50
Lincoln Public School- Lincoln, MA

Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Embed Size (px)

Citation preview

Page 1: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public School- Lincoln, MA

Page 2: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools2

March 8, 2011Meeting #2

Agenda

Consultant Introductions

Work Plan

Project Update

Site Analysis

Building Analysis

Space Usage Summary

Educational Philosophy Summary

Next Steps

Page 3: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools3

March 8, 2011Meeting #2

Consultants

Nitsch Engineering, Inc.• Sandra Brock, PE, LEED  AP - Civil Engineer

Foley Buhl Roberts & Associates, Inc• Jonathan Buhl, PE - Structural Engineer

Garcia.Galuska.DeSousa Consulting Engineers Inc.• Carlos DeSousa, PE – Electrical Engineer • Dominick Puniello, PE, LEED  AP – Mechanical Engineer• Christopher Garcia, PE – Plumbing/ Fire Protection Engineer 

                              

Page 4: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools4

March 8, 2011Meeting #2

Groundwork o Review existing conditions informationo Prepare schedule and work plan

Meeting # 1 Goals, Values and Visioning

Objectives Follow-upo Review schedule and process o Discuss goals, valueso Discuss upcoming Visioning sessions

o Site walk thru with Engineers and Facilities Coordinatoro Conduct Visioning Sessionso Conduct User Group meetings

Meeting # 2 Site Analysis, Existing Conditions, Building Usage and Philosophy

Objectives Follow-up

2/08/11

3/08/11

o Prepare contracto Obtain and review all available/ pertinent documents

o Review Educational Philosophyo Review site analysis, existing conditions and space usage

o Prepare goals and values from four visioning sessionso Prepare Initial Space Summaryo Develop evaluation criteria for preliminary alternatives

Meeting # 3 Goals, Values and Initial Space Summary

Objectives Follow-up3/22/11o Submit initial space summary to MSBA for reviewo Develop Preliminary Alternative Concepts

Meeting # 4 & 5 Preliminary Alternative Concepts

Objectives Follow-up4/05/11;4/12/11 o Review and Approve Preliminary Alternative Concepts

o Approve Preliminary Design Program Submission

o Complete Preliminary Design Program Submittal for MSBAo Meet with MSBAo Develop Proposed Alternatives & Preliminary Evaluation

Meeting # 6 Preliminary Evaluation of Proposed AlternativesObjectives Follow-up4/26/11o Review Preliminary Evaluation of Proposed Alternatives o Submit Preliminary Alternatives to MSBA for review

o Meet with MSBAo Develop Selected Alternatives and evaluate

Meeting # 7 Finalize Preliminary Alternatives

Objectives Follow-up5/10/11o Review and Approve Preliminary Alternative(s) o Develop Final Evaluation of Alternatives & Preferred Solution

Meeting # 8 Final Evaluation of AlternativesObjectives Follow-upo Review Final Evaluation of Alternatives & Confirm Preferred Solution o Prepare Preferred Schematic Report

5/24/11

*

Lincoln School Feasibility Study Work Plan

Meeting # 9 Preferred Schematic Report

Objectives Follow-upo Review and Approve Preferred Schematic Report o Submit Preferred Schematic Report to MSBA

o MSBA Facilities Assessment Subcommittee and BOD Vote

6/07/11

o Review goals and valueso Review and Approve Initial Space Summaryo Establish Alternative Evaluation Criteria

Page 5: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools5

March 8, 2011Meeting #2

Project Update

• Analysis of Existing Conditions and Reports

- Civil/Landscape- Architectural- MEP/FP - Structural- Food Service- Hazardous Materials

• Educational Program/Philosophy Meeting with LPS Administration

• School, Multi-Board and Community Visioning Meetings

• Initial User Group Programming Meetings (3 Days)

