1/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 1 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
LIST OF CONTENTS
1. PLANT DETAILS
2. TESTING OBJECTIVES
3. TESTING PROPOSALS
4. SERVICES REQUIRED
5. SAFETY PRECAUTIONS
6. EMERGENCY PROCEDURES
7. STATE OF THE PLANT
8. COMMISSIONING PROCEDURE
9. COMPLETION CRITERIA
10.APPENDICES
7/27/2019 Line Bay
2/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 2 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
1. PLANT DETAILS:
The system consists of
i. 400 kv line
ii. 400 kv switchyard feeder equipments
a) Lightning arrestor
b) Capacitor Voltage Transformer
c) Current transformers
d) Isolators
e) Earthswitches
f) Circuit breaker
iii. Control & Relay panels
MAKE : BHEL BHOPAL
RELAYS MOUNTED : LBB (ALSTOM Make,MCTI-40 Type)
(R,Y, B PHASES) Instantaneous Diff. Relay(ALSTOM Make,CAG-
34 Type)
Biased Differential Relay (ALSTOM Make,MBCH-13 Type)
Over Voltage Relay (ALSTOM Make, VTU 21 Type)
Distance relays for line protection(ALSTOM Make, EPAC
Type, MICROMHO-SHNB Type)
Line bay can be charged/commissioned in two ways
1 By charging the 400 KV main buses through Generator supply via
Generator transformer.Closing the breaker isolators,line isolators
7/27/2019 Line Bay
3/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 3 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
and Circuit breaker,Generator supply will be sent to Grid through
the main line after synchronization with the Generator supply.
2 By backcharging the bay through the line,for which, line isolator is
closed at first and the breaker isolator and circuit breaker are
closed subsequently after getting all required permissives.
7/27/2019 Line Bay
4/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 4 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
2. TESTING OBJECTIVE:
2.1To test and charge/commission the line bay and
2.2 extend the power upto the line
2.3To charge the main bus 1&2 after getting supply from the line
7/27/2019 Line Bay
5/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 5 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
3. TESTING PROPOSAL:
3.1 To test the protection relays for line bay in the Relay panel through
secondary injection
3.2 Scheme checking by green marking
3.3 To check the interlocking scheme
3.4 To check the voltage selection and synchronizing circuit
3.5 Secondary injection of CVT
3.6 To check the alarm/annunciation circuits
3.7 To check the event logger circuits
3.8 To check the disturbance recorder signals
3.9 To check the remote operation of yard equipments and their status in the
control panel
3.10 To check trip logics of Circuit breaker
3.11 Primary injection of current transformer
3.12 To check the stability of Tee differential protection
3.13 To check the stability of busbar protection
3.14 Final meggering of 400 KV bus before charging the line bay
7/27/2019 Line Bay
6/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 6 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
4. SERVICES REQUIRED:
4.1 Calibrated Test Kit
a. 5 KV DC Hand/Motorised Megger
b. 500 V DC Megger
c. Digital Multimeter
d. Clamp-on meter for current measurement
e. Phase sequence meter
4.2 ZFB Kit
4.3 Current Injection Kit (Primary & Secondary)
4.4 3 Phase 415 V AC 50 Hz Supply
4.5 Walkie talkie set for communication
7/27/2019 Line Bay
7/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 7 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
5. SAFETY PRECAUTIONS:
5.1 The engineer-in-charge of the testing team will inform each member of
the test as to exact nature and extent of his contribution and
responsibilities towards tests carried out.
5.2 Only nominated persons will take part in the tests. All others will remain
clear of the area.
5.3 All persons must acquaint themselves with use and location of fire
extinguishers and First-Aid Box.
5.4 Each test will be carried out under the control of test team leader
5.5 A strict and safe method of applying test leads shall be practiced. Bare
wires should not be used in stead proper lugs must be used. All test
connections shall be tightened and rechecked.
5.6 A record of any alterations made during the tests such as shorts or
disconnections shall be made and annexed to the relevant test
procedures.
5.7 Each test will be carefully planned so that there is no mechanical or
electrical damage to the equipment under test.
5.8 Test area will be kept clean ,clearly defined and cardoned off.
5.9 When high voltage test are being made Danger/Warning notices shall
be fixed at relevant points to ensure safety and a sanction for test taken.
All isolating points to be manned.
7/27/2019 Line Bay
8/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 8 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
6. EMERGENCY PROCEDURE:
6.1 Shock treatment chart and first-aid box will be made available.
6.2 Emergency telephone numbers for hospital and fire services shall be
prominently displayed.
