17
Long Lake Hydro Project Update Presented by David Carter Regional Power Minerals North 2011 Long Lake Joint Venture

Long Lake Small Hydro Project - Minerals North

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Long Lake

Hydro Project Update

Presented by

David Carter – Regional Power

Minerals North 2011

Long Lake Joint Venture

Long Lake Joint Venture

Project Location

25 km north of Stewart, in northwest B.C.

Situated near historic Premier & Big Missouri mining camps

Moderated coastal climate and terrain ideal for hydro

Long Lake valley

looking south

Long Lake Joint Venture

Developer Background

Regional Power

developer and operator of hydroelectric power plants since 1985, over 120 plant years of operating experience

Developed hydro plants in BC and Ontario

Regional has 6 hydroelectric development sites “under contract” representing 97 MW in capacity

Two 11 MW sites on Bear Creek, near Sechelt currently under construction and Long Lake access construction started summer 2010

a subsidiary of Manulife Financial

Long Lake Joint Venture

Developer Background

Joint Ventured with Premier Power

Corp. in Long Lake Project

Premier’s affiliate company,

Summit Power, owns and operates

two hydro developments in

southwestern B.C.

14 MW Soo River Hydro, near Whistler

5.3 MW Doran-Taylor Hydro, near

Port Alberni

Doran-Taylor 5.3 MW Project

Long Lake Joint Venture

Joint Venture Background

Innovative approach to Project development

Identify environmentally and economically sound opportunities

Established a favourable, cooperative relationship with government agencies, stakeholders

Doran-Taylor Hydro tailrace (Oct 98)(Fisheries Renewal BC project co-sponsored by Summit Power, DFO, Hupacasath First Nation, MC Wright & Associates)

Sechelt Creek Hydro spawn channel (Sep 03)(A cooperative arrangement between

Regional Power, DFO, Sechelt First Nation)

Long Lake Joint Venture

Project History

Several hydro schemes

powered the old Premier

and Big Missouri mines

during 1923 through

1956

Developments on lower

Cascade & Fletcher

Creeks provided power

to nearby Premier mine

and townsite

Long Lake Joint Venture

Project History

Cominco built dam

at Long Lake to

provide storage for

Big Missouri mine

power development

Storage provided

firm power year

round to mine and

townsite

Former Long Lake Dam

Long Lake Joint Venture

Project Background

Westmin studied Long Lake hydro concept to service a new 2,000 tpd mine in late 1980’s

Plans for the hydro plant were shelved when BC Hydro extended the 138kV transmission line from Aiyansh to Stewart

Premier Gold mine operated until mid 1990’s

Long Lake Joint Venture

Project Background

Summer 1999: Premier Powerinitiated technical, environmental and socioeconomic investigations

Late 2002: Premier Power and Regional Power formed Long Lake Joint Venture to advance the development

Early 2005: Completed regulatory review process for 2.83cms (CEAA / CWL)

Fall 2008: Project was successfully bid into BC Hydro’s 2008 Clean Power Call process

Summer 2010: Awarded Energy Purchase Agreement

Long Lake Joint Venture

Project Design

Redevelop concept using Westmin 1980’s strategy

Develop hydro power to optimize utilization of hydrologic resource

– 31 MW installed capacity

– 5.0 m3/s design flows

– utilize storage on Long Lake

– develop 776 m gross head

Long Lake Joint Venture

Project Design

Rockfill dam & intake structure designed for stability under MCE and PMF (highest Canadian Dam Safety Criteria)

7.25km penstock generally following Big Missouri Haul Road to vicinity of Premier Gold mill site

Powerhouse with two 16 MW two-jet Pelton-type turbine generator units

Power transmission via new 10km, 138kV line connecting to BC Hydro

Short tailrace to return water to Cascade Creek

Project fully designedSheet Pile / Rock Fill Dam construction at Pingston Creek(Photo: P. Kemp, Canadian Projects)

Long Lake Joint Venture

Project Design

Penstock:• Steel pipeline

• Integrated Resource Management

Planning

Long Lake Joint Venture

Construct new 10 km, 138kV transmission line, all within BC

Connecting to BC Hydro grid

Extending the 138kV transmission

Project Design

Long Lake Joint Venture

Project Design

Two jet pelton configuration similar to Dease Lake

Remote access of powerhouse controls

3-4 Operators

5.3 MW Pelton turbine

(similar to unit proposed for Long Lake)

Long Lake Joint Venture

Project Schedule

Design of Major Infrastructure Completion -

Summer 2005

Commenced construction –

August 2010

Rehabilitate BMHR –

August 2010

Major Equipment & General Contracts –

May / June 2011

Commercial Operation -

Summer 2013

Long Lake Joint Venture

Project Benefits

Project will become the largest tax base in the District of Stewart

Sustainable, long term resource investment in district

Help maintain valuable infrastructure

Affords numerous environmental benefits

Construction of “Soucie Pass” Road to Long Lake dam site

September 2010

Photo: S. Giesbrecht, Triton Environmental

Long Lake Joint Venture

Special Thanks…

District of Stewart, Mayor and council, and stakeholders, for their tireless and ongoing support for the Project

Nisga”a and SKLH for their support

Provincial and federal regulatory agency support and policies for promotion of development of clean energy

BC Hydro for awarding the Project the most northerly hydro contract under the 2008 Clean Power Call

Soucie Construction for their excellent work on pioneering the “Soucie Pass” access road summer 2010

Minerals North organizers and volunteers