Upload
others
View
6
Download
1
Embed Size (px)
Citation preview
1
Link Union Station (Link US) ProjectConstruction Manager/General Contractor (CM/GC)
Industry OutreachAugust 3, 2020
2
- Not Funded- Funded
I. WELCOMING REMARKS 9:00 – 9:10 am
a. CMGC Objectives by Rick Clarke, Metro
b. Change to CMGC Approach by Rick Clarke, Metro
II. LINK US PRESENTATION 9:10 - 9:30 am
a. Project Overview by Jeanet Owens, Metro
b. Project Benefits &
c. Phase A & B
d. Phase A Funding Plan
e. CMGC Key Constraints & Approach
3
- Not Funded- Funded
II. LINK US PRESENTATION (Continue)
d. PE Design by Tom Kim, HDR 10:00 - 10:30 am
i. Key Design Elements
ii. Design Schedule
iii. Subsurface Utility Investigationsi. Geotechnical
iv. Sound Wall & Quiet Zone by Vincent Chio, Metro
v. Station & Platform
vi. Track Alignment
vii. Caltrans Involvement
viii. US 101 Viaduct Structure
ix. 55 Hour Lane Closure Approach
x. ATP & LADWP Overhead Poles
4
- Not Funded- Funded
II. LINK US PRESENTATION (Continue)
e. CMGC Scope of Work 10:00 - 10:30 am
i. Construction Phasing & Schedule by Scott McConnell, Metro
ii. Constructability & Value Engineering by Scott McConnell, Metro
iii.Risk Management by Dave Davies, Metro
iv.Scheduling & Cost Estimating by Jay Yoon, Metro
III. SMALL BUSINESS REQUIREMENTS by Elke Campbell 10:30 - 10:45 am
IV. CMGC PROCUREMENT by Fred Origel, Metro 10:45 - 11:00 am
V. QUESTIONS & ANSWERS by all 11:00 - 11:45 am
VI. Closing by Miriam Long, Metro
5
Welcoming Remarks
- Not Funded- Funded
Rick ClarkeChief Program Management Officer
6
Link Union Station Overview
- Not Funded- Funded
Jeanet OwensSenior Executive Officer, Program Management and Regional Rail
7
Link US Project Overview (Phases A & B)
- Not Funded- Funded
8
The Link to Southern California
9
Los Angeles Union Station TodayBuilt in 1939 | Largest model hub in Southern California
1010
Metro Regional Rail focus on Network Integration
Union Station
1. Los Angeles Union
Station (LAUS) is the
largest multi-modal rail
and transit hub in
Southern California
serving over 100,000
passengers per day.
2. By 2028 Olympics,
LAUS will serve over
200,000 passengers per
day
Proposed Virgin Trains USA To Las VegasHigh Desert
CorridorHigh Speed Rail
VICTORVILLE
METROLINK SYSTEM
Amtrak Pacific Surfliner
1111
Link Union Station Regional Rail Overview
- Not Funded- Funded
Carrier Service # of Weekday Passengers
(2017)
# of WeekdayTrains(2017)
Estimated Number of Weekday Trains
(2040**)
Metrolink Riverside 2,985 12 22
91 / Perris Valley Line 2,608 9 23
Antelope Valley 4,854 30 48
Orange County 7,616 21 41
San Bernardino 7,161 38 48
Ventura 3,276 33 51
LOSSAN Pacific Surfliner 4,100 24 38
Amtrak Southwest Chief; Coast Starlight; Sunset Limited; [2040 includes future Coast Daylight, Coachella Valley]
540 5 9
Total *33,138 172 280
12
What will Link US Provide?
PROJECT BENEFITShttps://call.lifesizecloud.com/4705878
1313
Link US Phase A (Funded)
Combined Run-Through Tracks Structure without the loop track
Key Project Components
1. New rail communication, signals and early tracks to be performed by Metrolink
2. Utility relocation and street improvements
3. Platform #4 and Viaduct structure over the US 101 freeway
Early Track, Signal and
Communication
Improvements
Commercial and
Center Street
Improvements/Utility
Relocation/ROW
Platform 4
Modifications
Two initial run-
through tracks
on a new run-
through track
viaduct structure
1414
LINK US CMGC RFP PHASE B
A separate traditional CMGC RFP Phase B issued in January 2021 for development of 35% Preliminary Engineering Design only and negotiate a separate construction contract once Phase B has been funded.
