78
1 Link Union Station (Link US) Project Construction Manager/General Contractor (CM/GC) Industry Outreach August 3, 2020

Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

  • Upload
    others

  • View
    6

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

1

Link Union Station (Link US) ProjectConstruction Manager/General Contractor (CM/GC)

Industry OutreachAugust 3, 2020

Page 2: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

2

- Not Funded- Funded

I. WELCOMING REMARKS 9:00 – 9:10 am

a. CMGC Objectives by Rick Clarke, Metro

b. Change to CMGC Approach by Rick Clarke, Metro

II. LINK US PRESENTATION 9:10 - 9:30 am

a. Project Overview by Jeanet Owens, Metro

b. Project Benefits &

c. Phase A & B

d. Phase A Funding Plan

e. CMGC Key Constraints & Approach

Page 3: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

3

- Not Funded- Funded

II. LINK US PRESENTATION (Continue)

d. PE Design by Tom Kim, HDR 10:00 - 10:30 am

i. Key Design Elements

ii. Design Schedule

iii. Subsurface Utility Investigationsi. Geotechnical

iv. Sound Wall & Quiet Zone by Vincent Chio, Metro

v. Station & Platform

vi. Track Alignment

vii. Caltrans Involvement

viii. US 101 Viaduct Structure

ix. 55 Hour Lane Closure Approach

x. ATP & LADWP Overhead Poles

Page 4: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

4

- Not Funded- Funded

II. LINK US PRESENTATION (Continue)

e. CMGC Scope of Work 10:00 - 10:30 am

i. Construction Phasing & Schedule by Scott McConnell, Metro

ii. Constructability & Value Engineering by Scott McConnell, Metro

iii.Risk Management by Dave Davies, Metro

iv.Scheduling & Cost Estimating by Jay Yoon, Metro

III. SMALL BUSINESS REQUIREMENTS by Elke Campbell 10:30 - 10:45 am

IV. CMGC PROCUREMENT by Fred Origel, Metro 10:45 - 11:00 am

V. QUESTIONS & ANSWERS by all 11:00 - 11:45 am

VI. Closing by Miriam Long, Metro

Page 5: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

5

Welcoming Remarks

- Not Funded- Funded

Rick ClarkeChief Program Management Officer

Page 6: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

6

Link Union Station Overview

- Not Funded- Funded

Jeanet OwensSenior Executive Officer, Program Management and Regional Rail

Page 7: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

7

Link US Project Overview (Phases A & B)

- Not Funded- Funded

Page 8: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

8

The Link to Southern California

Page 9: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

9

Los Angeles Union Station TodayBuilt in 1939 | Largest model hub in Southern California

Page 10: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

1010

Metro Regional Rail focus on Network Integration

Union Station

1. Los Angeles Union

Station (LAUS) is the

largest multi-modal rail

and transit hub in

Southern California

serving over 100,000

passengers per day.

2. By 2028 Olympics,

LAUS will serve over

200,000 passengers per

day

Proposed Virgin Trains USA To Las VegasHigh Desert

CorridorHigh Speed Rail

VICTORVILLE

METROLINK SYSTEM

Amtrak Pacific Surfliner

Page 11: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

1111

Link Union Station Regional Rail Overview

- Not Funded- Funded

Carrier Service # of Weekday Passengers

(2017)

# of WeekdayTrains(2017)

Estimated Number of Weekday Trains

(2040**)

Metrolink Riverside 2,985 12 22

91 / Perris Valley Line 2,608 9 23

Antelope Valley 4,854 30 48

Orange County 7,616 21 41

San Bernardino 7,161 38 48

Ventura 3,276 33 51

LOSSAN Pacific Surfliner 4,100 24 38

Amtrak Southwest Chief; Coast Starlight; Sunset Limited; [2040 includes future Coast Daylight, Coachella Valley]

540 5 9

Total *33,138 172 280

Page 13: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

1313

Link US Phase A (Funded)

Combined Run-Through Tracks Structure without the loop track

Key Project Components

1. New rail communication, signals and early tracks to be performed by Metrolink

2. Utility relocation and street improvements

3. Platform #4 and Viaduct structure over the US 101 freeway

Early Track, Signal and

Communication

Improvements

Commercial and

Center Street

Improvements/Utility

Relocation/ROW

Platform 4

Modifications

Two initial run-

through tracks

on a new run-

through track

viaduct structure

Page 14: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

1414

LINK US CMGC RFP PHASE B

A separate traditional CMGC RFP Phase B issued in January 2021 for development of 35% Preliminary Engineering Design only and negotiate a separate construction contract once Phase B has been funded.

