Upload
trishya-j
View
217
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Assignment 1 Constructing Environments The University of Melbourne
Citation preview
THE UNIVERSITY OF MELBOURNE
Constructing Environments
Log Book Final Submission
Name : Trishya John
Student ID Number: 699579
1
Contents Week 1 – Introduction to Construction ........................................................................................... 2
Week 2 – Structural Loads and Forces ......................................................................................... 13
Week 3 – Footings and Foundations ............................................................................................. 24
Week 4 – Floor Systems and Horizontal Elements ...................................................................... 57
Week 5 – Columns, Grids and Wall Systems ............................................................................... 81
Week 6 – Spanning and Enclosing Space ..................................................................................... 96
Week 7 – Detailing Strategies 1.................................................................................................. 107
Week 8 - Openings...................................................................................................................... 115
Week 9 – Detailing Strategies 2.................................................................................................. 132
Week 10 – When things go wrong .............................................................................................. 152
Glossary of Terms ....................................................................................................................... 162
Reference List ............................................................................................................................. 182
Appendix ..................................................................................................................................... 187
2
Week 1 – Introduction to Construction
Knowledge maps
Loads on buildings (Ching, 2008)
Structural forces (Newton, 2014)
3
Materials (Newton, 2014)
4
Site Analysis
(Ching, 2008)
5
Theatre Session
We were introduced to the concept of loads on buildings in our first theatre session where we
were given a single sheet of blank A4 paper and tape and asked to build a structure that can
support a brick using only those materials. I formed a four point structure as shown below, which
I strengthened by folding repetitively. I was unable to test the structure at the lecture, so I
performed a test once I got back home by checking if the paper structure was able to support the
load of all my textbooks.
It was able to support my textbooks when the
thicker side of the structure made contact with
the ground, but not when the thinner side made
contact with the ground. One of the things that I was able to learn from this experience was that
it was crucial for a structure to have a very strong base in order to support an immense load. I
also realized that one of the reasons why my structure was successful was because the
symmetrical shape of it may have enabled an even distribution of the load of the textbooks
throughout the structure. These were some of the key elements that I tried to apply to our
structure that was built during the studio session.
Shape allows an even
distribution of the load of the
textbooks throughout the
structure
6
Studio Session
Construction procedure
In our first studio session we were divided into groups of 3 and given blocks of the same size and
shape made of MDF. As this was a compression challenge, blocks were an efficient building unit
as blocks are commonly used in structures that rely on compression forces, such as arches. We
were then told to make a tower as tall as possible that could accommodate a toy horse provided
by our tutor, which meant that we had to integrate an opening into our structure. Our first step
was to measure how high the opening had to be for the object to be able to enter the structure,
and we did so by stacking the blocks one on top of each other next to the horse until they were a
bit taller than the horse.
However, we then realized that constructing the
tower by placing the blocks as shown on the left
would result in a structure that was very likely to
collapse due to its instability, so we then decided to
place the blocks flat on top of each other as shown
below. We then had to re-estimate the height of the
horse using the height shown in the image on the
left.
Estimating height of the object
Re-estimating height of the object
7
We then decided to slightly change the laying of the blocks and place them the conventional way
bricks were laid in a building instead of merely stacking them one on top of each other. This
would have been more stable than originally planned, as the load from a block will be transferred
to two bricks below it instead of just one and thus be spread out more evenly.
We then started to build the structure
as shown below. Our aim was to pack
the blocks as tightly as possible in the
first ten rows to create a stable base
and then decide on how to change the
way the blocks were laid once the
structure gained a reasonable height.
Packing the blocks tightly together will
result in more blocks being laid at the
base, which then increases the
compression forces, causing the blocks
to be compact. This is what will ensure
stability for the whole structure.
Original block laying technique Modified block laying technique
Foundation of the structure
Aimed height of the opening
8
However, this layout of the structure had to
be changed once again. This was because
the object had to be rotated once it was
inside the building in order to make it fit
inside the structure. Therefore, there was a
risk of the structure collapsing if we rotated
the horse while sending it into the opening.
We then decided to remove the blocks from one side of the structure to form an opening as
shown below and covered the gap made in the original building. This would then resolve the
issue of the object being able to enter the structure without having to be rotated.
Details of the block laying
technique – high compression
forces due to tightly packed blocks
9
Even though we had now developed a
structure that could accommodate the object,
we still faced the issue of bridging the gap
created in order to form a doorway. We
attempted to stack the blocks in a ‘staircase’
manner on either side, but the blocks fell after
about two or three of them were placed, due
to the increasing load and the inability of the
blocks to support them, so we were unable to
create a bridge as the gap was too wide.
Our next idea was to warp the structure in order
to bring the gap closer so that a fewer amount of
blocks would have to be used in order to form a
bridge.
We attempted to bridge this much smaller
gap by stacking the bricks in a similar
manner to before, but unfortunately we were
unsuccessful again. As we could not make
the gap smaller, we decided to focus on
making the structure as tall as possible. Due
to the limit on the amount of MDF blocks
we were given, we decided to use less blocks to build the rest of the structure. I was able to
conclude that due to the fact that the blocks were packed tightly for approximately twelve rows,
the base would be strong enough to produce a stable structure that was capable of supporting a
heavy load. I based my conclusion on the paper structure I made in lecture 1, which was thick at
the bottom due to the folds, and thus was able to support the weight of all my books. We then
continued to lay the blocks on the structure, but left large gaps in between so that we would be
Attempt at
building a bridge
Modified layout to
accommodate object
Warping structure –
decreases compression
forces at base
10
left with more blocks to add height. As the blocks are now spread out towards the top, the
compression forces of the structure decrease with the height.
Figure 1: Increasing the height of the structure
We completed our structure by following the
same pattern established previously.
Deconstruction procedure
Figure 2: Structure during deconstruction process
We were then told to remove blocks from the
structure one at a time in order to test the
stability of the building. In the process, I was
able to find a method to create a doorway.
Although we had considered this idea before,
we did not think it would work as we
assumed that the structure would collapse,
and we only realized that it would have
worked during the deconstruction process. I
simply removed all the blocks in one area
and created a large gap, as seen on the left.
Compression decreases with height as
blocks are spaced widely
Final structure
Doorway – did not collapse due to
distribution of loads through the structure
11
The fact that our structure did not collapse even though all those blocks were removed indicates
that the loads were transferred through the structure in a manner that was able to prevent the
structure from collapsing. It is possible that our structure may have been able to support a
heavier load, if it had remained in a rectangular shape. This final structure may have encountered
difficulties with doing so because warping the structure pushed the blocks out of proportion in
the base, which may have reduced the compression forces that would have been much stronger if
the blocks were packed tightly together.
Figure 3: Load path diagram of structure with a few blocks removed
Figure 4: Comparison of compression forces between original structure and warped structure
12
Comparison with other groups
This group had built a structure that was most
similar to ours in terms of the way they laid
the blocks, and the fact that they packed the
blocks tightly for the first few rows and
incorporated gaps in the higher rows. The
only differences were the shape of the
building and the fact that they had managed
to successfully integrate a doorway into their
structure.
This was another structure created by one of
the groups, which had a very different block
laying technique and shape compared to the
structures of the other groups. It seems as
though their technique of laying blocks,
although aesthetically appealing, may have
used a relatively larger amount of blocks
compared to the conventional brick laying
technique that all the other groups adapted.
Even though their structure was able to
accommodate the object, they too appeared
to be unsuccessful in bridging the gap.
Strong compression forces enabled
structure to support a load of over
5kg, which was done near the end
of the studio session
The blocks are packed tightly
together, which will increase the
compression forces in the structure
13
Although the block laying technique is not
very visible in this photograph, it appears
that they adopted a similar method to our
structure. However, it appears that they
might have encountered difficulties during
the construction process as they too were
unsuccessful in creating a doorway, and
were not able to create a tall structure. The
blocks appear to be packed tightly together
and they have followed this method to
create the entire structure, which means that
the compression forces will be high.
Week 2 – Structural Loads and Forces
Knowledge maps
Structural systems
(Newton, 2014)
Structural joints
(Newton, 2014)
14
Common Environmentally
Sustainable Design Strategies
(Newton, 2014)
Building systems
(Ching, 2008)
15
Theatre session
We covered the importance of how trusses and a bracing system are key elements in supporting
loads in various structures. This was illustrated by various students having to build a truss on a
plastic cup with straws which had to be attached to the cup with pins. These are diagrams of two
structures that were made during this exercise, one which was successful and one which was not.
This structure was able to support
a load effectively because bending
the straws provided 8 paths for the
load to be transferred to the
ground. Folding also provided a
much shorter distance for the loads
to travel, and ensured structural
stability.
This structure was unable to
support a load because the long
straws were unable to support a
load easily, which caused the
whole structure to collapse. There
were also only four paths for the
load to be transferred.
Successful structure
Unsuccessful structure
16
The unsuccessful structure can be improved by introducing a bracing system as shown in the
figure above. The system is in the shape of triangles, which is a difficult shape to distort, and
therefore adds more stability to the system. It also provides more paths for the loads to be
transferred to the ground.
The concepts illustrated in the lecture were useful for the frame challenge in the studio session,
as they illustrated the different ways in which long, thin members could be used to effectively
carry and transfer loads.
Studio session
Construction procedure
This week’s studio introduced the concept of a frame structure, and to illustrate this, we were
told to build a frame tower out of only 20 strips of cut balsa wood in groups of 3. The tower had
to be as tall as possible, and we were encouraged to experiment with different types of joints. We
were told that the towers would have a load placed on it once they were completed to see at
which points they fail. Balsa wood was an efficient material for this challenge as the strips were
light and had a low density, which are properties that would have been needed to make a frame
structure. In order to save strips of balsa wood, we decided to make the tower in the shape of a
triangle instead of a square or rectangle. We cut 3 pieces of wood, of 20cm each, and used them
to form an equilateral triangle for the base. Then, we joined three strips of wood to each of the
corners of the triangle.
How unsuccessful structure can be
improved
17
We then cut a second triangle with sides
measuring 20cm and joined it with the three
strips of wood that were stuck onto the first
triangle.
The strips of wood were joined together
by masking tape, which, in the context
of this structure, can be considered a
fixed joint. A fixed joint resists rotation
and translation in any direction, and
provides force and moment resistance
(Ching, 2008), and as the structure was
relatively stable with an additional
successive level, we decided to
continue using fixed joints.
