www.a2gov.org/parks City of Ann Arbor 2013 – 2018 Park Maintenance and Capital Improvements Millage Status: For Fiscal Year 2016 City of Ann Arbor voters approved a six-year park millage in November 2012 that funds current, ongoing improvements to Ann Arbor’s park system, which consists of 159 parks spanning more than 2,104 acres. The table below lists park development, maintenance and improvement projects funded through your support of this millage; the fiscal year (FY) in which the improvement occurred is indicated. Also indicated on this table are park improvements made possible through other funding sources, as specified. If you have questions or comments regarding the projects below, please contact Parks and Recreation Services Manager Colin Smith at 734.794.6000, ext. 42500, or [email protected] . We hope you enjoy all that the Ann Arbor parks system has to offer! www.a2gov.org/parks Location Project Status 77 Playground Sites See Project Status Tables FY2008- 2015 for projects completed in previous years Allmendinger Park 645 Pauline Boulevard See Project Status Tables FY2008- 2015 for projects completed in previous years NAP active volunteer coordination Ongoing Paid for from each FY Tennis and basketball court replacement Design p hase, Project out for bid A nticipating summer 2015 construction Currently under construction Construction Complete Paid for from FY 2016 Millage Arboretum Nature Center Nichols Drive and East Medical Center Drive See Project Status Tables FY2008- 2011 for projects completed in previous years Arbor Hills Nature Area Green Road, between Kilburn Park Circle and Burbank Drive NAP plant and animal inventory Ongoing Paid for from each FY NAP active ecological restoration Ongoing Paid for from each FY Arbor Oaks Park Champagne Drive at Stratton Court See Project Status Tables FY2008- 2015 for projects completed in previous years NAP active volunteer coordination Ongoing Paid for from each FY Argo Nature Area 1055 Longshore Drive See Project Status Tables FY2008- 2015 for projects completed in previous years NAP plant and animal inventory Ongoing Paid for from each FY NAP active volunteer coordination Ongoing Paid for from each FY Native plant revegetation Ongoing Paid for from each FY NAP active ecological restoration Ongoing NAP/Northridge Church workday 07/30/2015. GIVE365 active volunteer coordination. Cleaned up trash near livery and trails. 9/17/2015 Completed Paid for from each FY

Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

www.a2gov.org/parks

City of Ann Arbor 2013 – 2018 Park Maintenance and Capital Improvements Millage Status: For Fiscal Year 2016

City of Ann Arbor voters approved a six-year park millage in November 2012 that funds current, ongoing improvements to Ann Arbor’s park system, which consists of 159 parks spanning more than 2,104 acres. The table below lists park development, maintenance and improvement projects funded through your support of this millage; the fiscal year (FY) in which the improvement occurred is indicated. Also indicated on this table are park improvements made possible through other funding sources, as specified.

If you have questions or comments regarding the projects below, please contact Parks and Recreation Services Manager Colin Smith at 734.794.6000, ext. 42500, or [email protected]. We hope you enjoy all that the Ann Arbor parks system has to offer!

www.a2gov.org/parks

 

Location  Project  Status 77 Playground Sites See Project Status Tables FY2008-

2015 for projects completed in previous years

Allmendinger Park 645 Pauline Boulevard

See Project Status Tables FY2008-2015 for projects completed in

previous years

NAP active volunteer coordination

Ongoing Paid for from each FY

Tennis and basketball court replacement

Design phase, Project out for bid Anticipating summer 2015 construction Currently under construction Construction Complete Paid for from FY 2016 Millage

Arboretum Nature Center Nichols Drive and East Medical Center Drive

See Project Status Tables FY2008-2011 for projects completed in

previous years

Arbor Hills Nature Area Green Road, between Kilburn Park Circle and Burbank Drive

NAP plant and animal inventory Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Arbor Oaks Park Champagne Drive at Stratton Court

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP active volunteer coordination Ongoing Paid for from each FY

Argo Nature Area 1055 Longshore Drive

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP plant and animal inventory Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

Native plant revegetation Ongoing Paid for from each FY

NAP active ecological restoration Ongoing NAP/Northridge Church workday

07/30/2015.

GIVE365 active volunteer coordination. Cleaned up trash near livery and trails. 9/17/2015

Completed Paid for from each FY

Page 2: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

2

NAP Public Workday 11/01/2015. 38 volunteers gave 105 hours.

NAP/UM School of Information workday 01/16/2016.

Give365 active volunteer coordination: Mulched beds near livery, covered graffiti near cascades with anti-graffiti art 4/30/2016

Completed

NAP/SBD North America workday 04/21/2016.

NAP Public Workday 05/07/2016. NAP/Community High School

workday 05/01/2016. 249 volunteers gave 628 hours in 8 parks.

Argo Canoe Livery 1055 Longshore Drive

See Project Status Tables FY2009-2015 for projects completed in previous years

Paid for from each FY

Give365 pond area trash pick up 7/30/2015

Completed Paid for from each FY

NAP/Northridge Church workday 07/30/2015.

