Load Out Plan

Embed Size (px)

Citation preview

  • 8/10/2019 Load Out Plan

    1/17

    LOAD OUTPLAN/PROCEDURE

    Rev. Status Date Revision memo Issuer Checker Approver

  • 8/10/2019 Load Out Plan

    2/17

    LOAD - OUT PLAN/PROCEDURE

    TABLE OF CONTENTS

    1.0 INTRODUCTION

    2.0 PURPOSE

    3.0 SCOPE

    4.0 DEFINITIONS

    5.0 REFERENCES

    6.0 SAFETY

    7.0 RECORDS AND DOCUMENTATION

    8.0 LOAD TRANSFER TO CARGO BARGE

    9.0 CARGO BARGE

    10.0 BARGE BALLASTING SYSTEM

    11.0 LOAD-OUT PLAN

    12.0 TIE-DOWN AND SEA-FASTENING DESIGN PROCEDURE

    13.0 SAFETY REQUIREMENT

  • 8/10/2019 Load Out Plan

    3/17

    LOAD - OUT PLAN/PROCEDURE

    1.0 INTRODUCTIONCLIENT), acting on its behalf as Technical Partner and on behalf of its partners CONTRACTOR A, andCONTRACTOR B, intend to develop the Akepo Field at OML-90.

    The existing Akepo- 1 well is located at Lat N 05 deg 15 18.837 Long E 05 deg 16 34.894. Thisexploratory well has recently been re-entered, tested and completed. At the present level ofcompletion, the well has been installed with a free standing 30-inch conductor, with a Christmastree at the top end. There is no other structure at the well location presently.

    CONTRACTOR with its partner CONTRACTOR C has been awarded a contract to undertake

    Engineering, Procurement and Construction (EPC) for the design, materials procurement,fabrication / construction, and installation of the Akepo wellhead deck structure, process pipingand its pipelines to tie-in at the Crude Processing Facility (CPF) installed within NAOC BeneboyeFlowstation perimeter.

    The Plan in conjunction with CONTRACTORs HSE Plan shall ensure that Loss Prevention ismaximized during the Load-Out phase of the project.

    The Load-Out activities shall be performed from Onne CONTRACTOR Cs pipe storage toCONTRACTORs Worji Base Yard, where all materials and equipment shall be assembled and

    subsequently loaded out from to project sites via the jetty to the Work/Lay Barge at the openCalabar River using the Utility barges and Trucks.

    Particular emphasis has been made to ensure harmonious Security network within, around, theload-out jetty, Mid River, and en-route Worji, Warri and Offshore.

    2.0 SCOPE2.1 This procedure defines the minimum requirement, methods to be applied and

    equipment to be used during the Load-Out and Sea-Fastening of the Equipment,Facilities, and Pre-fabrication on transportation Truck, Vessel/Craft using Cranes.

    2.2 CONTRACTOR shall use Cranes, Trucks, and Flat top barges to Load-Out all fabricatedstructures.

    3.0 DEFINITIONS3.1 Load-outLoad-out is the process of moving and materials and/or structures from Onne CONTRACTORCs pipe storage to CONTRACTORs Worji Base Yard, Warri and Offshore3.2 Sea-FasteningSea-Fastening is the process of installation of tie-down braces in such a way as to minimizedamage to the Linepipes, Equipment or Structure on the vehicle or water craft to provide a

    safe tie-down system during Load-out.

    4.0 REFERENCES

  • 8/10/2019 Load Out Plan

    4/17

    The following CONTRACTOR C approved Specifications, Industry Codes, Standards, &Recommended Practices shall be followed during the Load-out operations of the offshorestructures.

    4.1 CONTRACTOR C Job Specifications, Project AFC Drawings, and Contract.4.2 American Petroleum Institute API RP 2A; Recommended Practice for

    Planning, Designing, and Constructing Offshore Petroleum Platforms. 4.3 American Welding Society AWS D1.1 Steel; Structural Welding Code. 4.4 VESLs QA /QC Plan and other Procedures.

    5.0 RECORDS & DOCUMENTATION

    During the load-out and sea-fastening, all daily reports, logs, reports, etc. shall be prepared,compiled, and retained by VESL.

    These documents shall record, also, any deviations from the original plan, all un-usualenvironmental conditions that may occur.