Sketch of structure we
wanted
Foundation of
structure
18
However, as the structure began to increase in height, we
found that we had to add pins to the joints, thus creating pin
joints, along with the fixed joints, as strips of joined balsa
wood kept detaching, which suggested that just fixed joints
were not strong enough to hold the members together. We
joined the strips of wood with a pin, and then wrapped the
pin with masking tape.
Fixed joint
Details of fixed joint
Structure is stable but a
slight tilt can be observed
due to weak joints
19
Although we assumed that our
combination of pin and fixed joints
were strong enough to keep the
members in place, the tower began
to twist and lean as it increased in
height, possibly due to the
increasing load of the structure.
This was an indication that perhaps
the joints may have not been
efficient enough to transfer the
loads, possibly due to the way we
had attached the members. The
manner in which forces are
transferred from one structural
element to the next and how a
structural system performs depends
on the types of joints used, to a
large extent (Ching, 2008). The addition of the pin may have also caused the member to fold
backwards, based on the way we attached it, which may have also been a factor in causing the
structure to twist because the joints were not stable enough to transfer the loads.
The members were also
rectangular in shape, which
results in uneven distribution
of the load through the strips
of balsa wood. This would
have also been one of the
factors that caused the
torsion of the member,
resulting in the whole
structure twisting. If the
members were in the shape
of a square, there would have
been a more even
distribution of the load,
resulting in less torsion.
Details of pin joint
Load through individual members
20
As seen in this diagram, each joint will be connected
to three members and will thus receive loads in three
directions. If the joint is ineffective in transferring
these loads, the whole structure will be unstable.
Due to the structure twisting and bending as a result of
the joints failing, there came a point where the
structure was unable to stand without support because
it was unable to transfer the load effectively
throughout the structure, which resulted in it being
unable to support the load of the additional members.
This explains why the final structure was unable to
stand
without
support
Our idea was to form a bracing system in order to
prevent the members from twisting, so we cut a strip
of balsa wood and connected it to two of the
members that were twisting the most. However, it
did not fix the problem since the twists were due to
the joints, so we did not continue developing a
bracing system.
Load path
diagram of
structure
Attempt at
bracing
structure Lean in the structure can be
observed clearly due to the
increasing load
21
We finally added 3 more members to the 3rd triangle (excluding triangle made for the base) and
joined them at the ends. These are images of the final structure which was, as seen below, unable
to stand without being supported.
Deconstruction procedure
The structures then had a load applied to them, in order to estimate at which points they started
to fail.
Figure 5: Deconstruction procedure
As seen in the picture, the structure was bending at
the joints when a load was applied. It was mentioned
before that the purpose of a fixed joint was to prevent
rotation of the members, but ours failed to do so
because we connected the members incorrectly. This
was why the structure was bending at the joints.
Structure without a support
system
Point at which
structure was
unable to support
itself
Structure with a
support system
Bending occurring at the joints
when a load is applied – joint
should have resisted load
22
As the load increased, one of the members
that were joined at the second triangle
snapped at its mid-point. This was because
the increasing load was causing an increase
in the reaction force that was acting on the
member. The two forces met at the middle,
which then caused the structure to snap at
that point.
Load path diagram of a section of
structure during deconstruction
process
23
Comparison with other groups
All of the structures built by the other groups had a member snap at its mid-point when a load
was applied, due to the explanation given. However, as seen below, the members did not bend at
the joints the way they did in our structure, because they consisted of more effective joints.
Less bending occurs at the
structural joints when a load is
applied – only the individual
members bend. Structures all
displayed a bracing system that
would have reinforced the overall
stability.
24
Week 3 – Footings and Foundations
Knowledge Maps
Structural elements and concepts
Figure 6: Structural Elements (Newton, 2014)
Figure 7: Structural concepts (Newton, 2014)
25
Construction systems Figure 8: Footings and foundations (Ching, 2008) (Newton, 2014)
26
Materials Figure 9: Mass Materials (Newton, 2014)
Figure 10: Mass Construction (Newton, 2014)
27
Figure 11: Bricks (Newton, 2014)
28
Figure 12: Properties of bricks (Newton, 2014)
29
Figure 13: Concrete (Newton, 2014)
Figure 14: Properties of concrete (Newton, 2014)
30
Figure 15: Stone (Newton, 2014)
31
Figure 16: Properties of stone (Newton, 2014)
32
Theatre Session Figure 17: Olympic Games Park
33
Studio report
In the studio session, we examined the features of different buildings, such as the structural
elements, structural systems, joints and materials. The buildings were:
Lot 6 Café
Underground carpark and South Lawn
Arts West Student Centre
Stairs on west end of Student Union
North Court Union House
Beaurepaire Centre Pool
Oval Pavilion (north side of Oval)
Old Geology South Lecture Theatre Entry Structure
Frank Tate Pavilion
Lot 6 Café
Figure 18: Location of Lot 6 Café (The University of Melbourne, 2012)
The Lot 6 Café is located to the south of the Eastern Resource Centre, at the 1888 Building.
34
Structural elements
The ceiling of the café was supported by a beam which extended outside the building and was
supported by a brick column outside the café. The beam and the brick column are both load
bearing – the ceiling transfers loads to the beam, which will then transfer them to the brick
column, which transfers them to the ground.
Figure 19: Beam supporting ceiling (Design. City. Living., 2012)
Figure 20: Beam supported by brick column (Design. City. Living., 2012)
Beam supported by
a brick column
outside the building
Brick column
Beam
supporting
ceiling inside
the cafe
35
The beam supports the
load of the ceiling and
transfers these loads to
the brick column outside
Figure 21: Load path diagram of beam
Figure 22: Load path diagram of column
Beam from the café
transfers loads to the
column, which transfers
loads to the ground
Column transfers
load to the ground
36
Building Systems
The main types of building systems that can be observed are the enclosure system, the structural
system and the mechanical system. The enclosure system consists of walls that are made of
concrete panels and glass, along with glass doors to provide physical access. There is also a flat
roof which forms a part of the enclosure system that cannot be observed in the images, which
may be made of concrete.
Figure 23: Lot 6 Cafe Exterior
The services that can be observed from the outside are the electrical system, seen through the
lights on the concrete panels.
Glass and concrete forming a part
of the enclosure system
37
Materials
The main materials used in this building are concrete, glass, steel and clay bricks. Glass and
concrete were used to form the enclosure system of the building, with glass being used more than
concrete. This was done to allow the entry of natural light into the café in order to minimize
energy consumption through lights. Concrete may have been chosen as it has an excellent
thermal mass, which reduces energy needs from heating and air conditioning (Cement
Sustainability Initiative, 2012).
As seen in the diagram below, beams undergo both compression and tension. Mass materials
such as clay or concrete will not be suitable for a beam as they are strong in compression but
weak in tension. Therefore, steel was chosen as it has the ability to support both tension and
compression (Newton, 2014)
Figure 24: Forces acting on a beam
Bricks were used to construct the load bearing column that supports the steel beam. As columns
experience compressive forces (Newton, 2014) , clay bricks were chosen to build the column as
they are strong in compression (Newton, 2014).
Figure 25: Column
Compression forces experienced by
column
38
Underground car park and South Lawn
Figure 26: South Lawn Car Park (The University of Melbourne, 2012)
The underground car park is located below the South Lawn, within close proximity to the Baillieu Library
and the Brownless Biomedical Library. It was designed by engineering and planning practice Loder and
Bayly. Excavation work began in May 1971 and the car park was complete by November 1972 (Lovell
Chen Architecture & Heritage Consultants, 2011).
Structural Elements
The car park consists of load bearing concrete columns which are evenly spaced.
Figure 27: Typical column
Upper column cap
joined to the ceiling
above
Column drum – joined to upper column cap
with fixed joint
Concrete pad footing
39
Construction systems
The enclosure system consists of reinforced concrete panel walls, along with a concrete ceiling.
There are three pedestrian entrances and one entrance for vehicular access, but no windows as
the car park is underground (Lovell Chen Architecture & Heritage Consultants, 2011).
The storm water drainage system from the south lawn consists of 4 inch PVC downpipes
integrated into the centre of each concrete column throughout the Car Park's structural grid.
These downpipes discharge water into large ducts that run east-west in every second bay (Lovell
Chen Architecture & Heritage Consultants, 2011).
Figure 28: Method of drainage (Lovell Chen Architecture & Heritage Consultants, 2011)
40
Materials
The main material used in the car park is concrete. Concrete is a strong material which is capable
of supporting many different types of loads. It is used to build the panels in order to support the
ground pressure that will be exerted on the car park as it is built underground. It is used for the
roof to support the dead and live loads of the South Lawn and is used for the columns for the
same purpose.
Figure 29: Loads of underground carpark
However, due to the South Lawn being directly above the car park, water from the soil has
caused efflorescence in the concrete. This decreases the aesthetic quality of the concrete. This
may have been avoided by adding more than one drainage pipe in each column which will enable
the removal of more excess water from the soil.
Figure 30: Efflorescence
Efflorescence caused by
water from soil
41
Arts West Student Centre Figure 31: Location of the Arts West Student Centre (The University of Melbourne, 2012)
The arts west student centre is located close to the zoology building and the babel building.
Structural elements
The main structural elements visible are beams, which are fixed at only one end to form a
cantilever. They provide additional support to the loads of the large steel structure above it.
Figure 32: Structural elements
Cantilever
supports load of
structure above
[Type a quote from the document
or the summary of an interesting
point. You can position the text
box anywhere in the document.
Use the Drawing Tools tab to
change the formatting of the pull
quote text box.] Structural supports at the two sides
– will not be enough to support
entire structure without the
additional beams
42
Materials
Figure 33: Timber beams
In the image above, it can be seen that the beams are made of timber, and they are actually two
thinner beams that have been joined together with a smaller steel beam. This will reinforce the
supports and make them more effective in bearing the load of the larger steel structure. The steel
will also be galvanized to prevent corrosion.
The beams have also been placed as shown below in order to prevent bending.
Figure 34: Placing of beams
Timber beams joined together by a
smaller beam, which increases
efficiency as a support system
Steel structure supported by timber
beams – galvanized to prevent
corrosion
Beams placed in this manner, as
less surface are receives the load,
which minimizes bending
Beams are not placed in this
manner, as more surface are
receives the load, which may cause
bending
43
Stairs on west end of student union
Structural elements
The main structural element seen was beams which supported the load of the stairs and were fixed onto
the brick wall.