Page 6: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools6

March 8, 2011Meeting #2

N

Site Analysis - Natural Features

WetlandsWetlands

Wetlands

FIELDHOUSE

BROOKS SCHOOL

LINK

SMITH SCHOOL

Warm Summer Breezes

Cold Winter Winds • Solar Orientation

• Winds

• Tree Line/Wooded Areas

• Stream

• Wetlands

• 50 Foot Buffer

• 100 Foot Buffer

JUNE 21 AM

JUNE 21 PM

DEC 21 AM

MARCH 21 AMMARCH 21

PM

DEC 21 PM

LINCO

LN R

OAD

BALLFIELD ROAD

HARTWELL

PODS

Page 7: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools7

March 8, 2011Meeting #2

Site Analysis - Built Environment

N

• Vehicular Traffic

• Athletic Fields

• Playgrounds

• Community Spaces- Interior- Exterior- External program

• Views

• Neighbors

• Septic

• Emergency Drive

• Main Entrances

• Parking

• Property Line

• Conservation Land

LINCO

LN R

OAD

HARTWELL

PODS

Play

Play

Play

Play

Play

Play

SMITH SCHOOL

LINK

BROOKS SCHOOL

FIELDHOUSE

*

*

*

*

*

*

Page 8: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools8

March 8, 2011Meeting #2

Site Analysis - Site Circulation

N

• Parking- Remote from controlled entrances

• Buses- 3 Drop- off locations

• Inadequate parking at main entrances

• Inadequate parking for community use

• Congestion at Smith drop-off

LINCO

LN R

OAD

HARTWELL

PODSSMITH

SCHOOL

LINK

BROOKS SCHOOL

FIELDHOUSE

12

3

Page 9: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools9

March 8, 2011Meeting #2

Site Analysis - General Site/Civil/Fields

View Across Playfields View at Smith Lot Exit

Site Issues

• Storm drainage appears insufficient; ponding observed along paved edges

• Downspouts discharge directly onto ground

• Parking lot to east of Reed half underwater occasionally

• Driveways, parking lots, sidewalks and curbs in fair to poor condition

• Handicap accessibility does not meet MAAB code

• Water table is high, causing seasonal wet conditions at fields

Page 10: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools10

March 8, 2011Meeting #2

Permitting Issues - Wetlands

• Wetlands Protection Act (310 CMR 10.00) – The site falls within an environmentally sensitive area and a Notice of Intent is required, the wetland resource areas include:

• Riverfront – Critical to have the limit of Riverfront determined, this has a direct impact on project

• Bordering Vegetated Wetlands• Bank• Land Underwater

• Lincoln Wetlands Protection Bylaw - includes 50-foot “no disturb area”

• Natural Heritage & Endangered Species – the site does not fall within Priority or Estimated Habitat and does not contain a certified vernal pool per MASSGIS

• Flood Plain – the majority of the site is not located within a 100-year floodplain. There is a 100-year floodplain associated with Stony Brook but is generally confined to Stony Brook channel.

Limit of Riverfront Area?

Wetland Map From Lincoln GIS

Page 11: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools11

March 8, 2011Meeting #2

Permitting Issues

• Zoning - Zone – R-1, Single Family Residential – the zoning for schools vary greatly depending on the Town’s regulations and their interpretation of the Dover Amendment. The Dover Amendment exempts schools from certain requirements of a Zoning Bylaws and Ordinances. It is critical to have a full understanding of the Towns interpretation of the Dover Amendment and the requirements and extent of review.

• Surface Water Supply Protection – site falls within water supply protection zone – Zone II, this will impact the drainage design.

• USEPA NPDES – disturbances over one acre require a submission of a Notice of Intent (NOI) that includes the stormwater pollution prevention plan to the EPA prior to beginning construction. This permit is signed by the operators of the construction site – the Owner and the Contractor

• Sanitary Sewer – There is a functioning existing 14,000 gallon per day Title 5 Septic System (1994) on site. Recommend the existing site be maintained. The function, size, and status of the existing Septic System will need to be confirmed with the Board of Health.

Page 12: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools12

March 8, 2011Meeting #2

Existing Septic Information

3 septic fields • Main leach field under the soccer field (13,792 gpd) – 1994 designed for

14,000 gpd –not a pressure dosing system -  works on a siphon • Hartwell School leach field (2,880 gpd) – 1969 no design flows available• Codman Pool leach field (2,500 gpd) – 1984 no design flows available• Total of 19,172 gallons per day based on Title 5

• Board of Health could require installation a wastewater treatment plant to come into compliance with Title 5 and Groundwater Discharge permit

• It appears that the septic leach fields were functioning in 2000 and that the

nitrogen loading was below the 10 mg/l required

• The 2000 GZA report also indicated that the actually flows based on water meter readings was approximately 2,800 gpd (15% of design/Title 5) in 2000

• The GZA report indicated that monitoring wells were installed to monitor the water table water quality.