    At the completion of the Load-out Operation, CONTRACTOR,s QA/QC Department shall deliver tothe CONTRACTOR C these documents in a form suitable for permanent record.

    6.0 RESOURCES

    As a minimum requirement, the following list of manpower, tools and equipment shall be provided

    by VESL for execution of this works.

    6.1 RESOURCES

    6.1.1 Logistics support equipment.

    S/N DESCRIPTION UNIT CAPACITY QTY REMARK

    1 CARGO BARGE Pc 1000ton 1

    2 CREW BOAT Pc 150HP DS 1

    3 TUG BOAT Pc 400HP DS 1

    6.1.2 Load-Out Jetty key equipment/tools.

    S/N

    DESCRIPTION UNIT CAPACITY QTY REMARK

    1.0 Crawler Crane No 100 - 150ton 1

    2.0

    Utility Barge No 800 1500ton 13.0 Hydraulic Crane No 25 - 50ton 14.0 Trailer / Tractor No 30ton 105.0 Self Loader Truck No 3ton 36.0 Mechanical tool boxes set various 3

  • 8/10/2019 Load Out Plan

    5/17

    7.0 Chain Block No 5ton 48.0 Pick-Up Van No 3ton 19.0 Saloon Car No 2.0 210.0 Flat Back Wagon No 10T 1

    7.0 PERSONNEL LIST & RESPONSIBILITIES

    7.1 Personnel ListThe personnel listed below are essential to the safe and successful performance of theoperation.

    They shall attend the briefing meeting prior to the beginning of the operation. Project Manager Construction Superintendent Construction Supervisor Logistics Manager Equipment Engineer. QA/QC Engineer CASHES Officer Logistics Superintendent Lifting Supervisor Barge Superintendent Chief Barge Engineer Foremen

    Crane Operators Riggers Drivers Security ( SECURITY)

    7.2 RESPONSIBILITIESThe Responsibilities of the activity personnel are described here below:

    7.2.1 Project Manager.The Project Manager shall ensure that all activities are carried out in accordance withCONTRACTORs Quality, CASHES and CONTRACTOR C approved Standardconstruction specification and other applicable codes and standards, reporting to theProject Director.However, he shall be directly responsible to ensure:a) The adoption of safe working procedures including safe place of work.b) The establishment of CASHES Management system implementation program.c) Auditing of programme and plans to measure progress and identification of

    deficiencies.d) Adequate training of personnel to improve their safety at work.e) That adequate Liaison with Corporate CASHES Management for specialist advice

    is carried out.

    f) Selected Sub-contractors are able to meet company standards.g) Those deficiencies in equipment, standards, operating procedures or training are

    corrected.h) Promotion of a high degree of safety and environmental awareness by personal

    example.

  • 8/10/2019 Load Out Plan

    6/17

    i) All accidents are reported and investigated according to company proceduresand CONTRACTOR C requirements.

    7.2.2 Construction SuperintendentConstruction Superintendent shall perform the following duties: Draw up a sound Load-Out schedule consistent with the over all philosophy for

    the project construction execution plan. Liaise with the Project Manager and logistic team to reduce interface problems. Ensure the mobilization team is well orientated on the relevant Procedures and

    Safety Precautions that must be followed. Co-ordination and control of the mobilization operation to ensure continuous

    workflow and high productivity Monitor and review progress made and revise activity schedule to recover lost

    times if any. Draw up exhaustive equipment, materials, and tools checklist to be mobilized for

    site works.

    7.2.3 Construction SupervisorThe Construction Supervisor shall perform the following duties:- Follow up the loading activity to ensure that all the materials, equipment and

    tools loaded are according to schedule. Monitor progress and in consultation with Construction Superintendent draw up

    a revised program to keep the mobilization operation on course. Keep the mobilization team abreast of the materials handling and personnel

    safety as per work instructions.

    7.2.4 Logistics ManagerThe Logistics manager shall be responsible for the overall Logistics activities:He shall execute the following duties:

    Interface with the CONTRACTOR C's Rep on Logistics issues Ensure that this procedure as approved by CONTRACTOR C is made available on

    site for implementation Ensure that necessary PPE s are provided and utilized on site Ensure equipment/tools and load-out materials are on site on time and at right

    quantities Supervise the deployment of various categories of workers to different positions

    of the work area. Monitor the activities at different points and stages. Promptly report progress/difficulties to the Project Manager. Brief the Logistics Superintendent on all items of work to be carried out. Shall ensure that all safety measures are implemented.