1515
Concept Rendering – subject to change
1. Raising of entire rail yard from the Vignes Bridge up to 15 feet
2. New Platforms and Expanded Passageway with retail and passenger amenities including escalators and elevators to all platforms
3. Optimization of the throat with a new lead track
Link US Phase B Construction Not Funded
16
Link US Funding Plan (Phase A)
Metro’s funding partners includes CHSRA, CalSTA and SCRRA
Funding Source Amount ($ in millions)
State Proposition 1A/High Speed Rail Bonds $423.335
State Transit Intercity Rail Capital Program (TIRCP) $337.571
State Transportation Improvement Program (STIP) $60.820
Measure R $51.672
SCRRA JPA Contribution (Non-Metro) $40.000
Other HSR Funds $18.726
Measure M $13.274
LOSSAN/Amtrak $5.000
Total $950.398
17
SELECTED CMGC Project Delivery Method
1. Maintain operations at Los Angeles Union Station, largest multi-modal transit terminal in Southern California serving over 100,000 passengers every week day
2. Fixed Budget – Due to the financial constraint of a $950 millionfunding for the entire project, there is very limited ability to absorb cost overruns.
a) Maximize cost and schedule savings with early engagement of the Contractor (constructability review, value engineering analysis, bottom-up construction estimate, risk analysis and construction schedule) at every design submittal.
b) Minimize change orders during construction.
c) Minimize third party delays with flexible phasing plan based on GC construction schedule.
DUE TO 3 KEY CONSTRAINTS:
18
CMGC Project Delivery Method3rd KEY CONSTRAINT: Large Partners & Stakeholders
Key Stakeholders
Funding Partners
Metro CalSta SCRRAHSR
CALTRANSCity of Los
AngelesHSR
William Mead HomesArts District OthersBNSFFRA
LOSSAN/AMTRAK
SCRRA
19
CMGC Project Delivery MethodREVISED APPROACH
1. Classic CMGC Preconstruction Services• One Notice To Proceed for Preconstruction Services with off-ramps• Negotiate fixed lump sum price at 90% Design Plans for Early
Construction Work via Task Order (s)
2. Main Construction Services • Negotiate Final Firm Fixed Price by Supplemental Construction
Contract
20
Environmental
- Not Funded- Funded
Vincent ChioDirector, Metro Rail
Environmental Project Manager
21
LINK UNION STATIONEnvironmental Clearance StatusCalifornia Environmental Quality Act (CEQA)
1. Final EIR: Completed in June 27, 2019 (Board Certified)
2. CEQA Amendment: in Progress thru Spring 2021
A. Permanent BNSF Track Removal (West Bank, 1st Street)
B. BNSF Malabar Yard Improvements (City of Vernon)
❖ 49th Street: Close At-Grade Crossing
❖ 46th Street: Connect existing track segments
National Environmental Policy Act (NEPA)
1. Notice of Intent (NOI) to prepare EIS under FRA: Fall 2016
2. Revised NOI under HSR: Summer 2020 (BNSF West Bank & Malabar Yard)
3. Draft EIS: Spring 2021
4. Final EIS/ROD: Summer 2021 21
22
Preliminary Design
- Not Funded- Funded
Tom KimSenior Vice President, HDR
Link US Project Manager
23
HDR DESIGN TEAM
Tom Kim, PE Project Manager
Mike Grubstein, PEDeputy Project Manager
Andrew Mull, PETrack Lead
Mo Mah, AIA, LEED APArchitecture Lead
Marc Cooley, PECivil Lead
Dan Weddell, PEStructures Lead
Doug Smith, PETraffic Lead
Patrick O’NeilEnvironmental Lead
23
Key Discipline Leads
24
LINK UNION STATION PHASE A KEY DESIGN ELEMENTS
Area 1 - Throat (North of the Station)
Area 2 - Station Area & Platform Modifications
Area 3 - US-101 Viaduct Freeway Improvements & Commercial Street ATP
Area 4 - Run–through Tracks West Bank Tie-In & Bridge over Amtrak Lead 24
25
LINK UNION STATION CMGCList of Key Technical Documents
1. Subsurface Utility Investigation Data Reports
2. Geotechnical reports including boring data
3. Updated 35% Preliminary Engineering Design Plans
4. Caltrans approved Project Study Report/Project Report (PSR/PR)
5. Caltrans approved Type Selection Report for US-101 Bridge
6. Proposed approach to 55 hour lane closure of US-101 for run-through track viaduct construction (LADOT & Caltrans approved)