Completed Paid for from each FY

NAP Burn 4/14/2016. Give365 pond area trash clean

6/1/2016 Completed

Give365 river trash clean with Google 6/23/16

Completed

Bader Park Provincial Drive

See Project Status Tables FY2008-2014 for projects completed in

previous years

Bandemer Park 1352 Lakeshore Drive

See Project Status Tables FY2008-2015 for projects completed in

previous years

NAP active ecological restoration Ongoing Paid for from each FY

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

New barrier-free access to rowing docks

Design stage, work to be completed late summer - fall 2015 Construction Complete Paid for from Bandemer Fund

NAP/Northridge Church workday 07/29/2015.

Completed Paid for from each FY

GIVE365 active volunteer coordination. Trash pick up. 9/20/2015

Completed Paid for from each FY

NAP public workday 01/30/2016. Barton Nature Area Huron River Drive at Bird Road

See Project Status Tables FY2008-2015 for projects completed in

previous years

Page 3: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

3

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active ecological restoration

Ongoing Paid for from each FY

Woodchip pathways through nature area

In Progress Paid from FY15 Millage

NAP public workday 07/11/2015. Completed Paid for from each FY

NAP/YMCA Youth Volunteer Corp workday 07/27/2015.

Completed Paid for from each FY

NAP/Northridge Church workday 07/28/2015.

Completed Paid for from each FY

NAP public workday 8/23/2015. NAP/UM Medical School workday

08/14/2015. 38 volunteers gave 228 hours.

NAP/Greenhills School workday 9/18/2015. 85 volunteers gave 214 hours.

GIVE365 active volunteer coordination. Covered graffiti, sprayed anti-graffiti stencil art. 11/8/15

Completed

NAP controlled burn 11/16/2015. NAP public workday 11/21/2015. NAP public workday 01/18/2016. Baxter Park Baxter Road (north side), off of Green Road

See Project Status Tables FY2008-2013 for projects completed in

previous years

Berkshire Creek Nature Area South Huron Parkway and Washtenaw Avenue

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration

Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid from each FY

Beckley Park Argo Drive and Ottawa Street

NAP active volunteer coordination Ongoing Paid for from each FY

Belize Park 742 Franklin Street

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP active volunteer coordination Ongoing Paid for from each FY

NAP/Washtenaw County Water Resources Commissioners Office/YMCA Youth Volunteer Corp workday 07/21/2015.

Completed

NAP/Washtenaw County Water Resources Commissioners Office/YMCA Youth Volunteer Corp

Completed

Page 4: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

4

workday 07/28/2015. NAP/Washtenaw County Water

Resources Commissioners Office/YMCA Youth Volunteer Corp workday 08/03/2015.

NAP/Washtenaw County Water Resources Commissioners Office/YMCA Youth Volunteer Corp workday 08/11/2015.

NAP/Washtenaw County Water Resources Commissioners Office/YMCA Youth Volunteer Corp workday 08/18/2015.

Bird Hills Nature Area Newport Road on the west; Bird Road on the north; Huron River Drive on the east; M-14 on the south

See Project Status Tables FY2008-2015 for projects completed in

previous years

Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP active volunteer coordination NAP Native plant revegetation Ongoing

Paid for from each FY NAP Burn 03/21/2016 and

03/22/2016.

NAP/Community High School workday 05/01/2016. 249 volunteers gave 628 hours in 8 parks.

NAP public workday 05/21/2016. NAP public workday 6/4/2016. Black Pond Woods Nature Area 183 Traver Road

See Project Status Tables FY2008-2015 for projects completed in

previous years

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP controlled burn 11/04/2015. NAP public workday 11/15. NAP/Canton Prep High School

workday 05/13/2016.

NAP public workday 6/5/2016. Bluffs Nature Area 1099 N. Main Street

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

Page 5: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

5

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active ecological restoration

Ongoing Paid for from each FY

NAP/UM Michigan Community Scholars workday 9/5/2015. 165 volunteers gave 248 hours.

NAP Public Workday 11/08/2015. 36 volunteers gave 108 hours.

NAP Burn 03/30/2016. NAP/Community High School

workday 05/01/2016. 249 volunteers gave 628 hours in 8 parks.

Broadway Park Broadway Street at Huron River

See Project Status Tables FY2008-2014 for projects completed in

previous years

Dog Park proposed for site Work is underway. Fencing to be installed in early fall 2016. To be constructed, pending City Council approval, summer 2016 Paid from FY16 Millage

Bromley Park Briarcliff Street between Renfrew Street & Aurora Street

See the Project Status Table FY2009-2015 for projects completed

in previous years

Brookside Park Stone School Road and Brookside

See Project Status Tables FY2008-2014 for projects completed in

previous years

Bryant Community Center 3 West Eden Court

See Project Status Tables FY2008-2015 for projects completed in previous years

Adopt-a-Park active volunteer coordination

Ongoing Paid for from each FY

Bicycle rack installation Complete Building-addition planning Design stage, site plan approved

by Planning Commission. Site plan was approved by scheduled for City Council on June 6. Paid for from FY2016