Figure 35: Stairway with supporting beams
The cables that are connected to the beams appear to be ties which are tension elements.
However, as it is the beams that are the load bearing elements, it seems that the cables are simply
put in place to appear as though the stairs are suspended. However, they do provide lateral
stability to the stairs by supporting the beams as seen below.
Beams – support the
load of the stairs
44
Figure 36: Cables
Structural joints
In this instance, a fixed joint will be used to connect the beam to the brick wall, in order to avoid
rotation and translation of the beam.
Figure 37: Fixed joint between beam and wall
Beams fixed to the
brick wall
Cables provide lateral stability by
supporting beams but do not bear
the load of the stairs
Fixed joint between beam and wall
needed to prevent rotation or
translation of cantilever
45
When connecting the cable to the beam, a pinned joint will be used. This is to accommodate
movement due to the live loads of people walking on the stairs.
Figure 38: Pinned joint
Materials
The stairs are made of stainless steel that has been galvanized to prevent rust.
Pinned joint needed to connect
beam to cable to accommodate
movement of people walking on
stairs
46
North Court Union House Figure 39: Location of North Court (The University of Melbourne, 2012)
Membranes are thin, flexible surfaces that carry loads through tensile stresses (Ching, 2008). The
membrane structure in the North Court is stretched between various columns which receives
these tensile loads and transfers them to the ground through compression.
Figure 40: Membrane structure in North Court
Membrane structure
in tension
47
The membrane structure had a hole in the middle of it, where cables were connected to the
structure around the central hole. These cables were then connected to the ground using pinned
joints. When there are high wind loads, the cables undergo high tension forces.
Figure 41: Cable structures connecting membrane structure to ground
Figure 42: Cables undergoing tension
Cables connecting membrane structure
to ground. They undergo tension
forces.
High wind loads acting on the
membrane structure
This pushes membrane up, which
causes cables to become very tense
48
One of the main reasons why there was a hole in the middle was to allow water to escape during
periods of rain in order to prevent accumulated rain loads on the membrane structure. The hole is
directly above a drain, which the rainwater falls into, as seen in the diagram below.
Figure 43: Rainwater escape
Joints
The main types of joints used in this structure are pinned joints, in order to allow movement of
the membrane due to wind loads.
Figure 44: Pinned joint
Materials
Membranes are usually a woven textile or glass fibre coated fabric with a synthetic material such
as silicone (Ching, 2008). Steel may have been used for the cables because of their good tensile
properties.
Slope of membrane
allows water to flow
towards hole Movement of water towards drainage
Pinned joints are used to connect the
cables from the membrane to the
ground to accommodate movement
caused by wind loads
49
Beaurepaire Centre Pool
Figure 45: Location of Bureaepaire Centre Pool (The University of Melbourne, 2012)
Structural Elements
This structure was supported by flat columns that were placed at an angle to the beams above the
glass. These columns were also connected to large beams that ran across the ceiling inside the
building, and therefore carried the load of the roof structure.
Figure 46: Inside Bureaupaire Centre Pool (Lovell Chen Architecture & Heritage Consultants, 2014)
Beans are placed along the
pitched roof and transfer loads
to the columns
Columns then transfer
loads of the roof
structure to the ground
50
Figure 47: Load path diagram
Beams transferring load from roof
to columns that are outside
building
Glass
Structural steel
framing
Columns
transferring load
to the ground
51
Construction Systems
The glazing found in the Bureaupaire centre pool is not a part of the structural system, but a part
of the enclosure system. It is supported by vertical mullions and horizontal transoms. Without
these elements, the large spans of glass will not be able to support themselves.
Figure 48: Enclosure system
As seen in the image below, the column has a pad footing below it, and the stone below the glass
has a strip footing which indicates that the stone bears the load of the glazing.
Figure 49: Footing systems
Strip footing to bear
a continuous load of
the stone
Pad
footing to
bear load
of column These footing systems may have
been chosen as the centre pool
building does not have a
significantly large amount of loads
that need to be supported
Glazing
panels
Vertical mullions
Horizontal
transoms
Columns
Stone to support loads
of glass
52
Oval Pavilion
Structural elements and construction systems
The structural elements that can be observed are columns below the building which bear the
loads of the building and transfer them to pad footings. The reason why these will be pad
footings and not strip footings is because there are isolated point loads because of the columns as
opposed to a continuous load, which is where strip footings are used.
Figure 50: Foundations of building
Figure 51: Difference between pad footings and strip footings (Ching, 2008)
The columns which support the
building are seen in this image. Pad
footings are used because the
building is small and will have less
loads.
Pad footing – similar to what is
seen in the photograph because of
column
Strip footing supports continuous
load – will be used in load bearing
walls
53
Materials
The wall at the back of the Pavilion (northern side) is constructed out of bricks. As seen in this
image below, there are expansion joints in this wall to accommodate the expansion of bricks
which occurs due to moisture absorption.
Figure 52: Expansion joint
Expansion joint in
brick wall to
accommodate
expansion of bricks
– wall will start to
crack if joint was
absent
Weep holes needed to allow excess
moisture to escape
54
Old Geology South Lecture Theatre entrance
Construction systems
The lecture theatre entrance is circular with a circular slab on the top to enclose it. It comprises
of the enclosure system which are the glass doors and the brick wall. The brick wall also bears
the loads of the slab.
Figure 53: Lecture theatre entry Figure 54: Brick wall of lecture theatre entry
Glass panels with
framing as support
Brick wall on the other
side of the door
55
Materials
The materials used in this area are bricks for the load bearing wall and glass. Because the span of
glass is relatively large in this section, it requires a structural frame for support. Bricks are used
as they are good in compression and therefore are ideal in transferring vertical loads to the
ground. They also contain weepholes to allow moisture to exit.
Figure 55: Weep holes in brick wall
Weep holes needed to allow exit of
excess moisture
56
Frank Tate Pavilion
The main structural elements that can be observed in this image are a beam and a diagonal
column, which are load bearing and transfer the loads of the main structure to the ground.
Figure 56: Frank Tate Pavilion (TimberDesignAwards, 2010)
Figure 57: Load path diagram
Materials
The materials used in this structure are timber and steel. The timber is used for aesthetic
purposes, as indicated by its highly polished finish, and the steel is used for columns and beams
due to its good compressive and tensile properties.
Beam and column which
support loads of the main
structure
Beam transferring
load to column
57
Week 4 – Floor Systems and Horizontal Elements
Knowledge Maps
Structural Concepts Figure 58: Beams and Cantilevers (Newton, 2014)
Figure 59: Span and spacing (Newton, 2014)
58
Construction systems Figure 60: Floor and framing systems (Newton, 2014) (Ching, 2008)
59
Materials Figure 61: Concrete (Newton, 2014)
60
Figure 62: Pre-cast and in-situ concrete (Newton, 2014)
61
Case study in E Learnings Figure 63: The Pantheon (Hutson, 2014)
62
Theatre session Figure 64: Oval Pavilion – Managers
63
Studio Report
Discussion on Scale
Before beginning the questionnaire, we were divided into groups and told to discuss why and
how scale was used in documenting building projects. Scales are used in order to fit structures
into a paper, as it would be extremely difficult to draw a building in its actual dimensions. Larger
scales will be used to represent plans, which show the building as a whole and do not show many
details. An example is the ground floor plan of the Pavilion which is at a scale of 1:100. Smaller
scales are used when details of specific sections are needed – this would include information
such as structural joints and materials. Most of these details in the Pavilion drawing set are at a
scale of 1:5.
Construction Documentation Tour Questionnaire
TITLE BLOCK
List the types of information found in the title block on the floor plan page
- Consultants contact details e.g. structural and civil engineers, electrical engineers,
landscape architects
- Client name
- Project name
- Drawing title
- Drawing number
- Compass
- Construction issue
Why might this information be important?
Structural and civil engineers are critical for the construction of the building which is why the
contact details are required. The drawing title as well as the drawing number is needed to
categorize information. The drawing number also links to other sections of drawings. The
construction issue indicates that this section of the building is ready for construction.
DRAWING CONTENT – PLANS
What type of information is shown in this floor plan?
The floor plan shows an overview of the structure and includes general information such as
where the different rooms are located, where the stairs are, where the windows and doors are
placed in each room, what the different types of walls are and what materials are used in the
different sections of the building.
64
Provide an example of the dimensions as they appear on this floor plan. What units are
used for the dimensions?
Figure 65: Dimensions shown as distances between grids (Cox Architecture, 2014)
The distances between the grids are represented in
millimetres.
Is there a grid? What system is used for identifying the grid lines?
Yes, there is a grid. The horizontal lines are labelled alphabetically and the vertical lines are
labelled numerically. The gridlines are also dashed.
Figure 66: Grid in plan (Cox Architecture, 2014)
65
What is the purpose of the legend?
The legend symbolizes or abbreviates features of the ground floor plan. For example, ‘carpeted
tiles’ are represented by the abbreviation ‘FL-01’, and it is this abbreviation that is shown in the
plan. This ensures that the floor plan is neat and not cluttered with labels.
Figure 67: Abbreviation used in plan (Cox Architecture, 2014)
Why are some parts of the drawing annotated? Illustrate how the annotations are
associated with the relevant part of the drawing.
Annotations are used to indicate:
Structures that already exist on the site and are supposed to remain there
Figure 68: Structures that are not to be removed (Cox Architecture, 2014)
Features around the building that will be constructed newly
Abbreviation
for ‘carpeted
tiles'
66
Figure 69: Newer features surrounding the Pavilion (Cox Architecture, 2014)
Illustrate how references to other drawings are shown on the plan. What do these symbols
mean?
Figure 70: References to other drawings (Cox Architecture, 2014)
The number at the bottom indicates the page where the drawing will be found and the
number on top indicates the drawing number.
How are windows and doors identified? Provide an example of each. Is there a rationale to their
numbering? What do these numbers mean? Can you find the answer somewhere in the drawings?
Windows and doors are identified through symbols that are shown below.
Figure 71: Symbols for windows and doors (Cox Architecture, 2014)
The number at the top shows the window or door number of the particular room, and the bottom number
shows the room that the window or door belongs too. These numbers also give a reference to the window
or door schedule, which provides detailed information of how the windows or doors are to be constructed.
Symbol for
window Symbol for door
67
The windows are labelled clockwise and doors are labelled anticlockwise.
Figure 72: Labeling of windows and doors in plan (Cox Architecture, 2014)
Illustrate how floor levels are noted on the plan
Figure 73: Representation of floor levels (Cox Architecture, 2014)
FFL stands for
finished floor level
which is shown in
meters above datum
68
Are some areas of the drawing clouded? Why?