7. Structure Type Assessment Report for Center Street Bridge
8. Draft preliminary technical specifications
9. Preliminary construction phase risk register
25
26
Phase A Preliminary Design ScheduleSubject to Change
1. Review PE Designs with CMGC: April 2021 –July 2021
2. 65% Design Development: Aug 2021-March 2022
3. 90% Design: April 2022-Oct 2022
4
27
LINK US SUBSURFACE UTILITY INVESTIGATIONSInvestigation Summary by Project Area
1. Metro Property3 trenches and 4 potholes within Metro Division 20 property
2. BNSF Property3 trenches and 4 potholes within BSNF storage track area
3. SCRRA Right of Way12 trenches within rail corridor
4. Union Station Platform Area2 trenches within access road s/o platforms
5. MWD Property1 trench along MWD access road
6. City of LA Local Street Right of Way3 trenches and 3 potholes along Commercial and Vignes Streets
7. Caltrans Right of Way1 trench and 4 potholes within US-101 R/W
8. Amtrak Property3 potholes along Amtrak yard lead track
Total work completed: 24 trenches, 11 potholes
Total work to be completed upon agency approval:5 trenches, 7 potholes
Pothole/Trench Location Map27
28
LINK US GEOTECHNICAL & HAZMAT INVESTIGATIONSSummary of Field Investigations
Anticipated Work AreasCaltrans Right of Way
7 geotechnical borings and 4 hand auger hazmat borings
BNSF Property4 geotechnical borings
Metro Property & Private Property7 geotechnical borings and 1 hand auger hazmat boring
Preliminary Design PhaseTotal work completed: 20 Geotechnical Borings, 21 Shared Geotechnical Borings/Environmental Samples and 22 Hazmat Borings
Final Design PhaseTotal work to be completed: 18 Shared Geotechnical/Environmental Samples Borings and 5 Hazmat Borings
28
29
LINK US GEOTECHNICAL & HAZMAT DOCUMENTS Summary of Technical Documents
Discipline Status Document Title
Geotechnical Completed Preliminary Geotechnical Report- Existing Data, dated July 2016
Geotechnical Completed Draft- Preliminary Geotechnical Design Report - Improvements Outside Caltrans ROW, dated April 2020
Geotechnical Completed Link US Geotechnical Data Report Viaduct Over US 101, dated October 2017
Geotechnical Completed Preliminary Foundation Report Viaduct Over US 101, dated December 2019
Hazmat Completed Phase I Environmental Site Assessment Report, Link Union Station Project Area, dated October 26, 2016
Hazmat Completed Phase I Environmental Site Assessment Report, Los Angeles Union Station Area, dated October 26, 2016
Hazmat Completed Soil Management Plan for Investigations, Link Union Station, dated January 16, 2017
Hazmat Completed Initial Site Assessment Report - Caltrans ROW, dated April 5, 2017
Hazmat Completed Phase II Environmental Site Assessment Workplan, dated September 25, 2017
Hazmat Completed Initial Site Assessment Update Report – Caltrans ROW, dated June 19, 2019
Geotechnical Pending Completion Geotechnical Design Report- Improvements Outside Caltrans ROW
Geotechnical Pending Completion Final Foundation Report Viaduct Over US 101 - Caltrans ROW
Geotechnical Pending Completion Final Foundation Report Retaining Walls - Caltrans ROW
Hazmat Pending Completion Phase II Environmental Site Assessment Report
29
30
UPDATED LINK UNION STATION 35% DESIGNKey Project Changes to Address Stakeholder Comments
Key Changesa) Modified US-101 bridge piles at abutments from driven to CIDH to reduce noise
impacts
b) Modified design of Center Street Bridge to address City comments regarding safety
c) Added tunnel under track section for Metro maintenance/emergency access to Red/Purple Line portal trench
d) Modernized Platform 4 canopy design
e) Implemented ADA improvements along Commercial Street to address City comments
CMGC OpportunitiesModified 35% design for CMGC RFP and provided additional design details not typically provided at 35% to provide better starting point for contractor to review and make VE and constructability recommendations.
