Upload
anthony-mckenzie
View
215
Download
0
Embed Size (px)
Citation preview
Lincoln Public School- Lincoln, MA
Lincoln Public Schools2
March 8, 2011Meeting #2
Agenda
Consultant Introductions
Work Plan
Project Update
Site Analysis
Building Analysis
Space Usage Summary
Educational Philosophy Summary
Next Steps
Lincoln Public Schools3
March 8, 2011Meeting #2
Consultants
Nitsch Engineering, Inc.• Sandra Brock, PE, LEED AP - Civil Engineer
Foley Buhl Roberts & Associates, Inc• Jonathan Buhl, PE - Structural Engineer
Garcia.Galuska.DeSousa Consulting Engineers Inc.• Carlos DeSousa, PE – Electrical Engineer • Dominick Puniello, PE, LEED AP – Mechanical Engineer• Christopher Garcia, PE – Plumbing/ Fire Protection Engineer
Lincoln Public Schools4
March 8, 2011Meeting #2
Groundwork o Review existing conditions informationo Prepare schedule and work plan
Meeting # 1 Goals, Values and Visioning
Objectives Follow-upo Review schedule and process o Discuss goals, valueso Discuss upcoming Visioning sessions
o Site walk thru with Engineers and Facilities Coordinatoro Conduct Visioning Sessionso Conduct User Group meetings
Meeting # 2 Site Analysis, Existing Conditions, Building Usage and Philosophy
Objectives Follow-up
2/08/11
3/08/11
o Prepare contracto Obtain and review all available/ pertinent documents
o Review Educational Philosophyo Review site analysis, existing conditions and space usage
o Prepare goals and values from four visioning sessionso Prepare Initial Space Summaryo Develop evaluation criteria for preliminary alternatives
Meeting # 3 Goals, Values and Initial Space Summary
Objectives Follow-up3/22/11o Submit initial space summary to MSBA for reviewo Develop Preliminary Alternative Concepts
Meeting # 4 & 5 Preliminary Alternative Concepts
Objectives Follow-up4/05/11;4/12/11 o Review and Approve Preliminary Alternative Concepts
o Approve Preliminary Design Program Submission
o Complete Preliminary Design Program Submittal for MSBAo Meet with MSBAo Develop Proposed Alternatives & Preliminary Evaluation
Meeting # 6 Preliminary Evaluation of Proposed AlternativesObjectives Follow-up4/26/11o Review Preliminary Evaluation of Proposed Alternatives o Submit Preliminary Alternatives to MSBA for review
o Meet with MSBAo Develop Selected Alternatives and evaluate
Meeting # 7 Finalize Preliminary Alternatives
Objectives Follow-up5/10/11o Review and Approve Preliminary Alternative(s) o Develop Final Evaluation of Alternatives & Preferred Solution
Meeting # 8 Final Evaluation of AlternativesObjectives Follow-upo Review Final Evaluation of Alternatives & Confirm Preferred Solution o Prepare Preferred Schematic Report
5/24/11
*
Lincoln School Feasibility Study Work Plan
Meeting # 9 Preferred Schematic Report
Objectives Follow-upo Review and Approve Preferred Schematic Report o Submit Preferred Schematic Report to MSBA
o MSBA Facilities Assessment Subcommittee and BOD Vote
6/07/11
o Review goals and valueso Review and Approve Initial Space Summaryo Establish Alternative Evaluation Criteria
Lincoln Public Schools5
March 8, 2011Meeting #2
Project Update
• Analysis of Existing Conditions and Reports
- Civil/Landscape- Architectural- MEP/FP - Structural- Food Service- Hazardous Materials
• Educational Program/Philosophy Meeting with LPS Administration
• School, Multi-Board and Community Visioning Meetings
• Initial User Group Programming Meetings (3 Days)
Lincoln Public Schools6
March 8, 2011Meeting #2
N
Site Analysis - Natural Features
WetlandsWetlands
Wetlands
FIELDHOUSE
BROOKS SCHOOL
LINK
SMITH SCHOOL
Warm Summer Breezes
Cold Winter Winds • Solar Orientation
• Winds
• Tree Line/Wooded Areas
• Stream
• Wetlands
• 50 Foot Buffer
• 100 Foot Buffer
JUNE 21 AM
JUNE 21 PM
DEC 21 AM
MARCH 21 AMMARCH 21
PM
DEC 21 PM
LINCO
LN R
OAD
BALLFIELD ROAD
HARTWELL
PODS
Lincoln Public Schools7
March 8, 2011Meeting #2
Site Analysis - Built Environment
N
• Vehicular Traffic
• Athletic Fields
• Playgrounds
• Community Spaces- Interior- Exterior- External program
• Views
• Neighbors
• Septic
• Emergency Drive
