Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
LIMITED REEVALUATION REPORT LOWER MUD RIVER LOCAL PROTECTION PROJECT MILTON, CABELL COUNTY, WEST VIRGINIA
VOLUME 2 REAL ESTATE PLAN
TABLE OF CONTENTS PARAGRAPH DESCRIPTION PAGE 1 PROJECT DESCRIPTION 1 2 PROJECT AUTHORIZATION 2 3 GENERAL DESCRIPTION OF AREA 2 4 GOVERNMENT OR SPONSOR OWNED LAND 3 5 FACILITIES TO BE RELOCATED 4 6 ACQUISITION CRITERIA 8 7 P.L. 91-646 RELOCATION ASSISTANCE DATA 9 8 NEPA, NHPA, HTRW 10 9 ACQUISITION ESTIMATE AND SCHEDULE 17 10 SPONSOR CAPABILITIES 19 EXHIBITS a. Site Index Map b. State Hazard Mitigation Officer with the Office of Emergency Services (FEMA) c. Sponsor Capability Checklist d. Sponsor letter e. General LRD Comments
1
1. PROJECT DESCRIPTION. This Real Estate Plan (REP) covers the real estate necessary
for flood damage reduction measures in Milton, West Virginia. The Town of Milton is the non-
Federal sponsor. Typically, acquisition of lands, easements, rights-of-ways, relocations and
disposal lands (LERRD) would be the responsibility of the non-federal local sponsor. However,
the non-federal sponsor, the Town of Milton, has indicated that it wishes the Corps of Engineers
to perform the acquisition on its behalf. The town will be responsible for LERRD and operation
and maintenance. This is discussed further in Paragraph 10.
The proposed project is on the left descending bank of the Mud River. The levee starts on
the southern embankment of Route 60, approximately 1,350 feet east of its intersection with
John’s Creek Road. The levee follows the northern Mud River embankment for about 300 feet
before it heads in a southwesterly direction. At approximate station 20+50 the levee will cross
over what is now the existing Mud River. This portion of the river will be relocated. The levee
then continues westerly approximately 1,400 feet where it again crosses the existing Mud River.
Continuing westerly, it then follows the northern embankment of the Mud River on the northerly
side of the Milton Sanitary Lagoon, continuing westerly to the western embankment of Abbot
Street where it ties into high ground approximately 500 feet south of Route 60.
Property ownership maps and courthouse information indicate approximately 135 tracts
of land consisting of approximately 185 acres will be required for the proposed project. Of those
135 tracts, 53 tracts comprising about 150 acres of land will be acquired in fee for joint use
wetland and terrestrial mitigation purposes. Further project details follow in subsequent
paragraphs.
2
In accordance with Chapter 12 of ER 405-1-12, this Real Estate Plan (REP) is being
submitted as Volume 2 of the Limited Reevaluation Report (LRR) for approval. This REP is to
be considered tentative in nature and for planning purposes only. Both the final real property
acquisition line and the estimate of cost are subject to change, even after this report is approved.
2. PROJECT AUTHORIZATION. Authority for the Lower Mud River, Milton, West
Virginia Limited Reevaluation Study is Section 580 of the Water Resources Development Act of
1996 (Public Law 104-303) adopted 12 October 1996.
3. GENERAL DESCRIPTION OF AREA. The real estate required for this report is located
in the State of West Virginia, Cabell County, Town of Milton, on the Mud River. Milton had an
estimated 2000 population of 2,206. Cabell County is the second largest county in the state with
an estimated 2000 population of 96,784. Flooding has played a significant role in the history of
Milton. Nearly the entire town lies within the 100-year floodplain.
A retail area is located in downtown Milton. Milton’s business district has several types of
commercial activities such as restaurants, pharmacies, gas stations, grocery stores and banks, as
well as churches, the town hall and fire station. Two schools will also be protected. U.S. Route
60 with its nearby intersection to Interstate 64 provides the main highway link for the town.
The history of Milton’s flooding problems dates back to the turn of the century. The Mud
River has been out-of-banks in Milton more than 70 times since 1938.
Flooding in Milton is caused by a combination of both natural and manmade conditions.
Intense rainfall on high runoff producing soils in the headwaters of the watershed results in a
3
high volume of runoff. The steep stream gradients upstream from Milton combine with the
narrow valleys to create high flood peaks. These high peaks flow into Milton faster than the
flatter gradients downstream allow them to flow out. This creates a backwater condition that
inundates most of the residential and commercial areas in the city.
The most serious flooding in Milton occurs when floodwaters from Mud River back up and
overtop U.S. Route 60. Most of the commercial and residential areas of the city are located on
the north side of the highway. Flooding north of U.S. Route 60 also occurs from local drainage
as a result of high stages on Mud River that block drainage from outlets under the highway.
The 1978 flood was approximately a 30-year flood (frequency of occurrence) resulting
from 4.9 inches of rainfall over the watershed area in 23 hours. It produced a peak discharge of
14,600 cfs and overtopped U.S. Route 60 by about 1.8 feet. Approximately 500 homes and 100
businesses were flooded. Should a flood similar to the 1978 flood recur, damages would exceed
$30 million.
Approximately 8 inches of rain fell on the Lower Mud River Basin from February 28th to
March 3rd, 1997. This was the most damaging flood ever at Milton. The flood levels in the
downtown area were about 0.5 feet higher than in the December 1978 flood (the previous flood
of record). Hundreds of residences, businesses and two schools were damaged by flooding.
Some residences and businesses along U.S. 60 near the river had flood waters 1.5 to 2.0 feet over
their first floors.