30
31
LINK US PHASE A PROJECTArea 1 - William Meade Homes Sound Wall on Retaining Wall
WILLIAM MEAD HOMESSOUND/RETAINING WALL LAYOUT
WILLIAM MEAD HOMES
SOUND WALL ON RETAINING WALL
CMGC Collaboration Opportunities:a. How to minimize impacts to WMH residentsb. Determination of most efficient wall type c. Potential early construction package
Benefits:a. Reduced noise impacts to WMH residents which also
addresses request by Council District 1b. EIR mitigation measure
31
TYPICAL WALL SECTION
32
Looking Southwest from Bolero Lane/Bloom Street
NOISE MITIGATION - SOUND WALL
Conceptual Rendering
32
Existing Conditions Proposed Project - Vegetation (Vines) on Sound Wall and Retaining Wall
33
Noise from Train Operations (Proposed Project)
POTENTIAL IMPACTS MITIGATION
Noise from increased train activitya. Existing sound level – 69dB
(Currently 233 Metrolink and Amtrak trains enter and leave Union Station, including empty trains to Central Maintenance Facility)
b. Year 2040 future sound level – up to 75dB(830 Metrolink, Amtrak, and future High Speed Rail trains is projected to enter and leave Union Station)
Sound wall up to 22 feet tall to mitigate the impacts to less than significant level.a. Future sound level with
the sound wall – 62dB
33
34
TRAIN HORN NOISE NEAR WILLIAM MEAD HOMES
a. 40% of train horns heard at the William Mead Homes in the early morning hours had a noise level over 90 dBA.
b. Under the leadership of Council District 1, Metro is working with City of LA, Metrolink and CPUC on the implementation of the first quiet zone in City of LA.
Over 120 trains cross N Main Street every weekday, starting at around 4am and sounding
the train horns
William Mead Homes
Need for a Quiet Zone at Main Street
34
35
Quiet Zone Ready Improvements at N. Main Street Railroad Grade Crossing
PROPOSED LIMITS OF QUIET ZONE ON THE WEST BANK
N Main St Xing
DWP Pvt Xing
N Main St Xing
0.2
8 m
iles
a. In a Quiet Zone, railroads are directed to cease the routine sounding their horns when approaching public highway-rail grade crossings. Train horns may still be used in emergency situations.
b. Quiet Zones are subject to review and approval by CPUC. City of LA is responsible for applying for a Quiet Zone with the CPUC.
