    Loading Capicity Requirements for Scaffoldings

    Scaffoldings must have sufficient bearing force but can not be damaged by its self loadingcapacity and at least 4 times of calculated force. For safety handrails, hanging cables and wooden

    structures, they will be applied separately:

    Grades of loading forces: loading forces are classified as follows:

    Heavy loading force: applied for scaffoldings with working load of 375 kg/m2 for

    building bricks, stones, and materials placed on the scaffoldings.

    Medium loading force: applied for scaffoldings with working load of 250 kg/m2 for

    people and mortars

    Light loading force: a plied for scaffoldings with working load of 125 kg/m2 for people

    and working equipment.

    Requirements on loading force of peple: Design loading force for scaffoldings is calculated

    basically on one or more than one persons with the weight of 75 kg and 25 kg of workingequipment for each person. Each working platform must have capacity to carry at least one

    person as below regulation:

    Working platform used for one person is sufficiently designed and installed for supporting

    100kg weight place in the middle of working platform.

    Working platform used for two people is sufficiently designed and installed for supporting

    working load of 200 kg, of which 100kg is placed 0.45m from the left side and the rest is placed

    0.45m from the right side of the center line of working platform.

    Working platform used for 3 people is sufficiently designed and installed for supporting 300kg, of which 100 kg is placed 0.45m from the left side, 100 kg in the middle and the rest is

    placed 0.45m from the right side of the center line of working platform.