Permitting Issues - Septic

Page 13: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools13

March 8, 2011Meeting #2

Building Analysis – Existing Building Conditions

Leaching

Gutters

Staining

Exterior EnvelopeWalls

• Translucent panels in Smith Gym provide natural light

• Gutters damaged, corroded and leaking

• Soffit water damage and staining

• Exterior wall staining

Translucent Panels

Page 14: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools14

March 8, 2011Meeting #2

Building Analysis – Existing Building Conditions

Exterior Staining

Poor Sun Control Insulated Glass

Clerestories

Exterior EnvelopeWindows

• Limited and ineffective solar control

• Majority of windows insulated

• Staining at exterior window units

• Clerestory shades and windows difficult to operate

Page 15: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools15

March 8, 2011Meeting #2

Building Analysis – Existing Building Conditions

Heat Loss Ice Dams

Roof Leaks

Exterior EnvelopeRoof

• Melted snow pattern indicates heat loss in roof

• Ice damming along north elevation

• Roof leaks throughout the school

• Skylights leak at interior

• Roof access from one location at flat roofs. Pitched roofs accessed from ladders

• All Membrane seams repaired in 2010

Skylight

Page 16: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools16

March 8, 2011Meeting #2

Building Analysis – Existing Building Conditions

Walk-off MatsAccessibility

Lack of Vestibules Exterior Doors

Exterior EnvelopeDoors

• No vestibule at most main entrances

• Many exterior doors

• Main entrances are accessible

• Lack of effective entry mats

Page 17: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools17

March 8, 2011Meeting #2

Building Analysis – Existing Building Conditions

Ceiling Tiles

Furnishings and Storage

Retro-fitted Spaces

Classrooms and CorridorsSmith School

• Proper furnishings lead to improved acoustics and air quality

• Storage lacking within classrooms

• Water Damaged ceilings

• Mechanically and acoustically ill equiped occupied space

• Poor exhaust/ventilation in classrooms (Temperatures have reached 90’s in first grade classrooms)

Equipment in Corridors

Page 18: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools18

March 8, 2011Meeting #2

Building Analysis – Existing Building Conditions

Skylights

Asbestos Containing Materials

Classrooms and CorridorsBrooks School

• Ceiling tiles tested positive for asbestos

• VCT in Classroom is telegraphing and cracking at slab joint

• Skylights in classrooms are not equipped with light control

• Storage lacking in classrooms

• Ceilings have water damage

• Wall surfaces below 36” require frequent maintenance

• Missing or falling ceiling tiles

• Poor exhaust and ventilation in classrooms

Storage

Floor Tile

Page 19: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools19

March 8, 2011Meeting #2

Building Analysis – Existing Building Conditions

Raised CurbsRenovated Locker Rooms

No Natural Light Divider Curtain

Reed Gym/ Fieldhouse1971 Addition

• No natural light

• Not connected to school

• Half of gym used as cafeteria

• Divider curtain has no acoustic separation

• Small kitchen located in previous storage space

• Kitchen storage/receiving remote from kitchen

• Insufficient adult shower and locker facilities

• Noisy HVAC

• Used by community nights and weekends.

Page 20: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools20

March 8, 2011Meeting #2

Building Analysis – Existing Building Conditions

Auditorium Seating

Stage

Backstage

Return Air Grilles

Brooks Auditorium Capacity: 330

• Accessible seating distribution; replacement parts not available

• Curtains and lighting supported by chains, difficult to adjust

• Operation and acoustics performance lacking at partition

Page 21: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools21

March 8, 2011Meeting #2

Building Analysis – Existing Building Conditions

Stadium Seating

Operable PartitionAcoustical Treatment

Exit Access

Brooks Lecture HallCapacity: 226

• Space described as “gloomy” “bad acoustics”, and “difficult to use”.