    7.2.5 Logistics SuperintendentThe Logistics Superintendent shall report directly to the Logistics Manager.He shall be responsible for the following duties:-

    Co-ordinate all load-out and Sea-Fasting activities. Brief all Foremen on all items of work to be carried out. Ensure that all safety measures are implemented.

    7.2.6 Lifting Supervisor.

  • 8/10/2019 Load Out Plan

    7/17

    The Lifting Supervisor shall report directly to the Logistics Superintendent.He shall be responsible for the following duties:- Ensure all necessary equipment/tools are on site in the right quantity and

    capacity. Assemble the required equipment on site. Test and certify all equipment prior to commencement of the operation. Initiate, monitor and record the operation. Ensure that all items of work -load-out and Sea-Fasting- are carried out. Prepare report of the operation. Shall ensure that all safety measures are implemented.

    7.2.7 CASHES Officer.The CASHES Officer shall reports to the CASHES Manager.He shall be responsible for the following duties:- Obtaining the appropriate permit to work from CONTRACTOR C, Ensure that all necessary safety requirements for a successful job are met. Manage the health and safety functions of the activity. Manage the safety engineering function of the activity. Support and advise the project Team on health and safety of personnel. Introduce Safety notices, bulletins and posters at site. Contribute to the planning and implementation of risk assessment and control

    measures and contribute to the implementation of selected risk control andmitigation measures.

    Ensure that the Emergency Response Procedure is effectively drilled into theworkforce.

    Review all accidents and incidents report and remedial actions. Liaise with CONTRACTOR C Safety Representatives. Liaise with the CASHES Manager.

    7.2.8 QA/QC EngineerThe QA/QC Engineer shall: Ensure that the contents of this QA/QC Plan/Procedure are well understood and

    adhered to by all project personnel. Verify the implementation of this QA/QC Plan/Procedure and evaluate its

    adequacy, by means of monitoring and auditing the work performance in respectto the established quality objectives.

    Manage the Quality engineering function of the activity. Support and advise the project Team on quality of work.

    8.0 LOAD-OUT PLAN

    CONTRACTORshall be responsible for the following:- The Load-Out of the Line pipes, fabricated Structures, Piping Spools and shipped loose

    items onto Transportation Trucks, Barge or Vessel. Providing and installing Lifting Slings and Rigging Platforms for Load-Out. Ballast calculation and ballasting the transportation Barge or Vessel as required for

    Load-Out. Provision and pre-installation of Lifting Slings and Rigging Platforms for all structural

    items be by. Sea-fastening and Tie-down design shall be the responsibility of CONTRACTOR.

    Transportation analysis shall also be the responsibility of CONTRACTOR.

  • 8/10/2019 Load Out Plan

    8/17

    Ballasting the Transportation Barge or Vessel as required for transportation.CONTRACTOR shall provide the Barge or Vessel Ballasting Plan.

    A comprehensive List shall be compiled for all ship loose items on the Trucks, andBarges. This List shall also act as a checklist to ensure that all required items have beenplaced on the Trucks, and/or Barge.

    The ship-loose List shall contain the following information:- Structure Description.- Quantity.- Location on Truck, or barge (boxed or otherwise).

    8.1 Load-Out PreparationsVESL shall be responsible for the Load-out & Sea-Fastening Operations and shall prepare forthe steps as follows:-

    8.1.1 Prepare Loaded out items list (by Construction Superintendent).8.1.2 Make the necessary documentation, Procedures, Manuals available for

    CONTRACTOR C, Other Contractors, Third Party, and Work Force.8.1.3 Prepare the load-out arrangement in the Fabrication Yard, including clean way

    for Trailers.8.1.4 Preparation of Truck, and/or Barge Deck for Cargo.8.1.5 The Transportation/Installation Contractor(s) shall make available to

    Fabrication Supervisor all necessary Logistics spread that meets allrequirements for Trip & Tow Certification. Also, to provide the LogisticsSurveyor.