• Main Entrances
• Parking
• Property Line
• Conservation Land
LINCO
LN R
OAD
HARTWELL
PODS
Play
Play
Play
Play
Play
Play
SMITH SCHOOL
LINK
BROOKS SCHOOL
FIELDHOUSE
*
*
*
*
*
*
Lincoln Public Schools8
March 8, 2011Meeting #2
Site Analysis - Site Circulation
N
• Parking- Remote from controlled entrances
• Buses- 3 Drop- off locations
• Inadequate parking at main entrances
• Inadequate parking for community use
• Congestion at Smith drop-off
LINCO
LN R
OAD
HARTWELL
PODSSMITH
SCHOOL
LINK
BROOKS SCHOOL
FIELDHOUSE
12
3
Lincoln Public Schools9
March 8, 2011Meeting #2
Site Analysis - General Site/Civil/Fields
View Across Playfields View at Smith Lot Exit
Site Issues
• Storm drainage appears insufficient; ponding observed along paved edges
• Downspouts discharge directly onto ground
• Parking lot to east of Reed half underwater occasionally
• Driveways, parking lots, sidewalks and curbs in fair to poor condition
• Handicap accessibility does not meet MAAB code
• Water table is high, causing seasonal wet conditions at fields
Lincoln Public Schools10
March 8, 2011Meeting #2
Permitting Issues - Wetlands
• Wetlands Protection Act (310 CMR 10.00) – The site falls within an environmentally sensitive area and a Notice of Intent is required, the wetland resource areas include:
• Riverfront – Critical to have the limit of Riverfront determined, this has a direct impact on project
• Bordering Vegetated Wetlands• Bank• Land Underwater
• Lincoln Wetlands Protection Bylaw - includes 50-foot “no disturb area”
• Natural Heritage & Endangered Species – the site does not fall within Priority or Estimated Habitat and does not contain a certified vernal pool per MASSGIS
• Flood Plain – the majority of the site is not located within a 100-year floodplain. There is a 100-year floodplain associated with Stony Brook but is generally confined to Stony Brook channel.
Limit of Riverfront Area?
Wetland Map From Lincoln GIS
Lincoln Public Schools11
March 8, 2011Meeting #2
Permitting Issues
• Zoning - Zone – R-1, Single Family Residential – the zoning for schools vary greatly depending on the Town’s regulations and their interpretation of the Dover Amendment. The Dover Amendment exempts schools from certain requirements of a Zoning Bylaws and Ordinances. It is critical to have a full understanding of the Towns interpretation of the Dover Amendment and the requirements and extent of review.
• Surface Water Supply Protection – site falls within water supply protection zone – Zone II, this will impact the drainage design.
• USEPA NPDES – disturbances over one acre require a submission of a Notice of Intent (NOI) that includes the stormwater pollution prevention plan to the EPA prior to beginning construction. This permit is signed by the operators of the construction site – the Owner and the Contractor
• Sanitary Sewer – There is a functioning existing 14,000 gallon per day Title 5 Septic System (1994) on site. Recommend the existing site be maintained. The function, size, and status of the existing Septic System will need to be confirmed with the Board of Health.
Lincoln Public Schools12
March 8, 2011Meeting #2
Existing Septic Information
3 septic fields • Main leach field under the soccer field (13,792 gpd) – 1994 designed for
14,000 gpd –not a pressure dosing system - works on a siphon • Hartwell School leach field (2,880 gpd) – 1969 no design flows available• Codman Pool leach field (2,500 gpd) – 1984 no design flows available• Total of 19,172 gallons per day based on Title 5
• Board of Health could require installation a wastewater treatment plant to come into compliance with Title 5 and Groundwater Discharge permit
• It appears that the septic leach fields were functioning in 2000 and that the
nitrogen loading was below the 10 mg/l required
• The 2000 GZA report also indicated that the actually flows based on water meter readings was approximately 2,800 gpd (15% of design/Title 5) in 2000
• The GZA report indicated that monitoring wells were installed to monitor the water table water quality.