4. GOVERNMENT OR SPONSOR-OWNED LAND. There is no known Government
owned land within the boundary of the proposed construction work limit (CWL). The project
4
sponsor owns several tracts of land in the project area. FEMA has acquired approximately 14
tracts within the project area. The proposed project has been coordinated with FEMA, and a
copy of correspondence from Barry Macciocca, the State Hazard Mitigation Officer with the
Office of Emergency Services is included as Exhibit B. Preliminary investigations indicate that
many of the tracts the town owns were purchased by FEMA as part of their Hazardous Mitigation
Grant Program. This flood control project affects the former FEMA tracts with only flowage
easements. The issue of navigational servitude is not applicable to this project.
5. FACILITIES TO BE RELOCATED. Relocation Design Document Reports (DDR) for
the utilities and public facilities will be prepared in accordance with EFARS, Appendix Q and
will be used as a basis to negotiate relocations contracts with the affected owners. Preliminary
Attorney’s Opinions have been prepared and indicate a compensable interest exists for each of
the following impacted utilities and facilities unless otherwise noted. A contract between the
sponsor and the owner/operator of the facilities will be required to accommodate the proposed
project where appropriate. It is anticipated that any exchange of interest in lands required
for relocations or alterations will be within the proposed CWL and negotiated under a
relocation contract.
5.1 Utilities. Utilities possessing a compensable interest in land which may be affected by
the proposed project include natural gas, water, sanitary sewer, storm sewer, power, and
telephone. It is anticipated that any exchange of interest in lands required for
relocations or alterations will be within the proposed CWL and negotiated under
5
a relocation contract with the utility companies.
5.1.1 Natural Gas. Based on the proposed levee alignment, borrow area, and relocated river
channel, the relocation and/or abandonment of natural gas lines, including both
distribution and transmission are required. Approximately 1,900 feet of 24” high
pressure transmission line, owned and operated by Union Oil & Gas, Inc., will require
relocation. About 900 feet of 12” high pressure natural gas transmission line, owned and
operated by Columbia Gas Transmission, passes under the proposed primary borrow area,
in a limited work limit (LWL) area, and, as a result, will be avoided and will not require
relocation. Southern Public Service Company owns and operates approximately 960 feet
of natural gas distribution lines and appurtenances which will also require relocation
and/or abandonment..
5.1.2 Water. Water line relocation work is required. Approximately 3,200 feet of water line
and appurtenances will require relocation and/or abandonment to accommodate the
proposed project. The Town’s water intake and weir will require relocation as a result of
the proposed relocation of the river channel.
5.1.3 Sanitary Sewer. The main sewage lift station for the Town is located along the proposed
levee alignment and will require relocation to accommodate the project. In addition,
about 3,200 feet of sanitary sewer line and appurtenances will require relocation and/or
abandonment.
5.1.4 Storm Sewer. Based on the proposed alignment of the levee, storm sewer line relocation
appears to be relatively minimal. It is estimated that the project will require about 1,000
feet of storm sewer line to be relocated and/or abandoned.
6
5.1.5 Power. Power line relocation is required. Roughly 8,600 feet of single, two, and three
phase power lines and appurtenances will require relocation and/or abandonment to
accommodate the project.
5.1.6 Telephone. Verizon West Virginia, Inc. owns and operates about 2,500 feet of telephone
lines requiring relocation and/or abandonment.
5.2. Public Facilities. The public facilities affected by the proposed project possessing a
compensable interest include the following: Milton Middle School, State and county
roads, and Milton town streets and alleys.
5.2.1 Milton Middle School. Milton Middle School is located on approximately a 14.3 acre
tract along U.S. Route 60 just west of its intersection with County Route 25, and is owned
and operated, according to the preliminary attorney’s report, by the Cabell County Board
of Education. Currently, the school houses approximately 625 students in grades 6
through 8. A portion of the school’s property, not including the school building, will be
affected by the alignment of the proposed levee and an interior drainage ditch. An
existing gravel/dirt/grass running track will be severed by the proposed levee alignment,
and a paved lot in the rear of the school will be altered as a result of a proposed interior
drainage ditch alignment. About 7 acres of the 14.3 acre school tract will be affected by
the project, leaving the school with approximately 7 acres protected by the proposed levee
upon completion of the project. The West Virginia Department of Education has adopted
The Handbook on Planning School Facilities to provide guidelines to address the details
of evaluating and renovating existing school education facilities and the construction of
7
new school facilities. For middle childhood/junior high education programs (grades 5-8),
the handbook suggests that a school site have a minimum of 11 usable acres plus 1
additional acre for every 100 pupils over 600 students. Section 203.04 of the handbook
states that suggested site acreages apply to traditional suburban schools, but where the
nature of the neighborhood is urban, the school site shall be urban in scale. In addition,
where the terrain limits the land available, this factor shall be considered. The actual
settlement with the Board of Education will be determined in the Relocations DDR and
Contract and will depend on the current need, size and function of the school at that time.
The Current Working Estimate (CWE) for the Milton Middle School relocation will
consider the settlement as proposed at that time.
5.2.2 State Roads. Construction of the project will affect West Virginia County Routes 25
and 25/7, and U.S. Route 60. A preliminary attorney’s report indicates a relocation
contract between the sponsor and the West Virginia Department of Transportation
Division of Highways (WVDOH), the owner of U.S. Route 60, will be required for any
construction on WVDOH right-of-way in order to accommodate the project. In
particular, U.S. Route 60 will be temporarily affected during the installation of a
proposed 72-inch culvert crossing U.S. Route 60 at Newman’s Branch. In addition, this
relocation contract would also address County Routes 25/7 and 25 which, according to a
preliminary attorney’s report, are owned, operated, and maintained by the WVDOH.
