg Wall Angle 10.10 deg
Length of Lb 95.69
Interference
Labyrinth Rating Curve Lower Crest.xls 1
Gated Spillway Labyrinth Tailwater
Discharge
(cfs)
Elevation
(ft‐msl)
Discharge
(cfs)
Elevation
(ft‐msl)
Discharge
(cfs)
Elevation
(ft‐msl)
0 428.25 0 427.56 0 410.00
37,519 428.25 3,500 428.25 14,564 416.90
45,965 429.63 5,661 428.5 24,567 421.30
54,291 431.74 8,180 428.75 29,945 423.90
63,814 433.86 14,162 429.25 50,050 430.10
73,067 435.77 21,230 429.75 90,046 438.60
82,483 437.81 29,211 430.25 90,361 438.70
91,536 439.55 37,947 430.75 366,912 459.30
101,896 440.41 47,291 431.41 402,395 460.80
51,169 431.88
55,114 432.37
59,118 432.95
63,174 433.62
67,273 434.37
71,410 435.22
75,576 436.14
79,765 437.01
83,971 437.90
88,188 438.78
92,410 439.43
96,631 439.77
100,846 440.11
105,050 440.44
109,239 440.78
113,408 441.12
117,554 441.45
121,672 441.78
125,761 442.11
129,815 442.44
405
410
415
420
425
430
435
440
445
0 25000 50000 75000 100000 125000
Gated Spillway
Labyrinth
Tailwater
Longhorn Dam Labyrinth Weir Conceptual Evaluation Austin Energy
Appendix F Project Schedules
ID Task Name Duration
1 Notice to Proceed 0 days
2
3 Final Design 180 days
4 30% Plans 8 wks
5 30% Review 4 wks
6 60% Plans and Specifications 8 wks
7 60% Review 4 wks
8 90% Plans and Specifications 8 wks
9 90% Review 4 wks
10
11 PERMITTING 85 days
12 Prepare Permit Documents 10 days
13 Finalize Plans and Specifications 2 wks
14 Finalize Report / Summary 1 wk
15 Finalize Application 1 wk
16 Permit Review (General) 75 days
17 Completion Check (no appt) 1 wk
18 Permit Submittal (appt required) 1 wk
19 Permit Review 4 wks
20 Response to Comments 2 wks
21 Permit Submittal (appt required) 1 wk
22 Permit Review 4 wks
23 Finalize Permit 2 wks
24 PROJECT SETUP (COA) 10 days
25 Trade Summary 1 wk
26 COA Ecparis Setup 1 wk
27
28 Bid and Award 75 days
29 Finalize Front End 1 wk
30 CLMD Review 2 wks
31 Advertise 3 wks
32 Bid Opening 1 wk
33 Bid Evaluation 1 wk
34 Request Council Action 6 wks
35 Award 1 wk
36
37 Construction 15 mons
Month ‐2 Month 1 Month 3 Month 5 Month 7 Month 9 Month 11 Month 13 Month 15 Month 17 Month 19 Month 21 Month 23 Month 25 Month 27Quarter 1 Quarter 3 Quarter 5 Quarter 7 Quarter 9
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration‐only
Manual Summary Rollup
Manual Summary
Start‐only
Finish‐only
Deadline
Progress
Longhorn DamGate Repair Schedule
Page 1
Project: 2013‐04‐11 Longhorn DaDate: Jun 20 '13
ID Task Name Duration
1 Notice to Proceed 0 days
2
3 Preliminary Design 220 days
4 Develop Preferred Layout Based on Stakeholder Input
8 wks
5 Sectional Physical Model Study 6 wks
6 Geotechnical Investigation 10 wks
7 20% Drawings 3 wks
8 Full Width Model Study 16 wks
9 Backwater Model 2 wks
10 Preliminary Design Report (draft) 1 wk
11 City Review 4 wks
12 Preliminary Design Report (final) 2 wks
13 City Authorizes Final Design 4 wks
14
15 Final Design 170 days
16 30% Plans 6 wks
17 30% Review 4 wks
18 60% Plans and Specifications 8 wks
19 60% Review 4 wks
20 90% Plans and Specifications 8 wks
21 90% Review 4 wks
22
23 PERMITTING 85 days
24 Prepare Permit Documents 10 days
25 Finalize Plans and Specifications 2 wks
26 Finalize Report / Summary 1 wk
27 Finalize Application 1 wk
28 Permit Review (General) 75 days
29 Completion Check (no appt) 1 wk
30 Permit Submittal (appt required) 1 wk
31 Permit Review 4 wks
32 Response to Comments 2 wks
33 Permit Submittal (appt required) 1 wk
34 Permit Review 4 wks
35 Finalize Permit 2 wks
36 PROJECT SETUP (COA) 10 days
37 Trade Summary 1 wk
38 COA Ecparis Setup 1 wk
39
40 Bid and Award 75 days
41 Finalize Front End 1 wk
42 CLMD Review 2 wks
43 Advertise 3 wks
44 Bid Opening 1 wk
45 Bid Evaluation 1 wk
46 Request Council Action 6 wks
47 Award 1 wk
48
49 Construction 15 mons
Month ‐3 Month 1 Month 4 Month 7 Month 10 Month 13 Month 16 Month 19 Month 22 Month 25 Month 28 Month 31 Month 34 Month 37Quarter 1 Quarter 3 Quarter 5 Quarter 7 Quarter 9 Quarter 11 Quarter 13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration‐only
Manual Summary Rollup
Manual Summary
Start‐only
Finish‐only
Deadline
Progress
Longhorn DamLabryinth Weir Schedule
Page 1
Project: 2013‐04‐11 Longhorn DaDate: Jun 20 '13