Locally Administered Projects Manual Updates & Materials Quality Assurance Plan Requirements
March 19, 2015
W. R. Bailey PE
Assistant State Materials Engineer
LAP Manual Updates
Background• Joint effort between Materials and Local Assistance Division
• Group of District Materials Engineers, QA Managers, Materials Program Engineers and LAD Program Specialists
Purpose• Look for opportunities to improve and strengthen LAP program
• Develop Quality Assurance Plan • Coordinate Off-site inspections
– Table 1 in LAP Manual
• Explore ways to improve communications• Request to manage testing similar to VDOT
– Allow Localities to follow VDOT guidelines for Materials Testing
• Provide Training on LAP Manual through webinars
2
LAP Manual Updates
• Outcome of Presentation • What are the major changes being made to the LAP
Manual?• What is the localities’ role in executing an effective
Quality Assurance Plan?• Why is the Acceptance/Verification Process important?• What documentation is needed for Material
Acceptance? • What are some benefits to changes in the LAP Manual?
3
Quality Assurance Plan
4
For federal-aid or VDOT-maintained projects, the LPA shall submit a materials quality assurance plan
(QAP) for review and approval, prior to implementation.
LAP Manual Updates
Materials Acceptance/VerificationDefinitions
• Quality Assurance (QA) – All those planned and systematic actions necessary to provide confidence that a product will perform satisfactorily in service.
• Acceptance Testing (AT) - to determine if the quality of produced material meets specification.
• Quality Control (QC) – to assess production and construction processes to control the level of quality of the end product. 5
LAP Manual Updates
6
Quality Assurance Plan
Independent Assurance
(IA)Quality Control
(QC) Verification Sampling and
Testing (VST)
Acceptance Test(AT)
+
Inspection+
LAP Manual Updates
• Independent Assurance (IA) - to evaluate the accuracy of acceptance sampling and testing, operations and equipment by an independent party not responsible for QC or acceptance testing.
• Verification Sampling and Testing (VST) – to validate the quality of the product by comparing results to specification.
7
Materials Acceptance/VerificationDefinitions
LAP Manual Updates
• The plan is developed by the Locality using a template
provided in the LAP Manual.
• The LAP Manual contains a QAP commentary providing
direction for developing the QAP.
• The plan outlines how the Locality will assure that all
materials used on an LAP adhere to the sampling/testing and
acceptance processes defined in the LAP Manual. Deviations
from the LAP must be clearly documented.
• The QAP must be accepted by the District Project Coordinator
before any material is accepted on an LAP.9
LAP Manual Updates
Quality Assurance Plan
Main Components of the QAP• Cover Sheet - (“Responsible Charge Person”,
“Contact Person”, Organizational Chart, etc.)
I. Mission Statement - predefined
II. Personnel Certifications
III. Lab Accreditation
IV. Communication channels established
V. Resolution Procedure defined
VI. Progress Reports
10
Quality Assurance Plan
LAP Manual Updates
Main Components of the QAP
VII. Materials Acceptance and Test Data records
VIII.All materials testing, testing methods and frequencies shall follow LAP Manual. Any deviations for the sampling/testing and inspection frequencies are predefined.
IX. A “right to inspect” clause that documents events to be witnessed and hold points.
X. Non-Compliance Report and Recovery Plan
11
LAP Manual Updates
Quality Assurance Plan
Materials QAP Requirements
• Acceptance Methods• Testing• Inspection• Certification• Quality Assurance Plans• Approved Lists• Pre-Qualified Lists• LT Process
12
How to Use the LAP Manual to Develop a Quality Assurance Plan
Appendix 13.2 – G: Frequency Tables• Material Type• Specification and Test Reference• Acceptance Test• Verification Test• Independent Assurance Test• Number of Tests to run on each material and how often
13
Materials QAP Requirements
14
BRIDGE DECK POUR – 405 cubic yard (45 loads)
AIR CONTENT• Inspector AT –
1st 3 trucks (3) then every 3rd load thereafter (14): 3+14 = 17 tests
• VST – NONE• IA – 5 tests
from the same batch as when cylinders cast
Materials QAP Requirements
15
How will Acceptance be determined?
LPA or unaffiliated third party hired by LPA - AT
VDOT - ATContractor - QC
Who will perform Verification Testing and
Independent Assurance?