Buhr Park, Pool and Ice Arena 2751 Packard Road

See Project Status Tables FY2008-2015 for projects completed in previous years

Buhr Park: NAP Native plant revegetation

Ongoing Paid for from each FY

Buhr Park: NAP active volunteer coordination

Ongoing Paid for from each FY

Buhr Park: NAP active ecological restoration

Ongoing Paid for from each FY

Pool liner replacement Project complete Paid for from FY2016

NAP Burn 04/05/2016. Give365 active volunteer

coordination: Set up pool chairs, mulched garden beds 5/14/16

Completed

Page 6: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

6

Burns Park 1300 Baldwin Ave.

See Project Status Tables FY2008-2015 for projects completed in previous years

Adopt-a-Park and NAP active volunteer coordination

Ongoing Paid for from each FY

Adopt-A-Park 11/19/15: Weeded raingarden with Sigma Kappa and adopter

Adopt-A-Park 5/1/16: Trash clean-up following Burns Park Run

Completed

Give365 active volunteer coordination: Rain garden maintenance 6/8/2016

Completed

Burr Oak Park 528 and 601 Burr Oak Drive

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP active volunteer coordination Ongoing Paid for from each FY

Playground replacement and walk repairs

Scheduled for summer 2015 Construction underway Complete Paid for from FY2015 millage

Adopt-a-Park: Adopter spread mulch and compost in garden beds

Ongoing Paid for from each FY

Cedar Bend Nature Area Cedar Bend Drive at Broadway Street

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP/Team Awesome workday 07/22/2015.53 volunteers from China gave 106 hours.

Completed

NAP/UM Nam Center for Korean Studies workday 07/24/2015.37 volunteers from Korea gave 111 hours.

Completed

NAP/UM Law school workday workday 08/27/2015. 21 volunteers gave 115.5 hours.

NAP public workday 09/20/2015 NAP/Deloitte Consulting workday

9/11/2015.

NAP controlled burn 11/03/2015. NAP Public Workday 05/01/2016. NAP/Community High School

workday 05/01/2016. 249 volunteers gave 628 hours in 8 parks.

NAP/Ann Arbor Academy Workday 06/03/2016. 38 students gave 112 hours.

Churchill Downs Park 2100, 2110 Steeplechase Drive

See Project Status Table FY2008-2013 for projects completed in

Page 7: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

7

previous years GIVE365 Active volunteer

coordination: Spread fibar on playground 5/4/16

Completed

Clinton Park On Stone School Road, south of Eisenhower

See Project Status Tables FY2008-2015 for projects completed in previous years

GIVE365 volunteer workday. Spread fibar, weeded, cleaned trash. 11/1/15

Completed

Cloverdale Park 499 Cloverdale St.

See Project Status Tables FY2008-2015 for projects completed in previous years

Trim back trees and brush from around playground

Ongoing Paid for from FY 2013 Millage

Cobblestone Farm 2781 Packard Road

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Standby generator for the barn Bid package in process

Cedar siding replacement on barn Work to start in February. Work underway Work Complete Paid for from FY2016

Paint Cobblestone House exterior Work Complete Give365 active volunteer

coordination: painted small red barn, cleaned trash 4/11/2016

Completed

Cranbrook Park 300 W. Oakbrook Drive

See Project Status Tables FY2008-2015 for projects completed in

previous years

NAP active ecological restoration Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

Creal Park Creal Cresent at Helen Street

See Project Status Table FY2008-2014 for projects completed in

previous years

Dhu Varren Woods Nature Area Dhu Varren Road at Birchwood Drive

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP controlled burn 4/19/2016. Dicken Woods Nature Area South of Pauline Boulevard; east of South Maple Road; north of

See Project Status Tables FY2008-2015 for projects completed in

previous years

NAP active volunteer coordination Ongoing

Page 8: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

8

Paid for from each FY NAP Plant and animal inventory Ongoing

Paid for from each FY NAP Public Workday 10/24/2015.

45 volunteers gave 135 hours.

NAP/UM Engineering Global Leadership workday 11/21/2015.

NAP/Cub Scout Pack 131 workday 05/15/2016.

Dolph Nature Area Wagner Road on the west; Jackson Road on the north; Parklake Avenue on the east

See Project Status Tables FY2008-2015 for projects completed in

previous years

NAP active ecological restoration Paid from each FY

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP coordinated with Eagle Scout Nate Helberg to installing way-finding signs.

NAP community service volunteer cleared trails.

Douglas Park 1700 Washtenaw Ave.

Adopt-a-Park active volunteer coordination

Ongoing Paid for from each FY

Give365 active volunteer coordination: cleared invasives, spread mulch, cleared trash 4/3/2016

Completed

Earhart West 3603 Fox Hunt Drive

See Project Status Table FY2014-2015 for projects completed in previous year

NAP/King Elementary School workday 05/13/2016. 76 volunteers gave 190 hours.