Permitting Issues - Septic
Lincoln Public Schools13
March 8, 2011Meeting #2
Building Analysis – Existing Building Conditions
Leaching
Gutters
Staining
Exterior EnvelopeWalls
• Translucent panels in Smith Gym provide natural light
• Gutters damaged, corroded and leaking
• Soffit water damage and staining
• Exterior wall staining
Translucent Panels
Lincoln Public Schools14
March 8, 2011Meeting #2
Building Analysis – Existing Building Conditions
Exterior Staining
Poor Sun Control Insulated Glass
Clerestories
Exterior EnvelopeWindows
• Limited and ineffective solar control
• Majority of windows insulated
• Staining at exterior window units
• Clerestory shades and windows difficult to operate
Lincoln Public Schools15
March 8, 2011Meeting #2
Building Analysis – Existing Building Conditions
Heat Loss Ice Dams
Roof Leaks
Exterior EnvelopeRoof
• Melted snow pattern indicates heat loss in roof
• Ice damming along north elevation
• Roof leaks throughout the school
• Skylights leak at interior
• Roof access from one location at flat roofs. Pitched roofs accessed from ladders
• All Membrane seams repaired in 2010
Skylight
Lincoln Public Schools16
March 8, 2011Meeting #2
Building Analysis – Existing Building Conditions
Walk-off MatsAccessibility
Lack of Vestibules Exterior Doors
Exterior EnvelopeDoors
• No vestibule at most main entrances
• Many exterior doors
• Main entrances are accessible
• Lack of effective entry mats
Lincoln Public Schools17
March 8, 2011Meeting #2
Building Analysis – Existing Building Conditions
Ceiling Tiles
Furnishings and Storage
Retro-fitted Spaces
Classrooms and CorridorsSmith School
• Proper furnishings lead to improved acoustics and air quality
• Storage lacking within classrooms
• Water Damaged ceilings
• Mechanically and acoustically ill equiped occupied space
• Poor exhaust/ventilation in classrooms (Temperatures have reached 90’s in first grade classrooms)
Equipment in Corridors
Lincoln Public Schools18
March 8, 2011Meeting #2
Building Analysis – Existing Building Conditions
Skylights
Asbestos Containing Materials
Classrooms and CorridorsBrooks School
• Ceiling tiles tested positive for asbestos
• VCT in Classroom is telegraphing and cracking at slab joint
• Skylights in classrooms are not equipped with light control
• Storage lacking in classrooms
• Ceilings have water damage
• Wall surfaces below 36” require frequent maintenance
• Missing or falling ceiling tiles
• Poor exhaust and ventilation in classrooms
Storage
Floor Tile
Lincoln Public Schools19
March 8, 2011Meeting #2
Building Analysis – Existing Building Conditions
Raised CurbsRenovated Locker Rooms
No Natural Light Divider Curtain
Reed Gym/ Fieldhouse1971 Addition
• No natural light
• Not connected to school
• Half of gym used as cafeteria
• Divider curtain has no acoustic separation
• Small kitchen located in previous storage space
• Kitchen storage/receiving remote from kitchen
• Insufficient adult shower and locker facilities
• Noisy HVAC
• Used by community nights and weekends.
Lincoln Public Schools20
March 8, 2011Meeting #2
Building Analysis – Existing Building Conditions
Auditorium Seating
Stage
Backstage
Return Air Grilles
Brooks Auditorium Capacity: 330
• Accessible seating distribution; replacement parts not available
• Curtains and lighting supported by chains, difficult to adjust
• Operation and acoustics performance lacking at partition
Lincoln Public Schools21
March 8, 2011Meeting #2
Building Analysis – Existing Building Conditions
Stadium Seating
Operable PartitionAcoustical Treatment
Exit Access
Brooks Lecture HallCapacity: 226
• Space described as “gloomy” “bad acoustics”, and “difficult to use”.