6.3 A telephone will be available nearby
7/27/2019 Line Bay
9/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 9 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
7. STATE OF THE PLANT:
7.1 Erection of line bay equipments as listed in plant details are completed.
7.2 Earthing of the equipments completed
7.3 Oil level in CT,CVT & Circuit Breaker is OK.
7.4 400 KV Bus Bar is dead
7.5 Clearance from erection department for carrying out various tests obtained.
7.6 Area of test is completely isolated from illegal entry of trespassers
7/27/2019 Line Bay
10/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 10 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
8. COMMISSIONING PROCEDURE:
8.1 Testing of protection relays in Relay panel
The relays mounted in Relay panel are tested as per the checklist
8.2 Scheme checking by green marking :
The schematic drawings are fully checked for all trip logics, alarm/
annunciation logic and control logics by simulating the actual conditions. In
this manner, all the internal wiring/bus wiring of the control /Relay panel is
checked with the help of a digital multimeter and a continuity tester. Each
and every circuit is then green marked with the help of a highlighter.
8.3 Interlocking scheme checking:
The interlocking scheme is checked as per the schematic drawings(viz
schematic diagram No. 3 562 006 0296) for the sequential and correct
operation of isolators, circuit breaker and earthswitches.
8.4 Checking of Voltage selection and synchronizing circuit:
To check the voltage selection circuit and synchronisation circuit,selectedvoltage of Bus-1 and Bus-2 are extended to metering circuit andsynchronisation circuit through relays 75A and 75 B. Relays 75A & 75Boperate depending upon the selection of Main bus-1/2.
8.5 SECONDARY INJECTION OF CVT:
This involves passing current/voltage through protection relays i.e.
simulating CVT output voltages, and confirming correct operation at twosettings. The relay then has its recommended settings applied and theoperation is rechecked to confirm the set values of voltage. If applicable, thetimer of the relay is also tested. Modern relays, particularly those mounted inmodular cases, can be tested in panel by injection of a special plugconnected to the secondary injection test set.
7/27/2019 Line Bay
11/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 11 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
8.6Alarm/Annunciator circuit checking:The Alarm/Annunciator circuit is checked as per the schematic drawings(vizschematic diagram No. 3 562 006 0296)
8.7Checking of Event logger circuits:The checking for Event logger circuits are carried out as per their StandardCheck list.
8.8 Checking of Disturbance recorder signals:The checking for Disturbance recorder signals are carried out as per theirStandard Check list.
8.9 Remote operation of Yard equipments from the control panel:
Remote operation of Isolators and circuit breaker are done by givingmanual command from the control panel through a rotary switch and itsclose/open status is verified from glowing of signal lamps mounted oncontrol panel.
8.10 TRIP LOGICS OF CIRCUIT BREAKER:
Various protections / schemes are provided in a feeder / Transformer bay for
the safety of the equipment / system viz. LBB, Busbar, Over-current,
Restricted earth fault etc. The operation of the relays designated for the
above-mentioned protections can be tested by secondary injection. These
relays give command to a master trip relay, which in turn gives command to
the Breaker to trip, thus isolating the rest of the equipments from the faulty
zone.
In system-level testing, all trip tests of the Breaker are performed before
charging the system. The format for the above tests is to be filled in the
following way:
7/27/2019 Line Bay
12/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 12 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
TABULATION OF TRIP LOGICS
SL.
NO.
DESCRIPTION
TEST
SOURCE OF
INITIATION
WINDOW
DESCRIPTION
RESULT
OK/NOTOK
REMARKS
CLOSE THE BREAKERAND TRIP THROUGHPROTECTION WHICH
ARE APPLICABLE
PROTECTIONRELAY ASPER SCHEME.
BREAKERAUTO TRIP
I) MAIN - I BREAKERAUTO TRIP
II) MAIN - II BREAKERAUTO TRIP
III) OVER VOLTAGE BREAKERAUTO TRIP
IV) LBB BREAKERAUTO TRIP
V) BUS BAR BREAKERAUTO TRIP
VI) TEE DIFFERENTIAL I &II
BREAKERAUTO TRIP
8.11 PRIMARY INJECTION OF CURRENT TRANSFORMER:
This type of test involves each protection circuit, including all interconnectingwiring. It is usually carried out as a final proving test to ensure that allterminations are correct and that all CTs are mounted correctly. Typically, aprimary injection test set of up to 100A output should be adequate for themajority of circuits encountered in a switchyard.It is customary to see the operation of the relay during Primary injection. TheBreaker should trip as the relay operates. If required, the relay setting belowered to facilitate the operation of relay.
The observations can be recorded in the enclosed test format:
8.12 Checking the stability of TEE Differential Protection:
a) Through faultFollowing is the format for this testCTs involved :Stability : Through faultPhase :
7/27/2019 Line Bay
13/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 13 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
Procedure : Select any two CTs out of 3 CTs of TEE formation ofbusbar.Close the concerned isolator & circuit breaker connecting these twoselected CTs. Primary current is injected from P1 terminal of One of the
CTs(Say first CT) through a primary injection kit whose another end isconnected to earth. Close the Earthswitch after the P2 terminal of theSecond CT for return path so that primary current flows through both CTsand gets earthed after Second CT. In through fault stability or out zonefault,current in neutral circuit should be negligible. I.e. current in First CTssecondary circuit should balance with the current in second CTs secondarycircuit provided their polarity is correctly matched.