    8.1.6 All mooring hardware shall be ready at the quay.8.1.7 The barge ballasting system (pumps, headers, valves, hoses, etc.) must be

    capable of compensating the changes in tide, and barge load (weight)application.

    8.2 Load Out Sequence8.2.1 Plant and EquipmentAfter pre-mobilsation inspection and certification of all Plant and Equipment they shallbe moved from their various locations to the Load-Out yard at WORJI CONTRACTOR sBase Yard, prior to transfer to Work Sites and Work/Lay Barge.

    8.2.2 Prefabricated Items

    All prefabricated Structural Members, Linepipes, and Piping Spools shall be properlytagged and arranged according to their specific work areas/scope at WORJI Base Yardprior to transfer to Work Sites and the Work/Lay Barge.

    8.2.3 Free Issue Materials & EquipmentAll CONTRACTOR C free issue Items shall be moved from Kidney Island warehouse toVESLs WORJI Yard/Jetty using Carnes, Trailer/Trucks, for subsequent transfer to WorkSites and the Work/Lay Barge

    8.2.4 Personnel

    All personnel shall be transported to site by CONTRACTOR C air operations from PortHarcourt.

    Movement between the Jetty and Work/Lay Barge shall be by personnel carrier boatescorted by the Security boat.

  • 8/10/2019 Load Out Plan

    9/17

    8.2.5 Rigging & Lifting8.2.5.1 Lift PlansClear and concise Plans for any lift in the Fabrication Yard in course offabrication and erection shall be submitted to the Project Manager for reviewand approval prior to any lifting operation

    8.2.5.2 Weight of StructuresDuring the course of Fabrication activities, the assigned Project Engineer shallmonitor the weights of the individual structures. These weights shall becompiled from the theoretical weights of each individual section. Thisinformation shall be analyzed prior to the commencement of any lift.

    8.2.5.3 Certification of Lifting Equipment & SlingsLifting equipment shall be load-tested to confirm the lifting capabilities ofsuch equipment. All slings, shackles to be utilized on lifts shall also be

    Certified and accompanied by Certification Documents.

    8.2.5.4 Inspection of Rigging InstallationAfter rigging has been completed on any unit, the designated QC Inspectorshall ensure that all rigging has been implemented in accordance with theprovision of the pre-approved Plan and Job Safety Analysis, and that all itemsare properly installed.

    8.2.5.5 Lifting Tackle RequirementLifting tackle shall meet the following requirements:-8.2.5.1.1 Minimum Factor of Safety for slings and shackles shall be

    4.08.2.5.1.2 Attachment of each sling to its lift point shall be with a

    shackle and a pin to a pad eye. Only one sling shall beconnected to any one shackle.

    8.2.5.1.3 Slings in a loaded condition shall not bear against any partof the component being lifted.

    8.2.5.1.4 Slings intended for use on lifts exceeding 100 Short Tonsshall have a history of their past usage. When required, anIndependent Agency shall certify that each sling is capableof handling the forces anticipated during each lift.

    8.2.5.1.5 Slings intended for use on lifts not exceeding 500 ShortTons, need not be Re-Certified for the Work, if these havebeen certified within one (1) year of the date of theirplanned use.

    8.2.5.1.6 The Certification Documents shall include the measuredlength of the sling from the inside of one eye to the insideof the other eye. Length shall be measure with the slingunder axial tension of 5% of its Safe Working Load.

    9.0 LOAD TRANSFER TO CARGO BARGE

    9.1 During load-out, the cargo barge behavior shall be monitored.

  • 8/10/2019 Load Out Plan

    10/17

    *All structures shall be loaded to the cargo barge by Crane.*

    9.2 The data contained in the Cargo Barge Ballast Tables shall be adjusted one dayahead of the load-out according to the tide observation during 72 hours.

    9.3 These corrective measures shall revise the River Bar tide table.

    10.0 CARGO BARGE

    A cargo barge shall be furnished to carry the fabricated structures, materials and Equipment, fromthe Fabrication Shop / Jetty Yard to the installation Site.