Ellsworth Park East Ellsworth Road, between Jonathan Court and Braeburn Circle

See Project Status Table FY2008-2013 for projects completed in

previous years

Esch Park Esch at Winthrop Court

NAP and Adopt-a-Park active volunteer coordination

Ongoing Paid for from each FY

NAP and Adopt-a-Park expansion of native planting

Ongoing Paid from each FY

Evergreen Park 3131 Parkwood St.

NAP active volunteer coordination Ongoing Paid for from each FY

Farmers Market See Project Status Tables FY2008-

Page 9: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

9

315 Detroit St. 2015 for projects completed in previous years

Column repair on canopy structures Evaluation/design underway Repairs are underway. Paid for from FY2016

Farmers Market winter structure Design work underway Project on Planning Commission agenda, July 12 Paid from FY16 Millage

Give365 active volunteer coordination: Weeded and mulched tree beds, clean windows, sweep office 4/22/2016

Completed

Folkstone Park North Folkstone Drive north of Larchmont Drive

NAP active ecological restoration Ongoing Paid for from each FY

Forest Nature Area Handy Lane and Geddes Road

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Forsythe Park 752 Packard St.

NAP active volunteer coordination Ongoing Paid for from each FY

Foxfire North Park Hickory Pointe Drive at Omlesaad Drive

See Project Status Table FY2014-2015 for projects completed in previous years

Foxfire West Park Birchwood Drive between Hickory Point Drive and Timbercrest Court

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP public workday 2/15/2016. Foxfire South Park Olmstaad Drive, south of Dhu Varren

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Frisinger Park East Stadium Boulevard at Woodbury Drive

See Project Status Tables FY2008-2015 for projects completed in previous years/

Fritz Park 1450 Pauline Boulevard

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing

Page 10: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

10

Paid for from each FY NAP active ecological restoration Ongoing

Paid for from each FY Woodchip and slag pathways in

park and nature area In Progress Paid from FY15 Millage

Fuller Park 1519 Fuller Road

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Replacement of pool boiler In Progress Paid from FY14 Millage

Pool liner replacement Scheduled for fall 2014 Project Complete Paid for from FY2015

Restoration of soccer fields 6 and 7 (aerating, seeding, top dressing, irrigation)

In Progress Paid from FY2015 Millage

GIVE365/EMU community plunge workday. Readied for winter, put chairs away. 9/11/2015

Completed

NAP led nature walks for 420 Huron High School students on 9/29 and 10/1.

Give365 active volunteer coordination: Set up pool chairs, maintained flower beds 5/14/16

Completed

NAP/Community High School workday 05/01/2016. 249 volunteers gave 628 hours in 8 parks.

NAP Burn 4/18/2016. Furstenberg Nature Area 2626 Fuller Road

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Plant and animal inventory NAP Native plant revegetation Ongoing

Paid for from each FY NAP active volunteer coordination Ongoing

Paid for from each FY NAP active ecological restoration Ongoing

Paid for from each FY Parks: Tree trimming and removals Ongoing

Paid for from each FY NAP public workday 07/25/2015. Completed NAP public workday 8/8/2015. Completed NAP public workday 2/20/2016. NAP Burn 4/12/2016. NAP/Greenhills School workday

4/16/2016. 148 volunteers gave 444 hours in 3 parks.

NAP/Huron High School AP Biology Workday 5/12/2016.

NAP public workday 05/14/2016. NAP/Huron High Science Class

Workday 06/01/2016 390 students gave 293 hours.

Page 11: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

11

Gallup Park 3000 Fuller Road

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP active ecological restoration Ongoing Paid for from each FY

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP Native plant re-vegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

Boat ramp improvements, including parking area improvements, dock and ramp improvements.

Grant received for engineering portion of project. Engineering study completed. Work to commence contingent on grant receipt in 2014. Grant funding not available next year, project delayed. Matching grant funds paid for from FY 2012 Millage

Give365 picked up trash in pond area 7/1/2015

Completed

NAP/YMCA Youth Volunteer Corp workday 07/20/2015.

Completed

NAP public workday 07/25/2015. Completed

NAP/Hot Spot Life Group workday 07/25/2015.

Completed

NAP/YMCA Youth Volunteer Corp workday 07/27/2015.

Completed

NAP/ YMCA Youth Volunteer Corp workday 08/3/2015.

NAP/ YMCA Youth Volunteer Corp workday 08/10/2015.

NAP/ YMCA Youth Volunteer Corp workday 08/17/2015.

NAP/ YMCA Youth Volunteer Corp workday 08/30/2015.

