THIS VIEW IS LOOKING NORTH WEST AT THE BUILDING PAD. PAD IS WET DUE TO RECENT RAINS.
THIS VIEW IS LOOKING NORTH WEST AT THE BUILDING PAD. PAD IS WET DUE TO RECENT RAINS.
THIS VIEW IS LOOKING NORTHEAST AT THE BUILDING PAD. SURVEYORS ARE SETTING THE CORNER PINS FOR
THE BUILDING.
THIS VIEW IS LOOKING NORTHEAST AT THE BUILDING PAD. SURVEYORS ARE SETTING THE CORNER PINS FOR
THE BUILDING.
Santa Maria Elementary SchoolSanta Maria Elementary School
Construction Committee MeetingConstruction Committee Meeting
Tuesday, December 11, 2001Tuesday, December 11, 2001
PLUMBING SUBCONTRACTOR TRENCHING FOR THE INSTALLATION OF PLUMBING LINES.
PLUMBING SUBCONTRACTOR TRENCHING FOR THE INSTALLATION OF PLUMBING LINES.
THE PLUMBING LINES PREFABRICATED ON SITE FOR INSTALLATION IN THE PLUMBING TRENCH.
THE PLUMBING LINES PREFABRICATED ON SITE FOR INSTALLATION IN THE PLUMBING TRENCH.
Dovalina Elementary SchoolDovalina Elementary School
Construction Committee MeetingConstruction Committee Meeting
Tuesday, December 11, 2001Tuesday, December 11, 2001
VIEW LOOKING NORTH WEST AT THE CONCRETE FOUNDATION. MASONRY BLOCK WALLS BEING
CONSTRUCTED.
VIEW LOOKING NORTH WEST AT THE CONCRETE FOUNDATION. MASONRY BLOCK WALLS BEING
CONSTRUCTED.
SOUTHEAST VIEW OF THE COMPLETED FOUNDATION SYSTEM.
SOUTHEAST VIEW OF THE COMPLETED FOUNDATION SYSTEM.
Project:Christen Middle School
Architect: Sepulveda Associates Architects, Inc.
Status: Design Development
Budget: $7,193,380.
Timeline:
Start of Final Design Phase: Jan 2002
Present Final Contract Dwgs: Mar 2002
Completion of Construction: Dec 2003
Project: Martin High School
Architect: Sepulveda Associates Architects, Inc.
Status: Design Development
Budget: $7,823,946.
Timeline:
Start of Final Design Phase: Dec 2001
Present Final Contract Dwgs: Feb 2002
Completion of Construction: May 2003
THIS VIEW IS LOOKING SOUTH EAST AT THE BUILDING PAD.
THIS VIEW IS LOOKING SOUTH EAST AT THE BUILDING PAD.
EXISTING CITY SEWER LINE BEING REROUTED. NEW SEWER LINE BEING INSTALLED.
EXISTING CITY SEWER LINE BEING REROUTED. NEW SEWER LINE BEING INSTALLED.
Project: K.Tarver Elementary School
Architect: Cavazos & Associates Architects
Status: Design Development
Budget: $ 4,606,191.00 Dlls.Timeline:
Start of Final Design Phase: Feb 2002
Present Final Contract Dwgs: April 2002
Completion of Construction: June 2003
THIS VIEW IS OF THE PAD PREPARATION FOR THE NEW PORTABLE CLASSROOMS.
THIS IS A SOUTH EAST VIEW.
THIS VIEW IS OF THE PAD PREPARATION FOR THE NEW PORTABLE CLASSROOMS.
THIS IS A SOUTH EAST VIEW.
NORTH EAST VIEW OF THE PAD PREPARATION FOR THE PORTABLE BUILDINGS.
NORTH EAST VIEW OF THE PAD PREPARATION FOR THE PORTABLE BUILDINGS.
Project: J.C. Martin Elementary School
Architect: Ashley Humphries & Sanchez ArchitectsStatus: Preliminary Design
Budget: $1,997,044.
Timeline:
Start Design Development : Feb 2002
Start of Final Design Phase: April 2002
Present Final Contract Dwgs: June 2002
Completion of Construction: Aug 2003
Project: Lamar Middle School
Architect: Cavazos & Associates Architects
Status: Final Design Phase
Budget: $ 7,358,620.
Timeline:
Start of Final Design Phase: Aug 2001
Present Final Contract Dwgs: Feb 2002
Completion of Construction: June 2003
THIS IS A VIEW LOOKING WEST AT THE CANOPY ON THE SOUTH END OF THE PORTABLE BUILDING.
THIS IS A VIEW LOOKING WEST AT THE CANOPY ON THE SOUTH END OF THE PORTABLE BUILDING.
THIS VIEW IS LOOKING NORTH ALONG THE NEW SIDE WALK FOR THE STUDENTS.
THIS VIEW IS LOOKING NORTH ALONG THE NEW SIDE WALK FOR THE STUDENTS.
THIS VIEW SHOWS THE FENCING ON TOP OF THE EXISTING BLOCK WALL.
THIS VIEW SHOWS THE FENCING ON TOP OF THE EXISTING BLOCK WALL.
Project: Daiches Elementary School
Architect: Turner Hickey & Associates, Inc.
Status: Design Development
Budget: $5,191,225.Timeline:
Start of Final Design Phase: Dec 2001
Present Final Contract Dwgs: March 2002
Completion of Construction: April 2003
Project: Heights Elementary School
Architect: Pending
Status: Pending
Budget: Pending
Timeline: Pending
Project: Santo Nino Elementary School
Architect: Frank Architects Inc.
Status: Final Design Phase
Budget: $5,191,225.
Timeline:
Start of Final Design Phase: Sept. 2001
Present Final Contract Dwgs: Jan 2002
Completion of Construction: March 03
Project: Kawas Elementary School
Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase
Budget: $4,211,386.
Timeline:
Start of Final Design Phase: July 2001
Present Final Contract Dwgs: Oct 2001
Completion of Construction: Dec 2002
Project: H.B. Zachry Elementary School
Architect: Design Group International, Inc.
Status: Construction Documents Phase
Budget: $1,456,725.Timeline:
Start of Final Design Phase: Oct 2001
Present Final Contract Dwgs: Dec 2001
Completion of Construction: Dec 2002
Project: H. Ligarde Elementary School
Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase
Budget: $3,388,153.
Timeline:
Start of Final Design Phase: Oct 2001
Present Final Contract Dwgs: Dec 2001
Completion of Construction: Dec 2002
Project: Cigarroa Middle School
Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase
Budget: $3,314,867.Timeline:
Start of Final Design Phase: July 2001
Present Final Contract Dwgs: Dec 2001
Completion of Construction: June 2003