Upload
justin-kearney
View
218
Download
0
Tags:
Embed Size (px)
Citation preview
Long Term Capital Works
Programming to Achieve Better Project
OutcomesThursday 06 October 2011
Paul NortheyGeneral Manager Capital Projects
MELBOURNE 70 km
BARWON WATER
• Assets $1 billion
• Revenue $128 million
• Connected properties 133,000
• Growth 2% p.a.
• 20 treatment plants
• 10 reservoirs, 38 service basins
• 6 groundwater bores+7 under construction
• 6,000 km water and sewerage pipes
VICTORIAN GOVERNMENTMinister for Water
WATERCORPORATION
Department of Health
EssentialServices
Commission
EnvironmentProtectionAuthority
Drinking Water Quality
Environmental Compliance
Pricing,Customer Service StandardsBusiness Performance
Ultimate accountability
Statement of Obligations
CONTEXT: CLIMATE UNCERTAINTY
CONTEXT: MULTI – SITE DEVELOPMENT
Above Ground
Decommission
Rehabilitate / Replace
Operate & Maintain
Create Assets
Below Ground
CONTEXT: ASSET MANAGEMENT
Above Ground
Below Ground
Capital Works Process
- PARMS (Water)- SIMS (Sewer)
- FMMS
- FOCUS
- Spreadsheets
CONTEXTHistoric Capital Delivery Performance
Approach to Delivery
CAPITAL PROGRAM
• “Horses for courses” for major projects• Recurrent works by operations departments (term &
individual contracts)• Majority of works through a program alliance
BARWON WATER ALLIANCE
150 individual projects4 (+2) years~$450m80 EFT staffLocal subcontractors
Barwon Water Capital Works – Project Phases
Concept Planning Functional Design
HandoverConstructDetailed Design
Operation
Project Initiator / Asset Planning
Client DeptCapital Works Alliance
Milestone 1
Project included in BW Corporate Plan Budget
Milestone 3Functional design
developed. Procurement
strategy approved.
Milestone 4Detailed design
developed (>75%). Bus Case / TOC approved.
Milestone 5
Asset is operable.
Milestone 6Commissioning
and Testing complete. Handed
over to Client.
Milestone 2Planning Business
Case approved. Project handed over to Alliance
Milestone 7
Asset capitalised. Gain/Pain share
determined.
Project Initiation
Rel
evan
t P
oli
cy /
Pro
ced
ure
s
Project Prioritisation
Capital Works Management
Committee Charter
Risk Management
DTF Gateway
Procurement Policy
Project Program
Business Case
Statutory Engagement
Community Engagement
Project Reporting
Project Transfer
Risk Management
Contract Delivery Strategy
Design Management & Review
Community Engagement
Project ReportingBudget Variation
Budget Variation
Statutory Engagement
Procurement Policy
Envir Management
Safety Management
Statutory Engagement
Risk Management
Design Management &
Review
Community Engagement
Project Reporting
Budget Variation
Envir Management
Safety Management
Probity
Procurement Policy
Project Program Project Program
Risk Management
Envir Management
Safety Management
Probity
Community Engagement
Quality Plans
Statutory Engagement
Project Reporting
Budget Variation
Risk Management
Envir Management
Safety Management
Inspection & Test Plans
Quality Plans
Statutory Engagement
Project Reporting
Budget Variation
Commissioning Plan
Project Transfer
Final Cost Reporting
Project Review
Project Completion
Barwon Water
Barwon Water Alliance
CONSTRUCTIONUse of Subcontractors• Most construction delivered
by subcontractors• Limited ‘self-perform’ on
higher risk jobs with day-hire labour.
• Safety inducted over 1000 inductees in contractor induction program.
• SQE contractor forums – network forming between subcontractor.
• Lead to pre-qualification panel reduce site supervision over time.