Page 15: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

1515

Concept Rendering – subject to change

1. Raising of entire rail yard from the Vignes Bridge up to 15 feet

2. New Platforms and Expanded Passageway with retail and passenger amenities including escalators and elevators to all platforms

3. Optimization of the throat with a new lead track

Link US Phase B Construction Not Funded

Page 16: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

16

Link US Funding Plan (Phase A)

Metro’s funding partners includes CHSRA, CalSTA and SCRRA

Funding Source Amount ($ in millions)

State Proposition 1A/High Speed Rail Bonds $423.335

State Transit Intercity Rail Capital Program (TIRCP) $337.571

State Transportation Improvement Program (STIP) $60.820

Measure R $51.672

SCRRA JPA Contribution (Non-Metro) $40.000

Other HSR Funds $18.726

Measure M $13.274

LOSSAN/Amtrak $5.000

Total $950.398

Page 17: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

17

SELECTED CMGC Project Delivery Method

1. Maintain operations at Los Angeles Union Station, largest multi-modal transit terminal in Southern California serving over 100,000 passengers every week day

2. Fixed Budget – Due to the financial constraint of a $950 millionfunding for the entire project, there is very limited ability to absorb cost overruns.

a) Maximize cost and schedule savings with early engagement of the Contractor (constructability review, value engineering analysis, bottom-up construction estimate, risk analysis and construction schedule) at every design submittal.

b) Minimize change orders during construction.

c) Minimize third party delays with flexible phasing plan based on GC construction schedule.

DUE TO 3 KEY CONSTRAINTS:

Page 18: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

18

CMGC Project Delivery Method3rd KEY CONSTRAINT: Large Partners & Stakeholders

Key Stakeholders

Funding Partners

Metro CalSta SCRRAHSR

CALTRANSCity of Los

AngelesHSR

William Mead HomesArts District OthersBNSFFRA

LOSSAN/AMTRAK

SCRRA

Page 19: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

19

CMGC Project Delivery MethodREVISED APPROACH

1. Classic CMGC Preconstruction Services• One Notice To Proceed for Preconstruction Services with off-ramps• Negotiate fixed lump sum price at 90% Design Plans for Early

Construction Work via Task Order (s)

2. Main Construction Services • Negotiate Final Firm Fixed Price by Supplemental Construction

Contract

Page 20: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

20

Environmental

- Not Funded- Funded

Vincent ChioDirector, Metro Rail

Environmental Project Manager

Page 21: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

21

LINK UNION STATIONEnvironmental Clearance StatusCalifornia Environmental Quality Act (CEQA)

1. Final EIR: Completed in June 27, 2019 (Board Certified)

2. CEQA Amendment: in Progress thru Spring 2021

A. Permanent BNSF Track Removal (West Bank, 1st Street)

B. BNSF Malabar Yard Improvements (City of Vernon)

❖ 49th Street: Close At-Grade Crossing

❖ 46th Street: Connect existing track segments

National Environmental Policy Act (NEPA)

1. Notice of Intent (NOI) to prepare EIS under FRA: Fall 2016

2. Revised NOI under HSR: Summer 2020 (BNSF West Bank & Malabar Yard)

3. Draft EIS: Spring 2021

4. Final EIS/ROD: Summer 2021 21

Page 22: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

22

Preliminary Design

- Not Funded- Funded

Tom KimSenior Vice President, HDR

Link US Project Manager

Page 23: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

23

HDR DESIGN TEAM

Tom Kim, PE Project Manager

Mike Grubstein, PEDeputy Project Manager

Andrew Mull, PETrack Lead

Mo Mah, AIA, LEED APArchitecture Lead

Marc Cooley, PECivil Lead

Dan Weddell, PEStructures Lead

Doug Smith, PETraffic Lead

Patrick O’NeilEnvironmental Lead

23

Key Discipline Leads

Page 24: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

24

LINK UNION STATION PHASE A KEY DESIGN ELEMENTS

Area 1 - Throat (North of the Station)