Give365 YVC Trash Pick-up 8/3/2015 and 8/17/2015

New picnic shelter – replacement of old wooden shelter

Complete Paid for by private donation

Playground renovations at livery Complete Paid for by private donation

GIVE365 trash clean-up in pond area. 10/3/15

Completed Paid for by MDEQ grant

GIVE365 active volunteer coordination. Painted 95% of picnic tables in park. 10/31/15

Completed Paid for from each FY

Replacement of pathway between Geddes Dam and central parking lot

Construction to begin July/August 2016 Construction is underway. Paid for from FY2016 and grant from MDOT

Give365 active volunteer coordination: Prepped flower beds 4/15/2016

Completed

Give365 active volunteer coordination: Sprayed anti-graffiti stencils, cleared trash, weeded and spread mulch in beds by livery

Completed

Page 12: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

12

4/22/2016

NAP/Greenhills School workday 4/15/2016. 148 volunteers gave 444 hours in 3 parks.

Give365 pond area trash clean with Google 6/17/16

Completed

Give365 pond area trash clean with BSA troop 1 6/21/16

Completed

Garden Homes Park 1800 Franklin St.

NAP and Adopt-A-Park active ecological restoration

Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

Glacier Highlands Park Larchmont Drive at Barrister Road

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP active ecological restoration Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

Glazier Hill 3412 and 3420 E. Dobson Place

See Project Status Tables FY2008-2011 for projects completed in

previous years

Greenbrier Park 3695 & 3750 Frederick Drive

See Project Status Tables FY2008-2015 for projects completed in

previous years

Greenview Park (leased from Ann Arbor Public Schools) North of Scio Church Road, west of South Seventh and east of Greenview Drive

See Project Status Tables FY2008-2013 for projects completed in

previous years

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Hannah Nature Area 206 Mark Hannah Place

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration

Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP public workday11/21/2015. NAP Public Workday 05/07/2016. Hanover Square Packard and South Division

See Project Status Tables FY2008-2015 for projects completed in previous years

Page 13: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

13

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Replace bench boards with recycled plastic materials

Completed Paid for from FY 2015 Millage

Hansen Nature Area South Maple, north of Hansen Drive

NAP active volunteer coordination Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP active ecological restoration

Ongoing Paid for from each FY

NAP public workday 05/14/2016. Hollywood Nature Area Sequoia Parkway at Kuehnle Avenue

See Project Status Tables FY2008-2015 for projects completed in previous years

Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Hunt Park 1035 Daniel St.

See Project Status Tables FY2008-2015 for projects completed in previous years

Adopt-a-Park active volunteer coordination

Ongoing Paid for from each FY

Tennis court replacement Design phase, Out for bid Anticipating summer 2015 construction Project under construction Project complete Paid for from FY 2016 Millage

Huron Highlands Park Skydale Drive and Pontiac Trail

Adopt-a-Park active volunteer coordination

Ongoing Paid for from each FY

Huron Hills Golf Course 3465 E. Huron River Drive

NAP active ecological restoration

Ongoing Paid for from each FY

NAP Native plant revegetation NAP active volunteer coordination

Ongoing Paid for from each FY

NAP Burn 4/15/2016. Huron Parkway Nature Area Huron Parkway between Washtenaw Avenue and Huron River Drive

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP Public Workday 10/10/2015. NAP Controlled Burn 11/05/2015.

Page 14: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

14

NAP Public Workday 4/24/2016. 38 volunteers gave 105 hours.

Iroquois Park 1404 Iroquois Place

Adopt-a-Park active volunteer coordination

Ongoing Paid for from each FY

Island Park 1450 Island Drive

See Project Status Tables FY2008-2015 for projects completed in previous years

Adopt-A-Park/GIVE active volunteer coordination.

Ongoing Paid for from each FY

Replace lighting under shelter with new LED lighting

In Progress Paid for from FY 2015 Millage

Weeding, pulling invasives in September.

Pedestrian bridge repairs Construction complete Paid for from FY 2015 Millage

Adopt-A-Park 11/8/15: U of M RHA and adopter planted two trees and cut back invasives along river.

Give365 active volunteer coordination: Cleared invasive brush 4/3/2016

Completed

Give365 crew: Cleared invasive brush 6/18/16

Completed

Kempf House 312 S. Division St.

See Project Status Tables FY2008-2013 for projects completed in

previous years

Irrigation system renovations Complete Kilburn Park Kilburn Park Circle and Dunwoodie Drive

See Project Status Tables FY2008-2015 for projects completed in previous years

Adopt-A-Park/GIVE active volunteer coordination.

Ongoing Paid for from each FY

Weeded and planted flowers in garden bed in September.

Kuebler Langford Nature Area Huron River Drive and M-14

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP public workday 07/11/2015. Completed NAP Burn 4/13/2016. NAP/Community High School

workday 05/01/2016. 249 volunteers gave 628 hours in 8 parks.

Lakewood Nature Area Lakeview Avenue at West Liberty

See Project Status Tables FY2008-2015 for projects completed in

Page 15: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

15

previous years NAP Native plant revegetation Ongoing

Paid for from each FY NAP Plant and animal inventory Ongoing

Paid for from each FY NAP active volunteer coordination Ongoing

Paid for from each FY NAP active ecological restoration Ongoing

Paid for from each FY NAP public workday 05/14/2016.