• Perceived as “unsafe”
• Simultaneous use with auditorium - acoustics
Lincoln Public Schools22
March 8, 2011Meeting #2
Building Analysis – Existing Building Conditions
Story RoomLibrary Entrance
Reading Room
Library/Link
• Large space by today’s standards
• Circulation desk serves as a functional work space
• Main entrance houses printers and copiers
• Inadequate lighting
• Noisy HVAC
• Story Room: - used frequently - poor ventilation - acoustic issues - tiered seating issues
Circulation Desk
Lincoln Public Schools23
March 8, 2011Meeting #2
Building Analysis – Existing Building Conditions
Stage Storage
Motorized Partition
Smith School Gymnasium
• Gym separated by motorized partition, used frequently
• Acoustics need improvement
• Stage is useful but safety hazard
• No backstage; wings currently used as kitchen storage
• Dead spots in floor
• Parent pickup in gym causes floor damage
• Inadequate office
Acoustical Treatment
Lincoln Public Schools24
March 8, 2011Meeting #2
Building Analysis – Code Issues
Faculty Bathroom
Toilet Stalls
Stage
Exit Doors
Accessibility
• Stage not accessible
• Bathroom clearances and hardware
• Classroom exterior doors
• Raised curbs into locker room shower stalls
• Narrow circulation in bathrooms
• Noise levels: mechanicalacoustic separation
Lincoln Public Schools25
March 8, 2011Meeting #2
Building Analysis – Foodservice
Serving Area in Pantry Kitchen
View Through Serving Aisle
Pre-K through 4 Serving Pantry Kitchen
Congested Aisle
Cluttered Dish Washing Area
• Extremely congested space
• Electric oven used to cook limited range of items
• Inadequate aisle spacing
• Kitchen items stored outside kitchen, between kitchen servery and stage
• Some equipment could be reused in renovation
• Inadequate space for servery, food prep, cooking, and storage
Crabtree McGrath, Consulting Partners, Inc.: Preliminary Report, dated 3-23-2011
Lincoln Public Schools26
March 8, 2011Meeting #2
Building Analysis – Foodservice
• Addition off gym used as table, trash can, salad bar, and paper storage
• Deliveries travel across gym floor to reach kitchen
Crabtree McGrath, Consulting Partners, Inc.: Preliminary Report, dated 3-23-2011
View Through Galley Style Kitchen Gas Fired Range
Field House Kitchen Storage/Receiving Addition
Storage Addition Behind Gym Storage Addition Interior
Field House Kitchen• Congested room, difficult to maintain
proper separation of function
• Inefficient gas range, not allowed by Mass CHPS
• Equipment worn and end of life, Some could be reused in renovation
Lincoln Public Schools27
March 8, 2011Meeting #2
Building Analysis – Structural
• One-story
• Wood or steel framed roofs
• Concrete slab on grade
• Conventional spread footings
• Masonry veneer exterior with CMU or Steel stud backup
• Structure is in satisfactory condition – no evidence of failure or distress (Horizontal splitting/ checking in timber beams is normal, not a concern)
• Roofs designed for snow loads of 30 psf to 40 psf. Current code flat roof design snow load in Lincoln is 42.4 psf, plus drifting snow (as applicable).
• Pre-1994 buildings do not have clearly defined lateral load resisting systems
• Boiler Rooms and utility tunnels in Smith School experience seasonal flooding
FBRA Consultants: Preliminary Report, dated March 8, 2011
Snow Drift Conditions at Smith
Flooding in Boiler Room
Roof Beam Checking
Snow Drifting Conditions at Brooks
Lincoln Public Schools28
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
• Existing electrical equipment has reached life expectancy and requires replacement. The Link electrical service is in good condition.Original panels in the mechanical spaces are severely corroded and have live bussing.
Click to edit Master text stylesSecond level
Third level Fourth
level Fifth
level
Click to edit Master text stylesSecond level
Third level Fourth
level Fifth
level
Main Service Switch at Brooks Building
Main Service Switch at Link
Electric Panels at Field House
Corroded Electrical Panels at Brooks Building Boiler Room
Building Analysis – Electrical: Distribution System
Lincoln Public Schools29
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
• Receptacles are adequate but not optimal. Lack of outlets in Media Center.