Area 2 - Station Area & Platform Modifications

Area 3 - US-101 Viaduct Freeway Improvements & Commercial Street ATP

Area 4 - Run–through Tracks West Bank Tie-In & Bridge over Amtrak Lead 24

Page 25: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

25

LINK UNION STATION CMGCList of Key Technical Documents

1. Subsurface Utility Investigation Data Reports

2. Geotechnical reports including boring data

3. Updated 35% Preliminary Engineering Design Plans

4. Caltrans approved Project Study Report/Project Report (PSR/PR)

5. Caltrans approved Type Selection Report for US-101 Bridge

6. Proposed approach to 55 hour lane closure of US-101 for run-through track viaduct construction (LADOT & Caltrans approved)

7. Structure Type Assessment Report for Center Street Bridge

8. Draft preliminary technical specifications

9. Preliminary construction phase risk register

25

Page 26: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

26

Phase A Preliminary Design ScheduleSubject to Change

1. Review PE Designs with CMGC: April 2021 –July 2021

2. 65% Design Development: Aug 2021-March 2022

3. 90% Design: April 2022-Oct 2022

4

Page 27: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

27

LINK US SUBSURFACE UTILITY INVESTIGATIONSInvestigation Summary by Project Area

1. Metro Property3 trenches and 4 potholes within Metro Division 20 property

2. BNSF Property3 trenches and 4 potholes within BSNF storage track area

3. SCRRA Right of Way12 trenches within rail corridor

4. Union Station Platform Area2 trenches within access road s/o platforms

5. MWD Property1 trench along MWD access road

6. City of LA Local Street Right of Way3 trenches and 3 potholes along Commercial and Vignes Streets

7. Caltrans Right of Way1 trench and 4 potholes within US-101 R/W

8. Amtrak Property3 potholes along Amtrak yard lead track

Total work completed: 24 trenches, 11 potholes

Total work to be completed upon agency approval:5 trenches, 7 potholes

Pothole/Trench Location Map27

Page 28: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

28

LINK US GEOTECHNICAL & HAZMAT INVESTIGATIONSSummary of Field Investigations

Anticipated Work AreasCaltrans Right of Way

7 geotechnical borings and 4 hand auger hazmat borings

BNSF Property4 geotechnical borings

Metro Property & Private Property7 geotechnical borings and 1 hand auger hazmat boring

Preliminary Design PhaseTotal work completed: 20 Geotechnical Borings, 21 Shared Geotechnical Borings/Environmental Samples and 22 Hazmat Borings

Final Design PhaseTotal work to be completed: 18 Shared Geotechnical/Environmental Samples Borings and 5 Hazmat Borings

28

Page 29: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

29

LINK US GEOTECHNICAL & HAZMAT DOCUMENTS Summary of Technical Documents

Discipline Status Document Title

Geotechnical Completed Preliminary Geotechnical Report- Existing Data, dated July 2016

Geotechnical Completed Draft- Preliminary Geotechnical Design Report - Improvements Outside Caltrans ROW, dated April 2020

Geotechnical Completed Link US Geotechnical Data Report Viaduct Over US 101, dated October 2017

Geotechnical Completed Preliminary Foundation Report Viaduct Over US 101, dated December 2019

Hazmat Completed Phase I Environmental Site Assessment Report, Link Union Station Project Area, dated October 26, 2016

Hazmat Completed Phase I Environmental Site Assessment Report, Los Angeles Union Station Area, dated October 26, 2016

Hazmat Completed Soil Management Plan for Investigations, Link Union Station, dated January 16, 2017

Hazmat Completed Initial Site Assessment Report - Caltrans ROW, dated April 5, 2017

Hazmat Completed Phase II Environmental Site Assessment Workplan, dated September 25, 2017

Hazmat Completed Initial Site Assessment Update Report – Caltrans ROW, dated June 19, 2019

Geotechnical Pending Completion Geotechnical Design Report- Improvements Outside Caltrans ROW

Geotechnical Pending Completion Final Foundation Report Viaduct Over US 101 - Caltrans ROW

Geotechnical Pending Completion Final Foundation Report Retaining Walls - Caltrans ROW

Hazmat Pending Completion Phase II Environmental Site Assessment Report

29

Page 30: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

30

UPDATED LINK UNION STATION 35% DESIGNKey Project Changes to Address Stakeholder Comments

Key Changesa) Modified US-101 bridge piles at abutments from driven to CIDH to reduce noise

impacts

b) Modified design of Center Street Bridge to address City comments regarding safety

c) Added tunnel under track section for Metro maintenance/emergency access to Red/Purple Line portal trench

d) Modernized Platform 4 canopy design

e) Implemented ADA improvements along Commercial Street to address City comments

CMGC OpportunitiesModified 35% design for CMGC RFP and provided additional design details not typically provided at 35% to provide better starting point for contractor to review and make VE and constructability recommendations.