• Perceived as “unsafe”

• Simultaneous use with auditorium - acoustics

Page 22: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools22

March 8, 2011Meeting #2

Building Analysis – Existing Building Conditions

Story RoomLibrary Entrance

Reading Room

Library/Link

• Large space by today’s standards

• Circulation desk serves as a functional work space

• Main entrance houses printers and copiers

• Inadequate lighting

• Noisy HVAC

• Story Room: - used frequently - poor ventilation - acoustic issues - tiered seating issues

Circulation Desk

Page 23: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools23

March 8, 2011Meeting #2

Building Analysis – Existing Building Conditions

Stage Storage

Motorized Partition

Smith School Gymnasium

• Gym separated by motorized partition, used frequently

• Acoustics need improvement

• Stage is useful but safety hazard

• No backstage; wings currently used as kitchen storage

• Dead spots in floor

• Parent pickup in gym causes floor damage

• Inadequate office

Acoustical Treatment

Page 24: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools24

March 8, 2011Meeting #2

Building Analysis – Code Issues

Faculty Bathroom

Toilet Stalls

Stage

Exit Doors

Accessibility

• Stage not accessible

• Bathroom clearances and hardware

• Classroom exterior doors

• Raised curbs into locker room shower stalls

• Narrow circulation in bathrooms

• Noise levels: mechanicalacoustic separation

Page 25: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools25

March 8, 2011Meeting #2

Building Analysis – Foodservice

Serving Area in Pantry Kitchen

View Through Serving Aisle

Pre-K through 4 Serving Pantry Kitchen

Congested Aisle

Cluttered Dish Washing Area

• Extremely congested space

• Electric oven used to cook limited range of items

• Inadequate aisle spacing

• Kitchen items stored outside kitchen, between kitchen servery and stage

• Some equipment could be reused in renovation

• Inadequate space for servery, food prep, cooking, and storage

Crabtree McGrath, Consulting Partners, Inc.: Preliminary Report, dated 3-23-2011

Page 26: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools26

March 8, 2011Meeting #2

Building Analysis – Foodservice

• Addition off gym used as table, trash can, salad bar, and paper storage

• Deliveries travel across gym floor to reach kitchen

Crabtree McGrath, Consulting Partners, Inc.: Preliminary Report, dated 3-23-2011

View Through Galley Style Kitchen Gas Fired Range

Field House Kitchen Storage/Receiving Addition

Storage Addition Behind Gym Storage Addition Interior

Field House Kitchen• Congested room, difficult to maintain

proper separation of function

• Inefficient gas range, not allowed by Mass CHPS

• Equipment worn and end of life, Some could be reused in renovation

Page 27: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools27

March 8, 2011Meeting #2

Building Analysis – Structural

• One-story

• Wood or steel framed roofs

• Concrete slab on grade

• Conventional spread footings

• Masonry veneer exterior with CMU or Steel stud backup

• Structure is in satisfactory condition – no evidence of failure or distress (Horizontal splitting/ checking in timber beams is normal, not a concern)

• Roofs designed for snow loads of 30 psf to 40 psf. Current code flat roof design snow load in Lincoln is 42.4 psf, plus drifting snow (as applicable).

• Pre-1994 buildings do not have clearly defined lateral load resisting systems

• Boiler Rooms and utility tunnels in Smith School experience seasonal flooding

FBRA Consultants: Preliminary Report, dated March 8, 2011

Snow Drift Conditions at Smith

Flooding in Boiler Room

Roof Beam Checking

Snow Drifting Conditions at Brooks

Page 28: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools28

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

• Existing electrical equipment has reached life expectancy and requires replacement. The Link electrical service is in good condition.Original panels in the mechanical spaces are severely corroded and have live bussing.

Click to edit Master text stylesSecond level

Third level Fourth

level Fifth

level

Click to edit Master text stylesSecond level

Third level Fourth

level Fifth

level

Main Service Switch at Brooks Building

Main Service Switch at Link

Electric Panels at Field House

Corroded Electrical Panels at Brooks Building Boiler Room

Building Analysis – Electrical: Distribution System

Page 29: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools29

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

• Receptacles are adequate but not optimal. Lack of outlets in Media Center.

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth level

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth level

G4000 Wiremold with Data & Power at Classrooms

Lack of Media Center Receptacles at Computer Tables

Building Analysis – Electrical: Branch Circuits

Page 30: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools30

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

• Interior Lighting System - The lighting system has had lamps and ballasts changed to energy saving type. New lighting systems will control glare and have better controls such as daylight dimming. The Link lighting has glare control presently.