35
36
Quiet Zone Ready Improvements
PROPOSED SAFETY IMPROVEMENTS AT N. MAIN STREET
New Pedestrian Gates and Wider Sidewalks
New Raised Median with New Vehicular Gates
ADA and Access Improvements
New Traffic Signal
New Pedestrian Gates and Wider Sidewalks
36
37
Area 2 Station - Project Elements
MWD
PLATFORM 5
PLATFORM 3
PLATFORM 2
PLATFORM 1
PLATFORM 6
PLATFORM 7
LINK US PHASE A PROJECT
LegendUS-101 ViaductRetained Fill SectionReconstructed access roadExisting PlatformPlatform 4 modifications
SHORTEN/MODIFY PLATFORM 4 TO ACCOMMODATE TRACK RAMP
CONSTRUCT RAMP TO TRANSITION TRACK FROM PLATFORM LEVEL TO BRIDGE LEVEL
PLATFORM 4
CMGC Collaboration Opportunities:a. Plan construction access areas and routesb. Define interim baggage operations and passenger movementsc. Manage passenger movement and access for safety and convenienced. Determination of construction access/methods in confined space
LOWER ACCESS ROAD TO CROSS UNDER TRACK BRIDGE
37
38
Area 2 Station – Platform 4 Modifications
LINK US PHASE A PROJECT
CMGC Collaboration Opportunities:a. Architectural design refinementsb. Managing passenger movement and access during construction
38
39
LINK US PHASE A PROJECT
PROPOSED PLATFORM 4 IMPROVEMENTS WITH NEW CANOPY
Area 2 Station – Platform 4 Modifications
39
40
RUN-THROUGH TRACK ALIGNMENTArea 3 - Track Alignment and Property Needs South of Union Station
110+00
Alignment constrained by the following:a. Existing platforms at LAUSb. El Monte Busway, US-101, and on/off rampsc. Existing Red/Purple Line tunnel and portal trenchd. Center Street crossinge. Future Metro Center Projectf. Existing SCRRA and BNSF track infrastructureg. Existing adjacent developmenth. LADWP electrical transmission corridor
RUN THROUGH TRACKS
COMMERCIAL ST
GA
REY
ST
VIG
NES
ST
CEN
TER
ST
DUCOMMUN ST
SB US 101
NB US 101
LOS
AN
GEL
ES R
IVER
METRO CENTER SITE
LegendProperty AcquisitionEl Monte BuswayRun through tracks 40
UNION STATION
41
LINK US PHASE A PROJECTArea 3 – Run-through Track Structure South of Union Station
COMMERCIAL ST
CEN
TER
ST
SB US 101
NB US 101
UNION STATION
VIG
NES
ST
GA
REY
ST
DUCOMMUN ST
CENTER ST BRIDGE
MAINTENANCE VEHICLE ACCESS TUNNEL
RETAINED FILL SECTION
RETAINED FILL SECTION
EL MONTE BUSWAY
41
US-101 VIADUCT
42
Preliminary Design Phasea. Design exceptions for freeway geometry approved
b. Project Report approval expected August 2020
c. Type Selection Report approval expected August 2020
CMGC Collaboration Design Phasea. Review and approval of US-101 bridge and freeway
modification design packages
b. Open to early construction packages such as foundation installation
c. Working with designer and contractor on aesthetic treatments
Area 3 – Caltrans Involvement During Preliminary Engineering and CMGC Phases
LINK US PHASE A PROJECT
42
43
LINK US PHASE A PROJECTArea 3 – US 101 Viaduct and Freeway Modifications
COMMERCIAL ST
NB US 101
UN
ION
STA
TIO
NLegend
US-101 ViaductRetained Fill SectionEl Monte Busway PATSAOURAS
PLAZA
GA
REY
ST
VIG
NES
ST
CMGC Collaboration Opportunities:a. Construction staging of the bridge and freeway
improvements
Key Constraints:a. Preserve SB on-ramp geometryb. Provide std vertical clearance over US-101 and buswayc. Maintain US-101 thru lanes during construction
Key Features:a. Construct viaduct with 12’ to 14’ CIDH pilesb. Reconstruct retaining walls along El Monte Buswayc. Restripe US-101 to provide space for bridge bentsd. Reconstruct NB on-ramp from Vignes St
43
44
LINK US PHASE A PROJECTArea 3 – US 101 Viaduct
LOWER RUN-THROUGH TRACK PROFILE IN
PHASE A
Key Features:a. Spans 1-3 & 7-9 precastb. Spans 4-6 are CIP delta boxc. Bents 5 &6 are outriggers over
SB US-101d. Portion of Phase A deck profile
lower than ultimate
CMGC Collaboration Opportunities:a. Construct Spans 1 through 3 to
be raised in the futureb. Bridge and wall aestheticsc. Freeway closure schedule for
falsework and girder erection
TYPICAL SECTION ALONG BENT 2
TYPICAL SECTION ALONG BENTS 6R AND 6L44
45
APPROACH TO 55 HOUR LANE CLOSURE FOR CONSTRUCTION OF RUN-THROUGH TRACK BRIDGEArea 3 – Requires Joint Approval by Caltrans & LADOT