30

Page 31: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

31

LINK US PHASE A PROJECTArea 1 - William Meade Homes Sound Wall on Retaining Wall

WILLIAM MEAD HOMESSOUND/RETAINING WALL LAYOUT

WILLIAM MEAD HOMES

SOUND WALL ON RETAINING WALL

CMGC Collaboration Opportunities:a. How to minimize impacts to WMH residentsb. Determination of most efficient wall type c. Potential early construction package

Benefits:a. Reduced noise impacts to WMH residents which also

addresses request by Council District 1b. EIR mitigation measure

31

TYPICAL WALL SECTION

Page 32: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

32

Looking Southwest from Bolero Lane/Bloom Street

NOISE MITIGATION - SOUND WALL

Conceptual Rendering

32

Existing Conditions Proposed Project - Vegetation (Vines) on Sound Wall and Retaining Wall

Page 33: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

33

Noise from Train Operations (Proposed Project)

POTENTIAL IMPACTS MITIGATION

Noise from increased train activitya. Existing sound level – 69dB

(Currently 233 Metrolink and Amtrak trains enter and leave Union Station, including empty trains to Central Maintenance Facility)

b. Year 2040 future sound level – up to 75dB(830 Metrolink, Amtrak, and future High Speed Rail trains is projected to enter and leave Union Station)

Sound wall up to 22 feet tall to mitigate the impacts to less than significant level.a. Future sound level with

the sound wall – 62dB

33

Page 34: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

34

TRAIN HORN NOISE NEAR WILLIAM MEAD HOMES

a. 40% of train horns heard at the William Mead Homes in the early morning hours had a noise level over 90 dBA.

b. Under the leadership of Council District 1, Metro is working with City of LA, Metrolink and CPUC on the implementation of the first quiet zone in City of LA.

Over 120 trains cross N Main Street every weekday, starting at around 4am and sounding

the train horns

William Mead Homes

Need for a Quiet Zone at Main Street

34

Page 35: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

35

Quiet Zone Ready Improvements at N. Main Street Railroad Grade Crossing

PROPOSED LIMITS OF QUIET ZONE ON THE WEST BANK

N Main St Xing

DWP Pvt Xing

N Main St Xing

0.2

8 m

iles

a. In a Quiet Zone, railroads are directed to cease the routine sounding their horns when approaching public highway-rail grade crossings. Train horns may still be used in emergency situations.

b. Quiet Zones are subject to review and approval by CPUC. City of LA is responsible for applying for a Quiet Zone with the CPUC.

35

Page 36: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

36

Quiet Zone Ready Improvements

PROPOSED SAFETY IMPROVEMENTS AT N. MAIN STREET

New Pedestrian Gates and Wider Sidewalks

New Raised Median with New Vehicular Gates

ADA and Access Improvements

New Traffic Signal

New Pedestrian Gates and Wider Sidewalks

36

Page 37: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

37

Area 2 Station - Project Elements

MWD

PLATFORM 5

PLATFORM 3

PLATFORM 2

PLATFORM 1

PLATFORM 6

PLATFORM 7

LINK US PHASE A PROJECT

LegendUS-101 ViaductRetained Fill SectionReconstructed access roadExisting PlatformPlatform 4 modifications

SHORTEN/MODIFY PLATFORM 4 TO ACCOMMODATE TRACK RAMP

CONSTRUCT RAMP TO TRANSITION TRACK FROM PLATFORM LEVEL TO BRIDGE LEVEL

PLATFORM 4

CMGC Collaboration Opportunities:a. Plan construction access areas and routesb. Define interim baggage operations and passenger movementsc. Manage passenger movement and access for safety and convenienced. Determination of construction access/methods in confined space

LOWER ACCESS ROAD TO CROSS UNDER TRACK BRIDGE

37

Page 38: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

38

Area 2 Station – Platform 4 Modifications

LINK US PHASE A PROJECT

CMGC Collaboration Opportunities:a. Architectural design refinementsb. Managing passenger movement and access during construction