County Route 25/7 will be modified as a result of construction of a proposed gate closure
and will require closure from public travel during flood events as deemed necessary.
County Route 25 will be altered due to construction of the proposed levee. A relocation
8
contract will be obtained for the right, title, and interest (subordination, conveyance, etc.)
in lands necessary for the construction, operation, and maintenance of the proposed
project.
5.2.3 Town Streets and Alleys. Several town streets and alleys are currently located, at least in
part, within the CWL of the proposed project. In particular, Abbot and Damon Streets
currently cross the proposed levee alignment and will require modification due to
construction of the proposed project. A preliminary attorney’s report indicates the Town
of Milton, the owner of the town streets and alleys will be required to alter these facilities
to accommodate construction of the project.
5.2.4 Final Determinations. Any conclusion or categorization contained in this report that an
item is a utility or facility relocation to be performed by the non-federal sponsor as part of
its land acquisition responsibilities is preliminary only. The Government will make a
final determination of the relocations necessary for the construction, operation, or
maintenance of the project after further analysis and completion and approval of final
attorney’s opinions of compensability for each of the impacted utilities and facilities.
6. ACQUISITION CRITERIA. To accomplish the acquisition of real estate interests in the
proposed Lower Mud River Local Protection Project, it is proposed to acquire 53 tracts
(approximately 150 acres) of standard fee estates, and 82 tracts (35 acres) of temporary work area
easements, temporary access road easements for rock borrow and staging areas, and flowage
easements; as set forth in Chapter 5 of ER 405-12. Mitigation features lie within the project
limits. The standard fee estate has been proposed in areas where both project and mitigation
9
features are co-located.
The 14 tracts of land acquired by FEMA (mentioned previously in Paragraph 4)
were acquired in the name of the Town of Milton. There will be no cost to the Government to
obtain the estate needed over these tracts.
6.1 Induced Flooding. An Attorney’s Analysis of Taking is not necessary. Any project
impacts outside the area of protection are extremely minimal and infrequent and there are no
takings issues.
7. P.L. 91-646 RELOCATION ASSISTANCE DATA. Public Law 91-646, Title II,
authorizes payment of relocation benefits to persons displaced from their homes, businesses or
farms by federal and federally assisted programs. Those benefits are separate from and in
addition to the acquisition payments for real property. Estimated benefits for residential
displacements include moving expenses and replacement housing. Owner-occupants and tenant-
occupants of mobile homes will be accorded the same benefits as occupants of conventional
dwellings with respect to P.L. 91-646. Relocation benefits for non-residential displacements are
limited to moving and related expenses, including search expenses, and, if applicable, re-
establishment expenses.
A replacement housing survey was completed in July 2003. The conclusion of that survey
was: “The turnover in the general housing market in the project area of Milton, West Virginia,
appears to be more than adequate to accommodate the number of displaced person anticipated in
any year.”
10
(3) A 25 percent contingency allowance has been applied to the estimate of benefits
to cover possible changes in moving costs, unknown multi-family occupancies, financial
hardship cases, etc. The following table shows the number, type and number of structures
involved in the Lower Mud River Local Protection Project.
P.L. 91-646 Relocations Assistance Data
TYPE OF STRUCTURE NUMBER RESIDENCE 2 MOBILE HOME 11 BUSINESS 1 TOTALS 14
8. NEPA STATUS, NHPA COMPLIANCE and HAZARDOUS, TOXIC, OR RADIOACTIVE WASTE (HTRW).
An Environmental Impact Statement has been completed for this project. It is anticipated
that the Record of Decision will be signed in January 2007.
In accordance with established United States Corps of Engineers (USACE) Hazardous,
Toxic, and Radioactive Waste (HTRW) policies and ASTM Standards E 1527 and 1528, Phase I
HTRW Investigations have been conducted on 165 properties within the Contractor Work Limits
(CWLs). Phase I HTRW Investigations have also been conducted on proposed geotechnical
drilling locations and proposed soil borrow areas. Several boring locations were relocated to
avoid HTRW concerns. The findings of the investigation for the proposed soil borrow areas
revealed no areas of soil staining and no presence of solid waste. HTRW Investigations included
11
an investigation of surface water conditions of the Mud River associated within the vicinity of
the Town of Milton’s sanitary wastewater treatment system.
Further investigation was recommended for the following sites. Tracts listed are
identified by COE tract number as well as their corresponding Cabell County Courthouse tax
map numbers. Pertinent information on Phase II HTRW Investigations is discussed in Section
8.1.
8.1. Phase II HTRW Investigations. Phase II(A) HTRW Investigations are designed to
determine conclusively the presence or absence of environmental contamination, are intrusive,
and include sampling and analysis. Rights-of-Entry are required from the property owner in
order to conduct any Phase II HTRW Investigations. If the presence of contamination is
conclusively identified by the Phase II(A) HTRW Investigation, in-depth Phase II (B) HTRW
Investigations to quantify the types and extent of contamination present would be required.
To date, Phase II(A) HTRW Investigations have been conducted on Tracts 1117 (Tax
Map & Parcel # 5-318), 1201(Tax Map & Parcel # 8-15), on the right-of-way (ROW) adjacent to
Tract 1116 (Tax Map & Parcel # 8-10), and along portions of the Mud River. The surface water
and sediment from the river was evaluated for conditions associated with fecal coliforms in the
vicinity of the City of Milton’s sanitary wastewater treatment system within the Mud River.
Phase II (A & B) HTRW investigations have been conducted on Tract 926 (Tax Map & Parcel #
7-18).
