Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Iona Island Wastewater Treatment Plant ProjectsREVISED DESIGN CONCEPT
48468925Liquid Waste Committee, November 4, 2021
Cheryl Nelms, P.Eng., Ph.D.GENERAL MANAGER, PROJECT DELIVERY
Brett Young, M.Sc., MBA, P.Eng.DIRECTOR, IIWWTP PROGRAM, PROJECT DELIVERY
5.1
Peter Navratil, P.Eng.,MPAGENERAL MANAGER, LIQUID WASTE SERVICES
Liquid Waste Committee
AGENDA
2
1. Background2. Expert Panel Recommendations and Options Evaluation3. Revised Design Concept4. Public and First Nation Engagement5. Regional Park Impacts and Benefits6. Next Steps to Finalize Project Definition Report (PDR)7. Recommendation
Liquid Waste Committee
STAGE GATE PROCESS
3
Iona Island WWTP Projects
Liquid Waste Committee
Background
Liquid Waste Committee
JULY 2020 DESIGN CONCEPT
5
Evaluation of three alternate concepts for upgraded WWTP(not just a comparison of treatment technologies)
What’s changed since then?• Further work on constructability, cost
estimates, risks, and schedule• Ground improvement cost
assumptions changed materially • Costs and risks of interim solids
handling addressed in fall 2020 study
Challenges identified in July 2021
Information Report
Liquid Waste Committee
July 2021 Information ReportCHALLENGES IDENTIFIED
6
Solids handling • Interim trucking sludge to other WWTP for ~ 7 years
Constructability • Limited working space and flexibility in contract packaging
Schedule • Compliance with regulatory deadline ~2034 (4 years late) • Completion of solids treatment facilities ~ 2041
Capital costs • $6.7B in 2021 dollars• $10.4B with escalation and risk reserve
Rendering showing July 2020 Design Concept
Liquid Waste Committee
July 2021 Information ReportADDRESSING CHALLENGES
7
• Steps to Address Challenges• Value engineering• Expert panel challenge review• Identify and evaluate options• Structured decision making
• Revised Design Concept• Present to November 2021 Board
for endorsement
Independent Expert PanelRoy Simm – StantecKen Abraham – HDR
Viji Fernando – GolderFrank Margitan (Rtd) – Kiewit
Jeff Plant – Major Projects AdvisorPippa Brasher – Scape Studio
Brendan Avery – Francl ArchitectureShannon Katt – PMA Consultants
Ryan Ziels – UBC
Liquid Waste Committee
Expert Panel Recommendations & Options Evaluation
Liquid Waste Committee
EXPERT PANEL RECOMMENDATIONS
9
• Total of 35 recommendations from Challenge Review• wastewater treatment process design• ecological, community/park integration and resource recovery • construction considerations
• To address costs and other challenges, panel made specific recommendations related to:• additional seismic modelling to refine ground improvement cost estimates• wastewater treatment process design options, including technologies with
smaller footprints to offset the high costs of ground improvements
Liquid Waste Committee
SHORT-LIST OF TREATMENT OPTIONS
10
1. Base Case (July 2020 design concept)1a. Modified Base Case 2. Membrane Bioreactor (MBR)3. Aerobic Granular Sludge (AGS)
Liquid Waste Committee
11
PRELIMINARY COST COMPARISONS
+3%
-11%-9%
$10.365B
$3.718B 0%+21%
-6%
$14.084B +2%-1%
-10%
Capital Coststo 2034 and 2041 - including escalation and risk reserve
O&M Costs37-year NPV (2034-71)
Total Life Cycle Costscapital costs plus 37-year O&M NPV
1. Base Case1a. Modified Base Case 2. MBR3. AGS
Liquid Waste Committee
ADDRESSING CHALLENGES & OTHER CRITERIA
12Liquid Waste Committee
WHAT’S CHANGED FROM EARLIER EVALUATION
13
Nature of Change Example of Change
Addressing challenges Summary table includes each challenge
Criteria not shown that are similar for all options or do not influence decision
• Odour control and potential risks are similar in nature for all of the options
• Operational complexity and maintenance requirements are reflected in O&M costs
New criteria added for options evaluated
• Impacts on park lands and land tenure• Proven applications at scale and market competition
among technology vendors
Liquid Waste Committee
Public and First Nation Engagement
Liquid Waste Committee
July 30 to October 22, 2021PUBLIC AND FIRST NATION ENGAGEMENT
15