    The cargo barge shall be brought Stern to Quay and held secured on the mooring hardwarealready at the quay.11.0 BARGE BALLASTING SYSTEM

    11.1 IntroductionThe Barge Ballasting system consists of the followings:

    High capacity, low head, diesel driven, multi stage centrifugal pump(s). Suction Hoses, foot valves, & strainers. Discharge Header; containing:-

    - Header Pipe.- Tees.- Butterfly Valves.- Discharge Hoses.

    The Ballast Pumps, and the header / manifold (c/w valves) shall be installed onboard an800hp Tug Boat.

    Suitable hoses (c/w quick couplings) shall be used for water distribution.

    This shall help in giving room on barge deck, and improving pump NPSH.

    11.2 Ballasting Sequence

    i) Pre-ballasting

    a. Pre-ballasting of the barge shall be done using external pumps. This shall helpachieve zero trim and heel before load-out

    b. During the filling of the tanks, all pumps shall be tested so capacity of eachpump can be checked against the rated capacity. During this phase also thepumps which are pumping out shall be tested.

    c. The tank fillings shall be according to the pump schedule of the ballastprocedure.

    d. Water level at each tank shall be measured.ii) Preparations

    a. During pre-installation of the Ro-Ro ramps, the barge shall be leveled using the

    external pumps.b. Required pump capacity is subject to detailed barge features.

    c. Water level and tide shall be monitored on a gauge located at the load-outquay. Tide gauge monitoring shall start 3 days before Load Out date.

    iii) Monitoring ballasting during Load Out.

  • 8/10/2019 Load Out Plan

    11/17

    a. Sufficient mooring lines shall be installed to keep the barge within thetolerances

    b. Barge movements limitations:

    c. - Movement of barge in rolling direction: Subject to barge use- Movement of barge transverse to rolling skid direction: Subject to barge use

    iii) Monitoring ballasting during Load Out (contd.)

    d. During the load out the alignment of the barge shall be monitored.

    e.

    Due to limited inclination forces, the heel of the barge shall be monitored andcorrected if the inclination reaches 0.5%. The monitoring shall be done by

    means of a water level with a length of 30 mt from one side of the barge tothe other.

    f. In the same way the trim of the barge shall be monitored and corrected if theinclination reaches 0.5%.

    g. The level of the barge in relation to the quay edge shall be monitored with twogauges from the quay edge.

    iv) Ballasting of barge during Load Out

    a. The load out of the structures shall be done by crane

    b. The barge shall be ballasted during the load out according to the pump-schedule, which is based on the ballast calculation.

    c. The ballasting shall be carried out with external pumps.

    d. Water level @ each tank shall be measured

    11.3 Mooring AncillariesMooring system shall consist of the following minimum components:- Two sling wires tied to jetty mooring cleats.- Trucks (or Caterpillar crawler tractors) shall pull the said sling wires via turnbuckles.- Ocean going Tug Boat (Pusher) at the bow side of the Cargo Barge.

    12.0 TIE-DOWN & SEA FASTENING PROCEDURE

    12.1 TIE-DOWN The Truck and/or Barges characteristics, Sea and/or Road States , the structures position on the Truck and/or Barge and CONTRACTOR C requirement shall be considered during the

    planning of theTie-Down and Sea-Fastening process.

    The tie-down braces shall be located on the barge in such a way as to minimize installationand removal time, material requirement and damage to the equipment or structure and yetto provide a safe tie-down system.

  • 8/10/2019 Load Out Plan

    12/17

    12.2 SEA FASTENING VESL shall fabricate and install the Sea Fastening for the fabricated Structures and Shippedloose items onto the Transportation Truck and Barge supplied by CONTRACTOR.

    All Sea Fastening welds shall be classified as temporary welds in accordance with the

    Structural Welding and Inspection Specification.13.0 SAFETY REQUIREMENT

    Before the commencement of the Load-out operation, a Safety Meeting shall be held with the teaminvolved.

    This meeting shall brief to all concerned the load-out procedure, the associated emergencies,possible causes of Accidents, Near Misses, Unsafe Acts , and conditions noted from similaroperations.

    The dedicated Safety Officer shall cover the Load-out Operation activities.

    Also, a special transport / ambulance shall be standing-by during the Works.

    A detailed Job Safety Hazard Analysis shall be discussed.

    All personnel to be engaged for this work shall be mobilized and properly inducted, usingWorkbooks and Videotapes as Teaching Aids.