Phase II HTRW Investigation activities and recommendations are included below, for
areas of these properties within or immediately around the CWLs. Phase II HTRW
12
Investigations for the tracts listed have not been completed. The necessary investigations for
these properties will be scheduled and performed during the Preconstruction Engineering, and
Design Phase (PED). Any necessary remediation will be completed prior to acquisition.
8.1.1 Phase II (A) HTRW Investigation of Tract 1117 (Tax Map & Parcel # 7-18) & ROW
adjacent to Tract 1116 (Tax Map & Parcel # 8-10). The investigation of these tracts were
performed to assess potential impacts from a former service station on an adjacent tract. There
was one boring advanced on Tract 1117 (Tax Map & Parcel # 7-18). Since rights of entry could
not be obtained for Tract 1116 (Tax Map & Parcel # 8-10), sampling was conducted on the right-
of-way adjacent to Tract 1116 (Tax Map & Parcel # 8-10). There were two borings advanced on
the ROW. Based upon review of the analytical data and the comparison levels discussed in the
investigation report, there was no contamination identified above action levels on Tract 1117
(Tax Map & Parcel # 7-18) or the ROW due to the former Bias Service Station, adjacent Tract
1113 (Tax Map & Parcel # 5-317), and no further action as to HTRW is recommended for Tract
1117 (Tax Map & Parcel # 7-18) . The area in the vicinity of Tract 1116 (Tax Map & Parcel # 8-
10), needs further investigation due to the discovery of a former disposal area. Any further
investigation will be scheduled and performed during PED. Any necessary remediation of Tract
1116 (Tax Map & Parcel # 8-10), will be completed prior to acquisition.
8.1.2 Phase II (A) HTRW Investigation of 1201 (Tax Map & Parcel # 8-15). The
investigation of this tract was performed to assess potential impacts from soil contamination at
an adjacent service station. There were a total of seven borings advanced on Tract 1201 (Tax
13
Map & Parcel # 8-15). There were no detections of benzene, toluene, ethylbenzene, or xylene
(BTEX), methyl tertiary-butyl ether (MTBE), or polycyclic aromatic hydrocarbons (PAHs) in the
soil and groundwater samples submitted for analysis from this tract that exceeded West Virginia
Underground Storage Tank (UST) Division guidelines or EPA Region III risk-based
concentrations (RBCs) for residential or industrial soil and no further action as to HTRW is
recommended for this property.
8.2. Phase II(A) HTRW Investigation – Portions of the Mud River (surface water &
sediment). Phase II HTRW Investigations included an investigation of surface water and
sediment within the Mud River, including an investigation of conditions associated with fecal
coliforms, in the vicinities of the Town of Milton’s sanitary wastewater treatment system and the
system’s permitted emergency outfall. Analyses from sampling during non-flooding conditions
indicated fecal coliform levels below the level of concern. No additional HTRW Investigation of
the surface water and sediment are required time and no remedial activities are indicated from
this investigation.
8.3. Phase II(A & B) HTRW Investigation - Tract 926 (Tax Map & Parcel # 7-18). During
the Phase II Investigation, there were four different areas of concern (AOC) identified for Tract
926 (Tax Map & Parcel # 7-18). The four AOCs included treated wood areas, a discarded
equipment area, a stained soil area, and the former UST area. A background sampling location
was also required for Tract 926 (Tax Map & Parcel # 7-18).
Most of the areas investigated during this investigation were visibly stained areas less
than five feet in diameter. Based on this investigation, approximately 30-50 tons of soil would
14
require proper removal in the areas that were sampled; however, confirmation surface soil
sampling is recommended for Polyaromatic Hydrocarbons (PAH), total petroleum hydrocarbons-
diesel range organics/gasoline range organics (TPH-DRO/GRO), and arsenic analysis.
Additional background samples are recommended in the area of Tract 926 (Tax Map & Parcel #
7-18).
Because the site is covered with inoperable or staged equipment and miscellaneous
materials, additional investigation is recommended after the equipment and materials have been
removed. There may potentially be impacted areas below the equipment and materials that were
not apparent during this investigation. Also, removal of the staged equipment and materials on
this tract could result in a change in the condition of the surface soils by spreading contamination
or causing uncontaminated soil to mix with the contaminated areas.
Prior to the construction phase, removal of the on-site contamination will be performed,
along with the necessary confirmation sampling.
8.4 Phase II HTRW Investigations of Additional Sites. Several of the tracts recommended for
Phase II were eliminated from further study because of modification of the boundary for the
CWLs or because on-site conditions of concern were located outside of the CWLs. Further
investigation was eliminated for the following tracts:
• Tract 6-134, CWLs modified and site excluded from CWLs. • Tracts 6-163 and 20C-8, on-site materials located outside of CWLs. Phase II HTRW Investigations have been recommended, but not completed, for the tracts listed
below. Several of the tracts were identified as containing potential USTs for gasoline storage,
15
leaking containers, and/or solid waste concerns. The Phase II HTRW Investigation of these
properties will be scheduled and performed during PED. Any necessary remediation will be
completed prior to acquisition.
8.4.1. Tract 1404 (Tax Map & Parcel # 9-5.1). Much of this property is located within the
CWL and several leaking drums of unknown contents have visibly stained the soil. There are
construction materials and debris on-site, including piles of steel girders, a scrap 10,000 gallon
UST, vehicle fuel tank, and piles of asphalt. Additional investigations are recommended for this
property to include characterization of the contents of the leaking drums and surface and
subsurface soil sampling in the areas of the drums, USTs, and asphalt piles. Fill material from
unknown sources has been placed on-site. The investigation of the site will include the area of
the fill material. Removal of construction materials located within the CWLs, prior to
construction, is also recommended. These investigations were recommended in order to
determine if there were any HTRW concerns within the CWL for levee construction.
