    List of Major Permits and License Required During Construction

    Sl.No

    Clearance Agency Agency

    1

    .

    Right of way for all

    corridors to the Facility.

    Sate Government /

    Concerned Agency

    Required to obtained by

    Project Company

    2.

    Consent for thedevelopment of Projectsite

    Local Panchayet Required to obtained byProject Company

    3.

    Boiler & other pressurepart pipes & valveswithin purview of IBR

    The Chief Inspectorof Boilers

    Will be obtained byContractor(s)

    4.

    Electrical Plant andEquipment installation(pre & post)

    The Chief ofElectrical Inspector,Sate Govt.

    Will be obtained byContractor(s)

    5.

    Pre & Post installationapproval for buildings,pipe racks layout, cableroutes racks, acid andother chemical storage

    The Chief Inspectorof Factory, localmunicipality/Concern Authorities.

    Will be obtained byContractor(s)

    6.

    Fire Fighting/ Protectionsystem/Electricalsystem

    Tariff AdvisoryCommittee / LossPreventionAssociation (LPA)

    Will be obtained byContractor(s)

    7.

    Chlorine storage Chief Controller of Explosive, Nagpur

    Will be obtained byContractor(s)

    8.

    Fuel oil storage tank Chief Controller ofExplosive, Nagpur

    Not Required

    9.

    Approval of stack airemission levels(excluding groundconcentration)

    State PollutionControl Board,Inspector ofChimney

    Required to obtained byProject Company

    10.

    No Objection Certificate(NOC) for Storm Waterdrainage, fromconcerned authorities

    MunicipalCorporation:Executive Waterdrainage Design

    Will be obtained byContractor(s)

    11.

    Collection, storage &disposal of waste,effluent

    State PollutionControl Board Required to obtained byProject Company

    12.

    Site clearances, SafetyReport and Safety Audit

    State PollutionControl Board

    Required to obtained byProject Company

  • 8/6/2019 List of Permits and Clearences Construction

    2/3

    Sl.No

    Clearance Agency Agency

    13.

    Switchyard State ElectricityBoard/ CEA/ CEIG

    Will be obtained byContractor(s)

    14.

    Lift & Cranes Lift Inspector Will be obtained byContractor(s)

    15.

    Use of wireless set andallocation of frequencyof wireless

    ConcernedAuthorities, Wirelessadvisor to Govt. ofIndia

    Will be obtained byContractor(s)

    16.

    Clearance for StackObstruction Light

    Directorate of CivilAviation

    Will be obtained byContractor(s)

    17.

    Permission for Hook upwith GPS of Masterclock system

    Relevant Authorities Will be obtained byContractor(s)

    18.

    License for constructionlabour pursuant toContract Labour(Regulation & Abolition)Act 1970

    LabourCommissioner,State Govt.

    Will be obtained byContractor(s)

    1

    9.

    Registration of workers

    required pursuant tosection 2A of EmployeeState Insurance Act1984

    Labour

    Commissioner,State Govt.

    Will be obtained by

    Contractor(s)

    20.

    Consent of Collector ofExplosives to thepossession and use ofexplosives for thepurpose of blasting.

    Home Department,State Govt.

    Not Required

    21.

    Approval of temporaryconstruction powerlines within plant area

    ElectricalInspectorate, StateGovt.

    Required to obtained byProject Company

    22.

    Road/ Rail permit fortranspiration ofmaterial to Facility site

    ConcernedAuthorities

    Required to obtained byProject Company

    23.

    Use of Minerals andnatural aggregates forcivil works

    Dept. of Mines &Geology, Sate Govt.

    Not Required

  • 8/6/2019 List of Permits and Clearences Construction

    3/3

    Sl.No

    Clearance Agency Agency

    24

    .

    Permission for labourcamp

    ConcernedAuthorities

    Will be obtained byContractor(s)

    25.

    Work permit forexpatriate personnel

    ConcernedAuthorities

    Will be obtained byContractor(s)