Yes. Some areas of the drawing have been clouded, which means that information has been
revised or changed from a previous drawing.
DRAWING CONTENT – ELEVATIONS
What type of information is shown in this elevation? How does it differ from the
information shown on the plan?
The elevation shows the height of the building, as well as the types of materials and finishes. The
plan shows the general information of the Pavilion from an aerial view whereas the elevations
show specific information of the outside of the building in different areas of the Pavilion.
Are dimensions shown? If so, how do they differ from the dimensions shown on the plan?
Provide an example of the dimensions as they relate to the elevation.
Yes, dimensions are shown, which indicates the height of the parapet. This differs from the
dimensions shown on the plan which showed the distances between the grids.
Figure 74: Parapet dimension in South Elevation (Cox Architecture, 2014)
What types of levels are shown on the elevations? Illustrate how levels are shown in
relation to the elevation.
The levels shown are the finished floor level in meters above datum and the spot level – reduced
level in meters above datum, which are indicated in relation to the existing pavilion, the ground
floor and the function parapet.
69
Figure 75: Levels in South Elevation (Cox Architecture, 2014)
Is there a grid? If so, how/where is it shown?
The grid in the elevations is in the form of vertical lines only, as it is in relation to the floor plan
drawings.
Figure 76: Grids in South Elevation (Cox Architecture, 2014)
What types of information on the elevations are expressed using words? Illustrate how this
is done.
Specific details of features of the building are illustrated using words, such as the existing
structures that are to remain, information about new elements that are added to the existing
building.
70
Figure 77: Existing structures to remain in South Elevation (Cox Architecture, 2014)
Figure 78: New structures in South Elevation (Cox Architecture, 2014)
NEW DOUBLE
GLAZED
DOORS TO
MATCH
EXISTING
NEW TIMBER
COLUMNS AND
STRUCTURE
TO EXISTING
VERANDAH
71
Illustrate how doors and windows are identified on the elevations
Doors and windows are labelled with the same symbol shown in the plan. Doors are labelled from left to
right and windows are labelled from right to left.
Figure 79: Windows in South Elevation (Cox Architecture, 2014)
Figure 80: Doors in South Elevation (Cox Architecture, 2014)
Windows labeled from right to left
Doors labeled from
right to left
72
Find where this elevation is located on the plans
The elevations are located at the points shown below, where A is the South Elevation, B is the
North Elevation, C is the East Elevation and D is the West Elevation.
Figure 81: Location of elevations (Cox Architecture, 2014)
73
DRAWING CONTENT – SECTIONS
What type of information is shown in this section? How does it differ from the information
shown in the plan and elevation?
The sections show details of the foundation system of areas in the building as well as the cross
section of different rooms in the building, which the plans and the elevations do not show.
Illustrate how the section drawing differentiates between building elements that are cut
through and those that are shown in elevation.
The elements that are cut through have been backlined and the elements that are shown in
elevation are shown in thin lines.
Figure 82: Elements that are cut through and elements that are in elevation in Section 1 (Cox Architecture, 2014)
This element has been drawn with
thicker lines, indicating that it has
been cut through
This element has been drawn in thin
lines, indicating that it is in elevation
74
Provide examples of how different materials are shown on the sections.
The materials in the sections are not annotated, but are shown with enough detail to be identified.
Figure 83: Materials in the sections (Cox Architecture, 2014)
Find where this section is located on the plan
Brick walls, indicated by the blocks
laid with a stretcher course Foundation made
with concrete
Sections are represented on the ground
floor plan with the symbols shown in
this diagram. The number on top
indicates the section number and the
number at the bottom indicates the
drawing number where these sections
are found
75
DRAWING CONTENT – DETAILS
What sorts of things are detailed?
The walls, internal elements and finishes, the building, the canopy, the plan, the joineries, the stairs and
the external seating are detailed.
Are the details compressed using break lines? Why?
Yes. The details are drawn at a much larger scale, so certain features need to be shortened in order to fit
into the page.
Provide examples of how different materials are shown on drawings at this scale.
At this scale, the drawings provided more detailed descriptions of the materials in different areas of the
pavilion. Most materials were labelled with a reference that could be checked in the Technical Reference
Sheet that could be found at the back of the drawing set. The examples shown below are from the Link
Detail on drawing 46-01 from Cox Architecture (2014).
Figure 84: Material in Link Detail Figure 85: Material in Link Detail
Figure 86: Material in the Link Detail Figure 87: Material in the Link Detail
TIM-10: Internal timber batten screen CLG-06: Timber ceiling lining
INS-09: Thermal insulation RFS-01: Metal deck roof
76
Find the locations of these details on the plans, elevations and sections.
Figure 88: Canopy detail section on ground floor plans (Cox Architecture, 2014)
Figure 89: Canopy detail section on North Elevation (Cox Architecture, 2014)
INS-09: Thermal insulation
77
Figure 90: North Function Wall Detail in Section (Cox Architecture, 2014)
78
Answers to Part 3
How does the information in your drawing compare to what you saw on site last week?
We were not able to observe the Oval Pavilion within a close range last week. The photos were also taken
behind a fence, which impairs the view of the Pavilion under construction.
Figure 91: Pavilion under construction
I was able to locate this area of the building in the drawing set, which was the West Elevation of the
Pavilion. In terms of differences, the information in the drawing set gave the height of the section
observed as well as the materials used to build this part of the building, which could not be identified by
merely observing the building.
Figure 92: Structure with information from drawing set (Cox Architecture, 2014)
External timber lining External timber
lining
Galvanized roof
sheet
Repair existing roof
turret
Gutters to
existing
roof
Similar in terms of appearance to
drawing, but does not provide
information about materials or height
– materials cannot be identified at
distance we were at
79
How does the scale of the building compare to the scale of the drawings?
As stated before, the drawings have to be scaled down as the actual dimensions of the building cannot be
represented in a drawing. The second part of the building viewed was the North Elevation, which can be
seen entirely in the scaled 1:100 drawing. On site, it was just the brick wall that could be seen.
Figure 93: Brick wall of North Elevation
Figure 94: Drawing of part of North Elevation (Cox Architecture, 2014)
Due to larger scale of brick wall, more
details such as an expansion joint and
weep holes can be seen, which the
drawing does not show
Features seen in actual building cannot
be seen in drawing of elevation due to
difference in scale
80
How do architectural and structural drawings differ?
Architectural drawings show details in terms of aesthetics and structural drawings show how
individual elements are linked together. This is illustrated using the canopy as an example.
Figure 95: Architectural drawing of canopy (Cox Architecture, 2014)
Figure 96: Structural drawing (Wood & Grieve Engineers )
Indicates finishes on the
structural steel
Information
about materials
is provided
Shows exactly how all the
members in the truss beams are
linked together – no information
about materials or finishes
81
Week 5 – Columns, Grids and Wall Systems
Knowledge Maps
Structural Concepts Figure 97: Columns (Newton, 2014)
Figure 98: Frames (Ching, 2008)
82
Construction Systems Figure 99: Walls, Grids and Columns (Ching, 2008) (Newton, 2014)
83
Materials Figure 100: From wood to timber (Newton, 2014)
84
Figure 101: Engineered Timber Products (Newton, 2014)
85
Figure 102: Properties of timber (Newton, 2014)
86
Case Study in E Learnings Figure 103: Gehry's Own Home (Lewi, 2014)
87
Theatre Session
88
Studio Report In this studio session, we were divided into groups and had to build a 1:20 model of a section of
the Oval Pavilion.
Actual structure
The structure was the canopy located in the south of the Pavilion. It comprises of truss beams
and columns, which support the metal roof sheeting that is placed on top of it.
Figure 104: Canopy structural system (Wood & Grieve Engineers )
Identifying structural elements
As seen in the diagram above, the main structural elements are a truss beam and columns. The
truss beams bear the load of the metal roof structure that is laid on top and transfers these to the
columns. The columns then transfer the loads to the ground. A truss beam was used as it will
provide multiple load paths.
Figure 105: Load path diagram (Wood & Grieve Engineers )
Truss beam which
bears load of roof
structure
Columns transfer the loads from
the truss beam to the ground
Column transfers load
from a wide area to a
smaller point
89
Materials
The truss system is constructed with steel and has external timber panels and plywood cladding.
Steel was used for the main structural system as it is good in both compression and tension,
which is needed in a beam. It is also used for columns because it is good in compression.
Figure 106: Part of canopy detail section (Cox Architecture, 2014)
Figure 107: Part of canopy detail section (Cox Architecture, 2014)
External plywood
cladding
External timber panels
Structural
joint 1
Metal roof sheeting
External plywood
cladding
Structural
joint 2
Structural joint 3
Metal roof sheeting
Steel structural
system
90
Figure 108: Part of canopy detail section (Cox Architecture, 2014)
Structural joints
The joints that were used to connect the members to each other and to the ground were all fixed
joints, which were needed to prevent rotation and translation of the structural members, which
would have resulted in lateral instability.
Figure 109: Structural joint 1 (Cox Architecture, 2014)
(Cox
Architecture,
2014)
Structural
joint 4
External plywood cladding
Metal roof
decking
Metal roof decking
[Type a quote from the document
or the summary of an interesting
point. You can position the text
box anywhere in the document.
Use the Drawing Tools tab to
change the formatting of the pull
quote text box.]
End cap to match metal roof
decking
Steel angle to edge of
cladding
[Type a quote from the document
or the summary of an interesting
point. You can position the text
box anywhere in the document.
Use the Drawing Tools tab to
change the formatting of the pull
quote text box.]
External timber
panel
91
Figure 110: Structural joint 2 (Cox Architecture, 2014)
Figure 111: Structural joint 3 (Cox Architecture, 2014)
Figure 112: Structural joint 4 (Cox Architecture, 2014)
External plywood
cladding
Brass ceiling trim to mitre joint
External timber
panel
Steel base angle fixed to concrete
slab, paint to expose structural steel
Brass ceiling trim to mitre joint
External timber
panel
92
Materials used in model
As our section comprised of trusses, and columns, we decided to use 1.5mm sheets of balsa
wood cut into strips that were 2.5mm in width as they would facilitate the process of making
these structures.
Process
We started by assembling the individual trusses first, which were found on the structural drawing
number S04.01. As the drawings were on a scale of 1:100 on A1 paper, they were multiplied by
10 in order to get dimensions that would be at a scale of 1:20.