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth level
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth level
G4000 Wiremold with Data & Power at Classrooms
Lack of Media Center Receptacles at Computer Tables
Building Analysis – Electrical: Branch Circuits
Lincoln Public Schools30
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
• Interior Lighting System - The lighting system has had lamps and ballasts changed to energy saving type. New lighting systems will control glare and have better controls such as daylight dimming. The Link lighting has glare control presently.
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth level
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth level
Library/Media Center LightingAuditorium Housing Lighting
Typical Wraparound Classroom LightingTypical Linear Classroom Lighting at Link
Building Analysis – Electrical: Lighting System
Lincoln Public Schools31
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
• New code requires 2 hour rating of feeders and Equipment location. Emergency lighting is through battery units.
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth levelEmergency Generator Typical Emergency Battery Head
Building Analysis – Electrical: Emergency Lighting
Lincoln Public Schools32
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
System is up to code but is problematic. Panel is in “trouble”.
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth level
Main Fire Alarm Panel Typical Heat Detector
Building Analysis – Electrical: Fire Alarm System
Lincoln Public Schools33
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
Headend room is in good condition but not to current standards.
New Avaya telephone system in good condition.
Existing clock system needs to be replaced.
Click to edit Master text stylesSecond level
Third level Fourth
level Fifth
level
MDF Rack Telephone System
Classroom Telephone Handset with Clock/Speaker
Building Analysis – Data/Telephone/Clock System
Lincoln Public Schools34
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth level
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth level
Firetube Boiler Cast Iron Sectional Boiler
• The hot water heating plants should be upgraded in both buildings. The existing hot water boilers, pumps, accessories and associated wing and controls should be removed.
• A new high efficiency plant with all new boilers, pumps with VFDs, piping, breeching, combustion venting, accessories, power wiring and control would provide energy savings and long service life.
Building Analysis – Mechanical: Boiler Plant
Lincoln Public Schools35
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
• The building pneumatic control system should be removed and replaced with a new direct digital control system and building energy management system. New DDC/BMS system offers improved energy savings and temperature control.
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth level
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth level
ATC Compressor – Brooks Building
ATC Control Panel – Brooks Building
ATC Control Panel – Library Mechanical Room
ATC Compressor – Library Mechanical Room
Building Analysis – Mechanical: Automatic Temperature Control
Lincoln Public Schools36
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
Auditorium – Ductwork located in Crawlspace
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth level
Boy’s Locker room – Air Handling Unit
• The existing Locker room air handling units, ductwork and fin tube radiation should be replaced.
• The Auditorium and Lecture Hall air handling units should be replaced.
• The existing Field House heating and ventilation units and associated ductwork should be cleaned and refurbished at a minimum.
Building Analysis – Mechanical: Air Handling Equipment
Lincoln Public Schools37
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth level
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth level
Teachers Room – PTAC Unit (at window)
Computer Server Room AC unit
VAV Box Controls (Bypassed) Smith Building Classroom UV w/ DX cooling should be repaired (2 units)
• Smith building Teacher work and break room PTAC unit cooling should be repaired.
• Library Computer room VAV box installation and thermostat controls should be repaired. A new energy efficient computer room AC system should be installed to replace the existing split system unit.
Building Analysis – Mechanical: Air Conditioning System Repairs
Lincoln Public Schools38
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth levelCeiling Recessed Unit VentilatorWith Taped Grille
Click to edit Master text stylesSecond level
Third level Fourth level
Fifth level Field House Lobby – Damaged Fin Tube Radiation
Kitchen Hood - Brooks Building
• The existing Locker room air handling units, ductwork and fin tube radiation should be replaced.
• Damaged terminal heating equipment should be repaired or replaced.A new exhaust and make-up air system should be provided as part of any kitchen renovation project.
Building Analysis – Mechanical: Miscellaneous
Lincoln Public Schools39
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
• Toilet Fixtures are in fair condition however do not meet current code for accessibility.
• New “high efficiency” plumbing fixtures are recommended.
• Science classroom/Tech Lab emergency fixtures do meet current code. Fixtures are supplied with cold water only. Emergency Fixtures are required to be supplied by tepid water. New fixtures are recommended.
Floor Mounted Water Closet
Wall Hung Water Closet
Wall Hung Lavatories and Urinal
Building Analysis – Plumbing: Fixtures
Lincoln Public Schools40
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
• Water service is 4” in size and adequate for renovations.