Colac Pipeline
• Has delivered program to date• Equal number of employee’s from each
partner has led to strong culture• Development opportunity for client staff• Improve capability and capacity of regional
contractors• Bundle procurement of material delivering
cost savings• Manage workforce in areas to achieve
efficiencies
ALLIANCE
Positives
• High transaction cost $500k
• Early KPIs have required lot of monitoring and reporting streamlined down to 6
• TOCs are not like old project estimates on tendered prices – all cost identified – this lead to some tension on early TOC approvals.
• Can create differing standards within client organisation between Alliance and no – Alliance projects
ALLIANCE
Negatives
MELBOURNE TO GEELONG PIPELINE
• Competitive tenders received for construction contract
• Leaving pipe material option open led to competitive process for the pipe supply contract
• Managed risks with uncertainty on design of realigned section
• Pipe and fittings delivered to schedule or earlier
• Low transaction cost – use of AS2124
MGP PROCUREMENT MODELPositives
• Number of separable portions leads to complicated contract management
• Involved tender essessment process – difficultly in assessing
• Standard contract requires updating
MGP PROCUREMENT MODELNegatives
CORIO BAY
GEELONG
N
Proposed Northern Water Plant NORTHERN
WATERPLANT
Shell Refinery
10 km to Black Rock Water Reclamation Plant
and ocean outfall
NWP PROCUREMENT MODELGetting the Model Right
• Client involvement in design – managing whole of life risks
• Cost certaintity:– Single margin competitively big up front– Competitively tendered work packages– Fixed construction cost
• Contractor carries design into construction, provide working facility following proving period.
• Operational hand over and training for Barwon Water staff
• Transaction costs around $250K
NWP PROCUREMENT MODELPositives
• Stage 1 cost estimate process inefficient and difficult to
administrate due to:– contractor incentivised to influence work packages to
increase margin return
– Work packages tendering process not fully transparent
– considerable effort required through independent estimator
and extended negotiations to bring cost down
• Delay and variation claims for inefficient process
• Paying for risk twice?
NWP PROCUREMENT MODELNegatives
BIOSOLIDS DRYING FACILITY AT BLACK ROCK$76 million
21
TO PPP OR NOT?• Is project of sufficient value?
• Is there a history of in-house delivery and operation of this service?
– Is it ‘core’ business?• Characterise risks
– Are risks significant?– Which party is in the best position to manage risks (can
risks be transferred)?– How will the private sector cost the risks that will fall with
them?
• Will a PPP deliver economic value to the public sector?
• Will the project’s value bear the transaction costs (typ. $2-3 million)?
• Project costs and schedule have significantly extended but at no cost to Barwon Water.
• Proponent has had full responsibility for managing difficult IR issues.
BIOSOILDS - PPPPositives
• No Barwon Water control on how project was delivered or timeframes
• Agreements made by PPP proponent can influence other Barwon Water projects
• High transaction cost - $2-$3 million
BIOSOILDS - PPP Negatives
CONCLUSIONChoosing The Best Model
s t r u c t ,
F i n a n c e &
O p e r a t e )
MAX
MIN
LOW HIGH
E P C M
MIN
MIN
MAX
MAX
MAX
MIN
A
L I
N C
L
E
A
PPP
Project Procurement Options (adapted from PricewaterhouseCoopers, 2005,unpublished paper)
DBO
DBFO
D&C
EPCM
CFD
RISK TRANSFER (PRICE PREMIUM)
PRICE CERTAINTY
TRANSACTION COSTS
FLE
XIB
ILIT
Y T
O C
HA
NG
E
CO
NT
RO
L O
VE
R B
UIL
D Q
UA
LIT
Y
SUMMARY• Five year Water Plan requires assessment of
required capital spend and appropriate delivery strategy
• Bundling of projects enables cost savings in procurement of materials and construction
• Alliance has delivered increased capital works program
• Thorough business cases and demonstrated ability to deliver increases potential to obtain government funding
Thank you