Figure 113: Truss CT2
Figure 114: Truss CT6
Balsa wood members have been
connected using UHU glue to form
fixed joints that do not undergo
rotation or translation
Signs of failure can be observed –
members started to snap as they
were too thin, and had to be fixed
93
Figure 115: Truss CT5
The individual trusses were then put together as shown in the structural drawing S03.02 which
indicated how they were all supposed to be put together. They were joined together with UHU
glue, which formed fixed joints.
Figure 116: Joining truss CT8 and CT9
Column at the end of the truss was
too thin – had to be removed later
Truss CT8
Truss CT9
Beam that connects
the two trusses
Column which transfers loads to
the ground
94
Figure 117: Part of roof structure
Figure 118: Completed roof structure
Although we managed to finish the roof structure, we were unable to turn it over as the structure
could not stand without support, as the thin members were not strong enough to bear the load of
the entire structure. They represented long columns which buckled due to a compression force
that was too large compared to their cross section.
Roof structure with
most of the trusses
Member sizes of columns were
very thin, made it difficult for
structure to stand without support
95
Comparison with other models
Figure 119: Model of another roof system
The other roof system constructed was more stable than our model due to the thicker columns,
which meant that they were able to bear the load of the truss beam. Therefore, the whole
structural system was able to stand without support. The members were also fixed together with
masking tape whereas ours were fixed with glue.
Figure 120: Model of enclosure system
The main structural elements in this model are columns, panels and slabs as this forms an
enclosure system. As there were no thin members in this system, materials like rigifoam and box
board were used, and materials like balsa wood strips were not needed.
Fixed joints between
members with masking tape [Type a quote from the document
or the summary of an interesting
point. You can position the text
box anywhere in the document.
Use the Drawing Tools tab to
change the formatting of the pull
quote text box.]
Thicker members
compared to our
model
Box board and rigifoam used to
form enclosure system
96
Week 6 – Spanning and Enclosing Space
Knowledge Maps
Structural concepts
Figure 121: Trusses (Ching, 2008)
97
Figure 122: Plates and grids (Ching, 2008)
98
Construction systems
Figure 123: Roof types (Newton, 2014) (Ching, 2008)
99
Figure 124: Types of roofs (materials) (Ching, 2008) (Newton, 2014)
100
Materials Figure 125: Introduction to metals (Newton, 2014)
101
Figure 126: Properties of metals (Newton, 2014)
102
Figure 127: Ferrous metals (Newton, 2014)
Figure 128: Uses of non-ferrous metals (Newton, W06_m3 Non ferrous Metals, 2014)
103
Case study in E Learnings Figure 129: Spanning Spaces (Lewis, 2014)
104
Theatre Session
Figure 130: Concepts of successful development
105
Studio Report
Knowledge Maps of Site Visit Presentations Figure 131: Yarraville Site
106
Figure 132: North Melbourne Site
107
Week 7 – Detailing Strategies 1
Knowledge maps
Structural concepts
Figure 133: Arches, Domes and Shells (Ching, 2008)
108
Construction systems
Figure 134: Detailing for moisture (Newton, 2014)(Ching, 2008)
109
Figure 135: Detailing for heat (Ching, 2008) (Newton, 2014)
110
Materials
Figure 136: Rubber (Newton, 2014)
111
Figure 137: Properties of rubber (Newton, 2014)
112
Figure 138: Plastics (Newton, 2014)
113
Figure 139: Properties of plastic (Newton, 2014)
114
Figure 140: Paints (Newton, 2014)
Figure 141: Properties of paint (Newton, 2014)
115
Week 8 - Openings
Knowledge Maps
Structural concepts
Figure 142: Geometry and moment of inertia (Ching, 2008)
Figure 143: Deformation (Ching, 2008)
116
Construction Systems
Figure 144: Door elements (Ching, 2008)
117
Figure 145: Door types (Ching, 2008)
118
Figure 146: Door types (materials) (Newton, 2014)
119
Figure 147: Window elements (Ching, 2008)
120
Figure 148: Window types (Ching, 2008)
121
Figure 149: Window types (materials) (Ching, 2008)
122
Figure 150: Glazed curtain walls (Ching, 2008)
123
Materials
Figure 151: Glass components (Newton, 2014)
124
Figure 152: Properties of glass (Newton, 2014)
125
Figure 153: Glass types and manufacturing (Newton, 2014)
126
Figure 154: Other types of glass and products (Newton, 2014)
127
Case Study from E Learnings Figure 155: Glass skins (Sadar, 2014)
128
Studio Report The class was given various areas of the Oval Pavilion to draw at a 1:1 scale on A1 paper. I was assigned
drawing 7 which was a section of a service area in the façade details of the Oval Pavilion. As it is located
in close proximity to the wet area, it functions as a drainage system allowing the exit of moisture through
a cavity flashing. The water then leaves through the weep hole in the brick face.
As this was a section of the building, it could not be completely observed from the outside of the Pavilion.
The only visible element of the drawing was the brick face, shown in figure 156, which is why many
photos were not taken.
Figure 156: Brick face of section
Figure 157: Section of service area
Face brickwork
Weep holes
Gap between
brick wall and
ground where
structural steel
angle is
129
This service section is located in the North Function wall. The location of the wet area in relation to the
service section can be seen in Figure 158 and 159.
Figure 158: Part of the north Function Wall (Cox Architecture, 2014)
130
Figure 159: Service section represented in the north function wall on section 2 of Pavilion (Cox Architecture, 2014)
131
An annotated copy of the diagram is shown in Figure 160.
Figure 160: Annotated diagram of section
Face blockwork
(concrete)
Face brickwork
Vapour barrier
Weep holes as required
Cavity flashing
Paint to expose
structural steel to
shelf angle
As this section is located within close proximity to a wet area, the vapour barrier, or the vapour diffusion retarder
was introduced to regulate moisture flow at the molecular level. This moisture control function happens wherever
the VDR is used in the structure. Unlike an air infiltration barrier, the VDR does not have to be continuous,
sealed, or free of holes; a perforation in a VDR simply allows more vapor diffusion in that area compared with
other areas where vapor diffusion is less restrictive (EcoBuilding Pulse, 2009), which explains why the barrier is
indicated using dashed lines.
132
Week 9 – Detailing Strategies 2
Knowledge Maps
Structural concepts
Figure 161: Stress and Structural Members (Ching, 2008)
Figure 162: Structural joints (Ching, 2008)
133
Figure 163: Movement joints (Ching, 2008)
134
Construction systems
Figure 164: Construction detailing (Newton, 2014) (Ching, 2008)
135
Materials Figure 165: Comparing monolithic and composite materials (Newton, 2014)
136
Figure 166: Composite materials (Newton, 2014)
Figure 167: Fibre Glass (Newton, 2014)
137
Figure 168: Aluminium sheet composites (Newton, 2014)
Figure 169: Timber composites (Newton, 2014)
138
Figure 170: Fibre reinforced polymers (Newton, 2014)
139
Figure 171: Finish work
140
Studio Report The site visited was the Watersun site at the corner of Queensbury Street and Dryburgh Street in North
Melbourne. The site consisted of apartments and townhouses which were situated in various areas of the
building.
Location 1 – Basement
The basement of the building was to be used as a car park. The whole area was constructed using
concrete, as it is a load bearing material, and is needed to withstand the loads of the building along with
the loads of the cars that will be parked there.
Retaining walls
As these walls need to withstand ground pressure which acts upon it, they were made of concrete blocks
that were corefilled and reinforced with steel. As concrete is strong in compression but weak in tension,
adding steel in the form of a mesh or bars, which is strong in tension, will improve the structural
performance of concrete (Newton, 2014). This forms a composite material.
Figure 172: Concrete retaining wall
As this section of the building is underground, waterproofing is required to prevent efflorescence taking
place, which will deteriorate the aesthetic quality and structural performance of the concrete. All external
walls are therefore waterproofed using corrugated drip systems.
Concrete retaining wall –
core filled blockwork with
steel reinforcement
141
Columns
Concrete columns were used in the basement to support the loads from the rest of the building. These
columns were cast in situ, where the formwork and reinforcement was first assembled and the concrete
was poured from the top. Concrete was chosen as a material for columns because it is good in
compression. Reinforcement was added to improve the structural performance of concrete, in the same
manner as the blockwork.
Figure 173: Concrete columns Figure 174: Column formwork
Once the concrete is poured, it is then vibrated (generally using poker vibrators) to remove air
bubbles. The formwork may usually be removed the day after the concrete is cast, taking care not
to damage the surface and corners of the concrete (The Concrete Society, n.d.)
In situ load bearing
concrete columns Reinforcement – steel
bars which project
from the ground
Yokes – clamping devices for keeping
column forms and the tops of wall
forms from spreading under the fluid
pressure of concrete
Concrete is poured
from the top
142
Figure 175: Load path diagram of concrete columns
Ceiling
The concrete ceiling was also cast on site, where concrete was poured into formwork sheets, which are
indicated by the lines on the ceiling shown below. As the electrical work was done in the formwork, it
needs to be completed before the concrete is poured.
Figure 176: In situ concrete ceiling
In situ concrete ceiling,
where lines indicate
placement of formwork
Loads from the
building are
transferred to the
foundations
through concrete
columns
143
Service systems
The service systems that are found in the basement are pipes for stormwater drainage, gas and fire service
systems. Sprinklers are included in this category. Suspended cable trays are included to support cables.
Figure 177: Cable trays
Suspended cable tray used to support
cables
144
Location 2 – Roof
Roof details
The second location in the building was the roof, which was a flat roof made out of reinforced concrete.
As it is a flat roof, it requires a continuous membrane roofing material, which was done through two
layers of waterproof coating and a layer of screed. The roof also consisted of an upturned edge beam to
form a parapet wall.
Figure 178: Concrete roof with parapet wall
The roof is also made from in situ concrete, where the formwork has been laid in place and the concrete is
poured using a bubble crane. The bubble crane also assembled the precast concrete panels that formed the
exterior walls of the building. The panels were precast because casting panels in situ will be difficult and
time consuming. As the panels below the concrete slab that forms the roof are load bearing, as will be
discussed later, they will be connected to the roof as shown below.
Figure 179: Connection between slab and bearing panel (Ching, 2008)
Parapet wall
formed by
upturned edge
beam
High density plastic bearing strip
Steel dowel to
connect slab to
panel Parapet wall
Connection is a fixed
joint – maintains
angular relationship
between joined
elements and restricts
rotation and translation
(Ching, 2008), which is
what is needed when
connecting a slab and a
panel.