45
Proposed Closure (Year 2022)a. 55 Hours on Weekend
b. Closure Duration: From Friday 10 PM to Monday 5 AM
c. 5 Weekend Closure in NB US-101 and 5 Weekend Closure in SB US-101
d. Only 1 direction of US-101 will be closed on a particular weekend
Executive Summarya. Tested three Diversion Patterns (60/40, 70/30, 100/0)
b. Tested two traffic levels (Actual at 5600 - 5800 vph and Max. Theoretical)
• Not a substantial difference
• Year 2022 Projections for Saturday Peak Hours, NB and SB
• Some freeway segments hit capacity at 70/30
• NB closure more complex
46
APPROACH TO 55 HOUR LANE CLOSURE FOR CONSTRUCTION OF RUN-THROUGH TRACK BRIDGEArea 3 – Requires Joint Approval by Caltrans & LADOT
46
TMP LOS Results
Using 70-30 split for NB and SB closure and existing volumes:
a. 2 Freeway segments impacted
b. 5 intersections impacted
47
APPROACH TO 55 HOUR LANE CLOSURE FOR CONSTRUCTION OF RUN-THROUGH TRACK BRIDGEArea 3 – Requires Joint Approval by Caltrans & LADOT
47
Proposed Recommendationsa. Maximum diversion is a 70/30
b. SB US 101 closure should stay open to Los Angeles Street
c. NB US 101 could close at I-5/I-10 Interchange with support from diversion to I-710
d. Significant Regional SB diversion needed for SB closure
e. I-110/I-10 ramps will need support
f. Significant public information campaign will be needed
Next Steps a. Work with Caltrans and LADOT to receive concurrence by August 2020
b. Work with CMGC on preparing Transportation Management Plan (TMP) and construction phasing
48
LINK US PHASE A PROJECTArea 3 – Proposed Active Transportation Improvements
View from Southeast Corner of Commercial/Garey Intersection
Note: Per agreement with City of LA, active transportation is limited to Class IV bike lanes only with bollards and associated restriping (no R/W takes included)
48
49
Area 3 – Existing LADWP Power Lines & Poles in Conflict with Project
COMMERCIAL ST
VIG
NES
ST
CEN
TER
ST
SB US 101
LegendExisting power polesExisting power poles in conflictExisting overhead power lines
LINK US PHASE A PROJECT
a. Conflicts to be mitigated through relocation strategy that involves both underground and overhead relocations to be designed and constructed by LADWP
b. Overhead relocations require use of engineered steel poles
ALISO ST
49
50
Area 3 – Relocation of Impacted Power Facilities by LADWP
Completion of Relocation Design and Construction is Time Sensitive:a. 18 month fabrication time for required engineered steel polesb. 1 year for relocation construction by LADWPc. Relocations need to be completed ahead of bridge construction
To Initiate Relocation Design, LADWP Needs Confirmation of Proposed Locations of:a. Curb, sidewalk, and curb rampsb. Street treesc. Street lightsd. Catch basinse. Other features that could influence pole placement
Project engineers to advance design to provide requested information and obtain
City of LA approval
LINK US PHASE A PROJECT
50
51
LINK US PHASE A PROJECTArea 3 – Center Street Bridge
COMMERCIAL ST
CEN
TER
ST
SB US 101
LegendCenter St BridgeRetained Fill SectionLimits of existing tunnelNew traffic signal
ALISO ST
CMGC Collaboration Opportunities:a. Staging and falsework design to maintain traffic operationsb. Develop construction methods to avoid impacts to the Red Line
tunnel including monitoring
AVOID EXISTINGRED/PURPLE LINE TUNNELS
RECONSTRUCT TRAFFIC ISLAND TO ACCCOMMODATE COLUMN
S
S
Key Features:a. Outrigger bent cap to span tunnel and preserve sight distanceb. Column and abutment foundations to avoid Red/Purple Line tunnel
Key Constraints:a. Vehicle sight distanceb. Avoid Red/Purple Line Tunnelc. Maintain traffic during construction
51
52
LINK US PHASE A PROJECTArea 3 – Center Street Bridge
TYPICAL SECTION
Key Constraints:a. Vehicle sight distanceb. Vertical clearance under bridgec. Avoid Red/Purple Line Tunnel belowd. Maintain traffic during construction
RED LINE TUNNEL STRUCTURES
Key Features:a. Outrigger bent cap to span tunnel