Audience Virtual Meeting DatesMusqueam Indian Band July 30, Sept 14Vancouver Airport Authority (YVR) Sept 22Deering Island Homeowners Society Sept 24
Georgia Strait Alliance Sept 29Vancouver Fraser Port Authority Oct 4Birders and naturalists Oct 18Online community meetings Oct 12 and 14 (55 participants)
Online public comment period Sept 27 to Oct 22 (52 submissions)
CoV, VSA, REAC, RAAC, RFAC Sept, Oct
Liquid Waste Committee
PUBLIC AND FIRST NATION ENGAGEMENT
16Liquid Waste Committee
Revised Design Concept
Liquid Waste Committee
REVISED DESIGN CONCEPT
18
• Concurrent construction of digesters and compact-footprint secondary treatment process (MBR or AGS)
• Offer capital cost savings in the order of 10%• Flexibility to validate performance and costs in next phases• Address commercial considerations as part of due-diligence
• What’s not changing• Tertiary level wastewater treatment • Odour control • Ecological restoration projects• Resource recovery opportunities
Reclaimed Water
Heat
Nutrients / Biosolids
Biofuels
Liquid Waste Committee
Primary Treatment
Preliminary Treatment
Secondary and Tertiary Treatment
REVISED DESIGN CONCEPT – WASTEWATER TREATMENT
19
Screening Grit Removal
Inclined Plate/Tube Settling (Lamella)
Membrane Biological Reactor
Aerobic Granular Sludge
Cloth Media Filtration
(Dry Weather Only)
Disinfection
Ultraviolet Disinfection
Wet Weather Flow Treatment
Cloth Media Filtration and Disinfection
Solids Treatment
Mesophilic Anaerobic Digestion
Biogas Use
Biogas Upgrade
From Influent Siphons
To Existing Outfall
MBR Option
AGS Option
Wet Weather Flow
Biosolids
Renewable Natural Gas
to Grid
Effluent Heat Recovery and Reclaimed Water
Liquid
SolidsGas
LEGEND
Liquid Waste Committee
Conceptual LayoutMEMBRANE BIOREACTOR (MBR)
20
Legend
Future Expansion 2051
MBR Secondary Treatment~ 2.4 hectares
Complete 2034 (primary, secondary, tertiary treatment processes, and new digesters)
Liquid Waste Committee
MEMBRANE BIOREACTOR (MBR)
21
Conceptual Rendering
Liquid Waste Committee
Conceptual LayoutAEROBIC GRANULAR SLUDGE (AGS)
22
Legend
Future Expansion 2051
AGS Secondary Treatment ~ 3.2 hectares
Complete 2034 (primary, secondary, tertiary treatment processes, and new digesters)
Liquid Waste Committee
AEROBIC GRANULAR SLUDGE (AGS)
23
Conceptual Rendering
Liquid Waste Committee
Issues to address in subsequent phasesREMAINING CHALLENGES & RISKS
24
ChallengesMBR• higher energy use and O&M costs• periodic replacement of membranesAGS• limited proven applications of scale at Iona• Commercial considerations for proprietary technology
Risk Schedule risk if land tenure resolution is delayed
Liquid Waste Committee
Regional Park Impacts and Benefits
Liquid Waste Committee
• Concurrent digester construction • Eliminates trucking sludge off-site • Protects desired Musqueam views• Net gain in park land, including
~ 18 ha transfer from GVS&DD
LAND REQUIREMENTS
26
Revised Design Concept layout requires ~3 ha of MVRD park land
Liquid Waste Committee
IONA ISLAND LAND TENURE – CURRENT
Liquid Waste Committee
IONA ISLAND LAND TENURE – PLANNED
Liquid Waste Committee
IONA ISLAND – PARK ENHANCEMENTS
29Liquid Waste Committee
30
Freshwater wetlands and tidal channels
Foreshore restorationTidal marsh south of treatment plant
View from knolls looking west
Liquid Waste Committee
Next Steps to Finalize Project Definition Report
Liquid Waste Committee
for March 2022 Board approvalWORK TO FINALIZE PDR
32
• Refine conceptual design and layouts• Advance land tenure transfer (MVRD and GVS&DD)• Update schedule and budget
• constructability review• risk assessment• cost estimates• cash flows
• Update financial model to estimate rate impacts (HHIs)• Update delivery strategy recommendations• Finalize project definition report
Liquid Waste Committee
Recommendation
Liquid Waste Committee
RECOMMENDATION
34
That the GVS&DD Board endorse the revised design concept for the Iona Island Wastewater Treatment Plant projects, as presented in the report dated October 27, 2021 titled “Iona Island Wastewater Treatment Plant Projects – Revised Design Concept”; and direct staff to finalize the project definition report for Board approval in March 2022.