145
Lightwells
In order to allow natural light into the building, lightwells are constructed on the roof, where the light is
used reaches the apartments and townhouses. This method is beneficial as it reduces the need for
electrical lighting.
Figure 180: Lightwells
Figure 181: Section of lightwell through the building
Lightwell to allow
natural light into
building
Apartments Apartments
Townhouses Townhouses
Section of one lightwell
through building – provides
natural light for all floors
Exterior concrete panels
146
Water escape from the roof
In order to allow water to leave the roof, a downpipe was fitted in the slit shown in the parapet wall below
and sealed in place with concrete. Therefore, the roof will be slightly sloped in order to facilitate the
movement of water towards this pipe.
Figure 182: Section showing downpipe
Figure 183: Section showing flow of water to downpipe
Downpipe which has
been sealed in place
with concrete
Roof slab will be at
a slight angle to
allow movement of
water towards the
downpipe
Downpipe which carries
water away from roof –
prevents penetration into
building
147
Considerations (control joints)
The parapet wall in the roof also had small slits in them, which may be possible areas for control joints to
accommodate the shrinking of concrete. These slits may be fitted with corking and a backrod which will
compress due to shrinkage.
Figure 184: Grooves in parapet wall
Figure 185: Control joint (Ching, 2008) Figure 186: Control joint once expanded (Ching,2008)
Grooves in parapet wall
for control joints
Control joint as installed
Control joint expands due to shrinking
of concrete
148
Location 3 – Apartment section
Walls
The walls in the apartment areas consist of a metal studwork framing system that comprises of
lightweight steel columns. They are used in both exterior loadbearing curtain walls and in nonloadbearing
partition walls within the building (Ching, 2008). The exterior walls transfer the loads of the roof to the
foundations and the steel frame
The steel studs are made from lightweight channel studs.
Figure 187: Channel studs (Ching, 2008)
Figure 103: Metal studwork
Metal studwork in a
partition wall – to be
plastered
Metal studwork in
external load bearing wall
– needed as a frame for
the plaster
Light gauge steel studs are
prepunched to allow piping,
wiring and bracing to pass
through
149
Precast concrete panels and in-situ ceiling
As mentioned before, the panels which formed the exterior walls were pre-cast and lifted into place using
a bubble crane. In Figure 105, the individual panels can be seen in the apartment section. These panels
will be load bearing, and may have metal studwork assembled later to facilitate plastering.
Figure 188: Precast concrete panels
As mentioned before, the roof was formed from in-situ concrete which was poured using a bubble crane.
The evidence of formwork can be seen in the image below.
Figure 189: Formwork for in-situ roof/ceiling
Individual concrete panels
Formwork for the ceiling made
evident through the lines visible in the
concrete slab
150
Connections
Figure 190: Connections between steel members (Ching, 2008)
Figure 191: Connection between member and wall
In both instances, they will be fixed joints as rotation and translation of the two elements will need to be
restricted in order to ensure structural stability.
Steel members
(channel studs)
The steel columns are connected to the foundation with an angle
clip which welded to the stud and then bolted to the foundation
In this image, the metal clip appears to
have been bolted into the concrete
wall and then connected to the steel
column
151
Location 4 – Townhouse section
There are two townhouse levels that are connected by a set of stairs for which the formwork is shown
below. This was constructed using timber.
Figure 192: Timber formwork for stairs
Figure 193: Metal stud framing in apartment
Timber formwork for stairs
leading to upper level
townhouse
As seen with the apartments, the concrete walls are loadbearing with a metal stud frame which will then be
plastered over.
Metal stud framing. As with the stud
framing before, there are holes within
the columns for services
152
Week 10 – When things go wrong
Knowledge Maps
Structural concepts Figure 194: Lateral supports (Newton, 2014)
153
Figure 195: Dynamic loads (Ching, 2008)
154
Construction systems Figure 196: Collapses and failures (Ashford, 2014)
155
Materials Figure 197: Heroes and Culprits (Hes, 2014)
156
Figure 198: Building Materials (Ching, 2008)
157
Figure 199: Building Materials (Ching, 2008)
158
Figure 200: The Statue of Liberty - A tale of corrosion (Cameron, 2014)
159
Studio Report For this studio session, we went to the Oval Pavilion and examined our detail and used it to form
the 3D drawings of the detail, which linked the 2D drawing with what was seen on site. The only
elements that were visible were the brick face, the weep holes and the structural steel.
Figure 201: Section on site
Figure 202: Close-up of detail
Brick face
visible
Weep holes to allow
moisture to leave
Gap between brick and
ground as indicated in the
section drawing. Structural
steel visible inside the gap.
160
Detailing decisions and purpose
The service area is in close proximity to a wet area, so the detailing decisions reflect the
waterproofing needed. There is a gap between the concrete wall and the visible brick face within
which there is a cavity flashing, which is put there to allow water from the wet area to leave
through gravity through the weephole.
Figure 203: Detailing decisions (Cox Architecture, 2014)
According to the detail drawings, the steel angle is connected to the flashing. The steel has been
painted instead of galvanized, which may have been done to save costs. The vapour barrier has
been placed on top of the concrete to control the entry of moisture into the structure.
161
Waterproofing elements
The main waterproofing elements in this section are a vapour barrier, a cavity flashing and weep
holes. As mentioned in the studio report of Week 8, the vapour barrier is used to prevent the
entry of moisture, the cavity flashing removes moisture through gravity, which exits through the
weep holes.
Why and where things go wrong
As the structure is located in a wet area, the brick will absorb a lot of moisture. Due to this, the
steel below the cavity flashing has begun to show signs of corrosion as it is extremely close to
the moisture containing bricks. The steel will also absorb moisture from the surrounding soil
Figure 204: Corrosion in structural steel
Economic implications
If the steel continues to corrode, it will have to be replaced which will be an expensive task. If
steel is to be placed next to bricks or in contact with the ground, it needs to be galvanized to
prevent corrosion. Other ways of preventing the steel from corroding is to have it at a higher
height above the ground so that it is in less contact with moisture.
Steel showing signs of corrosion
162
Glossary of Terms Week 1
Beam – rigid structural members designed to carry and transfer transverse loads across space to
supporting elements. The noncurrent pattern of forces subjects a beam to compression and
tension, which must be resisted by the internal strength of the material (Ching, 2008)
Compression forces – an external load pushing on a structural member, resulting on the
shortening of the material (Newton, 2014)
Load path – the route a load takes through a structural system to reach the ground (Ching, 2008)
Masonry – building with units of various natural or manufactured products, usually with the use
of mortar as a bonding agent (Ching, 2008)
Point load– A concentrated load in a specific position on a structural member (WebFinance Inc,
2014)
Reaction force – equal and opposite forces that resist an applied force (Ching, 2008)
Week 2
Brace - A diagonal tie that interconnects scaffold members (WebFinance Inc, 2014)
Columns – rigid, relatively slender structural members designed primarily to support axial
compressive loads applied to the ends of the members (Ching, 2008)
Frame – an assembly of vertical and horizontal structural members (WebFinance Inc, 2014)
Stability – the measure of the ability of a structure to withstand overturning, sliding, buckling or
collapsing (WebFinance Inc, 2014)
Structural joints – connectors used to joint structural elements (Ching, 2008)
Tension - external load pulling on a structural member, causing the material to elongate
(Newton, 2014)
163
Week 3
Moment - tendency of a force to produce rotation of a body about a point or line, equal in
magnitude to the product of the force and the moment arm and acting in a clockwise or
anticlockwise direction (Ching, 2008)
Figure 205: Moment (Ching, 2008)
Retaining wall – structure used to sustain the pressure of the earth behind it (WebFinance Inc,
2014)
Figure 206: Retaining wall (Ching, 2008)
164
Pad footings – individual spread footings supporting freestanding columns and piers (Ching,
2008)
Figure 207: Pad footing (Ching, 2008)
Slab on ground – a concrete slab supported directly by the earth and thickened to carry wall and
column loads from an economical foundation and floor system (Ching, 2008)
Figure 208: Slab on ground (Ching, 2008)
165
Strip footings – continuous spread footings of foundation walls (Ching, 2008)
Figure 209: Strip footing (Ching, 2008)
Substructure – lowest division of the building constructed partially or wholly below the ground.
Primary function is to support and anchor the superstructure above and transmit its loads to the
earth. (Ching, 2008)
Figure 210: Substructure (Ching, 2008)
Week 4
Concrete plank - A hollow-core or solid, flat beam used for floor or roof decking. Concrete
planks are usually precast and pre-stressed (WebFinance Inc, 2014)
166
Girder - A large principal beam of steel, reinforced concrete, timber, or a combination of these,
used to support other structural members at isolated points along its length (WebFinance Inc,
2014).
Figure 211: Girder (Ching, 2008)
Joist - Parallel beams of timber concrete, or steel used to support floor and ceiling systems
(WebFinance Inc, 2014)
Figure 212: Joist (WebFinance Inc, 2014)
167
Spacing – repeating distance between a series of like or similar elements (Newton, 2014)
Figure 213: Spacing (Newton, 2014)
Span – distance measured between two structural supports (Newton, 2014)
Figure 214: Span (Newton, 2014)
Steel decking – corrugated to increase its stiffness and spanning capability. Decking serves as a
working platform during construction and as formwork for an in situ concrete slab (WebFinance
Inc, 2014).
Figure 215: Steel decking (WebFinance Inc, 2014)
168
Week 5
Axial load - The longitudinal force acting on a structural member (WebFinance Inc, 2014).
Figure 216: Axial load (Ching, 2008)
Buckling – the sudden lateral or torsional inability of a slender structural member induced by the
action of an axial load before the yield stress of the material is reached
Figure 217: Buckling (Ching, 2008)
169
Lintel - A horizontal supporting member, installed above an opening such as a window or
a door, that serves to support the load of the wall above it (WebFinance Inc, 2014).
Figure 218: Lintel (WebFinance Inc, 2014)
Noggings – Members placed in rows holding together the long thin members in stud framing
together in order to prevent them from buckling (Newton, 2014)
Figure 219: Noggings (Ching, 2008)
Seasoned timber - Timber that is not green, having a moisture content of 19% or less, and is air-
or kiln-dried.