38

Page 39: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

39

LINK US PHASE A PROJECT

PROPOSED PLATFORM 4 IMPROVEMENTS WITH NEW CANOPY

Area 2 Station – Platform 4 Modifications

39

Page 40: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

40

RUN-THROUGH TRACK ALIGNMENTArea 3 - Track Alignment and Property Needs South of Union Station

110+00

Alignment constrained by the following:a. Existing platforms at LAUSb. El Monte Busway, US-101, and on/off rampsc. Existing Red/Purple Line tunnel and portal trenchd. Center Street crossinge. Future Metro Center Projectf. Existing SCRRA and BNSF track infrastructureg. Existing adjacent developmenth. LADWP electrical transmission corridor

RUN THROUGH TRACKS

COMMERCIAL ST

GA

REY

ST

VIG

NES

ST

CEN

TER

ST

DUCOMMUN ST

SB US 101

NB US 101

LOS

AN

GEL

ES R

IVER

METRO CENTER SITE

LegendProperty AcquisitionEl Monte BuswayRun through tracks 40

UNION STATION

Page 41: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

41

LINK US PHASE A PROJECTArea 3 – Run-through Track Structure South of Union Station

COMMERCIAL ST

CEN

TER

ST

SB US 101

NB US 101

UNION STATION

VIG

NES

ST

GA

REY

ST

DUCOMMUN ST

CENTER ST BRIDGE

MAINTENANCE VEHICLE ACCESS TUNNEL

RETAINED FILL SECTION

RETAINED FILL SECTION

EL MONTE BUSWAY

41

US-101 VIADUCT

Page 42: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

42

Preliminary Design Phasea. Design exceptions for freeway geometry approved

b. Project Report approval expected August 2020

c. Type Selection Report approval expected August 2020

CMGC Collaboration Design Phasea. Review and approval of US-101 bridge and freeway

modification design packages

b. Open to early construction packages such as foundation installation

c. Working with designer and contractor on aesthetic treatments

Area 3 – Caltrans Involvement During Preliminary Engineering and CMGC Phases

LINK US PHASE A PROJECT

42

Page 43: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

43

LINK US PHASE A PROJECTArea 3 – US 101 Viaduct and Freeway Modifications

COMMERCIAL ST

NB US 101

UN

ION

STA

TIO

NLegend

US-101 ViaductRetained Fill SectionEl Monte Busway PATSAOURAS

PLAZA

GA

REY

ST

VIG

NES

ST

CMGC Collaboration Opportunities:a. Construction staging of the bridge and freeway

improvements

Key Constraints:a. Preserve SB on-ramp geometryb. Provide std vertical clearance over US-101 and buswayc. Maintain US-101 thru lanes during construction

Key Features:a. Construct viaduct with 12’ to 14’ CIDH pilesb. Reconstruct retaining walls along El Monte Buswayc. Restripe US-101 to provide space for bridge bentsd. Reconstruct NB on-ramp from Vignes St

43

Page 44: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

44

LINK US PHASE A PROJECTArea 3 – US 101 Viaduct

LOWER RUN-THROUGH TRACK PROFILE IN

PHASE A

Key Features:a. Spans 1-3 & 7-9 precastb. Spans 4-6 are CIP delta boxc. Bents 5 &6 are outriggers over

SB US-101d. Portion of Phase A deck profile

lower than ultimate

CMGC Collaboration Opportunities:a. Construct Spans 1 through 3 to

be raised in the futureb. Bridge and wall aestheticsc. Freeway closure schedule for

falsework and girder erection

TYPICAL SECTION ALONG BENT 2

TYPICAL SECTION ALONG BENTS 6R AND 6L44

Page 45: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

45

APPROACH TO 55 HOUR LANE CLOSURE FOR CONSTRUCTION OF RUN-THROUGH TRACK BRIDGEArea 3 – Requires Joint Approval by Caltrans & LADOT

45

Proposed Closure (Year 2022)a. 55 Hours on Weekend

b. Closure Duration: From Friday 10 PM to Monday 5 AM

c. 5 Weekend Closure in NB US-101 and 5 Weekend Closure in SB US-101

d. Only 1 direction of US-101 will be closed on a particular weekend

Executive Summarya. Tested three Diversion Patterns (60/40, 70/30, 100/0)

b. Tested two traffic levels (Actual at 5600 - 5800 vph and Max. Theoretical)