LPA or unaffiliated third party hired by
LPA
VDOT
Who will perform Independent Assurance?
Who will perform Independent Assurance?
Different LPA personnel or unaffiliated third party
hired by LPAVDOT
VDOT
Asphalt Paving
Concrete, Aggregate and Soil
Quality Assurance Planning Flow Chart for Design-Bid-Build Project Site Testing
Always an Available Option
Materials QAP Requirements
How to Use the LAP Manual to Develop a Quality Assurance Plan
Appendix 13.2 – C: C-25 (Source of Materials) Example
Complete C-25 by filling in INSP/Test By Column • List Acceptance method• Determine Source Qualifications for fabricated items• Consider ability to perform Source Inspection and testing for
manufactured materials at locations other than job site• Decide to perform inspection or request that VDOT perform
inspection
• Send completed C-25 to VDOT for Review• After approval communicate to Contractor, Inspection staff and
VDOT Materials if requesting their services16
Materials QAP Requirements
17
SUBMITTED
PROJECT NUMBER EN97-080-115, C502 (UPC 103495) CONTRACT ID. NO. Hanging Rock Trail
PROJECT LOCATION 1.27 Mi. E Rte 795 DISTRICT Salem COUNTY Roanoke
PRIME CONTRACTOR with ADDRESS SUBCONTRACTOR with ADDRESS NAME and TELEPHONE NO.
Joe Smith of CONTACT PERSON4321 Expansion Drive Joe SmithRichmond, VA 231219 804-555-9999
ITEM NO.
SPEC.
NO.
ITEM DESCRIPTION
MANUFACTURER and/or SUPPLIER
COMPLETE ADDRESS VDOT USE INSP/TEST BY:
16242 308 & 309 Aggregate Base Material 21B Luck Stone Corporation Po Box 687 Keswick VA 22902
Culpeper Materials will perform plant testing when requested by LPA.
6501360404
404 Class A3, A4 Concrete Boxley Concrete 15580 Lynchburg Turnpike Roanoke VA 24064
Approved Mix DesignSalem MaterialsCylinders to be made by locality or their representative.
40161 520 8”,12”,16” DI Water Main12 “ sanitary Sewer Pipe
Consolidated Pipe and Supply
225 11th St Roanoke VA 24013
LT Number Required
1061210636
315 Asphalt Concrete TY BM-25.OA, SM-9.5D L. H. Sawyer Paving Company
2101 Salem Industrial Drive Salem VA 24153
Approved Mix DesignSalem Materials will perform plant testing when requested by LPA.
51347 700 Signal Poles and Mast Arms Atlantic Technical Sales 14555 Lee Road Chantilly VA 20151
Request Inspection from C.O. Structures section.
00596 302 Precast EW-12 and Precast Items Permatile Concrete 260 Shanks Road Blountville TN 37617
VDOT Precast QA Program Approved List 34
68125 407 Structural Steel Plate Girders Hirschfeld Industries Bridge
Po Box 20888 Greensboro NC 27420
Request Inspection from C.O. Structures section
VIRGINIA DEPARTMENT OF TRANSPORTATIONSOURCE OF MATERIALS
Opportunity for Improvement in Communication
18
LAP Manual revisions give communication responsibilities to Locality.
**NOTE: When coordinating a project, the Locality and Local Assistance District
Project Coordinator are responsible for proper coordination as follows.
LAP Manual Updates
Addition of Table 1
19
The LPA must identify if they are requesting that VDOT perform source inspections for Structural Steel, Signal poles or Pre- stressed Concrete elements when submitting C-25.
LAP Manual Updates
Galvanized Steel or Aluminum Light Poles
Spec. Section 407 of Road & Bridge Specification for Fabrication Procedures
Welding – Structural Steel or Aluminum Welding Code D1.1 or 1.2
Galvanizing Specification Section - 233
Acceptance – Shop inspected at the source by VDOT or Consultant Inspection agency for VDOT 20
Materials QAP Requirements
Welding Codes for Steel and Aluminum Structures
Materials Structures Section• Experienced Staff
• Program Specialist - NDT• 3 Engineers• 1 Technician
• Qualifications• Certified Welding Inspectors• Prestress Concrete Inspectors• Experts in Non Destructive
Testing
• 100 Fabrication Plants• Nationwide
21
Materials QAP Requirements
Addition of Table 1
22
The LPA must identify if they are requesting that VDOT perform source inspections for Asphalt or Central Mix Aggregate materials when submitting C-25.