Lansdowne Park Lans Way at Ascot Road

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Give365 active volunteer coordination: spread Fibar 5/28/16

Completed

Las Vegas Park Las Vegas Drive at Runnymede Boulevard

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Lawton Park Mershon Drive between Scio Church and Delaware

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Give365 cleared invasive plants 7/11/2015

Completed

Leslie Park Leslie Park Circle and DhuVarren Road

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP active ecological restoration Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

Install new swing set in north end playground

Paid for from FY 2013 Millage

Leslie Park Golf Course 2120 Traver Road

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

Leslie Science & Nature Center 1831 Traver Road

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP active ecological restoration Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

Basement renovations Out for bid Work to begin mid April, 2015 Cleanout underway complete Paid for from FY 2016 Millage

Page 16: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

16

Leslie Woods Nature Area South of Leslie Park Golf Course, north of Upland Drive

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP public workday 12/26/2015. Liberty Plaza 310 S. Division

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Longshore Park Longshore Drive

See Project Status Tables FY2008-2014 for projects completed in

previous years

Mack Pool 715 Brooks St.

See Project Status Tables FY2008-2015 for projects completed in

previous years

Paint pool ceiling In progress, pre bid meeting took place in March; work projected for completion in July/August 2015 Paid for from FY 2015/2016 Millage

Malletts Creek Nature Area Huron Parkway at Lindsay Lane

See Project Status Tables FY2008-2011 for projects completed in previous years

Marshall Nature Area Plymouth Road at North Dixboro Road

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP public workday 07/19/2015. Completed NAP/EMU Community Plunge

workday 09/11/2015.

NAP/EMU Bio 226 workday 10/3/2015.

NAP/EMU Vision Workday 01/15/2016.

NAP/EMU Green Club 03/26/2016. NAP controlled burn 04/20/2016 and

05/09/2016.

NAP/MSU Alumni workday 04/16/2016.

NAP Public Workday 05/07/2016. NAP/A2 Ward Cub Scouts workday

5/31/2016.

Page 17: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

17

Mary Beth Doyle Park South of Packard Road, east of Birch Hollow, west of Verle, and north of I-94

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

GIVE365/EMU community plunge active volunteer coordination. Weeded playground, picked up trash, scrubbed graffiti. 9/11/2015

Completed

NAP/UM Indian American Student Association workday 10/3/2015. 136 volunteers gave 613.5 hours.

NAP public workday 10/18/2015. 30 volunteers gave 97 hours.

NAP/Temple Beth Emeth workday 03/20/2016.

NAP/EMU Greek Life Workday 04/02/2016. 94 volunteers gave 265 hours.

NAP Public Workday 05/01/2016. Maryfield Wildwood Park On Linwood between Westwood and Maryfield

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP active ecological restoration Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

Meadowbrook Park 2500 7th St.

See Project Status Tables FY2008-2014 for projects completed in previous years

AAP/GIVE workday: weeded playground, spread fibar, trash clean up. 7/16/15 and 8/14/15.

Completed

Give365 crew spread fibar 6/14/16 Completed Miller Nature Area Miller Avenue at Pinetree Drive

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP public workday 8/16/2015. Completed NAP /YMCA Youth Volunteer Corp Completed

Page 18: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

18

workday 08/24/2015. NAP public workday 10/17/2015. NAP controlled burn 05/06/2016. NAP Public Workday 05/07/2016. NAP/Community High School

workday 05/01/2016. 249 volunteers gave 628 hours in 8 parks.

Mixtwood Pomona Mixtwood and Pomona streets

See Project Status Tables FY2008-2015 for projects completed in previous years

Molin Nature Area 2118 Columbia Avenue

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP Public Workday 10/24/2015. NAP Public Workday 4/23/2016. Mushroom Park Waltham Drive at Windsor Drive

See Project Status Tables FY2008-2015 for projects completed in previous years

Narrow Gauge Nature Area 3468 Narrow Gauge Way

NAP Plant and animal inventory

Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Newport Creek Nature Area 1600 Timber Trail

See Project Status Tables FY2008-2011 for projects completed in

previous years

North Main Park 604 N. Main

See Project Status Tables FY2008-2015 for projects completed in previous years

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Northside Park Pontiac Trail and Taylor Street

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Oakridge Nature Center Huron Parkway at Glazier Way

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Oakwoods Nature Area On Green Road between Kilburn

See Project Status Tables FY2008-2015 for projects completed in

Page 19: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

19

Park Circle and Whisperwood Drive

previous years

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP public workday 09/26/2015 Olson Park 1505 DhuVarren Road

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Soccer field irrigation project In Progress Paid from FY 2015 Millage

NAP coordinated with Eagle Scout Brian Dokas to install way-finding signs.