• Not a substantial difference

• Year 2022 Projections for Saturday Peak Hours, NB and SB

• Some freeway segments hit capacity at 70/30

• NB closure more complex

Page 46: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

46

APPROACH TO 55 HOUR LANE CLOSURE FOR CONSTRUCTION OF RUN-THROUGH TRACK BRIDGEArea 3 – Requires Joint Approval by Caltrans & LADOT

46

TMP LOS Results

Using 70-30 split for NB and SB closure and existing volumes:

a. 2 Freeway segments impacted

b. 5 intersections impacted

Page 47: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

47

APPROACH TO 55 HOUR LANE CLOSURE FOR CONSTRUCTION OF RUN-THROUGH TRACK BRIDGEArea 3 – Requires Joint Approval by Caltrans & LADOT

47

Proposed Recommendationsa. Maximum diversion is a 70/30

b. SB US 101 closure should stay open to Los Angeles Street

c. NB US 101 could close at I-5/I-10 Interchange with support from diversion to I-710

d. Significant Regional SB diversion needed for SB closure

e. I-110/I-10 ramps will need support

f. Significant public information campaign will be needed

Next Steps a. Work with Caltrans and LADOT to receive concurrence by August 2020

b. Work with CMGC on preparing Transportation Management Plan (TMP) and construction phasing

Page 48: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

48

LINK US PHASE A PROJECTArea 3 – Proposed Active Transportation Improvements

View from Southeast Corner of Commercial/Garey Intersection

Note: Per agreement with City of LA, active transportation is limited to Class IV bike lanes only with bollards and associated restriping (no R/W takes included)

48

Page 49: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

49

Area 3 – Existing LADWP Power Lines & Poles in Conflict with Project

COMMERCIAL ST

VIG

NES

ST

CEN

TER

ST

SB US 101

LegendExisting power polesExisting power poles in conflictExisting overhead power lines

LINK US PHASE A PROJECT

a. Conflicts to be mitigated through relocation strategy that involves both underground and overhead relocations to be designed and constructed by LADWP

b. Overhead relocations require use of engineered steel poles

ALISO ST

49

Page 50: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

50

Area 3 – Relocation of Impacted Power Facilities by LADWP

Completion of Relocation Design and Construction is Time Sensitive:a. 18 month fabrication time for required engineered steel polesb. 1 year for relocation construction by LADWPc. Relocations need to be completed ahead of bridge construction

To Initiate Relocation Design, LADWP Needs Confirmation of Proposed Locations of:a. Curb, sidewalk, and curb rampsb. Street treesc. Street lightsd. Catch basinse. Other features that could influence pole placement

Project engineers to advance design to provide requested information and obtain

City of LA approval

LINK US PHASE A PROJECT

50

Page 51: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

51

LINK US PHASE A PROJECTArea 3 – Center Street Bridge

COMMERCIAL ST

CEN

TER

ST

SB US 101

LegendCenter St BridgeRetained Fill SectionLimits of existing tunnelNew traffic signal

ALISO ST

CMGC Collaboration Opportunities:a. Staging and falsework design to maintain traffic operationsb. Develop construction methods to avoid impacts to the Red Line

tunnel including monitoring

AVOID EXISTINGRED/PURPLE LINE TUNNELS

RECONSTRUCT TRAFFIC ISLAND TO ACCCOMMODATE COLUMN

S

S

Key Features:a. Outrigger bent cap to span tunnel and preserve sight distanceb. Column and abutment foundations to avoid Red/Purple Line tunnel

Key Constraints:a. Vehicle sight distanceb. Avoid Red/Purple Line Tunnelc. Maintain traffic during construction

51

Page 52: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

52

LINK US PHASE A PROJECTArea 3 – Center Street Bridge

TYPICAL SECTION

Key Constraints:a. Vehicle sight distanceb. Vertical clearance under bridgec. Avoid Red/Purple Line Tunnel belowd. Maintain traffic during construction