and preserve sight distanceb. Column and abutment foundations
to avoid Red/Purple Line tunnelc. Columns located to preserve vehicle
sight distance
52
53
LINK US PHASE A PROJECTArea 4 - BNSF Yard – Project Elements
JAC
KSO
N S
T
METRO CENTERPROJECT SITE
DU
CO
MM
UN
ST
LOS ANGELES RIVERAMTRAK YARD LEAD BRIDGE CONSTRUCT RETAINED FILL SECTION
TO ACCOMMODATE RUN-THROUGH TRACK TRANSITION TO GRADE
RUN-THROUGH TRACKS
CONSTRUCT RETAINING WALL TO ACCOMMODATE LOWERED YARD LEAD
LegendAmtrak Yard Lead BridgeRetained Fill SectionMaintenance Vehicle TunnelStorm Drain Protection Slab
CMGC Collaboration Opportunities:a. Construction methods and abutment
design to maintain track operationb. Optimize lightweight fill retaining walls
and slab bridge protection structure
LOWER AMTRAK YARD LEAD TO ACCOMMODATE RUN-THROUGH TRACK CROSSINGCONSTRUCT PROTECTION SLAB
OVER 12’ DIA COLA STORM DRAIN
CONSTRUCT MAINTENANCE & EMERGENCY ACCESS TUNNEL TO SERVE PORTAL TRENCH
Key Features:a. Lightweight fill retaining wallsb. Box fire/maintenance access tunnelc. Protection slab over storm draind. Lowered Amtrak yard lead
Key Constraints:a. Red Line portal trenchb. 12’ dia COLA storm drainc. Need to maintain Amtrak yard leadd. Track clearance under First St Bridge
53
54
Benefits of BIM
Implementation of Building InformationModeling (BIM)
Risk Reduction
a. Find Coordination and Construction phasing issues in office rather than in field
Better Inform and Support Cost Estimation
a. Quantities can be dynamically pulled from models and trended over the design lifecycle
Automation of Plan Production from Model
a. Allow multiple alternative analysis when compared to traditional 2D plan production due to dynamic and parametric setup
Enhanced Coordination
a. BIM Models provide effective ways to communicate and coordinate design among multiple stakeholders
542
55
BIM Roles and Responsibilities
Implementation of Building InformationModeling (BIM)
Design Team
a. Developing 35% plan set to “BIM Ready”
b. Design for 65% and beyond done in BIM
c. Perform Survey Gap analysis to identify additional survey needs
d. Use models to facilitate coordination and communication with value engineering phase
e. Models used to enhance 4D phasing efforts with construction team
f. Models used to enhance 5D cost estimating efforts with construction team
Construction Team
a. 3D coordination with design and trade contractor models
b. Lead 4D phasing efforts with support of design team BIM models
c. Lead 5D cost estimating effort with support of design team BIM models
d. Progress design team BIM models as needed for use in shop drawings (BIM to fabrication models)
e. Generate BIM as-built documentation and models
33
56
CMGC Phasing and Scope of Services
- Not Funded- Funded
Scott McConnellExecutive Officer, Program
Management and Regional Rail
57
CMGC - Scope Elements
- Not Funded- Funded
A. Preconstruction Stage• By Fee
B. Construction Stage• By Task Order (Early Construction); or,• By Final Firm Fixed Contract
58
CMGC - Phasing
- Not Funded- Funded
59
CMGC - Phasing ScheduleC
ON
STR
UC
TIO
N
Early
Construction
Work
Final Firm
Fixed
Contract
2026 2027
PR
E-
CO
NST
RU
CT
ION CMGC
Procurement
CMGC Precon
Services
2020 2021 2022 2023 2024 2025
Board Approval
35% ~ 65% 90%
Off-ramp
FixedConstruction
NTP
US 101 Viaduct & Highway Modification
Platform 4
Track and Signal Work
Testing
WMH Retaining
Main Street Quiet
RSD
60
CMGC – Preconstruction Scope of Services
- Not Funded- Funded
A. Constructability Reviews
B. Value Engineering
C. Schedule Management
D. Cost Estimating
E. Risk Management
61
CMGC – Constructability
- Not Funded- Funded
A. Constructability Reviews
• Develop a Constructability Checklist to be performed at 35%, 65% and 90%
62
CMGC – Constructability Checklist Example
- Not Funded- Funded
63
CMGC – Value Engineering
- Not Funded- Funded
B. Value Engineering Analysis • Analysis can be provided during 35%,
65% and 90% Design Stages.• Value Engineering Applicable for only
major items, such as Bridge Span, Piles/Foundation, Track Work, etc.