Onder Park 295 Brookside Drive

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Pilgrim Park 2966 Verle Street

See Project Status Table FY2009-2013 for projects completed in

previous years

Give365 crew: Cleared weeds from playground area

Completed

Placid Way Park Placid Way at Tuebingen Way

See Project Status Tables FY2008-2013 for projects completed in

previous years

Plymouth Parkway Park On Plymouth Road between Broadway and Barton

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Redbud Nature Area On Parkwood Avenue at Jeanne Street

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP/Phi Sigma Rho workday 11/22/2015.

Page 20: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

20

NAP Public Workday 4/23/2016.

Redwood Park Redwood Avenue at Platt Road

See Project Status Tables FY2008-2015 for projects completed in previous years

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Riverside Park Canal Street at Island Drive

NAP Plant and animal inventory Ongoing Paid for from each FY

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

AAP/GIVE workday: trimmed back trees and shrubs in sign bed, weeded playground, planted flowers, trash clean up. 8/20/15 and 8/31/15

Completed

GIVE365 active volunteer coordination. Cleared invasive brush in front of park benches, spread Fibar at playground, cleaned trash. 10/25/15

Completed

Riverwood Nature Area Riverwood Drive and Newport Road

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Rose Park 2670 Packard Road

See Project Status Table FY2008-2013 for projects completed in

previous years

Give365 active volunteer coordination: Weeded playground, spread fibar 6/21/16

Completed

Rose White Park East Stadium, between Golden Avenue and White Street

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Ruthven Nature Area Huron Parkway at Geddes Road

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP Public Workday 11/07/2015.

NAP/Greenhills School workday 04/15/2016. 148 volunteers gave 444 hours in 3 parks.

NAP Burn 4/25/2016.

NAP public workday 6/4/2016.

Page 21: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

21

Scarlett Mitchell Nature Area Platt Road at I-94

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP Public Workday 10/10/2015.

NAP/UM Delta Sigma Phi workday 10/24/2015.

NAP/UM Delta Sigma Phi workday 11/14/2015.

Scheffler Park Platt Road at Edgewood Drive

See Project Status Tables FY2008-2015 for projects completed in previous years

Adopt-A-Park active volunteer coordination-multiple workdays- spreading compost, weeding.

Adopt-A-Park: weeding garden beds and spreading mulch

Sculpture Plaza Catherine Street at North Fourth Avenue

See Project Status Tables FY2008-2015 for projects completed in previous years

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Landscape planting restoration Planting beds cleared. Planting scheduled

Give365 cleared beds for adopter re-planting 7/13/2015

Completed

Senior Center 1320 Baldwin Ave.

See Project Status Tables FY2008-2015 for projects completed in

previous years

Renovations to interior, including new dry wall, paint, joists, skylights, carpeting and roofing.

Ongoing Paid for from FY2015

Give365 active volunteer coordination: Cleared trash, spread mulch, painted picnic table and bench 4/23/2016

Completed

South University Park 1505 S. University Ave.

See Project Status Tables FY2012-2015 for projects completed in

previous years

GIVE365 Weeded 2/3 of garden bed, mulch ordered 06/18/2015 Weeded again, mulched 2/3 of bed 7/28/2015

Ongoing

Southeast Area Park 2945 E. Ellsworth Road

See Project Status Tables FY2008-2015 for projects completed in

Page 22: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

22

previous years GIVE365 active volunteer

coordination. Cleaned up trash, weeded. 9/13/2015

Completed

Give365 active volunteer coordination: Picked up trash, planted flowers in bed at park sign 5/17/16

Completed

South Maple Park 2675 W. Liberty St.

See also the Project Status Table FY2009-2013 for projects completed in previous years

GIVE365 active volunteer coordination. Cleaned up trash, spread Fibar at playground area. 10/1/2015

Completed

Tennis courts to be renovated, including pickle ball lines

Summer 2016 Completed Paid from FY 2015 Millage

Give365 and Adopt-A-Park active volunteer coordination: Workday clearing brush 6/17/16

Completed

South Pond Nature Area 3899 E. Huron River Drive

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP coordinated with Eagle Scout Will Norton to build benches and a picnic table for osprey viewing.

Stapp Nature Area Huron Parkway between Traverwood Drive and Traver Boulevard

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP public workday 8/29/2015. Completed NAP public workday 12/12/2015. Sugarbush Park Green Road at Rumsey Drive

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Tennis courts to be renovated Summer 2016 Completed Paid from FY 2015 Millage

Sunset Brooks Nature Area See Project Status Tables FY2008-

Page 23: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

23

Sunset Road between Newport Road and Beechwood Drive

2015 for projects completed in previous years

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP Public Workday 11/08/2015. NAP/Community High School

workday 05/01/2016. 249 volunteers gave 628 hours in 8 parks.

NAP public workday 05/21/2016. Swift Run Dog Park Platt and Ellsworth roads

See Project Status Table FY2008-2009 for projects completed in

previous years

Swift Run Marsh Platt and Ellsworth roads

NAP Plant and animal inventory Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

NAP/UM Indian American Student Association workday 10/3/2015.

Sylvan Park Margaret Drive and Darrow Drive

NAP active ecological restoration Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing Paid for from each FY

The Ponds Park 2680 Emerald Ave.