    This shall enable the workers appreciate the hazards involves in the offshore operations.

    The following sign shall be observed during the Load-out:- READ & STUDY THIS PROCEDURE CAREFULLY, DO NOT HESITATE TO ASK IF YOU NEED

    ANY CLARIFICATION

    LISTEN CAREFULLY DURING LEAD-OUT SAFETY MEETING

    WATCH CAREFULLY THE SURROUNDING ENVIRONMENT AND FOLLOW THE WORKSITE SAFETY INSTRUCTIONS

    USE INTERNATIONAL RIGGING SIGNALS

    DURING LOADOUT, A LOADOUT MASTER RADIO CHANNEL IS ASSIGNED DO NOT USE ITFOR OTHER COMMUNICATIONS

    IN CASE OF EMERGENCY, CALL THE AVAILABLE

    13.1 Safety Measures To Be Put In Place.13.1.1 Position adequate fire extinguishers

    13.1.2 Position fire water pumps.

    13.1.3 Continue gas monitoring.

    13.1.4 Position fire blankets.

    13.1.5 Install safety signs.

    13.1.6 Install barricade where handrails are removed.

    13.1.7 Good house keeping.

  • 8/10/2019 Load Out Plan

    13/17

    13.2 Personal Protective Equipment. (PPE)Safety wears shall be provided as appropriate to the working conditions at site.

    Thus, Coveralls for all workmen,; Safety helmets, Safety boots and protective gloves to allworkmen handling heavy, sharp, awkward or hot materials or equipment; Safety goggles

    whenever grinding and blasting or other activity which could cause damage to the eyes isinvolved.

    Note: Personnel Protective Equipment shall be worn at all times within the lifting areaand vicinity.

    The PPEs shall include: Safety Boot, Coverall, Safety Glasses, Hand Gloves, Life Jackets, Helmet, Safety Harness, Ear Defender (Muff)

    13.3 Safety OfficerThe dedicated Site Safety Officer shall cover all work on the sites.

    The Safety Officer shall ensure that:All equipments are pre-mobilized by CONTRACTOR C i.e. Cranes, Barges/Vessels,

    welding machines,

    compressors, boats, etc

    All lifting equipment are tested, certified and inspected.

    Records of all inspection are kept and given to authorized personnel when demanded

    All lifting equipment are colour coded and their safe working load displayed

    Danger signs and barriers are positioned around lifting areas

    Cranes are use within their rated capacities at the required radius of liftSafety boat stands by throughout the operation

    Appropriate to PPE is used at all times i.e. safety harnesses & the personnel on the platformuse work vests.

    13.4 Fire Protection Equipment

    13.4.1 The Fire Protective Equipment shall include but not limited to the following:

  • 8/10/2019 Load Out Plan

    14/17

    S/No. FIRE PROTECTION EQUIPMENT SITE LOCATION

    1. 0 C02 Welding and Electrical work areas

    2. 0 Sand Buckets All areas

    3. 0 Dry chemical Powder (DCP) Heavy equipment area.Flammable materials storage area.

    4. 0 Fire Hoses/Nozzles Where required

    Standby firewater pumps/personnel are in place and shall be used asrequired for critical tie-ins and other hazardous operations in thefacilities.

    Workers shall be taken through induction courses on fire hazards,fighting, prevention and protection.

    Periodic fire drills shall be organized on site. Fire muster points shall be designated at every work place.

    13.5 Medical Coverage.All medical evacuation shall be as per the medical evacuation procedure.

    The operations shall be carried out in a manner that shall prevent health problems to thestaff and others, and give health of staff adequate attention backed up with requiredresources.

    All workers shall be medically certified fit to work at the site. The result and data

    obtained by medical examination shall be suitably recorded and kept for reference.The health, safety and environment of the workers shall be properly safeguarded toavoid injuries and illnessSite Clinics shall be located on each Barge. These shall be fully equipped withessential drugs, with qualified Nurses in charge.Any illness that could not be handled by the site Clinic shall be referred to thecompany retainer Clinic in Port Harcourt.Medivac shall be available to convey any victim to the nearest affiliated clinic shouldthere arise an emergency.All injuries/illnesses shall be recorded in the First Aid register and also treated as anaccident reported through normal lines of reporting.All Catering staff to be engaged in the catering services on the project shall undergothorough medical examination and certification before commencing the job.