RED LINE TUNNEL STRUCTURES

Key Features:a. Outrigger bent cap to span tunnel

and preserve sight distanceb. Column and abutment foundations

to avoid Red/Purple Line tunnelc. Columns located to preserve vehicle

sight distance

52

Page 53: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

53

LINK US PHASE A PROJECTArea 4 - BNSF Yard – Project Elements

JAC

KSO

N S

T

METRO CENTERPROJECT SITE

DU

CO

MM

UN

ST

LOS ANGELES RIVERAMTRAK YARD LEAD BRIDGE CONSTRUCT RETAINED FILL SECTION

TO ACCOMMODATE RUN-THROUGH TRACK TRANSITION TO GRADE

RUN-THROUGH TRACKS

CONSTRUCT RETAINING WALL TO ACCOMMODATE LOWERED YARD LEAD

LegendAmtrak Yard Lead BridgeRetained Fill SectionMaintenance Vehicle TunnelStorm Drain Protection Slab

CMGC Collaboration Opportunities:a. Construction methods and abutment

design to maintain track operationb. Optimize lightweight fill retaining walls

and slab bridge protection structure

LOWER AMTRAK YARD LEAD TO ACCOMMODATE RUN-THROUGH TRACK CROSSINGCONSTRUCT PROTECTION SLAB

OVER 12’ DIA COLA STORM DRAIN

CONSTRUCT MAINTENANCE & EMERGENCY ACCESS TUNNEL TO SERVE PORTAL TRENCH

Key Features:a. Lightweight fill retaining wallsb. Box fire/maintenance access tunnelc. Protection slab over storm draind. Lowered Amtrak yard lead

Key Constraints:a. Red Line portal trenchb. 12’ dia COLA storm drainc. Need to maintain Amtrak yard leadd. Track clearance under First St Bridge

53

Page 54: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

54

Benefits of BIM

Implementation of Building InformationModeling (BIM)

Risk Reduction

a. Find Coordination and Construction phasing issues in office rather than in field

Better Inform and Support Cost Estimation

a. Quantities can be dynamically pulled from models and trended over the design lifecycle

Automation of Plan Production from Model

a. Allow multiple alternative analysis when compared to traditional 2D plan production due to dynamic and parametric setup

Enhanced Coordination

a. BIM Models provide effective ways to communicate and coordinate design among multiple stakeholders

542

Page 55: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

55

BIM Roles and Responsibilities

Implementation of Building InformationModeling (BIM)

Design Team

a. Developing 35% plan set to “BIM Ready”

b. Design for 65% and beyond done in BIM

c. Perform Survey Gap analysis to identify additional survey needs

d. Use models to facilitate coordination and communication with value engineering phase

e. Models used to enhance 4D phasing efforts with construction team

f. Models used to enhance 5D cost estimating efforts with construction team

Construction Team

a. 3D coordination with design and trade contractor models

b. Lead 4D phasing efforts with support of design team BIM models

c. Lead 5D cost estimating effort with support of design team BIM models

d. Progress design team BIM models as needed for use in shop drawings (BIM to fabrication models)

e. Generate BIM as-built documentation and models

33

Page 56: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

56

CMGC Phasing and Scope of Services

- Not Funded- Funded

Scott McConnellExecutive Officer, Program

Management and Regional Rail

Page 57: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

57

CMGC - Scope Elements

- Not Funded- Funded

A. Preconstruction Stage• By Fee

B. Construction Stage• By Task Order (Early Construction); or,• By Final Firm Fixed Contract

Page 58: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

58

CMGC - Phasing

- Not Funded- Funded

Page 59: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

59

CMGC - Phasing ScheduleC

ON

STR

UC

TIO

N

Early

Construction

Work

Final Firm

Fixed

Contract

2026 2027

PR

E-

CO

NST

RU

CT

ION CMGC

Procurement

CMGC Precon

Services

2020 2021 2022 2023 2024 2025

Board Approval

35% ~ 65% 90%

Off-ramp

FixedConstruction

NTP

US 101 Viaduct & Highway Modification

Platform 4

Track and Signal Work

Testing

WMH Retaining

Main Street Quiet

RSD

Page 60: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

60

CMGC – Preconstruction Scope of Services

- Not Funded- Funded

A. Constructability Reviews

B. Value Engineering

C. Schedule Management

D. Cost Estimating

E. Risk Management

Page 61: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

61

CMGC – Constructability

- Not Funded- Funded

A. Constructability Reviews

• Develop a Constructability Checklist to be performed at 35%, 65% and 90%

Page 62: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

62

CMGC – Constructability Checklist Example

- Not Funded- Funded

Page 63: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

63

CMGC – Value Engineering

- Not Funded- Funded

B. Value Engineering Analysis • Analysis can be provided during 35%,

65% and 90% Design Stages.• Value Engineering Applicable for only

major items, such as Bridge Span, Piles/Foundation, Track Work, etc.