The potential contamination from petroleum UST’s is not regulated under CERCLA, but is
subject to promulgated Federal and State hazardous waste RCRA regulations and will be
investigated and remediated in accordance with RCRA regulations.
8.4.2. Proposed Emergency Ponding Area - Tracts 901E, 903E, 906E, and 907E (Tax Map
& Parcel #’s 4-77, 4-78, 4-79, 7-8). These tracts are located adjacent to one another in the
vicinity of Stewart Street on the western portion of the CWLs, within an area of the CWLs
designated as an emergency ponding area. Easements will be obtained to allow for the ponding
of this area. Tract 906E (Tax Map & Parcel # 4-79) is the site of a former service station and a
16
potential exists for USTs to be remaining on this property. Tract 903E (Tax Map & Parcel # 4-
78) is adjacent property to Tract 906E (Tax Map & Parcel # 4-79) to the west and is included in
the investigation due to the proximity of Tract 906E (Tax Map & Parcel # 4-79). Tract 901E
(Tax Map & Parcel # 4-77) is included in the investigation due to its proximity to both Tracts
906E (Tax Map & Parcel # 4-79) and 7-7. (Tract 7-7 is a property, located outside the CWL but
adjacent to Tract 903E (Tax Map & Parcel # 4-78), where USTs, although removed, may have
impacted surface and subsurface soil and groundwater in the area.) Tract 907E (Tax Map &
Parcel #7-8) is adjacent to Tract 7-7 to the north and is included in the investigation due to its
proximity to Tract 7-7. The Phase I HTRW Investigation recommended a magnetometer survey
to locate potential USTs and surface/subsurface soil sampling and groundwater sampling in order
to determine if the soil and groundwater have been contaminated from previous activities.
The potential contamination from petroleum UST’s is not regulated under CERCLA, but is
subject to promulgated Federal and State hazardous waste RCRA regulations and will be
investigated and remediated in accordance with RCRA regulations.
8.4.3. Former disposal area in vicinity of Tracts 1112 and 1116 (Tax Map & Parcel #’s 8-9
and 8-10). The Phase I HTRW Investigation findings indicated this area was used as a
dumping ground after a pre-WWII canning factory closed. Materials placed here included scrap
metal and trash. Further investigation of this area is recommended for further characterization of
this site and to determine the existence of contamination. This investigation may include test
pit exploration, surface and subsurface soil sampling, and the removal of any waste or materials
discovered within the CWL.
17
Scrap metal and trash disposal are considered non-CERCLA issues, regulated under
Federal and State RCRA solid waste regulations and will be investigated and remediated in
accordance with RCRA solid waste regulations.
8.5. NHPA Compliance. Pursuant to Section 106 of the National Historic Preservation Act
(NHPA), impact to cultural resources was considered and limited surveys on historic properties
were completed during the feasibility stage. Detailed surveys and testing will be conducted
during the Preconstruction Engineering Design Phase per the LRH Programmatic Agreement
which is located as an appendix of the Final EIS. Consistent with ER 1105-2-100 Appendix C-4
entitled “Cultural Resources”, this programmatic agreement specifies the process by with
required surveys, testing, evaluation, effect determination, mitigation planning, and coordination
shall be achieved. The District will follow this agreement prior to implementation of a selected
alternative in order to satisfy Section 106 of the NHPA for all project activities.
9. ACQUISITION ESTIMATE AND SCHEDULE A Real Estate Cost Estimate was
prepared for the area of this report in November 2003, and updated in January 2004. The Gross
Appraisal was reviewed again in January 2006. It was found that changes in the market were
insignificant and well within contingencies. The total estimated cost of the real estate for
this project is $4,475,000, which includes contingencies, relocation benefits, and administrative
costs. The breakdown on the next page is as follows:
18
Real Estate Acquisition
Land (approx 185 ac.) $ 1,912,200
Improvements $ 272,500
Damages $ 107,000
Subtotal $ 2,291,700
Contingencies +/- 25% $ 572,925
Total Value of Real Estate $2,864,625
Total Relocation Benefits (includes contingencies) $ 260,375
Administrative Costs
135 Tracts @ $10,000 $1,350,000
Total Administrative Costs $1,350,000
GRAND TOTAL REAL ESTATE COSTS $4,475,000
Acquisition of the 135 tracts covered in this report is expected to take 48 months.
Acquisition of the real estate interests covered herein will be initiated immediately upon the
approval of the LRR, and execution of the PCA and acquisition MOA. Accordingly, early
approval of this report is requested in order to complete the required acquisition in a timely
manner to comply with the construction schedules.
19
10. SPONSOR CAPABILITIES. Section 103m of the Water Resources Development Act of
1986 (P.L. 99-662), required that all future flood control projects be cost-shared with a non-
federal local sponsor. The Town of Milton is the non-federal sponsor. Typically, acquisition of
lands, easements, rights-of-ways, relocations and disposal lands (LERRD) would be the
responsibility of the non-federal local sponsor. However, the non-federal sponsor, the Town of
Milton, has indicated that it wishes the Corps of Engineers to perform the acquisition on its
behalf. Per Chapter 12, a determination of the Town’s land acquisition experience and ability
has been prepared, and it has been determined that the Town of Milton cannot acquire LER in a
timely fashion. Following execution of the Project Cooperation Agreement (PCA), a
Memorandum of Agreement (MOA) will be entered into between the Corps and the Town of
Milton that will provide for these services. The District has sufficient resources available to
perform the acquisitions in a timely fashion. Not more than five Federal condemnations actions
are anticipated. Generally, all project lands will be acquired in the name of the Town of Milton.