• Majority of distribution piping is original, several leaks have been repaired over time.
• Valves on the system show signs of corrosion.
• Science classrooms are supplied with domestic water. The system must be protected with backflow preventers to meet current code.
• Piping has reached its life expectancy. New piping systems are recommended.
Building Analysis – Plumbing: Domestic Water System
Lincoln Public Schools41
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
• Brooks School/Field House are supplied by gas fired heater with 120 gallon storage tank (standard efficiency).
• Smith School is supplied by gas fired tank type heater (standard efficiency).
• Field House kitchen supplied by 120 gallon electric water heater.
Field House Electric Water Heater
Smith Water Heater
Brooks Gas-Fired Water Heater
Building Analysis – Plumbing: Hot Water System
Lincoln Public Schools42
March 8, 2011Meeting #2
• Cast iron is used for sanitary and storm drainage.
• In general cast iron piping, above slab, can be reused in a major renovation where adequately sized.
• Video investigation of below slab piping is recommended.
• Science classroom piping system discharges to the on-site septic system. Majority of piping is cast iron. Traps and tailpieces of sinks are polypropylene.
Building Analysis – Plumbing: Drainage System
Lincoln Public Schools43
March 8, 2011Meeting #2
• Natural gas is supplied to each building. Exterior gas meters are located at the Field House, Smith Building and Brooks Building.
• Natural gas is provided in the
science classrooms. Classrooms are equipped with manual emergency shutoff valves.
• Natural gas is provided for
kitchen cooking equipment. Kitchen supply is equipped with an automatic shutoff valve.
Brooks School Gas Service Field House Gas Service
Building Analysis – Plumbing: Gas System
Lincoln Public Schools44
March 8, 2011Meeting #2
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level Fifth level
• There are no automatic sprinkler systems in the buildings.
• In general, Massachusetts General Law M.G.L. c.148, s.26G requires that any existing building, including any additions or major alterations, which total more than 7,500 square feet in aggregate floor area must be sprinklered. Should the existing building undergo a major renovation the building will require an automatic sprinkler system to provide complete protection of all spaces.
Building Analysis – Fire Protection
Lincoln Public Schools46
March 8, 2011Meeting #2
Space Usage Summary
• 1948
• 1953
• 1955
• 1963
• 1970
• 1994
K
GR 1
GR 2
GR 3
GR 4 & 5
GR 7 & 8
GR 6
SC
MUS ART
Lincoln Public Schools47
March 8, 2011Meeting #2
Lincoln Public Schools Mission
“The Lincoln Public Schools seeks to unite our communities in challenging and equipping our students to:
• Acquire essential knowledge
• Think critically and independently
• Exhibit academic excellence
• Appreciate and respect diversity
• Demonstrate creativity
• Value reflection
• Work hard and play fair.”
Lincoln Public Schools48
March 8, 2011Meeting #2
Educational Philosophy Summary
• Two Schools within a School: The philosophy and curriculum are articulated and aligned as a K-8 program, however, operationally the scheduling, structure and administration are separate between the elementary and middle schools.
• Relational teaching bound by a community of learners: Communities are formed by the classroom, the grade, the school and the families.
• Enrollment Projection: 600 students confirmed.
• Preferred Class Size: 18 (K); 20 (1st); 21 (2nd-3rd); 22 (4th- 5th); 24 (6th-8th).
• Grade transition is seamless within and between buildings.
• Scheduling of Space: One teacher per classroom. Classrooms are clustered by grades. Specialized spaces support grade group clusters.
• A high level of intervention, support and collaboration within classrooms reduces special education needs.
• Physical structure should promote collaboration.
• Transition from “curriculum silos” to “project based learning” opportunities.
• The school is a green community interlaced with the greater community.
Lincoln Public Schools49
March 8, 2011Meeting #2
A Shared View
“For a Pre-K-8 education, [the students] are together in the circle…
This is community.”
Lincoln Public Schools50
March 8, 2011Meeting #2
Next Steps
SBC Meeting #3, March 22, 2011
• Discuss Goals and Values
• Review and Approve Initial Space Summary
• Review Alternative Evaluation Criteria
Thank You