    13.6 Warning and Caution SignsAdequate number of specific warning and caution signs shall always be displayed.

    This shall include but not limited to:-Men at Work

    Muster pointWork in ProgressNo AccessNo SmokingToxic/Flammable liquids

  • 8/10/2019 Load Out Plan

    15/17

    Radiography in progressHard Hat and Helmet areaEar defender MUST be wornOthers as required.

    13.7 Gas TestingGas Detection Tests shall be carried out before any hot work, and shall be carried out byVESL, with a nominated CONTRACTOR Crepresentative witnessing and approving.

    Gas tests shall be continued throughout the course of the work where explosive gas build-up is suspected and the frequency and range of such tests shall be to the approval of theCONTRACTOR C Representative.

    No hot work shall be undertaken if the results of the gas tests show a level of gasconcentration that could constitute hazards.

    The Supervisor shall be held responsible and accountable for ensuring that no workcommences at such site without the required tests being performed.

    13.8 Swimming Test/CertificationEvery Personnel engaged in these operations should undergo Personal Survival SwimmingTest and Certification.

    All employees that shall be engaged in this project shall undergo medical fitness test prior toswim test and mobilization offshore.

    Arrangement shall be worked out with the Responsible Department to use CONTRACTOR Cfacility in

    Port Harcourt for the certification.

    13.9 Hazard Management SystemHazards on the project shall be identified and documented by the site Safety Officers.

    Hazard Management Forms shall be used in recording all types of Unsafe Acts/UnsafeConditions, health, Pollution, Environmental disorders, Security lapses as well as potential

    HSE hazards on a daily basis.The Safety Officer and Site Supervisor shall rectify the observed unsafe acts/conditionsimmediately. Daily copies shall be submitted to the Project Manager and CONTRACTOR CRepresentative.

    13.10 CASHES Meeting.

    13.10.1 Project CASHES meeting.The Project CASHES meeting shall be held bi-weekly and shall be chaired by theProject Manager or his designate.

    The meeting is intended to be a forum for the discussion of CASHES issues.

    All Managers, Supervisors and Superintendents present at site shall attend thismeeting.

  • 8/10/2019 Load Out Plan

    16/17

    This meeting shall be documented with minutes and all parties or individualsrequiring completing these action points named as action parties.

    The minutes of this meeting form the basis of communication downward throughthe general CASHES meeting as well as upward to the company wide CASHESmeeting.

    13.10.2 Unit level meeting.The unit level CASHES meetings shall be held weekly and shall be chaired by thesupervisor in charge of the unit.

    The meeting is intended to be a forum for the discussion of CASHES issues.

    All employees must attend these meetings. These meetings shall be documented

    with general topics noted.The meeting forms the basis of communication from the supervision level to theworker as well as upward to the project CASHES meeting.

    13.10.3 Morning unit meeting.The morning unit meetings shall be held daily. The meeting shall be chaired by theunit leader lasting not longer than 15 minutes.

    The purpose of the meeting is both safety of the worker at the tool handling level aswell as organization of the work on daily basis.

    The topic of the discussion shall be the days operations and to highlight the majorhazards which shall be encountered.

    13.10.4 On-the-job task meeting.On-the-job task meeting is the most important link in the CASHES communicationsystem.It is the responsibility of all supervisory personnel to address any hazardoussituations they envisage in the task to be perform and to inform workers under theirsupervision of the appropriate actions to pursue to alleviate these hazards.

    Also, it is the responsibility of any employee who perceives a situation to behazardous to notify his supervisor immediately.

    13.10.5 Accident Reporting.Every worker, working under this project shall immediately report to hisSupervisor/Foreman or Safety officer, any accident which occur to him, his fellowemployee/or any machinery/ equipment in his position of work.

    The Supervisor/Foreman and the Site CASHES Officer shall visit the accident sceneimmediately, with those involved to obtain information for Accident InvestigationReport Form.

    All accidents involving lost time injury or loss of equipment shall be immediatelyfollowed by stoppage of work on the area. Work shall only resume when the area isadjudged safe and all situations put under check.

  • 8/10/2019 Load Out Plan

    17/17