The Town of Milton will contribute cash to cover its cost-share portion of the total expected
obligations and expenditures for each fiscal year. The non-federal sponsor’s cost share has been
determined to be twenty-five percent (25%) in accordance with Section 103m of the Water
resources Development Act of 1986 (Public Law 99-662). The letter from the sponsor requesting
the district acquire LERRD on their behalf is attached as Exhibit D.
565
565
565
565
565
565
565
565
565
565
565
565
565
565
565
565
565
565
565
565
565
565
565
565
565 5
65
565
565
565
565
565
565
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570570
570
570
570
570
570
570
570
570
570
5705
70
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570 570
570
570
570
570
570
570
570
570
570
57
0
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
570
575
575
575
575
57
5
57
5
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
57
5
575
575
575
575
575
57
5
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575 575
575
575
575
575
575
575
575
575
575
575
575
575
575
575575
575
575
575
575
575
575
575
575
575
575
575
575
575
575
575 575
575
575
575
575
575
575
575
575
575
575
575
575
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580
580580
580
580
580
580
580
580
580
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585585
585
585
585 585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
585
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590 5
90
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
590
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
595
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605
605 605
605
605
605
605
605
605
605
605
605
605
605
605
605
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
610
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
615
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620
620 620
620
620
620
620
620
620
620
620
620
620
620
620
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
625
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
630
635
635
635
635
635
635
635
635
635 635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
635
64
0
640
640
640
640
640
640
640
640
640
640
640
640
640
640
64
0
640
640
640
640
640
640
640
640
640
640
64
0
640
640
640
640
640
640
640
640
64
0
640
640
640
640
640
640
640
64
0
640
640
640
640
64
0
640
640
64
5
645
645
645
645
645
645
645
645
645
645
645
645
645
64
5
645
645
645
645
645
645
645
645
645
645
645
64
5
645
645
645
645
645
645
645
64
5
645
645
645
645
645
645 645
645
645
645
645
645
645
645
645
645
645
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
650
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
655
660
660
660
660
660
660
660
660
660
660
660
660
660
660
660
660
660
660
660
660
660
660
660
660 660
660
660
660
660
660
660
660
660
660
660
660
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
665
670 6
70
670
670
670
670
670
670
670
670
670
670
670
670
670
670
670
670
670
670
670
670
670
670
670
67
0
670
670
675
675
675
675
675
675
675
675
675
675
675
675
675
675
675
675
675
675
675
680
680
680
680
680
680
680
680
680
680
680
680
680
680
680
680
685
685
685
685
685
685
685
685
685
685
685
685
685
685
685
685
685
685
685
690
690
690
690
690
690
690
690
690
690
690
695
695
695
695
BL
EA
CH
ER
S
MUD
RIV
ER
MU
D
RIVER
U.C.
PILE
U.C.
PARKING
PLAYGROUND
PLAYGROUND
PLAYGROUND
TENNIS
COURT
FIELD
ATHLETIC
SCOREBOARD
CEMETERY
U.C.
CEMETERY
U.C.
U.C.
U.C.
PILE
P
U.C.
Pile
P
O.S.
O.S.
O.S.
OPEN
STORAGE
PILE
O.S.
O.S.
PILE PILE
PILES
ATHLETIC
FIELDS
ATHLETIC
FIELD
REAL ESTATE TOPOGRAPHICAL MAP
0
SCALE IN FEET
OFSHEET 42NO.
DWG.
Lower Mud River
2.) Limited Re-evaluation Report
CABELL COUNTY, WEST VIRGINIA
1 2 3 4 5
1 2 3 4 5
A
B
C
D
A
B
C
D
LOWER MUD RIVER
MILTON WV
MILTON LLP
JO
HN'S
BR
AN
CH
MU
DRIVER
JO
HN'S
BR
AN
CH
MU
D
MUD RIVER
RIV
ER
RIVER
MUD
RIV
ER
MU
D
RIVER
MU
D
RIV
ER
MUD
RIV
R
2.0
ACRE P
OND
EL. 577'
PONDING TO
NO DAMAGE
EL. 581'
PONDING TO
NO DAMAGE
BRIDGE PIERS
EXISTING
CHANNEL
RELOCATED RIVER
FOR SEEPAGE
BEGIN PILING
LIFT STATION
RELOCATED SANITARY
INTAKE WEIR
RELOCATED WATERSAND PITS
FILL EXISTING
PROTECTION
STONE SLOPE
PROTECTION
STONE SLOPE
PUMP STATION
PUMP STATION
33' WIDE GATE CLOSURE
GATE STORAGE BLDG.
EXIST. WATER INTAKE WEIR
CO
NTR
OL R
OO
M
PU
MP
CO
NTR
OLS
CO
NTR
OL R
OO
M
PU
MP
CO
NTR
OLS
F
FF
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
1 1
600300300
LEGEND
FEE
PERMANENT FLOWAGE EASEMENT
TEMPORARY BORROW AREA EASEMENT
EXHIBIT A
FILE: c:\pwwork\h1pw02\dms02274\ExhibitA.dgn
DATE: 20-Aug-04 09:27
SHEET KEYPLAN
MUD
3 4 5 6
9 10 11 12 13 14
17 18 19 20 21 22
23 24 25 26
MUD
RIV
ER
V-3101
578.47
HV-3142
579.41
HV-4122
580.12
U.C.