Page 64: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

64

Scheduling and Cost Estimating

- Not Funded- Funded

Jay YoonDirector of Project Controls, Program

Management and Regional Rail

Page 65: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

65

CMGC – Schedule Management

- Not Funded- Funded

C. Schedule Management

1. CPM (Critical Path Method) Schedule for Precon and Construction Services

2. Cash Flow Analysis

Page 66: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

66

CMGC – Cost Estimating

- Not Funded- Funded

D. Cost Estimating

1. Construction Cost Estimate at 35%, 65%, & 90% design level (100% for US-101 viaduct)

2. Final Firm Fixed Price3. Collaboration with A/E and

Independent Cost Estimator (ICE)

Page 67: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

67

Risk Management

- Not Funded- Funded

Dave DaviesDeputy Executive Officer, Program

Management

Page 68: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

68

CMGC – Risk Management

- Not Funded- Funded

E. Risk Management1. Construction Risk Register will be issued with

the RFP2. Proposers are to identify Project Risks and

include a Risk Register in their Bid Package3. Consultants approach to Risk Management

during pre-construction and construction phases will be a bid evaluation criteria

4. Consultants Risk Register will be rolled into the Metro Risk Register

Page 69: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

69

PRELIMINARY CONSTRUCTION PHASE RISK REGISTERKey Project Risks

1. DWP Power Relocation: Schedule for design, procurement and installation of steel poles

2. Utility conflict not discovered by utility investigation or identified by utility companies

3. Delays due to discovery of historical, cultural or archeological artifacts

4. Construction of structural foundations in close proximity to Red/Purple Line Tunnel

5. Integrating new SCRRA track signals/systems into existing system

6. Boulders and obstructions at pile locations

Page from Project Risk Register

69

Page 70: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

70

CMGC – Risk Management

- Not Funded- Funded

E. Risk Management (Cont)1. Consultant will be an active participant in the risk

management process, both pre-construction and construction

2. During pre-construction a formal quantitative risk analysis will be performed to support the project estimating effort and establish appropriate project contingencies

3. Construction working contingency will be established at the 100% design milestone and the establishment of a GMP

4. Metro will manage the construction working contingency through the Metro Risk, Contingency, and Change Control Procedures

Page 71: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

71

Small Business Requirements

- Not Funded- Funded

Elke CampbellDirector, Diversity & Economic

Opportunity

Metro

Page 72: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

72

Disadvantage Business Enterprise (SBE) Goals & Programs

There will be a total of three (3) SBE Goals, one for each phase of the Project which will be stated in the RFP:

1. Preconstruction Services Phase

2. Early Construction Services Phase

3. Construction Service Phase

Page 73: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

73

Procurement Overview

- Not Funded- Funded

Fred Origel

Director, Contract Administration

Metro

Page 74: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

74

Procurement Overview

Dates Subject to Change

August 3, 2020

INDUSTRY OUTREACH

August 10, 2020

RELEASE RFQ

December 10, 2020

CMGC RFP Due DateMarch 25, 2021

Metro Board Award of CMGC

October 26, 2020

RELEASE RFP

Page 75: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

75

Fred Origel, Director, V/CM

(323) 903-4111 [email protected]

Noelle Santos, Sr. Contract Administrator, V/CM

(213) 922-3647 [email protected]

*During the proposal period, only contact the personnel listed above

with the exception of DEOD, Ethics, and Metro Pre-Qual Dept.

Vendor/Contract Management Points of Contact for this Procurement:

Procurement Overview

Page 76: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

76

QUESTIONS ?

- Not Funded- Funded

Page 77: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

77

Procurement Overview

- Not Funded- Funded

Miriam Long

Director, Diversity & Economic Opportunity Department

Page 78: Link Union Station (Link US) Project · 2020. 8. 7. · 2 - Funded - Not Funded I. WELCOMING REMARKS 9:00 –9:10 am a. CMGC Objectives by Rick Clarke, Metro b. Change to CMGC Approach

78

CLOSING

- Not Funded- Funded

Small Business Programs

1. Meet the Primes

2. DBE Mentoring