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth level

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth level

Library/Media Center LightingAuditorium Housing Lighting

Typical Wraparound Classroom LightingTypical Linear Classroom Lighting at Link

Building Analysis – Electrical: Lighting System

Page 31: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools31

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

• New code requires 2 hour rating of feeders and Equipment location. Emergency lighting is through battery units.

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth levelEmergency Generator Typical Emergency Battery Head

Building Analysis – Electrical: Emergency Lighting

Page 32: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools32

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

System is up to code but is problematic. Panel is in “trouble”.

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth level

Main Fire Alarm Panel Typical Heat Detector

Building Analysis – Electrical: Fire Alarm System

Page 33: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools33

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

Headend room is in good condition but not to current standards.

New Avaya telephone system in good condition.

Existing clock system needs to be replaced.

Click to edit Master text stylesSecond level

Third level Fourth

level Fifth

level

MDF Rack Telephone System

Classroom Telephone Handset with Clock/Speaker

Building Analysis – Data/Telephone/Clock System

Page 34: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools34

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth level

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth level

Firetube Boiler Cast Iron Sectional Boiler

• The hot water heating plants should be upgraded in both buildings. The existing hot water boilers, pumps, accessories and associated wing and controls should be removed.

• A new high efficiency plant with all new boilers, pumps with VFDs, piping, breeching, combustion venting, accessories, power wiring and control would provide energy savings and long service life.

Building Analysis – Mechanical: Boiler Plant

Page 35: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools35

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

• The building pneumatic control system should be removed and replaced with a new direct digital control system and building energy management system. New DDC/BMS system offers improved energy savings and temperature control.

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth level

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth level

ATC Compressor – Brooks Building

ATC Control Panel – Brooks Building

ATC Control Panel – Library Mechanical Room

ATC Compressor – Library Mechanical Room

Building Analysis – Mechanical: Automatic Temperature Control

Page 36: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools36

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

Auditorium – Ductwork located in Crawlspace

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth level

Boy’s Locker room – Air Handling Unit

• The existing Locker room air handling units, ductwork and fin tube radiation should be replaced.

• The Auditorium and Lecture Hall air handling units should be replaced.

• The existing Field House heating and ventilation units and associated ductwork should be cleaned and refurbished at a minimum.

Building Analysis – Mechanical: Air Handling Equipment

Page 37: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools37

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth level

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth level

Teachers Room – PTAC Unit (at window)

Computer Server Room AC unit

VAV Box Controls (Bypassed) Smith Building Classroom UV w/ DX cooling should be repaired (2 units)

• Smith building Teacher work and break room PTAC unit cooling should be repaired.

• Library Computer room VAV box installation and thermostat controls should be repaired. A new energy efficient computer room AC system should be installed to replace the existing split system unit.

Building Analysis – Mechanical: Air Conditioning System Repairs

Page 38: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools38

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth levelCeiling Recessed Unit VentilatorWith Taped Grille

Click to edit Master text stylesSecond level

Third level Fourth level

Fifth level Field House Lobby – Damaged Fin Tube Radiation

Kitchen Hood - Brooks Building

• The existing Locker room air handling units, ductwork and fin tube radiation should be replaced.

• Damaged terminal heating equipment should be repaired or replaced.A new exhaust and make-up air system should be provided as part of any kitchen renovation project.

Building Analysis – Mechanical: Miscellaneous

Page 39: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools39

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

• Toilet Fixtures are in fair condition however do not meet current code for accessibility.

• New “high efficiency” plumbing fixtures are recommended.

• Science classroom/Tech Lab emergency fixtures do meet current code. Fixtures are supplied with cold water only. Emergency Fixtures are required to be supplied by tepid water. New fixtures are recommended.

Floor Mounted Water Closet

Wall Hung Water Closet

Wall Hung Lavatories and Urinal

Building Analysis – Plumbing: Fixtures

Page 40: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools40

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

• Water service is 4” in size and adequate for renovations.

• Majority of distribution piping is original, several leaks have been repaired over time.

• Valves on the system show signs of corrosion.

• Science classrooms are supplied with domestic water. The system must be protected with backflow preventers to meet current code.

• Piping has reached its life expectancy. New piping systems are recommended.