PRIMARYCURRENT
PANELREFERENCE
TERMINALBLOCKNO.
RATIOUSED
ABSOLUTEVALUE OFSEC.CURRENT
RELAYCIRCUIT
Remarks:
b) Zone faultFollowing is the format for this testCTs involved :Stability : In Zone or Zone faultPhase :
Procedure : Select any one CT out of 3 CTs of TEE formation ofbusbar. Primary current is injected from P1 terminal of the CT through aprimary injection kit whose another end is connected to earth. Close theEarthswitch after the P2 terminal of the CT for return path so that primarycurrent flows through CT and gets earthed after the CT. In Zone faultstability or zone fault, current in secondary will not be balanced and relaywill sense differential current.87TT1 & 87TT2 relays are set at a particularvalue . Increase the primary current from Zero to a value for which relay inthe secondary circuit operates. Note those values as follows
PRIMARYCURRENT
PANELREFERENCE
TERMINALBLOCK
NO.
RATIOUSED
ABSOLUTEVALUE OF
SEC.CURRENT
RELAYCIRCUIT
Observation :Remarks :
7/27/2019 Line Bay
14/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 14 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
8.13 Checking the stability of Bus bar Differential Protection:
a) Through fault
Following is the format for this testCTs involved :Stability : Through faultPhase :Procedure : Select two CTs of same phase of the busbar. Close theconcerned isolator & circuit breaker connecting these two CTs. Primarycurrent is injected from P1 terminal of One of the CTs(Say first CT) througha primary injection kit whose another end is connected to earth. Close theEarthswitch after the P2 terminal of the Second CT for return path so thatprimary current flows through both CTs and gets earthed after Second CT.In through fault stability or out zone fault, current in neutral circuit should be
negligible. I.e. current in First CTs secondary circuit should balance withthe current in second CTs secondary circuit provided their polarity iscorrectly matched.
PRIMARYCURRENT
PANELREFERENCE
TERMINALBLOCKNO.
RATIOUSED
ABSOLUTEVALUE OFSEC.CURRENT
RELAYCIRCUIT
Remarks:b) Zone faultFollowing is the format for this testCTs involved :Stability : In Zone or Zone faultPhase :Procedure : Select any one CT out of above selected 2 CTs. Primarycurrent is injected from P1 terminal of the CT through a primary injection kitwhose another end is connected to earth. Close the Earthswitch after theP2 terminal of the CT for return path so that primary current flows throughCT and gets earthed after the CT. In Zone fault stability or zone fault,
current in secondary will not be balanced and relay will sense differentialcurrent. Bus bar differential relays, MBCZ(Main-1) & PBDCB(Main-2), areset at a particular value . Increase the primary current from Zero to a valuefor which relay in the secondary circuit operates. Note those values asfollows.
7/27/2019 Line Bay
15/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 15 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
PRIMARYCURRENT
PANELREFERENCE
TERMINALBLOCKNO.
RATIOUSED
ABSOLUTEVALUE OFSEC.
CURRENT
RELAYCIRCUIT
Observation :
Remarks :
8.14 Final meggering of 400 KV Line:Final Insulation Resistance is measured using a 5 KV Motorised Megger forchecking the healthiness of insulators. It is measured between pole-to-poleand between each pole and earth.
7/27/2019 Line Bay
16/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 16 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
9. COMPLETION CRITERIA:
ALL MEASUREMENTS TAKEN DURING TESTS HAVE BEEN
RECORDED AND FOUND IN ACCEPTANCE LIMITS. LINE BAY IS
CLEARED FOR COMMISSIONING/CHARGING.
7/27/2019 Line Bay
17/17
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 17 of 17
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : LINE BAY COMMISSIONING
10. APPENDICES:
DRAWING :
1. SINGLE LINE DIAGRAM OF 400 KV SWITCHYARD(NO: TB DG 186
510 0101,REV 02)
2. OGA DRAWINGS OF CT,CVT & LIGHTNING ARRESTORS(No: TB
DG 186 316 0241/01,251/01 & 351/01)
3. SCHEMATIC DRAWINGS FOR ISOLATORS AND EARTHSWITCHES
(No: 3 562 510 0277)
4. SCHEMATIC DRAWINGS FOR CONTROL & RELAY PANELS for
LINE-1 & 2(NO: 3 562 006 0296/Rev 03) and LINE-3 & 4(NO: 3 562
006 0298,Rev 02)