LAP Manual Updates
Hot Mix Asphalt QA Program
District Approves Plant
Mix Design
Asphalt IA and VST Testing at plant
Density tested at project 23
TL-102:
Weigh Person’s Daily Summary
24
The LPA project manager is responsible for ensuring that
the contractor informs the asphalt and aggregate
suppliers and VDOT District Materials that their project will
be handled the same as a VDOT project, which requires testing and submission of TL-
102A for documentation.
X
LAP Manual Updates
25
Asphalt Plant IA and Verification Testing
Materials QAP Requirements
Certifications• Special Testing
• Mill Analysis – Steel• Buy America
• Pavement Marking Materials• Same as original sample tested and approved• Harmful chemicals – Lead
• Cement, Concrete Admixtures• Annual
26
LAP Manual Updates
Long Term Performance Tests• Approved Lists• Certifications
• We certified that the material is the same as the original sample MS 12345 that was tested and approved for List XX
• Batch test and/or field test
27
LAP Manual Updates
Performance Test Decks
28Approved List 46Approved List 13
Approved List 17, 20, 73, 74, 75
• Quality Assurance Plans – Approved lists• Precast Concrete Items List 34• Metal, Concrete and Plastic Pipe List 25, 26 and 42 • Asphalt Binder and Emulsions List 50 and 50.1 • Castings – Manhole frames and covers List 61• Monitored by VDOT Materials
• Periodic testing & Inspections
29
LAP Manual Updates
Precast Concrete QA Program
• Item No. – Various - Drop inlets, risers, adjustment rings with QA stamp• Spec. No. – Section 302 of Road & Bridge Specification• Materials Specification Section – 232• Acceptance – Approved List 34 and Stamped Certified Delivery ticket with
statement in accordance with Virginia DOT Precast Concrete QA program 30
LAP Manual Updates
LT Process• Modified Acceptance
• Utilities– Stamped Catalog Cut/Certification
• Electrical– Pre Approved Traffic Engineering List– Stamped Catalog Cut/Certification
• Special Items
31
LAP Manual Updates
Utilities Fire Hydrant
Item No. – Attached or on Plans
Spec. No. – Section 520 of Road & Bridge Specification
Materials Specification - AWWA C502 or C503
Acceptance – Certification or stamped Approved Catalog Cuts 32
Project Documentation and Traceability during Construction• Materials Notebook
• Pay Quantities need supporting documents– Invoices– Inspection Reports– Physical Releases TL-109– Test Reports (TL forms)– Acceptance Tests in Field (TL 13, 28, 58, 59, 60…
141)
33
LAP Manual Updates
Materials Notebook (TL-142)
34
LOCALITY IS RESPONSIBLE FOR TRACKING QUANTITIES AND TESTING FREQUENCIES.
Materials Notebook shall be maintained at the job-site and available for inspection.
LAP Manual Updates
Materials
Notebook
(TL-142)
35
Whoever maintains the project (whether it is VDOT or Locality) must keep the Materials Notebook in the project records for three years after financial
closeout of the project.
LAP Manual Updates
Materials Certifications
36
• Must be backed up by inspections and tests• Must be verified in order to receive payment.
SOURCE OF MATERIALS and MATERIALS NOTEBOOK RESOURCE DOCUMENTS show
how to accept each material.
LAP Manual Updates
SOURCE OF MATERIALS RESOURCE DOCUMENT
37
http://www.virginiadot.org/business/resources/bu-mat-MAT.pdf
On VDOT External WebsiteMaterials Division
Materials Documents and Downloads
Non-Conformance Report
(NCR)
38
Aeris Contracting Co.
Rte 5 Bridge Ext.
VDOT
Fledge McFledgerson
01
0005-123-112,C501
2/8/2015
David Nelson
217.08 (a)
69.5 CY of A3 Concrete for WB pier cap 1 was placed on 2/5/2015. Loads, 3, 4, and 5 were out of tolerance for air (below 4.0).
Air requirement is 6+/- 2, for a range of 4 to 8.