Liquid Waste Committee
Questions
Liquid Waste Committee
Procurement Model For Regional Biosolids Drying Facility
Lillian ZarembaProgram Manager, Utility Residuals Management, Liquid Waste Services
Liquid Waste Committee, November 4, 202147862577
Drum dryer
5.2
Liquid Waste Committee
WHAT ARE BIOSOLIDS?
2
Treated solids recovered from wastewater treatment
Final product is a nutrient-rich material, similar to soil
Liquid Waste Committee
Land application to build healthy soilsBACKGROUND: CURRENT BENEFICIAL USE
3
Nutrifor Landscaping Soil at new Mountain Highway Interchange
• Landscaping soil • Rangeland fertilization • Agricultural land
reclamation• Mine restoration• Gravel pit restoration• Landfill closure
Liquid Waste Committee
0
50,000
100,000
150,000
200,000
2000
2005
2010
2015
2020
2025
2030
2035
2040
2045
2050
Bios
olid
s pro
duct
ion
(bul
k to
nnes
per
yea
r)
Increasing biosolids production cannot be handled by land application aloneBACKGROUND: DRIVERS
Land application($165/tonne)
Landfill disposal($275/tonne) (30-yr lifecycle
costs including carbon price)
Liquid Waste Committee
REGIONAL BIOSOLIDS DRYING FACILITY
Construction of CRD Residuals Handling Facility Dried biosolids pellets from drum dryer
Liquid Waste Committee
Biosolids processing systemWASTE-TO-ENERGY FACILITY
Waste-to-Energy Facility
6
Contingency approach:• Run at one-third capacity
(8,500 tonnes per year) to maintain operation
• Full capacity (25,000 tonnes per year) available if needed
Liquid Waste Committee
Solids management alternativeHYDROTHERMAL LIQUEFACTION (HTL)
7
New technology that replaces WWTP digestion and produces biofuel instead of biosolidsPilot in development at Annacis WWTPIf successful, possible larger scale implementation in late 2030sComplements biosolids nutrient recovery
Bio-crude oil from HTL
Liquid Waste Committee
PROPOSED BIOSOLIDS MANAGEMENT OPTIONS
8
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
160,000
180,000
200,000
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
2041
2042
2043
2044
2045
2046
2047
2048
2049
2050
Bios
olid
s pr
oduc
tion
(bul
k to
nnes
/yea
r) Dryer Waste-to-Energy Facility Land application Landfill disposal
Liquid Waste Committee
OCT. 4, 2019 BOARD MEETING
9
It was MOVED and SECONDEDThat the GVS&DD Board:a) endorse biosolids drying as a
biosolids management option; andb) direct staff to report back to the Board
with the recommended procurement model for implementation of a regional biosolids drying facility.
Dried biosolids pellets from fluidized bed dryer
Liquid Waste Committee
Procurement models for regional biosolids drying facility
VALUE-FOR-MONEY ANALYSIS
Hamilton dried biosolids storage silo
10
Design-Bid-Build (DBB)• base caseDesign-Build-Finance-Operate-Maintain (DBFOM) • 3% less costly than DBBDesign-Build-Operate (DBO)• 13% less costly than DBB,
$41M savings
Liquid Waste Committee
RECOMMENDED PROCUREMENT MODEL: DBO
11
Hamilton biosolids dryer building Hamilton drum dryer
Liquid Waste Committee
12
Thank you
Hamilton biosolids dryer
Liquid Waste Committee
Proposed Capital InvestmentSAPPERTON DISTRICT SEWER HEAT RECOVERY PROJECT
Jeff CarmichaelDIVISION MANAGER, BUSINESS DEVELOPMENT, LIQUID WASTE SERVICES
Liquid Waste Committee – November 4, 202145592530
5.4
Liquid Waste Committee
Photo Caption hereOPPORTUNITY TO ACT ON CLIMATE CHANGE• Climate 2050 GHG neutral goal
• Corporate GHG neutrality goal
• Integrated Liquid Waste and Resource Management Plan
• Other plans:
• Liquid Waste Heat Recovery Policy• Carbon Pricing Policy• Energy Management Policy• Sustainable Infrastructure Policy
2Liquid Waste Committee
Photo Caption hereSEWER HEAT OPPORTUNITIES
• Energy-rich, reliable local source of renewable energy
• Potential for significant regional GHG reductions
• High startup costs hinder implementation
• Capital investments will accelerate development of municipal sewer heat-sourced district energy systems
3Liquid Waste Committee
MOST RECENT BOARD ACTIONS
March 2021 approved amendments for wastewater recovery:
Tier III Cost Apportionment Bylaw Amendment: • Share costs proportionately and equitably for projects that reduce
regional greenhouse gas emissions