64
Scheduling and Cost Estimating
- Not Funded- Funded
Jay YoonDirector of Project Controls, Program
Management and Regional Rail
65
CMGC – Schedule Management
- Not Funded- Funded
C. Schedule Management
1. CPM (Critical Path Method) Schedule for Precon and Construction Services
2. Cash Flow Analysis
66
CMGC – Cost Estimating
- Not Funded- Funded
D. Cost Estimating
1. Construction Cost Estimate at 35%, 65%, & 90% design level (100% for US-101 viaduct)
2. Final Firm Fixed Price3. Collaboration with A/E and
Independent Cost Estimator (ICE)
67
Risk Management
- Not Funded- Funded
Dave DaviesDeputy Executive Officer, Program
Management
68
CMGC – Risk Management
- Not Funded- Funded
E. Risk Management1. Construction Risk Register will be issued with
the RFP2. Proposers are to identify Project Risks and
include a Risk Register in their Bid Package3. Consultants approach to Risk Management
during pre-construction and construction phases will be a bid evaluation criteria
4. Consultants Risk Register will be rolled into the Metro Risk Register
69
PRELIMINARY CONSTRUCTION PHASE RISK REGISTERKey Project Risks
1. DWP Power Relocation: Schedule for design, procurement and installation of steel poles
2. Utility conflict not discovered by utility investigation or identified by utility companies
3. Delays due to discovery of historical, cultural or archeological artifacts
4. Construction of structural foundations in close proximity to Red/Purple Line Tunnel
5. Integrating new SCRRA track signals/systems into existing system
6. Boulders and obstructions at pile locations
Page from Project Risk Register
69
70
CMGC – Risk Management
- Not Funded- Funded
E. Risk Management (Cont)1. Consultant will be an active participant in the risk
management process, both pre-construction and construction
2. During pre-construction a formal quantitative risk analysis will be performed to support the project estimating effort and establish appropriate project contingencies
3. Construction working contingency will be established at the 100% design milestone and the establishment of a GMP
4. Metro will manage the construction working contingency through the Metro Risk, Contingency, and Change Control Procedures
71
Small Business Requirements
- Not Funded- Funded
Elke CampbellDirector, Diversity & Economic
Opportunity
Metro
72
Disadvantage Business Enterprise (SBE) Goals & Programs
There will be a total of three (3) SBE Goals, one for each phase of the Project which will be stated in the RFP:
1. Preconstruction Services Phase
2. Early Construction Services Phase
3. Construction Service Phase
73
Procurement Overview
- Not Funded- Funded
Fred Origel
Director, Contract Administration
Metro
74
Procurement Overview
Dates Subject to Change
August 3, 2020
INDUSTRY OUTREACH
August 10, 2020
RELEASE RFQ
December 10, 2020
CMGC RFP Due DateMarch 25, 2021
Metro Board Award of CMGC
October 26, 2020
RELEASE RFP
75
Fred Origel, Director, V/CM
(323) 903-4111 [email protected]
Noelle Santos, Sr. Contract Administrator, V/CM
(213) 922-3647 [email protected]
*During the proposal period, only contact the personnel listed above
with the exception of DEOD, Ethics, and Metro Pre-Qual Dept.
Vendor/Contract Management Points of Contact for this Procurement:
Procurement Overview
76
QUESTIONS ?
- Not Funded- Funded
77
Procurement Overview
- Not Funded- Funded
Miriam Long
Director, Diversity & Economic Opportunity Department
78
CLOSING
- Not Funded- Funded
Small Business Programs
1. Meet the Primes
2. DBE Mentoring