See Project Status Tables FY2008-2013 for projects completed in previous years

Adopt-A-Park active volunteer coordination

Traver Creek Nature Area Traver Road, west of Ann Arbor Railroad

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Turnberry Park Turnberry Drive at Packard

NAP Native plant revegetation Ongoing Paid for from each FY

NAP active volunteer coordination Ongoing Paid for from each FY

NAP active ecological restoration Ongoing Paid for from each FY

Veterans Memorial Park 2150 Jackson Road

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP and Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

GIVE365 active volunteer coordination. Weeded beds, spread mulch, cleaned up trash. 9/2/2015

Completed

GIVE365 active volunteer coordination. Cleaned up trash in

Completed

Page 24: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

24

skatepark area. 11/7/2015 Give365 active volunteer

coordination: Cleaned up trash 4/23/2016

Completed

Give365 active volunteer coordination: Set up pool chairs, rain garden maintenance 5/15/16

Ongoing

Give365 active volunteer coordination: Rain garden maintenance 5/28/16

Ongoing

Give365 active volunteer coordination: Clearing main sign bed of invasives with Concordia Football 6/18/16

Completed

Virginia Park Virginia Avenue at Fair Street

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Ward Park East Oakbrook Road and South Main Street

See Project Status Tables FY2008-2015 for projects completed in

previous years

Waterworks Park Between South 7th and 8th streets, Liberty and Washington

See Project Status Tables FY2008-2014 for projects completed in previous years

Adopt-a-Park work day with adopter- spread fibar, weeded garden bed, trash pickup, rake leaves, on 10/23/15

Give365 active volunteer coordination: Maintained rain gardens, planted flowers, mulched around trees, cleared trash 5/28/16

Completed

Waymarket Park Signature Boulevard at Waymarket Drive

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Wellington Park On Bruce Street, between Alice and Arlene streets

See Project Status Tables FY2008-2015 for projects completed in previous years

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Install fibar (playground mulch) Completed Paid from FY 2015 Millage

West Park 215 Chaplin St.

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP active ecological restoration Ongoing Paid for from each FY

NAP and Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Master plan updates to include stormwater features and recreational amenities.

Construction complete Planting restoration continuing Storm system repairs complete Grant received from ARRA Federal Funding and the Stormwater fund

Page 25: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

25

NAP/YMCA Youth Volunteer Corp workday 07/06/2015.

Completed

NAP/First United Methodist Church workday 07/08/2015

Completed

NAP/A2 Open and Community High workday 05/25/2016. 69 volunteers gave 69 hours.

Wheeler Park 810 N. Fourth Ave.

See Project Status Tables FY2008-2015 for projects completed in previous years

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Water main to be replaced through park as part of street project. At that time, basketball courts will be replaced and running track renovated.

Fall 2014 Construction delayed Construction underway complete Paid from FY 2015 Millage

Wheeler Service Center, City Park Operations 4251 Stone School Road

NAP active ecological restoration Ongoing Paid for from each FY

Winchell Park St. Francis Drive and Winchell Drive

Adopt-A-Park/GIVE active volunteer coordination.

Ongoing Paid for from each FY

Weeded playground, spread fibar in September

Windemere Park Windemere Drive and Charter Place

See Project Status Tables FY2008-2015 for projects completed in previous years

Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

AAP/GIVE workday: spread fibar on playground, trimmed back trees/shrubs and weeded sign bed. 8/26/15. Finished spreading fibar in September

Completed

White Oak Park 2665 White Oak Drive

NAP Public Workday 05/07/2016.

Winewood Thaler 2091 Winewood Ave.

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP and Adopt-A-Park active volunteer coordination

Ongoing Paid for from each FY

Woodbury Park 1400 Astor Ave.

Tennis courts to be renovated Summer 2016 Fencing and asphalt repairs complete. Color coating and striping scheduled for August. Paid from FY 2015 Millage

Wurster Park West Madison Street and South Fourth Street

See Project Status Tables FY2008-2015 for projects completed in previous years

NAP and Adopt-A-Park active ecological restoration

Ongoing Paid for from each FY

NAP Native plant revegetation Ongoing

Page 26: Location Project Status - Ann Arbor, Michigan...NAP/Northridge Church workday 07/28/2015. Completed Paid for from each FY NAP public workday 8/23/2015. ... Fencing to be installed

26

Paid for from each FY NAP active volunteer coordination Ongoing

Paid for from each FY Adopt-A-Park/GIVE: weed, maintain

edible garden. Finished volleyball restoration

Paid from FY 2015 Millage

NAP public workday 09/26/2015 Adopt-A-Park 11/11/15: spread

woodchips around trees

Give365 active volunteer coordination: Cleaned sand volleyball court, weeded and mulched beds 4/24/2016

Completed

NAP public workday 04/16/2016 Zion Park Ridgemor Drive off W. Liberty Street

See Project Status Table FY2015 for projects completed in previous year

 

Last updated: July 8, 2016