170
Stud - A framing member, designed to be used in framing walls. Studs are most often 2" x 4",
but 2" x 3", 2" x 6" and other sizes are also included in the stud category. Studs may be of
timber, steel, or composite material (WebFinance Inc, 2014).
Figure 220: Stud (Ching, 2008)
Week 6
Alloy – a mixture of two or more metals (Newton, 2014)
Cantilever – created when a structural member is supported only at one end. The function of a
cantilever is to carry loads along the length of a member and transfer these loads to the support
(Newton, 2014)
Figure 221: Cantilever (Ching, 2008)
171
Eave - the portions of a roof that project beyond the exterior walls of a building (WebFinance
Inc, 2014)
Figure 222: Eave (WebFinance Inc, 2014)
Portal frame – a series of braced rigid frames with purlins for the roof and girts for the walls.
The walls are usually finished with sheet metal (Newton, 2014)
Figure 223: Portal frame (Ching, 2008)
172
Purlin - One of several horizontal structural members that support roof loads and transfer them
to roof beams
Figure 224: Purlin (WebFinance Inc, 2014)
Rafter – a series of sloping parallel beams used to support a roof covering (WebFinance Inc,
2014)
Figure 225: Rafter (WebFinance Inc, 2014)
Soffit - The underside of a part or member of a structure, such as a beam, stairway, or arch.
(WebFinance Inc, 2014)
Figure 226: Soffit (WebFinance Inc, 2014)
173
Top chord – the upper section of a truss (WebFinance Inc, 2014)
Figure 227: Top chord (Ching, 2008)
Week 7
Drip - A groove in the underside of a projection, such as a windowsill, that prevents water
from running back into the building wall (WebFinance Inc, 2014).
Figure 228: Drip (Ching, 2008)
Down pipe – pipe that takes excess water from a roof to a storm water sewer (Ching, 2008)
174
Flashing – thin continuous piece of material installed to prevent passage of water into a structure
from an angle or joint. The upturned edges and sloping surfaces use gravity to lead water to the
outside
Figure 229: Flashing (WebFinance Inc, 2014)
Gutter - A shallow channel positioned just below and following along the eaves of a building for
the purpose of collecting and diverting water from a roof (WebFinance Inc, 2014).
Figure 230: Gutter (WebFinance Inc, 2014)
Insulation - material used to reduce the effects of heat, cold, or sound (WebFinance Inc, 2014)
Parapet – the part of a wall that extends above roof level (WebFinance Inc, 2014).
Figure 231: Parapet (Ching, 2008)
175
Sealant - an impervious substance used to fill joints or cracks in concrete or mortar, or to
exclude water and solid matter from any joints (WebFinance Inc, 2014).
Figure 232: Sealant (Ching, 2008)
Vapour barrier - material used to prevent the passage of vapor or moisture into a structure or
another material, thus preventing condensation within them (WebFinance Inc, 2014)
Figure 233: Vapour barrier (WebFinance Inc, 2014)
176
Week 8
Deflection – the perpendicular distance a spanning member deviates from a true course under
transverse loading, increasing with load and span, and decreasing with an increase in the moment
of inertia of the section or the elasticity of the material (Ching, 2008)
Figure 234: Deflection (Ching, 2008)
Door Furniture – the parts of the door including the rough opening, head, jamb, stop, door
hardware and architrave (Ching, 2008)
Moment of inertia – the sum of the products of each element of an area and the square of its
distance from a coplanar axis of rotation. It is a geometric property that indicates how the cross
sectional area of a structural member is distributed and does not reflect the intrinsic physical
properties of a material (Ching, 2008)
Shear force - The algebraic sum of all the tangential forces acting on either side of the section at
a particular location in a flexural member (WebFinance Inc, 2014)
Figure 235: Shear force (Ching, 2008)
177
Stress - Intensity of internal force exerted by either of two adjacent parts of a body on the other
across an imagined plane of separation. When the forces are parallel to the plane, the
stress is called shear stress; when the forces are normal to the plane, the stress is called normal
stress; when the normal stress is directed toward the part on which it acts it is called compressive
stress; when it is directed away from the part on which it acts it is called tensile stress
(WebFinance Inc, 2014)
Figure 236: Stress (Ching, 2008)
Window sash – the fixed or movable framework of a window in which panes of glass are set. Its
section profile varies with material, manufacturer and type of operation (Ching, 2008).
Figure 237: Window sash (WebFinance Inc, 2014)
178
Week 9
Composite beam - A beam combining different materials to work as a single unit, such
as structural steel and concrete or cast-in-place and precast concrete (WebFinance Inc, 2014)
Figure 238: Composite beam (WebFinance Inc, 2014)
Cornice - An ornamental molding of wood or plaster that encircles a room just below the ceiling
(WebFinance Inc, 2014)
Figure 239: Cornice (WebFinance Inc, 2014)
Sandwich panel - A panel formed by bonding two thin facings to a thick, and usually
lightweight, core. Typical facing materials include plywood, single veneers, hardboard, plastics,
laminates, and various metals, such as aluminum or stainless steel. Typical core materials include
plastic foam sheets, rubber, and formed honeycombs of paper, metal, or cloth (WebFinance Inc,
2014)
179
Skirting – A corner block where a base and vertical framing meet (WebFinance Inc, 2014)
Figure 240: Skirting
Week 10
Braced Frame - a wooden structural framing system in which all vertical members, except
for corner posts, extend for one floor only. The corner posts are braced to the sill and plates
(WebFinance Inc, 2014)
Figure 241: Braced Frame (Ching, 2008)
Corrosion - The oxidation of a metal or other material by exposure to chemical or
electrochemical action such as rust (WebFinance Inc, 2014)
Defect - Any condition or characteristic that detracts from the appearance, strength, or durability
of an object (WebFinance Inc, 2014)
180
Fascia - A board used on the outside vertical face of a cornice (WebFinance Inc, 2014)
Figure 242: Fascia (WebFinance Inc, 2014)
IEQ - An important criterion for green, or sustainable, building design, this refers to
general overall building occupant comfort. Includes humidity, ventilation and air circulation,
acoustics, and lighting (WebFinance Inc, 2014)
Lifecycle - A term often used to describe the period of time that a building or material can be
expected to actively and adequately serve its intended function (WebFinance Inc, 2014)
Shear wall - A wall portion of a structural frame intended to resist lateral forces, such as
earthquake, wind, and blast, acting in the plane or parallel to the plane of the wall (WebFinance
Inc, 2014)
Figure 243: Shear wall (Ching, 2008)
181
Soft storey – has lateral stiffness or strength significantly less than the stories above. Deflects
considerably under seismic loads and will collapse while other floors remain intact, which leads
to the collapse of the whole building.
Figure 244: Soft storey (Ching, 2008)
.
Soft storey
182
Reference List Ashford, P. (2014). W10_c1 When things go wrong. Retrieved from Learning Management
System - Constructing Environments: http://www.youtube.com/watch?v=yNEl-
fYRi_I&feature=youtu.be
Cameron, R. (2014). W10_m2 A Tale of Corrosion. Retrieved from Learning Management
System - Constructing Environments:
http://www.youtube.com/watch?v=2IqhvAeDjlg&feature=youtu.be
Cement Sustainability Initiative. (2012). Sustainability Benefits of Concrete. Retrieved from
World Business Council for Sustainable Development :
http://www.wbcsdcement.org/index.php/about-cement/benefits-of-concrete
Ching, F. D. (2008). Building Construction Illustrated (4th ed.). Hoboken, New Jersey : John
Wiley & Sons.
Cox Architecture. (2014). Oval Pavilion Construction Drawings.