Liquid Waste Heat Recovery Policy Amendments:• Allow capital investments in such projects
4Liquid Waste Committee
Photo Caption here
SEWER HEAT CAPITAL INVESTMENT:NEW WESTMINSTER SAPPERTON DISTRICT
• Proposed 12 MW sewer heat project• Investment cap set based on GHG
reductions, valued per Carbon Price Policy = $18,000,000
• Voluntary GHG reduction 5,700 tonnes / yr• GHG credits to be allocated as per Liquid
Waste Heat Recovery Policy• Benefits exceed costs over life of project
Liquid Waste Committee
SEWER HEAT DISTRICT ENERGY SYSTEM SCOPE OVERVIEW
GVS&DD capital investment
City investments
Liquid Waste Committee
DRIVER FOR INVESTMENT: REGIONAL GHG REDUCTIONS
past future
Annual GHG
emissions
fossil fuel energy-based option
low GHG energy option
Existing and future energy users (including Royal Columbian Hospital):
Voluntary GHG reduction = difference
Liquid Waste Committee
8
Item GVS&DD New WestminsterEstimated capital cost ($14 million) ($64 million)
Operating costs ($900,000 / yr) tbd
Revenues from thermal energy +$900,000 / yr tbd, based on rate structure
Benefits from GHG reductions (as per Carbon Price Policy)
+$18 million
Net benefit to Metro Vancouver +$4 million
Spending authority requested $18 million
BUSINESS CASE SUMMARY
Liquid Waste Committee
Photo Caption hereFINANCIAL IMPLICATIONS: NEAR- AND LONG-TERM
• Near-term projects approved or under consideration: ~25MW• North Shore effluent heat • Sapperton District • Surrey Central District• Richmond OvalRatepayer impact: Less than $1 per household per year per project
• Estimated maximum buildout:• Estimated capacity of 105 MW of heat recovery without impacting wastewater
treatment = 700 high rises• Ratepayer impact of full near-term buildout: $1 per household per year over 10 years• Capacity will grow in future as regional population and sewage flows grow
Liquid Waste Committee
Thank you for your consideration.Liquid Waste Committee
Burnaby Lake North Interceptor No. 2AWARD OF CONTRACT RESULTING FROM RFP 20-345 CONSTRUCTION SERVICES
Colin MeldrumDirector, Engineering, Design and Construction, Liquid Waste Services
Liquid Waste Committee - November 4, 2021
48822155
Burnaby Lake North Interceptor No. 2 – Open Cut Construction
5.8
Liquid Waste Committee
2
BURNABY LAKE NORTH INTERCEPTOR NO. 2Phases 1 - 3
Liquid Waste Committee
Burnaby Lake North Interceptor No. 2PHASE 2: WINSTON ST. – TRENCHLESS SECTION
South Surrey Interceptor Ph.2 – Johnson Road Section Microtunnelling Operations
3
Details• 2.9 km long• Pipe diam. 2134 mm• Plastic-lined RCP• Microtunnel• 7 Shafts• Challenging soils
Estimated Construction Costs $77M (fall 2020)
Liquid Waste Committee
RFP 20-345 - Construction Contractor ServicesPHASE 2: WINSTON ST. – TRENCHLESS SECTION
4
Proposals were evaluated on technical merit (60%) and financial criteria (40%)
Company Cost
Pomerleau Bessac Infrastruture $62,942,479
Michels Canada $ 51,340,873
Ward & Burke Microtunneling $ 65,997,829
Shanghai Construction Group $ 65,806,666
Clearway Construction $ 55,503,787
Liquid Waste Committee
RFP 20-345 - Construction Contractor ServicesPHASE 2: WINSTON ST. – TRENCHLESS SECTION
5
Pomerleau Bessac Infrastructure (PBI)• Highest ranked technical score• Exceptional firm qualifications and experience• Key project personnel met and exceeded required
qualifications and experience • Project construction methodology/work plan demonstrated
excellent understanding of project challenges
Liquid Waste Committee
RFP 20-345 - Construction Contractor ServicesRECOMMENDATION
6
That the GVS&DD Board:a) approve award of a contract for an amount up to $62,942,479.02 (exclusive of
taxes) to Pomerleau Bessac Infrastructure resulting from Request for Proposal No. 20-345: Construction Services for the Burnaby Lake North Interceptor No. 2 – Winston St Phase 2 Trenchless Section, subject to final review by the Commissioner; and
b) authorize the Commissioner and the Corporate Officer to execute the required documentation once the Commissioner is satisfied that the award should proceed.
Liquid Waste Committee
7
Thank You
South Surrey Interceptor No. 2 – Johnson Road Section Construction
Liquid Waste Committee