HV-3121
581.94
HV-3091
583.01
HV-3143
588.12P
V-4102596.87
HV-2081
601.13
HV-4
091
607.5
9
V-4101
608.52
HV-4145610.46
V-4093666.67
V-3141
683.82
1122E
1901E
409E
2401E
2401E
2001E
2001
1901
2001
1801E
1806E
1307
1404
1406
1404
1406
1407
1701
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PA
RKIN
G
PARKING
PARKING
PARKING
PA
RKIN
G
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
SHORT
STREET
BRIC
KY
AR
D
AV
EN
UE
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
64
64
64
64
PARKING
PARKING
PARKING
PARKING
60
60
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKINGPARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKINGPARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
60
PARKING
PARKING
PARKINGPARKING
PARKING
60
PARKING
PARKING
CSXT
RR
CSXT RR
PARKING
CSXT
PARKING
PARKING
PARKING
CSXT
RR
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
PARKING
301E
1008E
1008E
1008E
1009E
1009E
301E
1008E
408E
404E
406E
401E
403E
402E
601E
602E
603E
604E
606E
607E
608E
609E
611E
E-1
616
E-1
616
901E
903E
907E
908E
906E
904E
E-2
909911E
912E
913E
914E
917
916
918
919
921
921
923
924
926
926
926
926
1702E1702E
1802E
1803E
1804E
913E
401E
402E
1126E
1128E
1129E
1127E
1104E
1131E
1301E
E-3
616
E-2
616
E-2
616
1303E
1211E
502E
1212E
503E
504E
501E2
506E
501E4
501E3507E1
508E
509E
511E
512E
513E
514E516E 517E
507E2
507E3
522E
519E
518E
521E
523E
524E
526E
527E
528E
529E
531E
531E
1217E
1218E
501E1
611E
1216E
1214E
1213E
1211E
501E2
1212E
523E
E-1
909
1003E
1106E
611E
1313E
E-2
1802
2001E
1703
1007
1006
1004
1001
1002
1112
1112
1117
1119
1117
1124
1124
1118
1123
1123
1124
1113
1116
1201
1202
1203
1204
1206
2001
1207
1208
1209
1209
1201
1201
1201
2001
1302
1304
1306
1308
1307
1307
1308
2001
1304
1307
1403
1802
1803
1804
1804
1117
1703
1804
1704E
1809E
1807E
1704E
1809E
1808E
914E
1123
1219E
2001E
2001E
2001
1901
STREET
RR
PARKING
PARKING
PARKING
PARKINGPARKING
PARKING
PARKING
CR. R
D. 9
DRYCREEK
ROAD
CO. RD. 34
CHURCH
ST
RE
ET
OR
CH
AR
D
OR
CH
AR
D
ST
RE
ET
MC
GH
EE
CIRCLE
ST
RE
ET
ST
RE
ET
HARRISON
PIK
E
ST
RE
ET
MC
GH
EE
DRIVE
PIK
E
AV
E.
ST
RE
ET
MASON
GE
OR
GE
RIVEREDGE
MASON
HE
CK
STREET
60
ST
RE
ET
AV
EN
UE
SMIT
H
STREET
SH
ORT
AV
EN
UE
ST
RE
ET
STREET
MASON
STREET
GE
OR
GE
ST
RE
ET
SMIT
H
BRIC
KY
AR
D
PIK
E
GL
EN
WO
OD
HARRISON
WA
SHIN
GT
ON
RO
AD
RO
AD
STREET
AD
AM
S
ST
RE
ET
ST.
STREET
LA
WH
OR
N
KANE
HARRISON
ST
RE
ET
RIV
ER
AV
EN
UE
MU
D
SH
AW
AV
EN
UE
SH
AW
ST
RE
ET
STREET
AV
E.
STREET
SH
AW
RO
AD
STREET
AV
EN
UE
AV
EN
UE
ORCHARD
DRIV
E
MU
D
RIV
ER
ST
RE
ET
FLORIDA
ST
RE
ET
ST
EW
AR
T
RO
AD
RIV
ER
MU
D
JO
HN
S
60
GL
EN
WO
OD
HIG
HL
AN
D
STREET
BR
AN
CH
CO. RD. 25
RIV
ER
MU
D
ST
RE
ET
MC
CO
MA
S
JEFF
ER
SO
N
RO
AD
CO. R
D. 9
2ND
AV
EN
UE
WA
SHIN
GT
ON
RO
AD
1ST
STREET
ORCHARD
LA
NE
2ND
60
FLORIDA
RIV
ER
JEFF
ER
SO
N
FLORIDA
STREET
STREET
MU
D
CO.
RD. 13
STREET
SU
MM
ER
AVENUE
HIL
LVIE
W
AV
EN
UE
CO. RD. 25
AD
AM
S
AV
EN
UE
HIL
LVIE
W
JO
HN'S
SU
MM
ER
S
AV
EN
UE
SU
MM
ER
S
DRIV
E
BR
AN
CH
WOODLAND WOODLANDDRIVE
DREW
JO
HN'S
BR
AN
CH
RD.