Design. City. Living. (2012). Lot 6 Cafe and Bar - Melbourne University. Retrieved from
http://www.designcityliving.com/2012/05/lot-6-cafe-and-bar-melbourne-university.html
EcoBuilding Pulse. (2009). Understanding Vapour Barriers. Retrieved from
http://www.ecobuildingpulse.com/building-science/understanding-vapor-barriers.aspx
Hes, D. D. (2014). W10_m1 Heroes and Culprits. Retrieved from Learning Management System
- Constructing Environments: http://www.youtube.com/watch?v=yNEl-
fYRi_I&feature=youtu.be
Hutson, A. (2014). The Pantheon. Retrieved from Learning Management System - Constructing
Environments: http://www.youtube.com/watch?v=9aL6EJaLXFY&feature=youtu.be
Lewi, D. H. (2014). Gehry's Own Home. Retrieved from Learning Management System -
Constructing Environments:
http://www.youtube.com/watch?v=iqn2bYoO8j4&feature=youtu.be
Lewis, D. M. (2014). Spanning Spaces. Retrieved from Learning Management System -
Constructing Environments: http://www.youtube.com/watch?v=Zx4tM-
uSaO8&feature=youtu.be
Lovell Chen Architecture & Heritage Consultants. (2011). Underground Carpark and South
Lawn Conservation Management Plan. Retrieved from
http://www.pcs.unimelb.edu.au/standards_and_policies/docs/master_plans/Underground_
Car_Park_and_South_Lawn_CMP.pdf
183
Lovell Chen Architecture & Heritage Consultants. (2014). Beaurepaire Centre. Retrieved from
http://www.lovellchen.com.au/beaurepaire.aspx
Newton, C. (2014). Beams and Cantilevers. Retrieved from Learning Management System -
Constructing Environments:
https://app.lms.unimelb.edu.au/bbcswebdav/courses/ENVS10003_2014_SM1/WEEK%2
004/BEAMS%20AND%20CANTILEVERS.pdf
Newton, C. (2014). Geometry and Equilibrium. Retrieved from Learning Management System -
Construction Environments:
https://app.lms.unimelb.edu.au/bbcswebdav/courses/ENVS10003_2014_SM1/WEEK%2
003/GEOMETRY%20AND%20EQUILIBRIUM.pdf
Newton, C. (2014). Lateral Supports. Retrieved from Learning Management System -
Constructing Environments:
https://app.lms.unimelb.edu.au/webapps/portal/frameset.jsp?tab_tab_group_id=_5_1&url
=%2Fwebapps%2Fblackboard%2Fexecute%2Flauncher%3Ftype%3DCourse%26id%3D
_271852_1%26url%3D
Newton, C. (2014). Short and Long Columns. Retrieved from Learning Management System -
Constructing Environments:
https://app.lms.unimelb.edu.au/bbcswebdav/courses/ENVS10003_2014_SM1/WEEK%2
005/SHORT%20AND%20LONG%20COLUMNS.pdf
Newton, C. (2014). Span and Spacing. Retrieved from Learning Management System -
Constructing Environments:
https://app.lms.unimelb.edu.au/bbcswebdav/courses/ENVS10003_2014_SM1/WEEK%2
004/SPAN%20AND%20SPACING.pdf
Newton, C. (2014). W03_c1 Footings & Foundations. Retrieved from Learning Management
System - Constructing Environments:
http://www.youtube.com/watch?v=PAcuwrecIz8&feature=youtu.be
Newton, C. (2014). W03_m1 Introduction to Mass Construction. Retrieved from Learning
Management System - Constructing Environments:
http://www.youtube.com/watch?v=8Au2upE9JN8&feature=youtu.be
Newton, C. (2014). W03_m2 Introduction to Masonry. Retrieved from Learning Management
System - Constructing Environments:
http://www.youtube.com/watch?v=DC8Hv8AKQ8A&feature=youtu.be
Newton, C. (2014). W03_m3 Bricks. Retrieved from Learning Management System -
Constructing Environments:
http://www.youtube.com/watch?v=4lYlQhkMYmE&feature=youtu.be
184
Newton, C. (2014). W03_m4 Stone. Retrieved from Learning Management System -
Constructing Environments:
http://www.youtube.com/watch?v=2Vn5_dk4RtQ&feature=youtu.be
Newton, C. (2014). W03_m5 Blocks. Retrieved from Learning Management System -
Constructing Environments:
http://www.youtube.com/watch?v=geJv5wZQtRQ&feature=youtu.be
Newton, C. (2014). W03_s1 Structural Elements. Retrieved from Learning Management System
- Constructing Environments:
http://www.youtube.com/watch?v=wQIa1O6fp98&feature=youtu.be
Newton, C. (2014). W04_c1 Floor and Framing Systems. Retrieved from Learning Management
System - Constructing Environments:
http://www.youtube.com/watch?v=otKffehOWaw&feature=youtu.be
Newton, C. (2014). W04_m1 Concrete. Retrieved from Learning Management System -
Constructing Environments:
http://www.youtube.com/watch?v=c1M19C25MLU&feature=youtu.be
Newton, C. (2014). W04_m2 In Situ Concrete. Retrieved from Learning Management System -
Constructing Environments:
http://www.youtube.com/watch?v=c3zW_TBGjfE&feature=youtu.be
Newton, C. (2014). W05_c1 Walls, Grids and Columns. Retrieved from Learning Management
System - Constructing Environments:
http://www.youtube.com/watch?v=Vq41q6gUIjI&feature=youtu.be
Newton, C. (2014). W05_m1 From wood to timber. Retrieved from Learning Management
System - Constructing Environments :
http://www.youtube.com/watch?v=YJL0vCwM0zg&feature=youtu.be
Newton, C. (2014). W05_m2 Timber Properties and Considerations. Retrieved from Learning
Management System - Constructing Environments:
http://www.youtube.com/watch?v=ul0r9OGkA9c&feature=youtu.be
Newton, C. (2014). W05_m3 Engineered Timber Products. Retrieved from Learning
Management System - Constructing Environments:
http://www.youtube.com/watch?v=0YrYOGSwtVc&feature=youtu.be
Newton, C. (2014). W06_c1 Roof Systems. Retrieved from Learning Management System -
Constructing Environments:
http://www.youtube.com/watch?v=q5ms8vmhs50&feature=youtu.be
185
Newton, C. (2014). W06_m1 Introduction to Metals. Retrieved from Learning Management
System - Constructing Environments:
http://www.youtube.com/watch?v=RttS_wgXGbI&feature=youtu.be
Newton, C. (2014). W06_m2 Ferrous Metals. Retrieved from Learning Management System -
Constructing Environments: http://www.youtube.com/watch?v=SQy3IyJy-
is&feature=youtu.be
Newton, C. (2014). W06_m3 Non ferrous Metals. Retrieved from Learning Management System
- Constructing Environments:
http://www.youtube.com/watch?v=EDtxb7Pgcrw&feature=youtu.be
Newton, C. (2014). W07 m_2 Plastics. Retrieved from Learning Management System -
Constructing Environments:
http://www.youtube.com/watch?v=5pfnCtUOfy4&feature=youtu.be
Newton, C. (2014). W07_c1 Detailing for heat and moisture. Retrieved from Learning
Management System - Constructing Environments:
http://www.youtube.com/watch?v=Lhwm8m5R_Co&feature=youtu.be
Newton, C. (2014). W07_m1 Rubber. Retrieved from Learning Management System -
Constructing Environments:
http://www.youtube.com/watch?v=OPhjDijdf6I&feature=youtu.be
Newton, C. (2014). W07_m3 Paints. Retrieved from Learning Management System -
Constructing Environments:
http://www.youtube.com/watch?v=WrydR4LA5e0&feature=youtu.be
Newton, C. (2014). W08_c1 Openings: Doors and Windows. Retrieved from Learning
Management System - Constructing Environments:
http://www.youtube.com/watch?v=g7QQIue58xY&feature=youtu.be
Newton, C. (2014). W08_m1 Glass. Retrieved from Learning Management System -
Constructing Environments:
http://www.youtube.com/watch?v=g7QQIue58xY&feature=youtu.be
Newton, C. (2014). W09_c1 Construction Detailing. Retrieved from Learning Management
System - Constructing Environments:
http://www.youtube.com/watch?v=yqVwAV7yJCI&feature=youtu.be
Newton, C. (2014). W09_m1 Composite Materials. Retrieved from Learning Management
System - Constructing Environments:
http://www.youtube.com/watch?v=Uem1_fBpjVQ&feature=youtu.be
186
Sadar, D. J. (2014). Glass Skins. Retrieved from Learning Management System - Constructing
Environments: http://www.youtube.com/watch?v=NW_GibnyBZc&feature=youtu.be
The Concrete Society. (n.d.). In Situ Columns. Retrieved from Concrete.org.uk:
http://www.concrete.org.uk/fingertips_nuggets.asp?cmd=display&id=353
The University of Melbourne. (2012). Parkville Campus. Retrieved from Maps:
http://maps.unimelb.edu.au/parkville
TimberDesignAwards. (2010). Frank Tate Pavilion. Retrieved from
http://www.timberawards.com.au/frank-tate-pavilion
WebFinance Inc. (2014). Dictionary of Construction.com. Retrieved March 15, 2014, from
http://www.dictionaryofconstruction.com/
Wood & Grieve Engineers . (n.d.). Oval Pavilion Construction Drawings.
187
Appendix
Construction Workshop
At the construction workshop, we were divided into groups and told to construct a structure that
spans 1000mm.
Materials and tools used
2 boards of plywood 42m x 19mm x 2.4m
2 boards of pine 1200 x 42 x 18
Hammer
Screws
Nails
Saw
Drill
Below is a diagram of our idea of what we wanted the structure to look like.
Figure 245: Intended structure
We used the thicker pine for the whole structural system and used the thinner plywood for
bracing so that the structure will be more stable.
188
Building the structure
The pine was cut into two equal lengths to form the two sides of the triangle. We used the second
piece of pine as the base, and then the remaining pieces from the pine to support the base.
Figure 246: Sides of the triangle
Figure 247: Structure
Pieces of pine for the sides of
the triangle. They were cut at
an angle at the bottom to
facilitate attachment to the
base
Thicker pieces of
pine to form side of
triangle
Plywood to form
bracing, which will
cause the load needed to
break the structure to
increase by providing
structural stability
189
Joints
Screws were used to connect the sides of the triangle to the base and to each other, and smaller
nails were used to fix the bracing together.
Figure 248: Joints
Figure 249: Final structure
Fixed together with
screws and a hammer
Fixed together
with nails and a
hammer
Fixed together
with the drill and
screws
Pine for the
two sides of
the triangle
Plywood bracing
Base for the
structure
190
Structural performance and failure mechanisms
Our structure was able to take a maximum load of 240kg before a structural failure occurred. The
maximum deflection of the beam, on which the triangle was mounted, was 20mm. This large
deflection may have occurred because of the way the beam was placed.
Figure 250: Placement of beam
Beams are in this manner, as more surface are receives
the load, which may cause bending. This caused the large
deflection of 20mm
The failure in our structure was the joints, because at 240kg, the screws connecting the two pine
members together got detached. If the screws had been drilled down instead of being hammered,
in, it is possible that that may have resulted in a more stable structure.
If beams were placed in this
manner, less surface are receives
the load, which would have
minimized bending.
191
Analysis of key concepts
Span
All structures had to span 1m. If we had been able to decrease the span, there may have been less
deflection of the beam.
Figure 251: Deflection of beam with increased span Figure 252: Reduced span
Shape and strength
Our structure could have been improved by providing additional bracing using the plywood
boards. Because the load applied was directed right to the top of the triangle, additional bracing
would have helped withstand a larger amount of load and increased the strength of the structure
as a whole.
Figure 253: Shape and strength
Increased deflection with increased
span of beam
Reduced deflection with decreased
span of beam
192
Material efficiency
The fact that our structure was able to withstand 240kg indicates that the materials were efficient
in terms of forming a stable structure. However, if we had connected them properly and used the
remaining plywood to form bracing, the structural performance of the structure may have been
better.
Joints
All the joints in the structure were pinned joints, because the members would still be able to
rotate if they were not connected at two ends. The structure did fail due to the joints, which may
have been improved by making them with the drill instead of the hammer,
Figure 254: Pinned joint
Comparison with other structures
Figure 255: Team 1 structure
High deflection of
beam due to the way it
was placed (similar to
ours)
Beam has
cracked due to
load
Joints have failed in this section
(similarly to ours), indicates
that members were not joined
together properly
193
Figure 256: Team 3 structure
Figure 257: Team 4 structure
Comparison between working with actual construction materials as opposed to scale model making
materials
Examples of construction materials include brick, concrete and steel, and examples of materials
that can be used for scale model making are balsa wood, cardboard, pine and plywood.
Construction materials will have a much higher strength than scale model making materials, and
would need a substantially larger load to destroy structures made compared to model making
materials. However, they are more difficult to work with. Cutting concrete, for example, will be
more difficult than cutting balsa wood. As a result, it takes a longer period of time to build
structures with construction materials than with model making materials.
Joints came apart with increased
load – however, was not the
main cause of structure failing
Shape was
similar to ours
Beam splintered
with increased load -
showed failure of
materials
Beam cracked in the middle with
increasing load – may have been
able to withstand higher loads if
there was support underneath