X
Use as is. See attached, Test Report and Results for 2/5/2015 And After Action Meeting and Acceptance Email from QAM
David Nelson
2/16/2015
Darby Darynn
2/16/2015
LAP Manual Updates
Auditing and Nonconformance
Recovery Plan
(AR Plan)
39
LAP Manual Updates
Darby Darynn
Rte 5 Bridge Ext. 0005-123-112,C501VDOT
Fledge McFledgerson
Of the 8 loads of A3 Concrete placed on 2/5/2015, 3 loads were out of tolerance for air. The QC technician misunderstood the requirements for A3 concrete and did not notify the contractor of the results. The QA Inspector was on site but was performing other duties.
After Action meeting, held 2/13/2015, included Aeris Contracting Co. and QC Staff:- Keep the concrete producer rep on site during pour- Show air/slump retests on test reports- Report failing or borderline test results immediately to Engineer- Keep mix design and spec book on site I accept this concrete because:- All A3 Concrete is from the same plant which has so far met 4000 psi at 28 days- Permeability results have also passed thus far- The average air for all 8 loads meets air requirements (4.1%)
CURRENT LAP MANUAL REQUIREMENT
TL-131 (LAP):
Letter of Materials Certification
40
Certifies that:• Acceptance testing of all materials met
specification• All independent assurance samples were within
tolerance of samples used for QC/AT• Certifications and test reports are on file • Signed by the LPA Construction Project Manager
The form must include failed materials and corrective actions taken, including pay adjustments.
41
LAP Manual Updates
LPA Materials related questions should first be directed to the:District Project Coordinator (PC)Construction Project Monitor (CPM)
The PC or CPM will coordinate with:• District Materials Engineer• District Materials QA Manager (Field Operations)
– Approved Ready Mix Suppliers in District– Approved Aggregate Suppliers– Approved Asphalt Suppliers
• District Notebook Person• CO Materials Quality Assurance Section• CO Materials Structures Section
43
PAVING PROJECT EXAMPLE
1,456
1,456
SM-12.5A
1,456 tons of Surface mix were received and placed on a project. No loads were rejected. Approximately two lane miles have been paved.
X
44
PAVING PROJECT EXAMPLE
Go to Appendix 13.2.G Frequency Tables in the LAP Manual.
NUCLEAR DENSITY TEST
• Contractor QC – 20 density test sites
• VST - Obtain 2 cores at one location.
• IA – Observe 2 density tests being performed, obtain control strip cores to reweigh
45
PAVING PROJECT EXAMPLE
Independent Assurance Testing:
Roller Pattern
46
PAVING PROJECTEXAMPLE
Independent Assurance
Testing:
Roller Pattern
47
PAVING PROJECT EXAMPLE
IA and Verification Sampling and
Testing
Depth Checks
Cores
Plugs
48
PAVING PROJECTEXAMPLE
APPENDIX 13.2 - E
Independent Assurance Tolerances
49
PAVING PROJECT EXAMPLE
Go to Appendix 13.2.G Frequency Tables in the LAP Manual.
IN-PLACE DENSITY TEST
• Contractor QC – 1 core
• VST – 1 core• IA – Observe 1
density test per 10 performed by QC, obtain all cores, reweigh 10%, minimum 1 per project.
**NOTE: If items are not in Frequency Tables, then refer to the Materials Manual of Instructions. The District Project Coordinator or Construction Project Monitor will coordinate discussions with the District Materials Engineer or Central office Materials Program Manager.
50
PAVING PROJECT EXAMPLE
LAP Manual Updates
• Outcome of Presentation • What are the major changes being made to the LAP
Manual?• What is the localities’ role in executing an effective
Quality Assurance Plan?• Why is the Acceptance/Verification Process important?• What documentation is needed for Material
Acceptance? • What are some benefits to changes in the LAP Manual?
51
Questions
52
?
LAP Manual Updates
Last Chance…
Materials updates to the LAP Manual sections 13.1 and 13.2 are scheduled to be published by the end of March
Submit any final comments or recommendations to:
• John Simmers ~ 804-786-2571 ~ [email protected]
• Russ Dudley ~ 804-786-6663 ~ [email protected]
53
Locally Administered Projects Manual Updates & Materials Quality Assurance Plan Requirements
March 19, 2015
W. R. Bailey PE
Assistant State Materials Engineer