DRIV
E
RO
AD
AVENUE
HIGHLAND
STREET
TR
EN
OL
DREW
DIVISION
ST
REET
STREET
STREET
RO
BE
RT
AV
EN
UE
3RD
ST
RE
ET
ST
EW
AR
T
General Comments: Comment: The ITR was not performed by another district as required by the attached Headquarters ITR memo. Response: This comment has been referred to PD/PM . Real Estate Plan Comments: Comment: Paragraph 1 6 Project Description and Acquisition Criteria. These paragraphs state that 53 of the tracts required for the project will be acquired in fee for “joint use wetland and terrestrial mitigation purposes. It is not clear why there is this requirement in this flood control project. The project is construction of a levee. Ordinarily, a levee easement would be sufficient to support construction and 0&M. The Acquisition Criteria paragraph needs to detail why fee is necessary. It is unclear why the temporary easement extends across the river. A map attached to the report indicates a requirement for permanent flowage easements. It is not clear from the Acquisition Criteria paragraph why the permanent flowage easements are necessary (hard to believe those areas are going to be permanently flooded) since that easement is not described in the paragraph. It is unclear where the location of the pump stations and gate closure (described elsewhere in the report) are located and what estate is proposed for those sites. It is also noted that page 28 of the main report it states that a perpetual floodwall easement will be required for construction. This is inconsistent with the REP. It is also pointed out that on page 38 the main report, the mitigation requirement is discussed and appears to be inconsistent with the fee estate contemplated by the REP. Also on page 38, ponding areas at two locations are discussed. These are not discussed in the REP and it is unclear what interests in land is contemplated. Response: Chapter 12 of ER405-1-12 states that generally, fee title is required for Fish and wildlife mitigation lands, ecosystem restoration, and other environmental purposes. The construction of the levee will involve significant alterations of the river’s channel. In order to most efficiently mitigate for the environmental impacts of the project, the majority of the mitigation features will be placed within the CWL of the project. While this will alleviate the need to acquire separable lands for mitigation, it is the opinion of the District that a fee estate should be acquired in lieu of easement to support both the levee and the mitigation features. The 53 tracts discussed in the REP are to be acquired for joint use to support the construction operation and maintenance of the levee, as well as, for wetland and terrestrial mitigation purposes. As stated in Paragraph 6 of the REP, Acquisition Criteria, “Mitigation features lie within the project limits. The standard fee estate has been proposed in areas where both project and mitigation features are co-located.” Exhibit A of the REP clearly depicts where those migration features are. The temporary easement extends across the river in order to expedite the transportation of borrow material to the project site.
The permanent flowage easements, as shown on Exhibit A, are necessary easements in order to gain the perpetual right to occasionally flood and submerge the land depicted in Exhibit A. The pump stations are located entirely within fee lands and will not need additional acquisition. Page 28 and 38 of the main report should be changed to reflect the mitigation features of the project. After consulting with CELRH-OC, the standard estate, Flowage Easement (Occasional Flooding) would be preferred to a non-standard Ponding Area Easement estate. Comment: Paragraph 5. Facilities to be relocated. Sub-paragraphs indicate relocation of some utilities/facilities. It needs to be clarified whether the relocations include an additional land requirement or if the utility will be able to be relocated within existing right of way. Additional land requirements need to be identified. Response: Utilities will be relocated within existing rights of ways. Comment: Paragraph 5.2.1. Milton Middle School. Evidently an additional land requirement is contemplated. This paragraph needs to indicate what the district’s proposed plan is for relocation and land acquisition requirements. Response: The school is urban. The gravel/dirt/grass running track and the paved lot in the rear of the school will be relocated on site. It is currently anticipated that no additional land will be required to meet State standards. Comment: Paragraph 5.2.4. As stated above, if your preliminary analysis indicates additional land requirements, they must be captured in the REP. Response: The REP currently describes the real estate requirements for the project based upon the baseline project design. Comment: Paragraph 7. P.L. 91-646 Relocation Assistance Data. Discussion with the district relocation specialist indicates that this paragraph does not describe what her survey indicated. This paragraph needs to be revised to indicate the area surveyed and that this is sufficient available housing in the area to accommodate displacees. Response: The District relocation specialist was consulted. There is sufficient available housing in the area to accommodate displacees. Page 9 of the REP states that “A replacement housing survey was completed in July 2003. The conclusion of that survey was: “The turnover in the general housing market in the project are of Milton, West Virginia, appears to be more than adequate to accommodate the number of displaced persons anticipated in any year.””
Comment: Paragraph 8. Neither NEPA or NHPA compliance status is described in this paragraph. In the sub-paragraphs there are many instances where the text states that any necessary remediation will be completed prior to construction. This needs to be changed to prior to acquisition. Paragraphs 8.4.1 and 8.4.2 should also indicate the cleanup will take place prior to acquisition. Response: An Environmental Impact Statement has been completed for this project. It is anticipated that the Record of Decision will be signed in April of 2006. The REP has been changed to include this information. The REP has been changed to reflect that any necessary remediation will be completed prior to acquisition. Comment: Paragraph 9. Acquisition Estimate and Schedule. While the Real Estate values conform to the gross appraisal, they are old and need to be updated. Response: Appraisal Branch has completed an update of the gross appraisal. The baseline cost estimate will not change. It was found that changes in the market were insignificant and well within contingencies. Comment: Paragraph 10. Sponsor capabilities. Real Estate Division must submit to CELRD-PDS-R for approval the Memorandum of Agreement between the District and non-federal sponsor to acquire lands on behalf of the non-federal sponsor. Chapter 12 requires submittal and approval of the MOA. This Division has a specific delegation to approve MOA’s (as well as Mr. Lijoi’s level 3 delegation that allows for approval of all real estate actions that do not require S/A approval. The draft MOA should be submitted at the earliest possible date. It should be negotiated and agreed to prior to the execution of the PCA. MOA execution should be simultaneous or subsequent to the PCA. A copy of the sponsor’s written request that the district acquire on their behalf must be attached as an exhibit to the REP. Response: Concur, CELRH-OC will draft and MOA for LERRD and will negotiate it with the sponsor in conjunction with the PCA negotiation. Our schedule reflects a PCA signing in October 2006. Comment: Paragraph 10. Sponsor Capabilities. There needs to be a letter from the sponsor attached as an exhibit requesting the district acquire on there behalf. The text should be revised to reflect the exhibit. Response: Concur, a letter from the sponsor requesting the district acquire LERRD on their behalf will be attached as an exhibit. The text will be revised to reflect the exhibit.