Building Analysis – Plumbing: Domestic Water System

Page 41: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools41

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

• Brooks School/Field House are supplied by gas fired heater with 120 gallon storage tank (standard efficiency).

• Smith School is supplied by gas fired tank type heater (standard efficiency).

• Field House kitchen supplied by 120 gallon electric water heater.

Field House Electric Water Heater

Smith Water Heater

Brooks Gas-Fired Water Heater

Building Analysis – Plumbing: Hot Water System

Page 42: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools42

March 8, 2011Meeting #2

• Cast iron is used for sanitary and storm drainage.

• In general cast iron piping, above slab, can be reused in a major renovation where adequately sized.

• Video investigation of below slab piping is recommended.

• Science classroom piping system discharges to the on-site septic system. Majority of piping is cast iron. Traps and tailpieces of sinks are polypropylene.

Building Analysis – Plumbing: Drainage System

Page 43: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools43

March 8, 2011Meeting #2

• Natural gas is supplied to each building. Exterior gas meters are located at the Field House, Smith Building and Brooks Building.

 • Natural gas is provided in the

science classrooms. Classrooms are equipped with manual emergency shutoff valves.

 • Natural gas is provided for

kitchen cooking equipment. Kitchen supply is equipped with an automatic shutoff valve.

Brooks School Gas Service Field House Gas Service

Building Analysis – Plumbing: Gas System

Page 44: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools44

March 8, 2011Meeting #2

Click to edit the outline text format

Second Outline Level Third Outline

Level Fourth Outline

Level Fifth

Outline Level

Sixth Outline Level

Seventh Outline Level

Eighth Outline Level

Ninth Outline LevelClick to edit Master text styles

Second level Third level

Fourth level Fifth level

• There are no automatic sprinkler systems in the buildings.

• In general, Massachusetts General Law M.G.L. c.148, s.26G requires that any existing building, including any additions or major alterations, which total more than 7,500 square feet in aggregate floor area must be sprinklered. Should the existing building undergo a major renovation the building will require an automatic sprinkler system to provide complete protection of all spaces.

Building Analysis – Fire Protection

Page 45: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools46

March 8, 2011Meeting #2

Space Usage Summary

• 1948

• 1953

• 1955

• 1963

• 1970

• 1994

K

GR 1

GR 2

GR 3

GR 4 & 5

GR 7 & 8

GR 6

SC

MUS ART

Page 46: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools47

March 8, 2011Meeting #2

Lincoln Public Schools Mission

“The Lincoln Public Schools seeks to unite our communities in challenging and equipping our students to:

• Acquire essential knowledge

• Think critically and independently

• Exhibit academic excellence

• Appreciate and respect diversity

• Demonstrate creativity

• Value reflection

• Work hard and play fair.”

Page 47: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools48

March 8, 2011Meeting #2

Educational Philosophy Summary

• Two Schools within a School: The philosophy and curriculum are articulated and aligned as a K-8 program, however, operationally the scheduling, structure and administration are separate between the elementary and middle schools.

• Relational teaching bound by a community of learners: Communities are formed by the classroom, the grade, the school and the families.

• Enrollment Projection: 600 students confirmed.

• Preferred Class Size: 18 (K); 20 (1st); 21 (2nd-3rd); 22 (4th- 5th); 24 (6th-8th).

• Grade transition is seamless within and between buildings.

• Scheduling of Space: One teacher per classroom. Classrooms are clustered by grades. Specialized spaces support grade group clusters.

• A high level of intervention, support and collaboration within classrooms reduces special education needs.

• Physical structure should promote collaboration.

• Transition from “curriculum silos” to “project based learning” opportunities.

• The school is a green community interlaced with the greater community.

Page 48: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools49

March 8, 2011Meeting #2

A Shared View

“For a Pre-K-8 education, [the students] are together in the circle…

This is community.”

Page 49: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Lincoln Public Schools50

March 8, 2011Meeting #2

Next Steps

SBC Meeting #3, March 22, 2011

• Discuss Goals and Values

• Review and Approve Initial Space Summary

• Review Alternative Evaluation Criteria

Page 50: Lincoln Public School- Lincoln, MA. Lincoln Public Schools 2 March 8, 2011 Meeting #2 Agenda Consultant Introductions Work Plan Project Update Site Analysis

Thank You